JPH0776458B2 - Construction method for additional bearing wall - Google Patents
Construction method for additional bearing wallInfo
- Publication number
- JPH0776458B2 JPH0776458B2 JP2877787A JP2877787A JPH0776458B2 JP H0776458 B2 JPH0776458 B2 JP H0776458B2 JP 2877787 A JP2877787 A JP 2877787A JP 2877787 A JP2877787 A JP 2877787A JP H0776458 B2 JPH0776458 B2 JP H0776458B2
- Authority
- JP
- Japan
- Prior art keywords
- brace
- frame
- construction method
- center
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】 産業上の利用分野 この発明は、特に鉄骨の軸組とパネルを用いた工業化プ
レハブ住宅において、耐力構造となっていない既設の軸
組を耐力壁に改造するための工法に関する。Description: TECHNICAL FIELD The present invention relates to a method for converting an existing frame not having a load bearing structure into a load bearing wall, particularly in an industrialized prefabricated house using a steel frame and a panel. Regarding
従来の技術 例えば、1階建ての建物に2階を増築する場合、新たに
耐力壁を増設することが必要となる。2. Description of the Related Art For example, when adding a second floor to a one-story building, it is necessary to newly install a bearing wall.
このような場合、従来では、外壁パネル等の外装材を取
り外したのち、更に改造しようとする部分の軸組を外し
て、耐力壁構造の新たな軸組と交換していた。また、こ
れと異なる方法では、現場で直接ブレースを溶接する方
法も考えられる。In such a case, conventionally, after removing the exterior material such as the outer wall panel, the framework of the portion to be further modified is removed and replaced with a new framework of the load bearing wall structure. Alternatively, a method of welding the braces directly on site may be considered as a different method.
発明が解決しようとする問題点 しかしながら、上記従来の工法において、軸組を交換す
る方法では、外壁パネルのみならず内装材をも解体する
必要があり、更には増築部分とは関係の内部分にまで工
事が拡大することとなって、工費が嵩み工期も長くなる
欠点がある。DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention However, in the above-mentioned conventional construction method, in the method of exchanging the frame, not only the outer wall panel but also the interior material needs to be disassembled, and further, the interior portion is related to the extension portion. However, the construction cost will increase and the construction period will become longer.
他方、ブレースを現場溶接する方法では、現場溶接の品
質を確保することが困難であるという問がある。On the other hand, it is difficult to secure the quality of in-situ welding by the method of in-situ welding of braces.
この発明は、そのような従来工法の欠点を解消して、短
期間で低コストに工事を行うことのできる耐力壁の増設
工法を提供するものである。The present invention solves the drawbacks of the conventional construction method, and provides an additional construction method of a load-bearing wall capable of performing construction at a low cost in a short period of time.
問題点を解決するための手段 上記の問題点を完結するため、この発明は、左右の縦方
向枠材(3)(3)と上下の横方向枠材(4)(4)と
によって方形枠状に形成され、かつ、この枠体(5)の
略中央を横切って中柱(6)及び/又は横桟(7)を備
えた軸組(1)において、 前記中柱及び/又は横桟(6)(7)の中央にブレース
(13)を通すための穴(14)を開ける工程と、継手部分
で2分割されたタンバックル式のブレース(13)の一方
を上記穴(14)へ通し、かつ、分割された両ブレース部
材(16)(17)を相互に連結する工程と、前記ブレース
(13)の端部に固着した接合部材(19)(20)を、各軸
組(1)(2)を相互に連結するボルト(8)若しくは
アンカーボルト(10)を用いてその軸組(1)の対角コ
ーナーへ固定する工程とからなることを特徴とするもの
である。Means for Solving the Problems In order to complete the above problems, the present invention provides a rectangular frame by the left and right vertical frame members (3) (3) and the upper and lower horizontal frame members (4) (4). In a framework (1) which is formed in a shape and which includes a middle pillar (6) and / or a horizontal rail (7) across substantially the center of the frame body (5), the middle pillar and / or the horizontal rail (6) A step of forming a hole (14) for passing the brace (13) in the center of (7), and one of the tuck buckle type brace (13) divided into two at the joint part to the hole (14). The step of connecting the two brace members (16) (17), which are passed through and divided, to each other, and the joining members (19) (20) fixed to the ends of the brace (13), And (2) fixing the two (2) to the diagonal corners of the frame (1) using bolts (8) or anchor bolts (10) that connect them to each other. It is characterized by consisting of.
なお、この発明において、分割されたブレース部材(1
6)(17)相互の連結と両端の軸組(1)への固定の順
序は、上記の記載の順に限定されるものではなく、適宜
前後して行ってもよいものである。In the present invention, the divided brace member (1
6) The order of (17) mutual connection and fixing to the shaft set (1) at both ends is not limited to the order described above, and may be appropriately performed before or after.
作用 上記この発明によれば、軸組(1)を取り外すことな
く、穴開け、ボルトの取り外し及び締め付けなどをおこ
なうのみで、耐力壁への改造を行うことが出来る。Effect According to the present invention described above, the bearing wall can be remodeled by merely drilling holes, removing bolts, and tightening the bolts without removing the frame assembly (1).
実施例 次に、この発明の工法を、その施工順序に従って説明す
る。Example Next, the construction method of the present invention will be described according to the construction order.
第5図において、(1)は、耐力壁に改造しようとする
この発明の軸組であり、まず、この軸組(1)及びその
両側の軸組(2)(2)部分に跨がって、外壁パネルそ
の他の桁材等の外装部材を取り外す。第1図でも示すよ
うに、改造を行う軸組(1)は、金属製チャンネルから
なる左右一対の縦枠(3)(3)と同じくチャンネルか
らなる上下一対の横枠(4)(4)とによって方形の枠
体(5)を構成している。この枠体(5)内には、その
左右の中央において、一対のチャンネル材を背中合わせ
に配置した中柱(6)が、両横枠(4)(4)間に渡し
て取り付けられ、更に、縦枠(3)(3)とその横枠
(4)(4)の中央部間に、横桟(7)(7)が取り付
けられている。In FIG. 5, (1) is a frame set of the present invention to be modified into a load bearing wall, and first, the frame set (1) and the frame sets (2) and (2) on both sides thereof are straddled. The outer wall panel and other exterior members such as girders. As shown in FIG. 1, the modified frame assembly (1) includes a pair of left and right vertical frames (3) and (3) made of metal channels, and a pair of upper and lower horizontal frames (4) and (4) also made of channels. And form a rectangular frame (5). Inside the frame body (5), a center pillar (6) in which a pair of channel materials are arranged back to back is attached in the center of the left and right of the frame body across both lateral frames (4) and (4). The horizontal rails (7) and (7) are attached between the central portions of the vertical frames (3) and (3) and the horizontal frames (4) and (4).
そして、外壁パネル等を取り外した段階で、第5図で示
すように、縦枠(3)(3)と両隣の軸組(2)(2)
とを連結している上下2個計8個のボルト・ナット
(8)(9)、(8)(9)…、及び、下側の横枠
(4)を基礎(10)へ固定しているアンカーボルト(1
1)のナット(12)を、外しておく。Then, when the outer wall panel and the like are removed, as shown in FIG. 5, the vertical frames (3) and (3) and the adjacent frame sets (2) and (2) are provided.
By fixing the upper and lower two bolts and nuts (8) (9), (8) (9), ... and the lower horizontal frame (4) that are connected to the base (10) Anchor bolt (1
Remove the nut (12) from 1).
しかる後、第6図のように、中柱(6)の上下の中央
に、第7図のようなタンバックル式のブレース(13)を
通すための穴(14)を開口する。このブレース(13)
は、互いの対向端部に逆方向の雄螺子(15)(15)を備
えた一対の螺子杆(16)(17)と、両雄螺子(15)(1
5)を螺込んでこれらの螺子杆(16)(17)を連結する
継手(18)とからなる。各螺子杆(16)(17)の他方の
端部には、それぞれ接合プレート(19)(20)が、予め
溶接されている。また、それらの接合プレート(19)
(20)には、各々直角方向の固定片(21)(21)が一体
に形成してある。After that, as shown in FIG. 6, a hole (14) for passing a tan buckle type brace (13) as shown in FIG. 7 is opened at the upper and lower centers of the center pillar (6). This brace (13)
Is a pair of screw rods (16) (17) having opposite male screws (15) (15) at opposite ends, and both male screws (15) (1).
It is composed of a joint (18) for screwing (5) and connecting these screw rods (16, 17). Joining plates (19) (20) are pre-welded to the other end of each screw rod (16) (17). Also, joining plates for them (19)
Fixing pieces (21) and (21) in the right-angle direction are integrally formed on the (20).
次に、上記ブレース(13)を、第7図のように、長い方
の螺子杆(16)を継手(18)より抜き出して、他方の短
い雄螺子杆(17)と分離状態に分割する。次いで、切り
離した長い方の雄螺子杆(16)を、第1図のように、中
柱(6)に開口した穴(14)へ横桟(7)の下方より斜
め上方に向けて挿通する。この状態で、第2図の如く、
接合プレート(19)を縦枠(3)と下側横枠(4)との
コーナーにおけるフランジ(22)(22)間に挿入し、固
定片(21)を、縦枠(3)側においては、前記綴りボル
ト(8)とナット(9)を利用して、隣接軸組(2)と
の再連結とともに、その縦枠(3)へ固定する。また、
下側横枠(4)(4)には、その横枠(4)より突出し
ているアンカーボルト(11)へ、予め取り外したナット
(12)を締め付けて固定する。なお、固定片(21)に
は、予めそれらのボルト(8)(11)を挿入するボルト
穴を形成しておく。Next, as shown in FIG. 7, the longer brace (16) of the brace (13) is pulled out from the joint (18) and separated from the other short male rod (17). Next, as shown in FIG. 1, the separated long male threaded rod (16) is inserted into the hole (14) opened in the center pillar (6) obliquely upward from below the horizontal rail (7). . In this state, as shown in FIG.
The joining plate (19) is inserted between the flanges (22) (22) at the corners of the vertical frame (3) and the lower horizontal frame (4), and the fixing piece (21) is attached on the vertical frame (3) side. The spelling bolt (8) and the nut (9) are used to reconnect the adjacent shaft set (2) and fix it to the vertical frame (3). Also,
On the lower lateral frames (4) and (4), the nuts (12) removed in advance are fastened and fixed to the anchor bolts (11) protruding from the lateral frames (4). In addition, the fixing piece (21) is previously formed with a bolt hole into which the bolt (8) (11) is inserted.
上記のようにして、長い方の雄螺子杆(16)を固定した
後、もう1つの短い方の雄螺子杆(17)を、その接合プ
レート(20)を、前記コーナーの対角にある上部側横枠
(4)と縦枠(3)とのコーナー差し込んで配置する
(第3図)。このとき、継手(18)を螺込んでより短く
して、その継手(18)を相手方雄螺子杆(16)の雄螺子
(15)へ対向させ、再びこの継手(18)を伸ばしてその
雄螺子(15)へ螺合して連結する。この連結の後又はそ
の前に、接合プレート(20)の固定片(21)を、軸組
(1)(2)同士を綴るボルト(8)とナット(9)を
用いて取り付ける。After fixing the longer male threaded rod (16) as described above, the other shorter male threaded rod (17) is attached to the joining plate (20) at the diagonally upper corner. The side horizontal frame (4) and the vertical frame (3) are placed by inserting the corners (Fig. 3). At this time, the joint (18) is screwed in to shorten it, the joint (18) is opposed to the male screw (15) of the mating male screw rod (16), and the joint (18) is extended again to extend the male joint. It is connected to the screw (15) by screwing. After or before this connection, the fixing piece (21) of the joining plate (20) is attached using the bolts (8) and nuts (9) that bind the shaft sets (1) and (2) together.
最後に、第4図の如く、一方の対角方向のブレース(1
3)の取り付けが済んだら、同様にして、他方のブレー
ス(13)を取り付ける。Finally, as shown in Fig. 4, one diagonal brace (1
After installing 3), similarly install the other brace (13).
なお、上記において、ブレース(13)を通す穴(14)
は、横桟(7)或いは中柱(6)と横桟(7)の双方に
開口することもある。In addition, in the above, the hole (14) through which the brace (13) passes
May open to the cross rail (7) or both the middle pillar (6) and the cross rail (7).
発明の効果 以上のように、この発明によれば、外壁パネル等の外装
材を取り外し、中柱や横桟へ穴開けを行ってブレースを
通し、軸組相互又は横組を基礎へ固定しているボルトを
用いて、そのブレースを固定するという簡単な工法であ
るため、軸組を入れ換える場合に比較して、内装材の取
り外しやその他不必要に広範囲に亘って解体を行う必要
がなく、短期間で低コストに施行できる効果がある。ま
た、軸組を取り替える方法では、取り外した軸組は廃材
として処理せざるを得なかったが、この発明では、かか
る不都合が無くより低コストに実施できる。更に、現場
での溶接を行うものではないため、溶接精度のような品
質上の問題を生ずる恐れが少なく、かつ、溶接工のよう
な専門技能工も不要である。EFFECTS OF THE INVENTION As described above, according to the present invention, the exterior material such as the outer wall panel is removed, the central pillar or the horizontal rail is perforated, the brace is passed through, and the shafts or the horizontal frames are fixed to the foundation. Since this is a simple method of fixing the brace using the bolts, it is not necessary to remove the interior materials or unnecessarily dismantle over a wide area compared to replacing the frame, There is an effect that it can be implemented at low cost. Further, in the method of replacing the shaft assembly, the removed shaft assembly had to be treated as a waste material, but in the present invention, there is no such inconvenience and it can be implemented at a lower cost. Furthermore, since welding is not performed on site, there is less risk of quality problems such as welding accuracy, and specialized technicians such as welders are unnecessary.
第1図は、分割したブレースの差し込み方法を示す斜視
図、第2図は、接合プレートの取り付け状態を示す要部
の斜視図、第3図及び第4図は、第2図以後の施工方法
を示す斜視図、第5図は、外装材の取り外し状態の正面
図、第6図は、中柱に開口したブレース挿通穴を示す要
部斜視図、段7図は、ブレースの分割状態の斜視図であ
る。 (1)……軸組、(3)……縦枠、(4)……横枠、
(5)……枠体、(6)……中柱、(7)……横桟、
(8)……ボルト、(11)……アンカーボルト、(13)
……ブレース、(14)……穴、(16)(17)……分割ブ
レース部材、(18)……継手、(19)(20)……接合プ
レート。FIG. 1 is a perspective view showing a method of inserting a divided brace, FIG. 2 is a perspective view of an essential part showing a mounting state of a joining plate, and FIGS. 3 and 4 are construction methods after FIG. FIG. 5 is a front view of a state in which the exterior material is removed, FIG. 6 is a perspective view of a main portion showing a brace insertion hole opened in the center pillar, and step 7 is a perspective view of a divided brace. It is a figure. (1) …… framework, (3) …… vertical frame, (4) …… horizontal frame,
(5) …… Frame, (6) …… Center pillar, (7) …… Horizontal bar,
(8) …… Bolt, (11) …… Anchor bolt, (13)
…… Brace, (14) …… Hole, (16) (17) …… Divided brace member, (18) …… Fitting, (19) (20) …… Join plate.
Claims (1)
よって方形枠状に形成され、かつ、この枠体の略中央を
横切って中柱及び/又は横桟を備えた軸組において、 前記中柱及び/又は横桟の中央にブレースを通すための
穴を開ける工程と、継手部分で2分割されたタンバック
ル式のブレースの一方を上記穴へ通し、かつ、分割され
た両ブレース部材を相互に連結する工程と、前記ブレー
スの端部に固着した接合部材を、各軸組を相互に連結す
るボルト若しくはアンカーボルトを用いてその軸組の対
角コーナーへ固定する工程とからなることを特徴とする
耐力壁の増設工法。1. A frame assembly which is formed into a rectangular frame shape by left and right vertical frame members and upper and lower horizontal frame members, and which is provided with a middle pillar and / or a horizontal rail across substantially the center of the frame body. In the step of making a hole for passing a brace in the center of the center pillar and / or the horizontal rail, and passing one of the tan buckle type brace divided into two in the joint portion through the hole and dividing the two. From the step of connecting the brace members to each other, and the step of fixing the joining member fixed to the end of the brace to the diagonal corner of the shaft using bolts or anchor bolts that connect the shafts to each other. This is an additional construction method for bearing walls.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2877787A JPH0776458B2 (en) | 1987-02-10 | 1987-02-10 | Construction method for additional bearing wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2877787A JPH0776458B2 (en) | 1987-02-10 | 1987-02-10 | Construction method for additional bearing wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63197744A JPS63197744A (en) | 1988-08-16 |
| JPH0776458B2 true JPH0776458B2 (en) | 1995-08-16 |
Family
ID=12257832
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2877787A Expired - Fee Related JPH0776458B2 (en) | 1987-02-10 | 1987-02-10 | Construction method for additional bearing wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0776458B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3448426B2 (en) * | 1996-04-05 | 2003-09-22 | 新日本製鐵株式会社 | Joint structure of frame material for wall mounting in steel house |
| JP6079446B2 (en) * | 2013-06-03 | 2017-02-15 | 積水ハウス株式会社 | Bearing walls and houses |
-
1987
- 1987-02-10 JP JP2877787A patent/JPH0776458B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63197744A (en) | 1988-08-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210104967U (en) | Assembled house structure | |
| JPH0776458B2 (en) | Construction method for additional bearing wall | |
| JPS6047140A (en) | Steel plate concrete structure | |
| JPH10176378A (en) | Installation structure of earthquakeproofing wall | |
| JP2000273952A (en) | Connecting device of structural material for building | |
| JP3311223B2 (en) | Temporary column structure and building unit and construction method of unit building | |
| JP2001234590A (en) | Fitting for jointing members | |
| JP2000087455A (en) | Temporary pillar structure, building unit and construction method of unit building | |
| JP4411478B2 (en) | Wooden frame unit housing | |
| JP3156014B2 (en) | Precast reinforced concrete frame with end steel joints | |
| JPH084289A (en) | Form timbering member | |
| JP3284383B2 (en) | Support hardware for SRC beam construction | |
| JP7380042B2 (en) | Building column and beam connection method | |
| JP5358202B2 (en) | Connection structure of building unit and incidental structure, and unit building | |
| JPH0390760A (en) | Connection of steel beam to closed section type steel column | |
| JPH01182460A (en) | Beam mold frame | |
| JPS6140842Y2 (en) | ||
| JP2816127B2 (en) | Joint construction method of frame material and joint structure of frame material | |
| JP2709155B2 (en) | ALC floor panel mounting method | |
| JPH08199689A (en) | Reinforced construction of unit box frame | |
| JPS628246Y2 (en) | ||
| JPH0688381A (en) | Structural unit body for unit house | |
| JP2003336317A (en) | Earthquake resistant structure of wooden building | |
| JPS58213935A (en) | Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof | |
| JPH024735B2 (en) |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |