JPH08218325A - How to repair and regenerate railway bridges - Google Patents
How to repair and regenerate railway bridgesInfo
- Publication number
- JPH08218325A JPH08218325A JP5173895A JP5173895A JPH08218325A JP H08218325 A JPH08218325 A JP H08218325A JP 5173895 A JP5173895 A JP 5173895A JP 5173895 A JP5173895 A JP 5173895A JP H08218325 A JPH08218325 A JP H08218325A
- Authority
- JP
- Japan
- Prior art keywords
- girder
- bridge
- truck
- rail
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
(57)【要約】
【目的】 昼,夜を問わず線路閉鎖を行うことなく、保
線作業を含めた鉄道橋の補修,再生が低コストで行うこ
とができる工法を提供することにある。
【構成】 鉄道橋を補修又は再生するに際し、前記本設
レール2を利用して橋脚1支点間スパン長を有する複数
の桁台車6を橋架1上に誘導設置するとともに、各桁台
車6と各橋脚1間に支持手段10を介設して橋脚1に桁
台車6の荷重を支持せしめ、一方、前記桁台車6群上に
両端が前記本設レール2に接続される仮設レール9,1
3を敷設し、この仮設レール9,13上を通常に列車7
を運行させながら桁台車6と橋脚1間に形成される作業
空間11を利用して橋梁1の補修および/または再生を
行ったのち、前記全ての桁台車6を系外に退去せしめる
ことを特徴とする。
(57) [Summary] [Purpose] It is intended to provide a construction method capable of repairing and rehabilitating a railway bridge including maintenance work at low cost without closing the track both day and night. [Structure] When repairing or rehabilitating a railway bridge, a plurality of girder trucks 6 each having a span length between piers 1 and fulcrums are guided and installed on the bridge 1 using the main rail 2 and each girder truck 6 and A support means 10 is provided between the piers 1 to support the load of the girder truck 6 on the pier 1, while the both ends of the girder truck 6 group are connected to the main rails 2 and 1, respectively.
3 is laid and the train 7 is normally run on the temporary rails 9 and 13.
After operating and repairing and / or regenerating the bridge 1 using the working space 11 formed between the girder truck 6 and the bridge pier 1, all the girder trucks 6 can be moved out of the system. And
Description
【0001】[0001]
【産業上の利用分野】本発明は、鉄道橋の補修,再生方
法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of repairing and rehabilitating a railway bridge.
【0002】[0002]
【従来の技術】従来一般に行われている鉄道橋の補修,
再生の際には、小規模の補修であれば夜間に線路閉鎖し
て実施できる。大規模の補修や老朽化した橋桁の更新等
では昼夜を問わず線路閉鎖し、並設の線路を仮使用して
車両を運行させたり、バイパス的橋架を仮設して車両運
行せざるを得なかった。(例えば、「日本鉄道施設協会
誌」1994年11月号P48〜P53参照)2. Description of the Related Art The repair of railway bridges that has been commonly used in the past,
In the case of rehabilitation, the track can be closed at night for small-scale repairs. For large-scale repairs and replacement of dilapidated girders, the tracks must be closed day and night, and vehicles must be operated by temporarily using parallel tracks or temporary bypass bridges must be operated. It was (For example, refer to "Nippon Railroad Facilities Association" November 1994 issue P48-P53)
【0003】[0003]
【発明が解決しようとする課題】従来の鉄道橋の補修,
再生方法には次のような課題がある。 (a)補修又は再生しようとする鉄道橋の近傍に、別途
橋脚を構築する工事,橋梁の架設工事,軌道の敷設工事
などが要求され、このような仮設橋梁の完成を待って鉄
道橋の各種保線作業を含めた補修又は再生を行うため、
工事そのものが長期にわたる。 (b)仮設橋梁が設置できる立地条件がない場合には鉄
道橋の補修,再生工事を行うことができず、長期の線路
閉鎖を行なうか列車が運行されない断片的夜間作業に頼
らざるを得ず、更に工事が長期化される。 (c)工費が嵩みきわめて不経済であるとともに、仮設
橋梁そのものの信頼性がなく、かつ、列車の運行維持に
制約をうける。[Problems to be solved by the invention] Repair of conventional railway bridges,
The reproduction method has the following problems. (A) Separate construction of bridge piers, bridge erection work, track laying work, etc. are required in the vicinity of the railway bridge to be repaired or rehabilitated. In order to perform repairs or regeneration including track maintenance work,
The construction itself will take a long time. (B) If there is no location condition where a temporary bridge can be installed, repair and rehabilitation work cannot be performed on the railway bridge, and we have no choice but to resort to long-term track closures or fragmentary nighttime work in which the train does not operate. The construction will be prolonged. (C) The construction cost is very high and uneconomical, the temporary bridge itself is not reliable, and the operation of trains is restricted.
【0004】本発明の目的は、昼,夜を問わず線路閉鎖
を行うことなく、保線作業を含めた鉄道橋の補修,再生
が低コストで行うことができる工法を提供することにあ
る。An object of the present invention is to provide a construction method capable of repairing and rehabilitating a railway bridge including maintenance work at low cost without closing the track day and night.
【0005】[0005]
【課題を解決するための手段】従来技術の課題を解決す
る本発明の構成は、適当間隔を介して立設した橋脚上に
本設レールを敷設せる橋梁を架設した鉄道橋を補修又は
再生するに際し、前記本設レールを利用して橋脚支点間
スパン長を有する複数の桁台車を橋架上に誘導設置する
とともに、各桁台車と各橋脚間に支持手段を介設して橋
脚に桁台車の荷重を支持せしめ、一方、前記桁台車群上
に両端が前記本設レールに接続される仮設レールを敷設
し、この仮設レール上を通常に列車を運行させながら桁
台車と橋脚間に形成される作業空間を利用して橋梁の補
修および/または再生を行ったのち、前記全ての桁台車
を系外に退去せしめること、前記仮設レールをあらかじ
め桁台車に敷設しておくこと、適当間隔を介して立設し
た橋脚上に本設レールを敷設せる橋梁を架設した鉄道橋
を再生するに際し、本設レールを利用して前記橋脚支点
間スパン長を有する複数の桁台車を橋梁上に誘導設置す
るとともに、各桁台車を各橋脚間に支持手段を介設して
橋脚に桁台車の荷重を支持せしめ、一方、前記桁台車上
に両端が前記本設レールに接続される更換用の仮設レー
ルを敷設し、この仮設レール上を通常に列車を運行させ
ながら桁台車の下面と橋脚間に形成される作業空間を利
用して橋梁及び本設レールの撤去を行ったのち、各桁台
車を橋脚上に降下設置させ、桁台車をそのまま橋梁とす
るとともに、仮設レールをそのまま新たな本設レールと
すること、及び、前記仮設レール(更換レール)をあら
かじめ桁台車上に敷設しておくものである。The structure of the present invention for solving the problems of the prior art is to repair or rehabilitate a railway bridge having a bridge on which permanent rails can be laid on piers erected at appropriate intervals. At this time, a plurality of girder trucks having span lengths between pier fulcrums are guided and installed on the bridge using the main rail, and a supporting means is provided between each girder truck and each pier to install the girder trucks on the pier. The load is supported, and on the other hand, a temporary rail whose both ends are connected to the main rail is laid on the girder truck group, and is formed between the girder truck and the pier while operating the train normally on this temporary rail. After repairing and / or rehabilitating the bridge using the working space, move all the girders out of the system, lay the temporary rails in advance in the girders, and at appropriate intervals. On the vertically installed bridge pier, When reconstructing a railway bridge with a bridge that can be laid, a plurality of girder trucks with the span length between the pier fulcrums are guided and installed on the bridge using the main rail, and each girder truck is installed between the piers. In order to support the load of the girder trolley on the bridge pier through the support means, on the other hand, a temporary rail for replacement whose both ends are connected to the main rail is laid on the girder trolley, and on this temporary rail is usually While operating the train, the bridge and main rails were removed using the work space formed between the lower surface of the girder trolley and the pier, and then each girder trolley was dropped onto the pier and the girder trolley was left as it was. In addition to the bridge, the temporary rail is used as a new main rail as it is, and the temporary rail (replacement rail) is laid in advance on the girder truck.
【0006】[0006]
【作用】本設レールを敷設した鉄道橋を補修又は再生す
るに際し、本設レールを利用して橋脚支点間スパン長を
有する複数の桁台車を橋梁上に誘導設置及び退去が短時
間で行われ、補修又は再生工事中は列車の通常運行が可
能であるため、保線作業を含む橋梁の補修,再生に対す
る工期上の制約が殆んどなく、大巾な工期の短縮が図れ
る。桁台車がそのまま新橋梁への転用が可能で大巾なコ
ストダウンと更に工期の短縮が図れる。[Operation] When repairing or rehabilitating a railway bridge on which the main rail is laid, a plurality of girder trucks with span lengths between pier fulcrums are installed on the bridge and removed in a short time using the main rail. Since normal train operation is possible during repair or rehabilitation work, there are almost no constraints on the repair or rehabilitation of bridges including track maintenance work, and the construction period can be greatly shortened. The girder dolly can be used as it is for a new bridge, which can greatly reduce costs and shorten the construction period.
【0007】[0007]
【実施例】次に、図面について本発明方法の実施例の詳
細を説明する。図1は補修又は再生しようとする橋梁上
を列車が通常運行されている状態を示す正面図、図2は
橋梁上に桁台車を誘導設置した状態の正面図、図3は桁
台車を支持手段を介して橋脚上に橋架支承させ、橋梁構
造本設レールを撤去し作業空間を形成した状態の正面
図、図4〜図11は鉄道橋の補修,再生手順を示す説明
図である。DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, details of embodiments of the method of the present invention will be described with reference to the drawings. FIG. 1 is a front view showing a state where a train is normally operating on a bridge to be repaired or regenerated, FIG. 2 is a front view showing a state where a girder truck is installed on the bridge, and FIG. 3 is a supporting means for the girder truck. Is a front view of a state in which a work space is formed by supporting the bridge on the pier via the bridge and removing the bridge structure main rail, and FIGS. 4 to 11 are explanatory views showing repair and rehabilitation procedures of the railway bridge.
【0008】図1と図4が対応、図2と図5,図6とが
夫々対応、図3と図7,図8,図9が対応している。次
に、本発明の鉄道橋を構成する橋梁1及び本設レール2
の再生手段について説明する。前記鉄道橋を構成する橋
梁1は、適当間隔を介して立設した橋脚3の支点間スパ
ンに架設した鈑桁4と、この鈑桁4間に本設レール2を
支架した多数の橋桁5などによって構成されている。図
示のものは鈑桁橋であるが本発明は、トラス橋その他で
も適用できる。また、電車の場合には図4にトロリー線
(空中架線)が追加される。図2に示すように、本設レ
ール2を利用して橋脚3の支点間スパン長を有する複数
の桁台車6を、この桁台車6の前後端が橋脚3上に臨む
よう橋梁1上に誘導設置する。この桁台車6の誘導設置
手段としては、図5に示すようにバラの状態にある桁台
車6を1台づつ誘導するか、あるいは、図6に示すよう
に互いに連結した所要数の桁台車6群を誘導設置するも
のである。尚、この桁台車6の上面には、本設レール2
上を走行する列車7の車輪8に対するレール9が設けて
あり、前後部の桁台車6に形成したレール9が、本設レ
ール2と一致するように上がり勾配,下り勾配に形成
し、本設レール2上を走行する列車の車輪8が円滑に本
設レール2からレール9に、又はその逆に移行されるよ
うに構成してある。なお、レール9の形状は図示のごと
く溝レール状として車輪8の踏面が係合するようにして
も、或は、本設レール2と同一の形状のレールとしても
よい。FIGS. 1 and 4 correspond to each other, FIGS. 2 to 5 and 6 correspond to each other, and FIGS. 3 to 7, 8 and 9 correspond to each other. Next, the bridge 1 and the main rail 2 which constitute the railway bridge of the present invention
The reproducing means will be described. The bridge 1 constituting the railway bridge is composed of a plate girder 4 erected on a span between fulcrums of bridge piers 3 erected at appropriate intervals, and a large number of bridge girders 5 having a main rail 2 erected between the plate girders 4 and the like. Has been done. Although the one shown is a girder bridge, the present invention can also be applied to a truss bridge or the like. In the case of a train, a trolley wire (aerial overhead line) is added to FIG. As shown in FIG. 2, a plurality of girder trucks 6 each having a span length between fulcrums of the bridge piers 3 are guided on the bridge 1 using the main rails 2 so that the front and rear ends of the girder trucks 6 face the piers 3. Install. As the guide installation means of the girder truck 6, as shown in FIG. 5, the girder trucks 6 in a loose state are guided one by one, or as shown in FIG. A group is installed by induction. In addition, on the upper surface of the girder truck 6, the main rail 2
Rails 9 for wheels 8 of a train 7 traveling above are provided, and rails 9 formed on the front and rear girder trucks 6 are formed in an upslope and a downslope so as to match the mains installation rail 2, and The wheels 8 of the train running on the rails 2 are configured to be smoothly transferred from the main rails 2 to the rails 9 and vice versa. The shape of the rail 9 may be a grooved rail shape so that the tread surface of the wheel 8 is engaged as shown in the figure, or a rail having the same shape as the main rail 2.
【0009】桁台車6群が橋梁1上及び橋梁1以外の陸
上部に所要長だけ配設されたら、橋脚1上に臨む桁台車
6の下面と橋脚3の上面間に支持構又はジャッキ機能を
もつ支持構10を夫々介設し、桁台車6の荷重を橋脚1
に支持せしめる。桁台車6を橋脚3に支持させたのち、
図3の仮想線部,図7,図8,図9に示すように橋梁1
の一部あるいは全部及び本設レール2を解体撤去するこ
とにより作業空間11が形成される。この解体撤去及び
新たな橋梁や本設レールの構築或は橋梁の補修をするに
当たり、必要に応じて別途足場(図示略)を設置する。
次いで、図10に示すように、前記作業空間11を利用
して橋梁1の更新,補修あるいは本設レール2を更新す
る。この工期中桁台車6に設けた前記レール9を利用し
て列車7の運行維持がなされる。全ての再生工事が終っ
たのち、桁台車6の車輪を新たな本設レール2aに乗
せ、桁台車6を系外に退去処理する。尚、桁台車6の橋
脚1に対する支持及び桁台車6の撤去作業には短時間な
がら列車7の運行が閉鎖されるため、例えば1:00〜
5:00AMの間に行うことが望ましい。When the group of girder trucks 6 is arranged on the bridge 1 and on the land portion other than the bridge 1 for a required length, a supporting structure or a jack function is provided between the lower surface of the girder truck 6 facing the bridge pier 1 and the upper surface of the pier 3. Each supporting structure 10 is installed to support the load of the girder truck 6 on the pier 1.
Support me. After supporting the girder truck 6 on the pier 3,
The phantom line part of FIG. 3 and the bridge 1 as shown in FIG. 7, FIG. 8 and FIG.
A work space 11 is formed by disassembling and removing a part or all of the main rail 2 and the main rail 2. A separate scaffold (not shown) will be installed if necessary for the dismantling and removal, construction of new bridges and permanent rails, or repair of bridges.
Next, as shown in FIG. 10, the working space 11 is used to renew or repair the bridge 1 or renew the main rail 2. The operation of the train 7 is maintained by using the rails 9 provided on the girder truck 6 during the construction period. After all the regeneration work is completed, the wheels of the girder truck 6 are placed on the new main rail 2a, and the girder truck 6 is moved out of the system. In addition, since the operation of the train 7 is closed for a short time for supporting the girder truck 6 on the pier 1 and removing the girder truck 6, for example, 1: 00
It is desirable to do it during 5:00 AM.
【0010】本発明の別の適用法としては図11に示す
ように、前記レール9に代えて何れ本設レールとなる仮
設レール12を敷設しておき、この仮設レール12上を
通常に列車7を運行維持させながら橋桁1,古い本設レ
ール2を解体撤去したのち、支持構10を徐々に解体し
て橋脚1上に桁台車6を降下設置し、この桁台車6群を
そのまま利用して新たな橋梁を構成するとともに、前記
仮設レール12をそのまま新たな本設レールとなし、仮
設レール12端を陸上の既設本設レール2に接続するも
のである。尚、この場合も、桁台車6の橋脚1に対する
支持及び桁台車6の橋脚1上へのて移し替え作業は多少
の時間を要するため、列車7の運行が閉鎖される1:0
0〜5:00AMの時間帯を利用して行うことが望まし
い。As another application method of the present invention, as shown in FIG. 11, instead of the rail 9, a temporary rail 12 which will eventually become a permanent rail is laid, and the train 7 is normally placed on the temporary rail 12. After dismantling and removing the bridge girder 1 and the old main rail 2 while maintaining operation, the support structure 10 is gradually dismantled and the girder truck 6 is set down on the pier 1, and the girder truck 6 group is used as it is. While constructing a new bridge, the temporary rail 12 is used as a new permanent rail as it is, and the end of the temporary rail 12 is connected to the existing permanent rail 2 on land. In this case as well, since the work of supporting the girder truck 6 on the pier 1 and transferring the girder truck 6 onto the pier 1 requires some time, the operation of the train 7 is closed 1: 0
It is desirable to use the time zone of 0 to 5:00 AM.
【0011】[0011]
【発明の効果】上述のように本発明の構成によれば、次
のような効果が得られる。 (a)本設レールを敷設した鉄道橋を補修又は再生する
に際し、本設レールを利用して橋脚支点間スパン長を有
する複数の桁台車を橋梁上に誘導設置及び退去が短時間
で行われ、補修又は再生工事中は列車の通常運行が可能
であるため、保線作業を含む橋梁の補修,再生に対する
工期上の制約が殆んどなく、大巾な工期の短縮が図れ
る。 (b)桁台車がそのまま新橋梁への転用が可能で大巾な
コストダウンと更に工期の短縮が図れる。As described above, according to the structure of the present invention, the following effects can be obtained. (A) When repairing or rehabilitating a railway bridge on which main rails have been laid, a plurality of girder trucks with span lengths between pier fulcrums are installed and removed on the bridge in a short time using main rails. Since normal train operation is possible during repair or rehabilitation work, there are almost no constraints on the repair or rehabilitation of bridges including track maintenance work, and the construction period can be greatly shortened. (B) The girder truck can be used as it is for a new bridge, which can greatly reduce the cost and shorten the construction period.
【図1】補修又は再生しようとする橋架上を列車が通常
運行されている状態を示す正面図である。FIG. 1 is a front view showing a state in which a train is normally operating on a bridge to be repaired or regenerated.
【図2】橋梁上に桁台車を誘導設置した状態の正面図で
ある。FIG. 2 is a front view of a state in which a girder cart is guided and installed on a bridge.
【図3】桁台車を支持手段を介して橋脚上に橋架支承さ
せ、橋梁構造本設レールを撤去し作業空間を形成した状
態の正面図である。FIG. 3 is a front view showing a state in which a working space is formed by supporting a girder cart on a bridge pier via a supporting means and removing a bridge structure main rail.
【図4】鉄道橋の補修,再生手順を示す説明図である。FIG. 4 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図5】鉄道橋の補修,再生手順を示す説明図である。FIG. 5 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図6】鉄道橋の補修,再生手順を示す説明図である。FIG. 6 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図7】鉄道橋の補修,再生手順を示す説明図である。FIG. 7 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図8】鉄道橋の補修,再生手順を示す説明図である。FIG. 8 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図9】鉄道橋の補修,再生手順を示す説明図である。FIG. 9 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図10】鉄道橋の補修,再生手順を示す説明図であ
る。FIG. 10 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
【図11】鉄道橋の補修,再生手順を示す説明図であ
る。FIG. 11 is an explanatory diagram showing a procedure for repairing and regenerating a railway bridge.
1 橋梁 2 本設レール 2a 新たな本設レール 3 橋脚 4 鈑桁 5 橋桁 6 桁台車 7 列車 8 車輪 9 レール 10 支持構 11 作業空間 12 仮設レール 1 Bridge 2 Main rail 2a New main rail 3 Pier 4 Plate girder 5 Bridge girder 6 Girder truck 7 Train 8 Wheel 9 Rail 10 Support structure 11 Working space 12 Temporary rail
Claims (4)
レールを敷設せる橋梁を架設した鉄道橋を補修又は再生
するに際し、前記本設レールを利用して橋脚支点間スパ
ン長を有する複数の桁台車を橋架上に誘導設置するとと
もに、各桁台車と各橋脚間に支持手段を介設して橋脚に
桁台車の荷重を支持せしめ、一方、前記桁台車群上に両
端が前記本設レールに接続される仮設レールを敷設し、
この仮設レール上を通常に列車を運行させながら桁台車
と橋脚間に形成される作業空間を利用して橋梁の補修お
よび/または再生を行ったのち、前記全ての桁台車を系
外に退去せしめることを特徴とする鉄道橋の補修,再生
方法。1. A span length between pier fulcrums is utilized by repairing or regenerating a railway bridge in which a bridge for laying a main rail is erected on piers erected at appropriate intervals, using the main rail. A plurality of girder trucks are installed on the bridge, and a supporting means is provided between each girder truck and each pier to support the load of the girder truck on the pier, while both ends of the girder truck group are connected to the book. Laying a temporary rail connected to the installation rail,
After operating the train on this temporary rail normally, repair and / or regenerate the bridge using the work space formed between the girder truck and the pier, and then move all the girder trucks out of the system. A method of repairing and rehabilitating railway bridges characterized by the following.
設しておくことを特徴とする請求項1記載の鉄道橋の補
修,再生方法。2. The method of repairing and rehabilitating a railway bridge according to claim 1, wherein the temporary rail is laid in advance on a girder truck.
レールを敷設せる橋梁を架設した鉄道橋を再生するに際
し、本設レールを利用して前記橋脚支点間スパン長を有
する複数の桁台車を橋梁上に誘導設置するとともに、各
桁台車を各橋脚間に支持手段を介設して橋脚に桁台車の
荷重を支持せしめ、一方、前記桁台車上に両端が前記本
設レールに接続される更換用の仮設レールを敷設し、こ
の仮設レール上を通常に列車を運行させながら桁台車の
下面と橋脚間に形成される作業空間を利用して橋梁及び
本設レールの撤去を行ったのち、各桁台車を橋脚上に降
下設置させ、桁台車をそのまま橋梁とするとともに、仮
設レールをそのまま新たな本設レールとすることを特徴
とする鉄道橋の再生方法。3. When reconstructing a railway bridge in which a bridge for laying a main rail is erected on piers erected at appropriate intervals, a plurality of span lengths between the pier fulcrums are utilized by using the main rail. The girder trucks are installed on the bridge, and each girder truck is supported by supporting means between the bridge piers to support the load of the girder trucks on the bridge piers. A temporary rail for replacement that will be connected is laid, and while the train is operating normally on this temporary rail, the bridge and main rail are removed using the work space formed between the lower surface of the girder truck and the pier. After that, each girder truck is set down on the pier, the girder truck is used as a bridge as it is, and the temporary rail is used as a new main rail as it is.
じめ桁台車上に敷設しておくことを特徴とする請求項3
記載の鉄道橋の再生方法。4. The temporary rail (replacement rail) is previously laid on the girder truck.
How to regenerate the stated railway bridge.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5173895A JPH08218325A (en) | 1995-02-15 | 1995-02-15 | How to repair and regenerate railway bridges |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5173895A JPH08218325A (en) | 1995-02-15 | 1995-02-15 | How to repair and regenerate railway bridges |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH08218325A true JPH08218325A (en) | 1996-08-27 |
Family
ID=12895252
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP5173895A Pending JPH08218325A (en) | 1995-02-15 | 1995-02-15 | How to repair and regenerate railway bridges |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH08218325A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009052305A (en) * | 2007-08-28 | 2009-03-12 | Kajima Corp | Bridge girder replacement method |
| JP2020153184A (en) * | 2019-03-22 | 2020-09-24 | 株式会社横河ブリッジ | How to replace the existing superstructure |
-
1995
- 1995-02-15 JP JP5173895A patent/JPH08218325A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009052305A (en) * | 2007-08-28 | 2009-03-12 | Kajima Corp | Bridge girder replacement method |
| JP2020153184A (en) * | 2019-03-22 | 2020-09-24 | 株式会社横河ブリッジ | How to replace the existing superstructure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204919230U (en) | Pivot type switch structure | |
| US4542697A (en) | Train for laying a new railroad track | |
| JP3765096B2 (en) | Bridge construction replacement method | |
| JP2019044453A (en) | Replacement method and construction machine | |
| CN112477908B (en) | A bogie with liftable guide wheels, a track beam and a rail transportation system | |
| CN215562009U (en) | Novel turning system with track and turning trolley | |
| JP2021050512A (en) | Bridge replacement method and bridge upper structure | |
| Gesner et al. | Bridge within a bridge | |
| CN115652820B (en) | Construction method of longitudinal shift and closure of double-rotating steel truss bridge above railway station | |
| CN111254762A (en) | A four-wheeled small flatbed truck for pre-assembled switch slip and construction method | |
| CN106677076A (en) | Simple and rapid method and device for mounting box girder at the top of adjacent bent cap by using span pier gantry crane | |
| CN110804958A (en) | A method for changing the frame of a whole-hole beam | |
| CN114875771A (en) | Design and construction method of track-laying base bridge | |
| CN106192761B (en) | A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel | |
| JP3086946B2 (en) | How to rebuild a railway bridge | |
| CN105714691B (en) | A construction method of staggered arrangement of hanging baskets and lateral movement of a curved low-tower cable-stayed bridge | |
| JP2909814B2 (en) | How to update a railway bridge | |
| JPH10338902A (en) | Rail changer for railroad and method of changing rails using the same | |
| CN214882899U (en) | Rail connecting structure on integral cast-in-place frame bridge | |
| JPS5812894Y2 (en) | Assembly bridge for construction site | |
| Hołowaty | Removing weak spots from Polish railways | |
| US3998166A (en) | Multi-rail system and method of installation | |
| JP2673165B2 (en) | Mobile scaffolding equipment for bridges | |
| CN107893376B (en) | Method and device for erecting container type railway overhead longitudinal beam | |
| JP3873101B2 (en) | Equipment for placing slabs |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A02 | Decision of refusal |
Effective date: 20040511 Free format text: JAPANESE INTERMEDIATE CODE: A02 |