JPH0820910A - Construction method of PC cable stayed bridge - Google Patents

Construction method of PC cable stayed bridge

Info

Publication number
JPH0820910A
JPH0820910A JP15344694A JP15344694A JPH0820910A JP H0820910 A JPH0820910 A JP H0820910A JP 15344694 A JP15344694 A JP 15344694A JP 15344694 A JP15344694 A JP 15344694A JP H0820910 A JPH0820910 A JP H0820910A
Authority
JP
Japan
Prior art keywords
main
cable
block
constructed
main tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15344694A
Other languages
Japanese (ja)
Inventor
Takeshi Takao
武 鷹尾
Tadashi Igarashi
正 五十嵐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP15344694A priority Critical patent/JPH0820910A/en
Publication of JPH0820910A publication Critical patent/JPH0820910A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】 【目的】 PC斜張橋の工法に於いて、従来は単独に桁
柱頭部を施工していたが、主塔ブロックの斜材ケーブル
の定着部まで先行して施工し、工期を短縮する工法を提
供する。 【構成】 コーベル部のブロックと下部主塔部のブロッ
クの一部を施工し、上段の主塔のブロックと下段横梁を
施工すると同時に主桁柱頭部を構築し、更に主塔側の定
着ブロックとなる上段の主塔まで施工し、主桁柱頭部に
ワーゲンを組立て主桁の斜材ケーブルとなる定着部を施
工することを繰り返してなるPC斜張橋の施工法。
(57) [Summary] [Purpose] In the construction method of PC cable-stayed bridges, conventionally, girder heads were constructed independently, but construction was carried out prior to the anchorage section of the diagonal cable of the main tower block. Provide a construction method that shortens the construction period. [Structure] A part of the corbel block and a part of the lower main tower block are constructed, an upper main tower block and a lower horizontal beam are constructed, and at the same time a main girder head is constructed, and further, an anchoring block on the main tower side. The construction method of the PC cable-stayed bridge, which is repeated by constructing up to the upper main tower, assembling the wagon on the main girder column head, and constructing the anchoring part that becomes the diagonal cable of the main girder.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、PC斜張橋の主塔、主
桁の施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for a main tower and a main girder of a PC cable-stayed bridge.

【0002】[0002]

【従来の技術】従来は、(1)図5に示すようにコーベ
ル部C1〜C4のブロックを先ず施工する。
2. Description of the Related Art Conventionally, (1) as shown in FIG. 5, a block of corbel parts C1 to C4 is first constructed.

【0003】(2)次いで図6に示すようにコーベル部
C5と主桁柱頭部H1、H2を施工する。該主桁柱頭部
H1、H2はワーゲン(作業架設車)を組立てるための
スペースとなる。
(2) Next, as shown in FIG. 6, a corbel portion C5 and main girder column heads H1 and H2 are installed. The main girder column heads H1 and H2 serve as a space for assembling a wagon (work erection vehicle).

【0004】(3)次ぎに図7に示すように前記主桁柱
頭部H1、H2の上に枠組足場2を架設し主塔T1、T
2のブロックを施工する。
(3) Next, as shown in FIG. 7, a frame scaffold 2 is erected on the main girder heads H1 and H2, and main towers T1 and T
Build block 2.

【0005】(4)次ぎに図8に示すように枠組足場2
の盛り替えを行い主塔T3〜T6のブロック及び下段横
梁を施工する。
(4) Next, as shown in FIG. 8, the frame scaffold 2
And the blocks of the main towers T3 to T6 and the lower horizontal beams are constructed.

【0006】(5)次ぎに図9に示すように主塔T7〜
T9のブロックを施工する。この例の場合、主塔T9は
第一段目の斜材ケーブルB1、B2の定着ブロックにな
る。一般的に最初の斜材ケーブルB1、B2の定着位置
は主塔の、かなり上の方にあるのが普通である。さらに
ワーゲンW1、W2を組立て主桁K1、K2のブロック
を施工する。ここに主桁K1、K2は第一段目の斜材ケ
ーブルB1、B2の桁側の定着ブロックとなる。
(5) Next, as shown in FIG.
Build a block of T9. In the case of this example, the main tower T9 serves as a fixing block for the first diagonal cables B1 and B2. Generally, the fixing position of the first diagonal cables B1 and B2 is usually located considerably above the main tower. Further, the wagens W1 and W2 are assembled and the blocks of the main girders K1 and K2 are constructed. Here, the main girders K1 and K2 are fixing blocks on the girder side of the first-stage diagonal cables B1 and B2.

【0007】(6)以下図10に示すように主塔の施工
とワーゲンW1、W2の移動による主桁ブロックの施工
を並行させ斜材ケーブルB3、B4を緊張することを繰
り返して斜張橋を構築していた。
(6) As shown in FIG. 10 below, the construction of the main tower and the construction of the main girder block by the movement of the wages W1 and W2 are carried out in parallel and the tensions of the diagonal cables B3 and B4 are repeated to construct the cable-stayed bridge. Was building.

【0008】[0008]

【発明が解決しようとする課題】上述のように、PC斜
張橋の張出架設工法では、斜材ケーブルを架設しながら
主桁を張出施工するため主塔の定着ブロックまで構築が
完了しないと主桁工事に着手出来なかった。
As described above, in the erection erection method for the PC cable-stayed bridge, the main girder is erected while the diagonal cable is erected, so the construction is not completed up to the anchoring block of the main tower. And I could not start the main girder construction.

【0009】本発明では、主塔ブロックの斜材ケーブル
の定着部まで先行して施工し、工期を短縮する工法を提
供することを目的とする。
It is an object of the present invention to provide a method of constructing a slant cable of a main tower block in advance by fixing it to a fixing portion to shorten the construction period.

【0010】[0010]

【課題を解決するための手段】PC斜張橋において、コ
ーベル部のブロックと下部主塔部のブロックの一部を施
工し、枠組足場の盛り替えを行い上段の主塔のブロック
と下段横梁を施工すると同時に主桁柱頭部を構築し、更
に主塔側の定着ブロックとなる上段の主塔まで施工し、
主桁柱頭部にワーゲンを組立て主桁の第一斜材ケーブル
となる定着部を施工し、第一斜材ケーブルを緊張し、主
塔と主桁を同時に施工を繰り返しながら斜材ケーブルを
緊張せしめて斜張橋を構築する。
[Means for Solving the Problem] In a PC cable-stayed bridge, a part of the block of the corbel part and a block of the lower main tower part are constructed, and the frame scaffolding is re-established so that the upper main tower block and the lower horizontal beam are installed. At the same time as the construction, construct the main girder head, and also construct up to the upper main tower which will be the anchoring block on the main tower side,
Assembling the wagon on the main girder column head, constructing the fixing part that will be the first diagonal cable of the main girder, tensioning the first diagonal cable, and tensioning the diagonal cable while repeating the construction of the main tower and the main girder at the same time. Build a cable-stayed bridge.

【0011】[0011]

【実施例】以下実施例を図1〜図4に従って説明する。EXAMPLES Examples will be described below with reference to FIGS.

【0012】先ず(1)図1でコーベル部のブロックC
1〜C5と主塔部のブロックT1、T2を施工する。
First, (1) in FIG. 1, the block C of the corbel portion
1 to C5 and blocks T1 and T2 of the main tower are constructed.

【0013】(2)次ぎに、図2で枠組足場の盛り替え
を行い主塔のブロックT3〜T6と下段横梁を施工し、
同時に主桁柱頭部H1、H2を構築する。
(2) Next, in FIG. 2, the frame scaffolding is refilled and blocks T3 to T6 of the main tower and the lower horizontal beams are constructed.
At the same time, the main girder stigmas H1 and H2 are constructed.

【0014】(3)次ぎに図3で主塔T7〜T9を施工
し、主塔部のブロックT9を主塔側の定着部とする。更
にワーゲンW1、W2を組立て主桁の第一斜材ケーブル
B1、B2の定着部K1、K2を施工し斜材ケーブルを
緊張する。
(3) Next, the main towers T7 to T9 are constructed in FIG. 3, and the block T9 in the main tower portion is used as the fixing portion on the main tower side. Further, the wagens W1 and W2 are assembled, the fixing portions K1 and K2 of the first diagonal cables B1 and B2 of the main girder are installed, and the diagonal cables are tensioned.

【0015】(4)主塔と主桁を同時に施工を繰り返し
ながら斜材ケーブルを緊張せしめて斜張橋を構築する。
(4) A cable-stayed bridge is constructed by tensioning a diagonal cable while repeating construction of a main tower and a main girder at the same time.

【0016】[0016]

【発明の効果】この発明では、主桁柱頭部の施工と同時
に、斜張材の定着部となる主塔まで構築するので、従来
のように別に施工する主桁柱頭部施工日数だけ工期が短
縮される。平均短縮日数を表1に示す。
According to the present invention, since the main tower, which is the anchoring portion for the cable-stayed material, is constructed at the same time as the construction of the main girder column head, the construction period is shortened by the number of construction days of the main girder column head separately constructed as in the conventional case. To be done. Table 1 shows the average shortened days.

【0017】[0017]

【表1】 [Table 1]

【図面の簡単な説明】[Brief description of drawings]

【図1】コーベル部のブロックC1〜C5と主塔部のブ
ロックT1、T2を施工する図である。
FIG. 1 is a diagram of constructing blocks C1 to C5 of a corbel portion and blocks T1 and T2 of a main tower portion.

【図2】枠組足場の盛り替えを行い主塔のブロックT3
〜T6と下段横梁を施工し、同時に主桁柱頭部H1、H
2を構築する図である。
[Fig. 2] Block T3 of the main tower after the frame scaffolding was replaced
~ T6 and lower cross beam are installed, and at the same time, main girder column heads H1, H
It is a figure which builds 2.

【図3】主塔T7〜T9を施工し、主塔部のブロックT
9を主塔側の定着部とする。更にワーゲンW1、W2を
組立て主桁の第一斜材ケーブルB1、B2の定着部K
1、K2を施工し斜材ケーブルを緊張する図である。
[Fig. 3] Construction of main towers T7 to T9, block T of the main tower
9 is the fixing section on the main tower side. Further, the wagons W1 and W2 are assembled to fix the fixing portion K of the first diagonal cable B1 and B2 of the main girder.
It is a figure which tensions a diagonal cable by constructing No. 1 and K2.

【図4】主塔と主桁を同時に施工を繰り返しながら斜材
ケーブルを緊張せしめて斜張橋を構築する図である。
FIG. 4 is a diagram in which a cable-stayed bridge is constructed by tensioning a diagonal cable while repeating construction of a main tower and a main girder at the same time.

【図5】従来の工法でコーベル部C1〜C4のブロック
を先ず施工する図である。
FIG. 5 is a diagram in which blocks of corbel parts C1 to C4 are first constructed by a conventional method.

【図6】従来の工法でコーベル部C5と主桁柱頭部H
1、H2を施工する図である。
[Fig. 6] Corbel part C5 and main girder head H by the conventional method
It is a figure which constructs 1 and H2.

【図7】従来の工法で主桁柱頭部H1、H2の上に枠組
足場2を架設し主塔T1、T2のブロックを施工する図
である。
FIG. 7 is a view in which the frame scaffolding 2 is installed on the main girder column heads H1 and H2 and the blocks of the main towers T1 and T2 are constructed by the conventional method.

【図8】従来の工法で枠組足場2の盛り替えを行い主塔
T3〜T6のブロック及び下段横梁を施工する図であ
る。
FIG. 8 is a diagram in which the blocks of the main towers T3 to T6 and the lower horizontal beams are constructed by refilling the framework scaffold 2 by a conventional construction method.

【図9】従来の工法で主塔T7〜T9のブロックを施工
する。この例の場合、主塔T9は第一段目の斜材ケーブ
ルB1、B2の定着ブロックになる。さらにワーゲンW
1、W2を組立て主桁K1、K2のブロックを施工す
る。ここに主桁K1、K2は第一段目の斜材ケーブルB
1、B2の桁側の定着ブロックとなる図である。
FIG. 9: Construct blocks of the main towers T7 to T9 by a conventional method. In the case of this example, the main tower T9 serves as a fixing block for the first diagonal cables B1 and B2. Further Wagen W
1 and W2 are assembled and the blocks of the main girders K1 and K2 are constructed. Here, the main girders K1 and K2 are the diagonal cable B of the first stage.
FIG. 3 is a diagram illustrating a fixing block on the digit side of 1 and B2.

【図10】従来の工法で主塔の施工とワーゲンW1、W
2の移動による主桁ブロックの施工を並行させ斜材ケー
ブルB3、B4を緊張することを繰り返して斜張橋を構
築していく図である。
[Fig. 10] Construction of the main tower and wagons W1, W by the conventional method
It is a figure which constructs a cable-stayed bridge by repeating construction of the main girder block by moving 2 and tensioning the diagonal cable B3, B4 repeatedly.

【符号の説明】[Explanation of symbols]

1・・・ブラケット、2・・・枠組足場、3・・・支保
工、B1、B2・・・第一段斜材ケーブル、B3、B4
・・・第二段斜材ケーブル、C1〜C5・・・コーベル
部1〜5、H1、H2・・・主桁柱頭部、K1、K2・
・・主桁、T1〜T9・・・主塔1〜9、W1、W2・
・・ワーゲン
1 ... Bracket, 2 ... Frame scaffolding, 3 ... Supporting work, B1, B2 ... First stage diagonal cable, B3, B4
... Second-stage diagonal cable, C1-C5 ... Corbel parts 1-5, H1, H2 ... Main girder column head, K1, K2 ...
..Main girders, T1-T9 ... Main towers 1-9, W1, W2
..Wagen

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 PC斜張橋において、コーベル部のブロ
ックと下部主塔部のブロックの一部を施工し、枠組足場
の盛り替えを行い上段の主塔のブロックと下段横梁を施
工すると同時に主桁柱頭部を構築し、更に主塔側の定着
ブロックとなる上段の主塔まで施工し、主桁柱頭部にワ
ーゲンを組立て主桁の第一斜材ケーブルとなる定着部を
施工し、第一斜材ケーブルを緊張し、主塔と主桁を同時
に施工を繰り返しながら斜材ケーブルを緊張せしめて斜
張橋を構築することを特徴とするPC斜張橋の施工法。
1. In a PC cable-stayed bridge, a part of the block of the corbel part and a block of the lower main tower part are constructed, and the frame scaffolding is re-established to construct the main tower block of the upper stage and the lower horizontal beam at the same time. After constructing the girder pillar head, further constructing up to the upper main tower that will be the anchoring block on the main tower side, assembling the wagon on the main girder pillar head and constructing the anchoring part that will be the first diagonal cable of the main girder, A construction method for a PC cable-stayed bridge, characterized in that the cable-stayed bridge is constructed by tensioning the cable diagonally and simultaneously tensioning the cable diagonally while repeating the construction of the main tower and main girder.
JP15344694A 1994-07-05 1994-07-05 Construction method of PC cable stayed bridge Pending JPH0820910A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15344694A JPH0820910A (en) 1994-07-05 1994-07-05 Construction method of PC cable stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15344694A JPH0820910A (en) 1994-07-05 1994-07-05 Construction method of PC cable stayed bridge

Publications (1)

Publication Number Publication Date
JPH0820910A true JPH0820910A (en) 1996-01-23

Family

ID=15562732

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15344694A Pending JPH0820910A (en) 1994-07-05 1994-07-05 Construction method of PC cable stayed bridge

Country Status (1)

Country Link
JP (1) JPH0820910A (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09296416A (en) * 1996-04-30 1997-11-18 Nippon Steel Corp Construction of cable-stayed frame and its construction method
CN101418542A (en) * 2008-11-21 2009-04-29 上海市政工程设计研究总院 Cable system construction method of spatial self-anchored rope-suspension bridge
CN102900022A (en) * 2012-10-22 2013-01-30 中铁十局集团有限公司 Hydraulic climbing formwork construction method for leaning tower of cable-stayed bridge
CN103103925A (en) * 2013-02-06 2013-05-15 中铁大桥局集团第八工程有限公司 Combined H-shaped steel column bracket
CN103147404A (en) * 2013-04-02 2013-06-12 中铁大桥局股份有限公司 System and method for hanging stay cable at tower end of height limiting cable-stayed bridge
CN103334378A (en) * 2012-11-26 2013-10-02 中铁四局集团第二工程有限公司 Few-circulation sling graded tension construction method of concrete self-anchored suspension bridge
CN103437292A (en) * 2013-08-07 2013-12-11 邢台市政建设集团有限公司 Lifting combination device for bidirectional inclined A-shaped main tower cable-stayed bridge template
CN103741601A (en) * 2013-06-28 2014-04-23 中交第三航务工程局有限公司 Tower, beam and cable synchronous bridge forming technology
CN103835238A (en) * 2014-02-21 2014-06-04 中铁大桥局股份有限公司 High-pier cable-stayed bridge zero-number block non-bracket construction method and structure in construction process
CN104005338A (en) * 2014-05-06 2014-08-27 中铁港航局集团有限公司 Three-directional temporary tower and girder consolidation structure of large-span cable-stayed bridge
CN104109999A (en) * 2014-06-26 2014-10-22 中铁大桥局股份有限公司 Construction method for bridge tower transverse beams
CN104328739A (en) * 2014-10-29 2015-02-04 上海建工集团股份有限公司 Cable-force testing method of lifting rod of tied-arch bridge and construction control method thereof
CN104480863A (en) * 2014-12-12 2015-04-01 上海市基础工程集团有限公司 Method for mounting and positioning steel anchor beams for constructing cable-stayed bridge main tower
CN105887679A (en) * 2016-01-20 2016-08-24 广东省交通规划设计研究院股份有限公司 Space twisting curved surface A type bridge cable tower and construction method thereof
CN106284073A (en) * 2016-08-25 2017-01-04 中铁大桥局集团有限公司 A kind of suspension cable beam-ends hanging cable equipment
CN106480814A (en) * 2016-11-17 2017-03-08 济南轨道交通集团有限公司 A kind of assembled rail transit elevated bridge beam construction method and structure
CN106702896A (en) * 2016-12-01 2017-05-24 中铁大桥局集团有限公司 Prestressed steel strands contained main tower and construction method thereof
CN106884384A (en) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 A kind of mountain area steel-concrete composite beam cable-stayed bridge erection crane method
CN106894328A (en) * 2017-02-20 2017-06-27 重庆大学 A kind of processing method of Π shapes bondbeam Shear Lag
CN110983945A (en) * 2019-12-31 2020-04-10 中铁二院工程集团有限责任公司 Invisible supporting structure of main beam cable-stayed bridge with double branch boxes penetrating through bridge tower
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN112554055A (en) * 2020-10-09 2021-03-26 安徽省交通控股集团有限公司 Cable-stayed bridge cable tower structure system and rapid construction method thereof
CN113123244A (en) * 2021-04-19 2021-07-16 中铁十九局集团第三工程有限公司 Temporary steel box girder consolidation structure
CN116397539A (en) * 2023-04-10 2023-07-07 中国建筑第六工程局有限公司 A Synchronous Construction Method for Tower and Girder of Special-shaped Steel Tower Cable-Stayed Bridge
CN116446259A (en) * 2023-03-31 2023-07-18 浙江数智交院科技股份有限公司 Landscape concrete cable tower of overpass bridge and installation method thereof

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09296416A (en) * 1996-04-30 1997-11-18 Nippon Steel Corp Construction of cable-stayed frame and its construction method
CN101418542A (en) * 2008-11-21 2009-04-29 上海市政工程设计研究总院 Cable system construction method of spatial self-anchored rope-suspension bridge
CN102900022B (en) * 2012-10-22 2015-09-30 中铁十局集团有限公司 Cable stayed bridge leaning tower hydraulic climbing mould construction method
CN102900022A (en) * 2012-10-22 2013-01-30 中铁十局集团有限公司 Hydraulic climbing formwork construction method for leaning tower of cable-stayed bridge
CN103334378A (en) * 2012-11-26 2013-10-02 中铁四局集团第二工程有限公司 Few-circulation sling graded tension construction method of concrete self-anchored suspension bridge
CN103334378B (en) * 2012-11-26 2015-11-18 中铁四局集团第二工程有限公司 The few circulation classification stretch-draw construction method of Self-Anchored Concrete Suspension hoist cable
CN103103925A (en) * 2013-02-06 2013-05-15 中铁大桥局集团第八工程有限公司 Combined H-shaped steel column bracket
CN103147404A (en) * 2013-04-02 2013-06-12 中铁大桥局股份有限公司 System and method for hanging stay cable at tower end of height limiting cable-stayed bridge
CN103741601A (en) * 2013-06-28 2014-04-23 中交第三航务工程局有限公司 Tower, beam and cable synchronous bridge forming technology
CN103437292A (en) * 2013-08-07 2013-12-11 邢台市政建设集团有限公司 Lifting combination device for bidirectional inclined A-shaped main tower cable-stayed bridge template
CN103437292B (en) * 2013-08-07 2016-01-06 邢台市政建设集团股份有限公司 The lifting combination unit of inclined in two-way A shape king-tower cable stayed bridge template
CN103835238A (en) * 2014-02-21 2014-06-04 中铁大桥局股份有限公司 High-pier cable-stayed bridge zero-number block non-bracket construction method and structure in construction process
CN104005338B (en) * 2014-05-06 2016-08-03 中铁港航局集团有限公司 A kind of long-span cablestayed bridges tower beam three-dimensional temporary consolidation structure
CN104005338A (en) * 2014-05-06 2014-08-27 中铁港航局集团有限公司 Three-directional temporary tower and girder consolidation structure of large-span cable-stayed bridge
CN104109999A (en) * 2014-06-26 2014-10-22 中铁大桥局股份有限公司 Construction method for bridge tower transverse beams
CN104109999B (en) * 2014-06-26 2016-08-24 中铁大桥局集团有限公司 The construction method of bridge tower thwart beam
CN104328739A (en) * 2014-10-29 2015-02-04 上海建工集团股份有限公司 Cable-force testing method of lifting rod of tied-arch bridge and construction control method thereof
CN104328739B (en) * 2014-10-29 2016-09-14 上海建工集团股份有限公司 The cable tension test of tied arch bridge hanger rod and construction control method thereof
CN104480863A (en) * 2014-12-12 2015-04-01 上海市基础工程集团有限公司 Method for mounting and positioning steel anchor beams for constructing cable-stayed bridge main tower
CN105887679A (en) * 2016-01-20 2016-08-24 广东省交通规划设计研究院股份有限公司 Space twisting curved surface A type bridge cable tower and construction method thereof
CN106284073A (en) * 2016-08-25 2017-01-04 中铁大桥局集团有限公司 A kind of suspension cable beam-ends hanging cable equipment
CN106480814A (en) * 2016-11-17 2017-03-08 济南轨道交通集团有限公司 A kind of assembled rail transit elevated bridge beam construction method and structure
CN106702896A (en) * 2016-12-01 2017-05-24 中铁大桥局集团有限公司 Prestressed steel strands contained main tower and construction method thereof
CN106894328B (en) * 2017-02-20 2018-11-23 重庆大学 A kind of processing method of Π shape bondbeam Shear Lag
CN106894328A (en) * 2017-02-20 2017-06-27 重庆大学 A kind of processing method of Π shapes bondbeam Shear Lag
CN106884384A (en) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 A kind of mountain area steel-concrete composite beam cable-stayed bridge erection crane method
CN110983945A (en) * 2019-12-31 2020-04-10 中铁二院工程集团有限责任公司 Invisible supporting structure of main beam cable-stayed bridge with double branch boxes penetrating through bridge tower
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN111455855B (en) * 2020-04-16 2021-11-12 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN112554055A (en) * 2020-10-09 2021-03-26 安徽省交通控股集团有限公司 Cable-stayed bridge cable tower structure system and rapid construction method thereof
CN112554055B (en) * 2020-10-09 2022-01-07 安徽省交通控股集团有限公司 Rapid construction method for cable-stayed bridge cable tower structural system
CN113123244A (en) * 2021-04-19 2021-07-16 中铁十九局集团第三工程有限公司 Temporary steel box girder consolidation structure
CN116446259A (en) * 2023-03-31 2023-07-18 浙江数智交院科技股份有限公司 Landscape concrete cable tower of overpass bridge and installation method thereof
CN116397539A (en) * 2023-04-10 2023-07-07 中国建筑第六工程局有限公司 A Synchronous Construction Method for Tower and Girder of Special-shaped Steel Tower Cable-Stayed Bridge

Similar Documents

Publication Publication Date Title
US4352220A (en) Method for the construction of a cable-stayed or rein-girth bridge
CN107882328B (en) Construction method of large-span steel truss suspension structure
JPH11181725A (en) Construction method of horizontal beam of concrete main tower
JPH02503099A (en) Cable supported bridge and construction method
JPH06235208A (en) Method for building upper structure in high structure
JP2003027427A (en) How to build an elevated railway bridge
JPH0633627B2 (en) New construction method on existing facility
CN115595881B (en) Integrated transport and erection construction method for assembled bridge
CN111094100B (en) Truss Track Structures and Rails
US4319374A (en) Method of constructing a stayed girder bridge
JP3378286B2 (en) Construction method of steel roof using out-cable beam beams
JP3326724B2 (en) Construction method of concrete cable-stayed bridge and form support trolley used for it
CN120701140B (en) Method for installing variable-section large cantilever steel structure with swing column
CN217169021U (en) Prefabricated box girder inner box bottom plate tooth block prestress tensioning support
CN117265991B (en) Suspension type monorail cable-stayed bridge combined structure built by pavilion, pier and tower together
JPS5845522B2 (en) How to build a bridge
JPH03293447A (en) Erection of long span construction
JP2613552B2 (en) Precast concrete frame and its construction method
JP2517211B2 (en) Construction method of bridge girder in concrete bridge
JPH102017A (en) Building units and how to build them
SU1317080A1 (en) Metal skeleton of multispan industrial building
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JPH0688309A (en) Method for constructing pc cable stayed bridge
JP2630328B2 (en) String beam roof
JPS634141A (en) Construction of three-dimensional truss structure

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20030506