JPH08226101A - Construction method for upper subgrade and upper subgrade material - Google Patents
Construction method for upper subgrade and upper subgrade materialInfo
- Publication number
- JPH08226101A JPH08226101A JP5985495A JP5985495A JPH08226101A JP H08226101 A JPH08226101 A JP H08226101A JP 5985495 A JP5985495 A JP 5985495A JP 5985495 A JP5985495 A JP 5985495A JP H08226101 A JPH08226101 A JP H08226101A
- Authority
- JP
- Japan
- Prior art keywords
- cement
- upper layer
- roadbed
- construction
- crushed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 title claims abstract description 40
- 238000010276 construction Methods 0.000 title claims abstract description 39
- 239000004568 cement Substances 0.000 claims abstract description 41
- 239000010426 asphalt Substances 0.000 claims abstract description 24
- 239000002699 waste material Substances 0.000 claims abstract description 20
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 15
- 239000002245 particle Substances 0.000 claims description 18
- 238000002156 mixing Methods 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 7
- 239000000203 mixture Substances 0.000 claims description 4
- 239000000428 dust Substances 0.000 abstract description 6
- 239000006185 dispersion Substances 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 33
- 238000012360 testing method Methods 0.000 description 8
- 239000004575 stone Substances 0.000 description 5
- 239000000843 powder Substances 0.000 description 4
- 239000004576 sand Substances 0.000 description 3
- 230000006641 stabilisation Effects 0.000 description 2
- 238000011105 stabilization Methods 0.000 description 2
- 239000011400 blast furnace cement Substances 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000003995 emulsifying agent Substances 0.000 description 1
- 239000000047 product Substances 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は道路の施工方法および道
路の構成材料に関するものであり、特にアスファルト廃
材等を使用した上層路盤の施工方法および上層路盤材料
に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a road construction method and road constituent materials, and more particularly to a construction method for an upper layer roadbed using waste asphalt and the like and an upper layer roadbed material.
【0002】[0002]
【従来の技術】従来より上層路盤を施工する場合には砕
石等の骨材、セメント、アスファルト乳化剤等を施工現
場で混合し施工するのが通例である。2. Description of the Related Art Conventionally, when constructing an upper layer roadbed, it is customary to mix aggregates such as crushed stone, cement, asphalt emulsifiers, etc. at the construction site.
【0003】[0003]
【発明が解決しようとする課題】ところが、従来の施工
方法では、セメント等のような飛散し易い材料を施工現
場で混合するので、周り一面にもうもうたる粉塵がたち
込め、特に民家や商店等の付近では一種の公害をひき起
こすおそれがあり、また、作業者にとっても作業環境が
劣悪であり、これらの点から、上記上層路盤の施工が非
常にしづらいという問題点があった。上記骨材としてア
スファルト廃材の破砕物を使用して施工する場合も同様
な問題点があり、また強度的にも充分でないので、上層
路盤の厚さを厚くして強度を補うようにしなければなら
ず、従って施工個所の土砂を深く掘り取って除かなけれ
ばならないので、施工コストが高くなるという問題点が
あった。本発明はこのような事情を背景としてなされた
ものであり、本発明の目的は、施工時に粉塵が生ぜず、
かつ路盤の強度を向上させ得るアスファルト廃材を使用
した上層路盤の施工方法および上層路盤材料を提供しよ
うとするものである。本願発明者は、前記問題点を解決
するため種々研究をすすめているうちに、アスファルト
廃材を使用した上層路盤の強度が低いのは、各種材料の
混合が充分でないために、本来の性質が発揮できていな
いことを見い出し、本願発明を想到するに至ったもので
ある。However, in the conventional construction method, a material that easily scatters, such as cement, is mixed at the construction site, so dust is accumulated on the entire surface, especially in private houses and shops. There is a possibility of causing a kind of pollution in the vicinity of, and the working environment is also poor for workers, and from these points, there is a problem that the above-mentioned upper roadbed is very difficult to construct. There are similar problems when using crushed materials of asphalt waste as the above aggregate, and since the strength is also insufficient, it is necessary to increase the thickness of the upper roadbed to supplement the strength. Therefore, since the earth and sand at the construction site must be dug deeply and removed, there is a problem that the construction cost becomes high. The present invention has been made against the background of such circumstances, the object of the present invention, no dust occurs during construction,
Moreover, it is an object of the present invention to provide an upper layer roadbed construction method and an upper layer roadbed material using waste asphalt material that can improve the strength of the roadbed. While the inventors of the present application are conducting various researches to solve the above-mentioned problems, the strength of the upper layer roadbed using waste asphalt is low, because the mixing of various materials is not sufficient, the original property is exhibited. The inventor of the present invention has come to the present invention by discovering that it has not been completed.
【0004】[0004]
【課題を解決するための手段】本発明は、前記目的を達
成するためになされたものであり、本発明は下記のよう
に構成される。 A 粒径が40mm以下のアスファルト廃材の破砕物と
セメントとセメントが飛散しない程度に加えた水とを生
コンプラントで混合してから、該混合物を施工個所に運
搬し、施工するようにした上層路盤の施工方法。 B 前記A項記載の上層路盤の施工方法において、前記
セメントはアスファルト廃材の破砕物に対する重量比が
5〜6%であり、前記水は前記破砕物とセメントとの合
計量に対する重量比が3〜7%である上層路盤の施工方
法。 C 粒径が40mm以下のアスファルト廃材の破砕物
と、セメントとセメントが飛散しない程度の水とを少な
くとも含み、かつこれらを生コンプラントにより混合し
てなる上層路盤材料。 D 前記C項記載の上層路盤材料において、前記セメン
トはアスファルト廃材の破砕物に対する重量比が5〜6
%で、前記水は前記破砕物とセメントとの合計量に対す
る重量比が3〜7%である上層路盤材料。 ここに、「粒径が40mm以下の……破砕物」とは、4
0mm角の篩目から落ちる程度の大きさの破砕物を意味
する。The present invention has been made to achieve the above object, and the present invention is configured as follows. A Upper-layer roadbed for crushing asphalt waste material with a particle size of 40 mm or less, cement, and water added to the extent that cement does not scatter in a ready-mixed plant, and then transporting the mixture to a construction site for construction Construction method. B In the method for constructing an upper layer roadbed according to the item A, the cement has a weight ratio of 5 to 6% to the crushed material of the asphalt waste material, and the water has a weight ratio of 3 to the total amount of the crushed material and the cement. 7% construction method of upper roadbed. C An upper layer roadbed material containing at least a crushed material of asphalt waste material having a particle size of 40 mm or less, and cement and water to the extent that the cement does not scatter, and mixing them in a raw plant. D In the upper layer roadbed material according to the item C, the cement has a weight ratio of the asphalt waste material to the crushed material of 5 to 6
%, The water has a weight ratio of 3 to 7% with respect to the total amount of the crushed material and cement. Here, "crushed material with a particle size of 40 mm or less" means 4
It means a crushed product that is small enough to fall from a 0 mm square sieve mesh.
【0005】[0005]
【実施例】以下本発明の実施例を詳細に説明する。 [実施例1]あらかじめ粒度調整したアスファルト廃材
の破砕物と、破砕物に対する重量比が2%、4%、6%
に相当するセメントと、セメントの粉が飛散しない程度
の水分とを、生コンプラントでよく混合してから、日本
道路協会のアスファルト舗装要綱に基づき、直径10c
mの供試体を締固めて作成した。供試体の個数はセメン
ト添加量2、4、6%ごとに3個、合計9個とした。セ
メントの粉が飛散しない程度の水分量として破砕物とセ
メントの合計量に対して重量比で3〜7%を使用した。
使用セメントの種類は高炉セメントB種(麻生セメント
製)である。EXAMPLES Examples of the present invention will be described in detail below. [Example 1] Crushed material of asphalt waste material whose particle size was adjusted in advance, and the weight ratio to the crushed material was 2%, 4%, 6%
After mixing well the cement which is equivalent to the cement and the water to the extent that the cement powder does not scatter, in the asphalt pavement summary of the Japan Road Association, a diameter of 10c
It was prepared by compacting the test piece of m. The number of test specimens was 3 for each cement addition amount of 2, 4, and 6%, for a total of 9 specimens. A water content of 3 to 7% by weight relative to the total amount of crushed material and cement was used as the amount of water such that the cement powder did not scatter.
The type of cement used is blast furnace cement type B (made by Aso Cement).
【0006】上記供試体を用いて、セメント添加量と圧
縮強さ等の関係を試験した結果を表1に示す。Table 1 shows the results of testing the relationship between the amount of cement added and the compressive strength using the above specimens.
【表1】 表1に基づき、セメント添加量に対する圧縮強さ(一軸
圧縮強さ)をプロットし、線で結べば図1のようにな
る。図1によれば、セメント添加量が5〜6%のときに
は、一軸圧縮強さは28〜32.8(kgf/cm2)となる
が、前記アスファルト舗装要綱によれば、粒度調整砕石
にセメントを加えセメント安定処理をした上層路盤の一
軸圧縮強さは30(kgf/cm2)であるから、本実施例の
上層路盤材料はこれと略同等の強度を有することにな
る。すなわち、本実施例によれば道路用生コンと同等程
度に強度が向上する。[Table 1] Based on Table 1, the compressive strength (uniaxial compressive strength) with respect to the amount of cement added is plotted and connected by a line, as shown in FIG. According to FIG. 1, when the amount of cement added is 5 to 6%, the uniaxial compressive strength is 28 to 32.8 (kgf / cm 2 ). Since the uniaxial compressive strength of the upper layer roadbed subjected to cement stabilization treatment by adding 30 is 30 (kgf / cm 2 ), the upper layer roadbed material of the present example has substantially the same strength. That is, according to this embodiment, the strength is improved to the same extent as that of the ready-mixed concrete for road.
【0007】表層・基層用加熱アスファルト混合物の何
cmに相当するかを示す等値換算係数αは、上層路盤に
おいて粒度調整砕石にセメント安定処理をした場合一軸
圧縮強さ30(kgf/cm2)ではα=0.55(本実施例
の場合もこれと同じ)であるのに対し、粒度調整砕石の
場合ではα=0.35である。施工現場でアスファルト
廃材の破砕物にセメントを混合して上層路盤とする場合
も上記粒度調整砕石の場合と略同じである。従って、そ
の比は0.55/0.35=1.57となる。換言すれ
ば、従来の粒度調整砕石を使用した場合や施工現場でア
スファルト廃材とセメントとを混合調整して使用する場
合に上層路盤の必要な厚さが例えば20cmであるとす
れば、本実施例の上記上層路盤材料を使用すれば20/
1.57=12.7cmの厚さでよいことになる。従っ
て、道路建設のために路面を掘り下げる深さが従来の約
6割(12.7/20=0.64)に減少すると共に、
掘り取って運搬すべき土砂の量も同程度に減少するの
で、道路建設コストを軽減できると共に、工期を短縮で
きる利点がある。また、前記アスファルト舗装要綱によ
れば上層路盤では一層当りの厚さは15cmまでとされ
ているので、前述の例のように従来の路盤で20cm厚
さが必要な場合は、2回に分けて2層で施工しなければ
ならないが、本実施例の場合には、上層路盤の厚さは1
2.7cmあればよいので、一層のみの施工で済み、大
幅なコスト軽減と、工期の短縮を図ることができる。The equivalent conversion factor α, which indicates how many centimeters of the hot asphalt mixture for the surface layer / base layer, corresponds to the uniaxial compressive strength of 30 (kgf / cm 2 ) when the cement stabilization treatment is applied to the crushed stone of the particle size control in the upper layer roadbed. Is α = 0.55 (this is the same in the case of the present embodiment), while α = 0.35 is used in the case of the crushed particle size control. When the cement is mixed with the crushed material of asphalt waste material at the construction site to form the upper layer roadbed, it is almost the same as the case of the above-mentioned crushed stone of particle size adjustment. Therefore, the ratio is 0.55 / 0.35 = 1.57. In other words, if the required thickness of the upper layer roadbed is, for example, 20 cm when using conventional crushed stones with a controlled particle size or when mixing and adjusting asphalt waste materials and cement at the construction site, this embodiment 20 / if using the above-mentioned upper layer roadbed material
A thickness of 1.57 = 12.7 cm will suffice. Therefore, the depth of digging the road surface for road construction is reduced to about 60% (12.7 / 20 = 0.64) of the conventional one, and
Since the amount of earth and sand to be dug and transported is reduced to the same extent, there are advantages that road construction costs can be reduced and construction period can be shortened. According to the asphalt pavement guideline, the upper layer roadbed has a thickness of up to 15 cm per layer, so if the conventional roadbed requires a thickness of 20 cm as in the above example, divide it into two times. Although the construction must be performed in two layers, in the case of this embodiment, the thickness of the upper layer roadbed is 1
Since it only needs to be 2.7 cm, only one layer of construction is required, and the cost can be significantly reduced and the construction period can be shortened.
【0008】[実施例2]実施例1の場合と材料の種
類、配合比および粒度調整が同じもの並びに粒度調整方
法を変えたもの(最大粒径が40mm以下の数種類を設
定かつ粒径組成を変更)をそれぞれ生コンプラントで混
合した上層路盤材料を、道路建設現場に運搬し、常法に
従い上層路盤の施工を行なった。上層路盤材料には、そ
の全量の3〜7%の水分を添加しているので、施工時セ
メントの粉が飛散せず、従って粉塵公害の発生もなく、
また、粉塵の激しかった従来の施工現場の労働環境を改
善することができた。なお、アスファルト廃材の破砕物
は粒径40mm程度のものが混じっていてもよいが、施
工時の作業性の点を考慮すれば最大粒径30mm以下と
することが望ましい。[Embodiment 2] Same as in Embodiment 1 with the same kind of material, blending ratio and particle size adjustment and different particle size adjusting method (several kinds with maximum particle size of 40 mm or less are set and particle size composition is set). The upper layer roadbed materials, which were mixed with each other in the ready-mixed plant, were transported to the road construction site, and the upper layer roadbeds were constructed according to the usual method. Since 3 to 7% of the total amount of water is added to the upper layer roadbed material, the cement powder does not scatter during construction, and therefore dust pollution does not occur.
In addition, it was possible to improve the working environment of the conventional construction site where dust was intense. The crushed asphalt waste may have a particle size of about 40 mm, but the maximum particle size is preferably 30 mm or less in consideration of workability during construction.
【0009】[試験例1]最大粒径25mmのアスファ
ルト廃材の破砕物に重量比で4%のセメントを混合した
上層路盤材料について、突固めによる土の締固め試験
(JIS A1210)を行なった。試験は試験方法:
1.4b、突固め方法:第1方法、モールド内径:10
cmとした。試験結果を表2と図2に示す。含水比9.
0%において最大乾燥密度は2.041g/cm3であ
り、上層路盤として充分な結果が得られた。[Test Example 1] A soil compaction test (JIS A1210) was carried out on the upper layer roadbed material obtained by mixing 4% by weight of cement with a crushed material of asphalt waste having a maximum particle diameter of 25 mm. The test is a test method:
1.4b, tamping method: 1st method, mold inner diameter: 10
cm. The test results are shown in Table 2 and FIG. Moisture content 9.
At 0%, the maximum dry density was 2.041 g / cm 3 , and sufficient results were obtained for the upper layer roadbed.
【表2】 以上本発明のいくつかの実施例について説明したが、本
発明はこのような実施例に何等限定されるものではな
く、本発明の要旨を逸脱しない範囲において種々なる態
様で実施し得ることはもちろんである。[Table 2] Although some embodiments of the present invention have been described above, the present invention is not limited to such embodiments, and it goes without saying that the present invention can be implemented in various modes without departing from the scope of the present invention. Is.
【0010】[0010]
【発明の効果】本発明は上述の通り構成されているの
で、次に記載する効果を奏する。請求項1〜請求項4記
載の上層路盤の施工方法および上層路盤材料によれば、
従来の粒度調整砕石を使用する場合や、施工現場でアス
ファルト廃材の破砕物とセメントとを混合して使用する
場合に比し、強度が約6割増程度に大幅に向上すると共
に、強度上のばらつきを減少させ、信頼性を高めること
ができる。(その原因は生コンプラントによる混合にあ
ると考えられるが、強度向上の程度は当業者の常識をは
るかに超えるものである。) 上層路盤の強度が向上すれば、それに反比例して上層路
盤の厚さを薄くすることができるので、使用する上層路
盤材料が減少すると共に、道路建設現場での掘り下げる
深さ、運搬除去すべき土砂の量も上層路盤の強度に反比
例して減少するので、道路建設コストの大幅な低減と工
期の短縮を図ることができる。また、請求項1〜請求項
4記載の上層路盤の施工方法および上層路盤材料によれ
ば、セメントが飛散しない程度の水分を添加しているの
で、施工時セメントの粉が立ち込めず、粉塵公害の発生
が防止されると共に、施工現場の労働環境が改善され、
ひいては施工時の作業能率の向上を図ることができる。Since the present invention is configured as described above, it has the following effects. According to the construction method of the upper layer roadbed and the upper layer roadbed material according to claims 1 to 4,
Compared to the case of using conventional particle size controlled crushed stone or mixing crushed material of asphalt waste material with cement at the construction site, the strength is significantly improved by about 60% and the variation in strength Can be reduced and reliability can be increased. (It is considered that the cause is mixing by the ready-mixed plant, but the degree of strength improvement is far beyond the common sense of those skilled in the art.) If the strength of the upper layer roadbed is improved, the thickness of the upper layer roadbed will be inversely proportional to it. As the material of the upper roadbed is reduced, the depth to be dug at the road construction site and the amount of earth and sand to be transported and removed are also reduced in inverse proportion to the strength of the upper roadbed. It is possible to significantly reduce the cost and shorten the construction period. Further, according to the method for constructing the upper layer roadbed and the material for the upper layer roadbed according to claims 1 to 4, since water is added to the extent that the cement does not scatter, the cement powder cannot enter during the construction, and dust pollution is avoided. This will prevent the outbreak and improve the working environment at the construction site.
As a result, it is possible to improve work efficiency during construction.
【図1】本発明の実施例における実験結果を示すグラフ
である。FIG. 1 is a graph showing experimental results in an example of the present invention.
【図2】本発明に関する試験結果を示すグラフである。FIG. 2 is a graph showing test results relating to the present invention.
Claims (4)
の破砕物とセメントとセメントが飛散しない程度に加え
た水とを生コンプラントで混合してから、該混合物を施
工個所に運搬し、施工するようにした上層路盤の施工方
法。1. A crushed product of asphalt waste material having a particle size of 40 mm or less, cement and water added to the extent that the cement does not scatter are mixed in a ready-mixed plant, and then the mixture is transported to a construction site for construction. Construction method of the upper roadbed.
いて、前記セメントはアスファルト廃材の破砕物に対す
る重量比が5〜6%であり、前記水は前記破砕物とセメ
ントとの合計量に対する重量比が3〜7%である上層路
盤の施工方法。2. The method for constructing an upper layer roadbed according to claim 1, wherein the cement has a weight ratio of the asphalt waste material to a crushed material of 5 to 6%, and the water has a weight to a total amount of the crushed material and the cement. Construction method for upper roadbed with a ratio of 3 to 7%.
の破砕物と、セメントとセメントが飛散しない程度の水
とを少なくとも含み、かつこれらを生コンプラントによ
り混合してなる上層路盤材料。3. An upper layer roadbed material containing at least a crushed material of asphalt waste material having a particle size of 40 mm or less, cement and water to the extent that the cement does not scatter, and mixing these by a raw concrete plant.
前記セメントはアスファルト廃材の破砕物に対する重量
比が5〜6%で、前記水は前記破砕物とセメントとの合
計量に対する重量比が3〜7%である上層路盤材料。4. The upper layer roadbed material according to claim 3,
An upper layer roadbed material, wherein the cement has a weight ratio of 5 to 6% to the crushed material of asphalt waste, and the water has a weight ratio of 3 to 7% to the total amount of the crushed material and cement.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5985495A JPH08226101A (en) | 1995-02-22 | 1995-02-22 | Construction method for upper subgrade and upper subgrade material |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5985495A JPH08226101A (en) | 1995-02-22 | 1995-02-22 | Construction method for upper subgrade and upper subgrade material |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH08226101A true JPH08226101A (en) | 1996-09-03 |
Family
ID=13125202
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP5985495A Pending JPH08226101A (en) | 1995-02-22 | 1995-02-22 | Construction method for upper subgrade and upper subgrade material |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH08226101A (en) |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5494722A (en) * | 1978-01-10 | 1979-07-26 | Nippon Hodo | Roadbed material |
| JPS6010004A (en) * | 1983-06-28 | 1985-01-19 | 日本道路株式会社 | Room temperature regnerating paving material |
-
1995
- 1995-02-22 JP JP5985495A patent/JPH08226101A/en active Pending
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5494722A (en) * | 1978-01-10 | 1979-07-26 | Nippon Hodo | Roadbed material |
| JPS6010004A (en) * | 1983-06-28 | 1985-01-19 | 日本道路株式会社 | Room temperature regnerating paving material |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US12017963B2 (en) | Flowable compositions and methods of utilizing and producing the same | |
| Buck | Recycled concrete as a source of aggregate | |
| US8080105B2 (en) | Methods of manufacturing and using a flowable cement-based material | |
| JP2011038104A (en) | Chemical agent for improving engineering properties of soil | |
| JPH0813413A (en) | Improvement method for poor subgrade soil | |
| US6439805B1 (en) | Method of stabilizing the ground in road construction work | |
| JP4814643B2 (en) | Cement solidified soil composition | |
| JP2004345885A (en) | Hydraulic composition, ground backfill material using the same, non-high-strength hardened part structural material, and backfill method for excavated ground | |
| JP4054848B2 (en) | Method for producing fluidized soil | |
| JP3372280B2 (en) | Roadbed reinforcement method | |
| DE2163347C3 (en) | Mixed building material for road construction and civil engineering from combustion residues from coal-fired power plants and conventional building materials | |
| JP3288106B2 (en) | Paving material | |
| JP2005015321A (en) | Cement hydration accelerator | |
| JP2003002725A (en) | Construction materials using locally generated rock materials | |
| JP2004108027A (en) | Filler and water retaining pavement | |
| JP2021035900A (en) | CSG and CSG method | |
| US6375736B1 (en) | Structure cellular grout | |
| Widodo et al. | Effectiveness of 2 phase stabilization lime-cement on high plasticity clay | |
| US2323435A (en) | Method of preserving quicklime | |
| JP2001199776A (en) | Binder for porous concrete for greening and cast-in-place porous concrete for greening | |
| JP2003049401A (en) | Roadbed material | |
| JPH0734903B2 (en) | Improved soil for construction work | |
| JP3383289B2 (en) | Subgrade and transportation routes including it | |
| JP2004115999A (en) | Low-strength surface ground improvement method | |
| JP2003010809A (en) | Water barrier layer and method of forming the same |