JPH0835209A - Installation method for large structures - Google Patents
Installation method for large structuresInfo
- Publication number
- JPH0835209A JPH0835209A JP19184894A JP19184894A JPH0835209A JP H0835209 A JPH0835209 A JP H0835209A JP 19184894 A JP19184894 A JP 19184894A JP 19184894 A JP19184894 A JP 19184894A JP H0835209 A JPH0835209 A JP H0835209A
- Authority
- JP
- Japan
- Prior art keywords
- support
- plate
- bearing
- unit
- receiving
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000009434 installation Methods 0.000 title abstract description 7
- 238000004804 winding Methods 0.000 abstract description 8
- 238000010002 mechanical finishing Methods 0.000 abstract description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- Pipeline Systems (AREA)
Abstract
(57)【要約】
【目的】 支承を受板に載せて据え付ける場合に、受板
の設置が簡単にでき、しかも据え付けの際の損傷も防止
できる大型構造物の据付方法を提供すること。
【構成】 ユニット4のラック3の下面に取付ける支承
5にほぼ十字状の突出部5aを形成し、その下面5dを
機械仕上などで平坦に仕上げる。一方、橋脚2上に基準
高さHで受板10を取付ける。クレーンで吊り上げたユ
ニット4の支承5の十字状の下面5dを受板10に載せ
た後、位置決めして据え付ける。これにより、簡単に支
承5を受板10に設置でき、支承5を介して荷重を受板
10に均等に伝達できるとともに、平坦な受板により突
出部5aで受部材10aを損傷することもない。また、
受板10とワインディングパイプ7とのスペースも大き
く、受板10を設置する場合のコンクリートの打設も簡
単にできるようになる。
(57) [Abstract] [Purpose] To provide a method for installing a large structure in which the support plate can be easily installed when the support is mounted on the support plate and the damage during the installation can be prevented. [Structure] A substantially cross-shaped protrusion 5a is formed on a bearing 5 attached to the lower surface of a rack 3 of a unit 4, and the lower surface 5d is finished flat by mechanical finishing or the like. On the other hand, the backing plate 10 is mounted on the pier 2 at the reference height H. After mounting the cross-shaped lower surface 5d of the support 5 of the unit 4 lifted by the crane on the receiving plate 10, it is positioned and installed. As a result, the bearing 5 can be easily installed on the receiving plate 10, the load can be evenly transmitted to the receiving plate 10 through the bearing 5, and the flat receiving plate does not damage the receiving member 10a by the protruding portion 5a. . Also,
The space between the backing plate 10 and the winding pipe 7 is large, so that concrete can be easily placed when the backing plate 10 is installed.
Description
【0001】[0001]
【産業上の利用分野】この発明は、大型構造物の据付方
法に関し、海上や陸上に設置するパイプライン等の大型
構造物に支承を取付けて橋脚などの基礎上に高精度に据
え付け、パイプ同志の溶接ができる程度に据え付けるの
に好適なものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing a large structure, in which a bearing is attached to a large structure such as a pipeline installed on the sea or on land, and the pipe is installed on a foundation such as a pier with high precision. It is suitable for installation to the extent that welding can be performed.
【0002】[0002]
【従来の技術】大型構造物を基礎上に高精度に据え付け
なければならない場合の一つに、海上のシーバースと陸
上タンクとを結ぶパイプラインがある。2. Description of the Related Art One of the cases in which a large structure must be installed on a foundation with high precision is a pipeline connecting a sea berth to a sea tank.
【0003】このパイプライン1は、例えば図2に示す
ように、基礎となる橋脚2をシーバースと陸上との間に
一定の間隔で設置し、これらの橋脚2の間隔に対応した
長さ(支間)ごとに必要なパイプ等をラック3に取付け
てユニット4として予め工場で製作し、各ユニット4を
クレーンで吊り上げて橋脚2,2間にラック3を据え付
け、ユニット4,4同志のパイプを溶接などで接合して
構築するようにしている。As shown in FIG. 2, for example, this pipeline 1 is provided with foundation piers 2 installed at a fixed interval between the seaverse and the land, and has a length (branch) corresponding to the interval between these piers 2. ) Attach the necessary pipes etc. to the rack 3 and make it as a unit 4 in the factory beforehand, hoist each unit 4 with a crane and install the rack 3 between the piers 2 and 2 and weld the pipes of the units 4 and 4 We are trying to build it by joining with.
【0004】このようなパイプライン1における各ユニ
ット4は重量が数10〜400トン程度の大型構造物を
構成しており、これを橋脚2にラック3を据え付けてユ
ニット4,4のパイプ同志を溶接しようとすると、1mm
程度の精度に据え付けなければならない。Each unit 4 in such a pipeline 1 constitutes a large structure having a weight of about 10 to 400 tons, and a rack 3 is installed on the pier 2 to connect the pipes of the units 4 and 4. 1mm when trying to weld
It must be installed with a certain degree of accuracy.
【0005】このため各ユニット4の下面4隅に支承5
を取付けておき、図3に示すように、橋脚2の対応する
部分に受板6及びボルト7を取付け、受板6上に支承5
を載置してナットで締め付けて固定するようにする。For this reason, the bearings 5 are provided at the four corners of the lower surface of each unit 4.
3, the support plate 6 and the bolt 7 are attached to the corresponding portions of the pier 2 as shown in FIG. 3, and the support 5 is supported on the support plate 6.
Place and tighten the nuts to fix it.
【0006】ところが、通常、橋脚2の表面の高さは厳
密に作られていないことから、受板6を橋脚2上に取付
ける場合に測量などを行って基準高さとなるようにする
とともに、図4に示すように、支承5の十字状の突出部
5aと干渉しないように4個の受部材6aに分割して設
置することが行われており、これに対応して支承5の十
字状の突出部5aの周囲の下面5bを機械加工によって
平坦に仕上げておき、クレーンで吊り上げたユニット4
を下ろす場合に、ラック3に取付けた支承5の突出部5
aの周囲の下面5bが受板6の4個の受部材6aに載る
ようにして所定の高さとなるようにしたのち、スライド
ジャッキ等で左右・前後の位置を調整するようにしてい
る。However, since the height of the surface of the pier 2 is not usually made strictly, when the support plate 6 is mounted on the pier 2, surveying is performed so that the height becomes the reference height. As shown in FIG. 4, the bearing 5 is divided into four receiving members 6a so as not to interfere with the cross-shaped protrusion 5a of the support 5, and correspondingly, the support 5 is shaped like a cross. A unit 4 in which a lower surface 5b around the protruding portion 5a is machined to be flat and lifted by a crane.
When lowering, the protrusion 5 of the bearing 5 attached to the rack 3
The lower surface 5b around a is placed on the four receiving members 6a of the receiving plate 6 so as to have a predetermined height, and then the left, right, front and rear positions are adjusted by a slide jack or the like.
【0007】[0007]
【発明が解決しようとする課題】ところが、各ユニット
4をクレーンで吊り上げた状態から橋脚2上に下ろす場
合に、支承5の突出部5aを受板6の各受部材6aに載
せずに、周囲の下面5bを受板6の各受部材6aに載せ
るようにすることが難しく、4個の受部材6aに均等に
支承5を介して荷重を均等に伝達することが出来ず、受
板6の受部材6aを損傷するなどの問題がある。However, when lowering each unit 4 from the state where it is lifted by the crane onto the pier 2, the projection 5a of the support 5 is not placed on each receiving member 6a of the receiving plate 6, It is difficult to place the lower surface 5b of the receiving plate 6 on each receiving member 6a of the receiving plate 6, and the load cannot be evenly transmitted to the four receiving members 6a via the bearings 5, and There is a problem such as damage to the receiving member 6a.
【0008】また、受板6の周囲には、通常ワインディ
ングパイプ8が取付けられてボルト7が埋め込まれる
が、受板6とワインディングパイプ8とのスペースが小
さく、コンクリートを打設して受板を作る場合にも作業
がやりにくいという問題がある。A winding pipe 8 is usually attached around the receiving plate 6 and bolts 7 are embedded therein. However, since the space between the receiving plate 6 and the winding pipe 8 is small, concrete is placed to form the receiving plate. There is also the problem that the work is difficult to do when making it.
【0009】この発明は、かかる従来技術の課題に鑑み
てなされたもので、支承を受板に載せて据え付ける場合
に、受板の設置が簡単にでき、しかも据え付けの際の損
傷も防止できる大型構造物の据付方法を提供しようとす
るものである。The present invention has been made in view of the above problems of the prior art. When the bearing is mounted on the backing plate and installed, the backing plate can be easily installed, and damage during the installation can be prevented. It is intended to provide a method of installing a structure.
【0010】[0010]
【課題を解決するための手段】上記課題を解決するため
この発明の大型構造物の据付方法は、大型構造物を基礎
上に設置するに際し、大型構造物の支持位置にほぼ十字
状の突出部を備えその下面を平坦に仕上げた支承を取付
ける一方、基礎上に前記支承のほぼ十字状の突出部の下
面が載置される受板を基準高さに設置した後、前記大型
構造物の支承の突出部を前記基礎上の受板上に載置して
位置決めして据え付けるようにしたことを特徴とするも
のである。In order to solve the above-mentioned problems, a method for installing a large structure according to the present invention is such that, when a large structure is installed on a foundation, an approximately cross-shaped protrusion is provided at a supporting position of the large structure. While mounting a bearing whose bottom surface is finished to be flat, the bearing plate on which the lower surface of the substantially cross-shaped protrusion of the bearing is placed is installed on the foundation at the reference height, and then the bearing of the large structure is supported. The protrusion is placed on the backing plate on the foundation to be positioned and installed.
【0011】[0011]
【作用】この発明の大型構造物の据付方法によれば、大
型構造物の下面に取付ける支承にほぼ十字状の突出部を
形成し、その下面を機械仕上などで平坦に仕上げるよう
にする一方、橋脚等の基礎上に基準高さで受板を取付け
るようにしておき、クレーン等で吊り上げた大型構造物
の支承の十字状の下面を受板に載せた後、位置決めして
据え付けるようにしており、従来のように、支承の突出
部を受板の間に入れるようにして受板に載せる必要がな
く、簡単に支承を受板に設置することができ、しかも支
承を介して荷重を受板に均等に伝達することができると
ともに、平坦な受板であり、突出部で受板を損傷するこ
ともない。According to the method for installing a large structure of the present invention, a substantially cruciform protrusion is formed on the support attached to the lower surface of the large structure, and the lower surface is finished flat by mechanical finishing or the like. The support plate is mounted on the foundation such as a pier at the standard height, and after placing the cross-shaped lower surface of the support of a large structure lifted by a crane etc. on the support plate, it is positioned and installed. , It is not necessary to put the protruding part of the bearing between the receiving plates and put it on the receiving plate as in the past, and the bearing can be easily installed on the receiving plate, and the load is evenly applied to the receiving plate via the bearing. And the flat receiving plate does not damage the receiving plate at the protrusion.
【0012】また、受板とワインディングパイプとのス
ペースも大きく、受板を設置する場合のコンクリートの
打設も簡単にできるようになる。Further, since the space between the receiving plate and the winding pipe is large, concrete can be easily placed when the receiving plate is installed.
【0013】[0013]
【実施例】以下、この発明の一実施例を図面を参照しな
がら詳細に説明する。図1はこの発明の大型構造物の据
付方法の一実施例にかかる一部分を拡大した工程説明図
である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail below with reference to the drawings. FIG. 1 is an enlarged process explanatory view according to an embodiment of the method for installing a large structure of the present invention.
【0014】この大型構造物の据付方法は、例えば図2
で説明したシーバースと陸上タンクとを結ぶパイプライ
ン1を工場でラック3に取付けてユニット化し、各ユニ
ット4を橋脚2,2間に据え付ける場合などに適用され
るものである。The method of installing this large structure is shown in FIG.
The pipeline 1 that connects the sea berth and the onshore tank described above is attached to a rack 3 at a factory to form a unit, and each unit 4 is installed between the piers 2 and 2.
【0015】この大型構造物の据付方法では、大型構造
物を構成するパイプラインのユニット4のラック3の下
面の4隅が支持位置Aとされ(図2及び図3参照)、こ
のラック3の支持位置Aに支承5が取付けられる。In this method of installing a large structure, the four corners of the lower surface of the rack 3 of the pipeline unit 4 constituting the large structure are set to the support positions A (see FIGS. 2 and 3), and the rack 3 is installed. The support 5 is attached to the support position A.
【0016】この支承5は、図1(a)に正面状態と底
面状態で示すように、鋳物で形成されてラック3の下面
の支持位置Aに図示しないボルトで取付けられており、
支承5の下面には、ほぼ十字状の突出部5aが形成さ
れ、この突出部5aを挾むようにして支持することで、
左右・前後の移動を規制できるようにしてある。As shown in the front view and the bottom view in FIG. 1 (a), the support 5 is made of cast metal and is attached to a supporting position A on the lower surface of the rack 3 by a bolt (not shown).
A substantially cruciform protrusion 5a is formed on the lower surface of the support 5, and by supporting the protrusion 5a so as to sandwich it,
It is designed to be able to regulate movement to the left, right, front and back.
【0017】また、支承5には、据え付け用のボルト7
を挿通するためのボルト孔5cが形成されている。Further, the bearing 5 has a bolt 7 for installation.
Is formed with a bolt hole 5c.
【0018】そして、この支承5を介して基準高さにユ
ニット4のラック3を据え付けるため、鋳物の支承5の
突出部5aの下面5dが機械加工で平坦に仕上げてあ
る。In order to mount the rack 3 of the unit 4 at the reference height through the support 5, the lower surface 5d of the projection 5a of the cast support 5 is machined to be flat.
【0019】一方、このような支承5が4隅の支持位置
Aに取付けられたユニット4が据え付けられる橋脚2の
上面には、図1(b)に断面状態と平面状態で示すよう
に、受板10が基準高さHに調整されて取付けられる。On the other hand, on the upper surface of the pier 2 on which the unit 4 having such bearings 5 mounted at the supporting positions A at the four corners is installed, as shown in a sectional state and a plane state in FIG. The plate 10 is adjusted to the reference height H and attached.
【0020】この受板10は、支承5の突出部5aの下
面5dを載置するためのものであり、ほぼ十字状に鉄板
等の受部材10aを配置して、基準高さHとなるように
コンクリート等で取付けられる。The receiving plate 10 is for mounting the lower surface 5d of the protruding portion 5a of the support 5, and the receiving member 10a such as an iron plate is arranged in a substantially cross shape so that the reference height H is obtained. Can be mounted on concrete, etc.
【0021】したがって、この受板10の受部材10a
は、従来の支承5の十字状の突出部5aの周囲の下面5
bを基準高さに設置するものに比較して突出部5aの高
さ分だけ低い位置が基準高さHとなっており、受板10
の受部材10aが橋脚2の上面から余り突き出さない状
態になっている。Therefore, the receiving member 10a of the receiving plate 10
Is the lower surface 5 around the cross-shaped protrusion 5a of the conventional bearing 5.
The reference height H is at a position lower by the height of the protruding portion 5a than that in which b is installed at the reference height.
The receiving member 10a of No. 2 is in a state of not protruding much from the upper surface of the pier 2.
【0022】この受板10には、ワインディングパイプ
8が4隅に配置され、支承5取付用のボルト7が植え込
まれてコンクリート等で固定されている。Winding pipes 8 are arranged at four corners of the receiving plate 10, and bolts 7 for mounting the bearings 5 are implanted and fixed with concrete or the like.
【0023】このような受板10及びボルト7が取付け
られた橋脚2へのユニット4のラック3の支承5の据付
けは、図1(c)に断面状態を示すように、ユニット4
をクレーン等で吊り上げて橋脚2,2間に移動し、補助
ワイヤ等を連結して誘導しながら降下させ、ユニット4
のラック3の下面の支承5の突出部5aを基礎である橋
脚2に取付けた受板10の受部材10aに載せるように
する。The installation of the support 5 of the rack 3 of the unit 4 on the bridge pier 2 to which the support plate 10 and the bolts 7 are mounted as described above is shown in FIG.
The unit 4 is lifted by a crane or the like and moved between the piers 2 and 2.
The protruding portion 5a of the support 5 on the lower surface of the rack 3 is placed on the receiving member 10a of the receiving plate 10 attached to the pier 2, which is the foundation.
【0024】このとき、橋脚2に取付けてある受板10
の受部材10aが従来のように突き出した状態に設置し
てないので、ユニット4が揺れることがあっても支承5
の突出部5aによって損傷することがなく、簡単に支承
5の突出部5aを十字状の受部材10a上に載置するこ
とができる。At this time, the receiving plate 10 attached to the pier 2
Since the receiving member 10a is not installed in a protruding state as in the conventional case, even if the unit 4 shakes, the support 5
The protrusion 5a of the bearing 5 can be easily placed on the cross-shaped receiving member 10a without being damaged by the protrusion 5a.
【0025】こうして各ユニット4のラック3の4隅の
支承5を橋脚2,2の対応する受板10の受部材10a
上に載置することで上下方向位置を所定の基準高さHに
設置することができる。Thus, the bearings 5 at the four corners of the rack 3 of each unit 4 are received by the receiving members 10a of the corresponding receiving plates 10 of the piers 2 and 2.
By mounting it on the top, the vertical position can be set at a predetermined reference height H.
【0026】こうして橋脚2,2の受板10上に支承5
を介してユニット4を載置した状態にした後、クレーン
でから切り離す。Thus, the bearing 5 is mounted on the receiving plate 10 of the piers 2 and 2.
After placing the unit 4 through the, remove it with a crane.
【0027】この後、スライドジャッキ等でユニット4
の左右・前後の位置を調整し、ラック3に取付けてある
パイプ同志を溶接できる程度の精度、例えば1mm程度の
範囲にして固定する。After that, the unit 4 is attached with a slide jack or the like.
Adjust the left, right, front and rear positions of the pipes, and fix the pipes attached to the rack 3 to an accuracy with which welding can be performed, for example, within a range of about 1 mm.
【0028】こうしてユニット4の上下、左右・前後の
位置決めが完了した後、ボルト7にナットを締付けて固
定するとともに、支承5と受板10との間にコンクリー
ト11などを打設して支承5の突出部5aだけでなく、
支承5の全面を介して橋脚2に荷重を伝達できる状態に
して据え付けが完了する。After the positioning of the unit 4 in the vertical, horizontal and longitudinal directions is completed in this way, the nut is tightened and fixed to the bolt 7, and concrete 11 or the like is placed between the bearing 5 and the support plate 10 to support the bearing 5. Not only the protruding portion 5a of
The installation is completed after the load can be transmitted to the pier 2 through the entire surface of the bearing 5.
【0029】こうしてユニット4が橋脚2,2間に据え
付けられた後、ラック3に取付けてあるパイプを溶接す
ることでパイプライン1が完成する。After the unit 4 is thus installed between the piers 2 and 2, the pipes attached to the rack 3 are welded to complete the pipeline 1.
【0030】このような大型構造物の据付方法によれ
ば、橋脚2に取付ける受け板10を突き出した状態に設
置する必要がなく、支承5の突出部5aによって損傷す
ることもなく、しかも十字状に受部材10aを取付けれ
ば良いので、ワインディングパイプ8と受部材10aと
の間にスペースがあり、コンクリートの打設も簡単に行
うことができる。According to such a method of installing a large structure, it is not necessary to install the receiving plate 10 attached to the pier 2 in a protruding state, and the projecting portion 5a of the support 5 does not damage the receiving plate 10, and the cross shape Since the receiving member 10a may be attached to the space, there is a space between the winding pipe 8 and the receiving member 10a, and concrete can be easily placed.
【0031】なお、上記実施例では、大型構造物として
パイプラインを構成するユニットをあげ、これを橋脚上
に据え付ける場合で説明したが、これに限らず、海上や
陸上の大型構造物を1mm程度の高精度に据え付ける必要
がある場合に適用して有効である。In the above embodiment, the unit that constitutes the pipeline is given as a large structure, and the unit is installed on the pier. However, the structure is not limited to this, and a large structure on the sea or on land is about 1 mm. It is effective to apply when it is necessary to install with high precision.
【0032】[0032]
【発明の効果】以上、一実施例とともに具体的に説明し
たように、この発明の大型構造物の据付方法によれば、
大型構造物の下面に取付ける支承にほぼ十字状の突出部
を形成し、その下面を機械仕上などで平坦に仕上げるよ
うにする一方、橋脚等の基礎上に基準高さで受板を取付
けるようにしておき、クレーン等で吊り上げた大型構造
物の支承の十字状の下面を受板に載せた後、位置決めし
て据え付けるようにしたので、従来のように、支承の突
出部を受板の間に入れいるようにして受板に載せる必要
がなく、簡単に支承を受板に設置することができ、しか
も支承を介して荷重を受板に均等に伝達することができ
るとともに、平坦な受板であり、突出部で受板を損傷す
ることもない。As described above in detail with the embodiment, according to the method for installing a large structure of the present invention,
A cruciform protrusion is formed on the support to be attached to the bottom surface of a large structure, and the bottom surface is made flat by mechanical finishing, etc., while the backing plate is attached to the foundation such as a pier at the standard height. In addition, after placing the cross-shaped lower surface of the support of a large structure that was lifted by a crane etc. on the backing plate, it was positioned and installed, so that the protruding part of the support is inserted between the backing plates as in the past. In this way, it is not necessary to place it on the backing plate, the bearing can be easily installed on the backing plate, and the load can be evenly transmitted to the backing plate through the bearing, and it is a flat backing plate. The receiving plate is not damaged by the protrusion.
【0033】また、受板とワインディングパイプとのス
ペースも大きく、受板を設置する場合のコンクリートの
打設も簡単にできる。Further, since the space between the receiving plate and the winding pipe is large, concrete can be easily placed when the receiving plate is installed.
【図面の簡単な説明】[Brief description of drawings]
【図1】この発明の大型構造物の据付方法の一実施例に
かかる一部分を拡大した工程説明図である。FIG. 1 is an enlarged process explanatory view according to an embodiment of a method for installing a large structure of the present invention.
【図2】この発明の大型構造物の据付方法が適用される
一例のパイプラインのユニットの説明図である。FIG. 2 is an explanatory diagram of an example pipeline unit to which the method for installing a large structure according to the present invention is applied.
【図3】この発明の大型構造物の据付方法が適用される
一例のパイプラインの橋脚の平面ず及び正面図である。FIG. 3 is a plan view and a front view of a pier of an example pipeline to which the method for installing a large structure of the present invention is applied.
【図4】従来のパイプラインのユニットの橋脚への据付
状態の説明図である。FIG. 4 is an explanatory view of a conventional pipeline unit installed on a pier.
1 パイプライン 2 橋脚(基礎) 3 ラック 4 ユニット(大型構造物) 5 支承 5a 突出部 5c ボルト孔 5d 突出部下面 7 ボルト 8 ワインディングパイプ 10 受板 10a 受部材 11 コンクリート A 支持位置 1 Pipeline 2 Bridge Pier (Foundation) 3 Rack 4 Unit (Large Structure) 5 Support 5a Projection 5c Bolt Hole 5d Projection Lower Surface 7 Bolt 8 Winding Pipe 10 Support Plate 10a Support Member 11 Concrete A Support Position
Claims (1)
大型構造物の支持位置にほぼ十字状の突出部を備えその
下面を平坦に仕上げた支承を取付ける一方、基礎上に前
記支承のほぼ十字状の突出部の下面が載置される受板を
基準高さに設置した後、前記大型構造物の支承の突出部
を前記基礎上の受板上に載置して位置決めして据え付け
るようにしたことを特徴とする大型構造物の据付方法。1. When installing a large structure on a foundation,
While mounting a bearing that has a substantially cross-shaped protrusion at the supporting position of a large structure and has its lower surface flattened, a base plate on which the lower surface of the substantially cross-shaped protrusion of the bearing is placed on the foundation A method for installing a large structure, characterized in that, after being installed at a height, a protrusion of a support for the large structure is placed on a backing plate on the foundation, positioned and installed.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19184894A JPH0835209A (en) | 1994-07-22 | 1994-07-22 | Installation method for large structures |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19184894A JPH0835209A (en) | 1994-07-22 | 1994-07-22 | Installation method for large structures |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0835209A true JPH0835209A (en) | 1996-02-06 |
Family
ID=16281520
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19184894A Pending JPH0835209A (en) | 1994-07-22 | 1994-07-22 | Installation method for large structures |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0835209A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100791834B1 (en) * | 2007-03-13 | 2008-01-07 | (주)영광산업개발 | Variable elastic bearing structure according to the load direction of the bridge |
-
1994
- 1994-07-22 JP JP19184894A patent/JPH0835209A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100791834B1 (en) * | 2007-03-13 | 2008-01-07 | (주)영광산업개발 | Variable elastic bearing structure according to the load direction of the bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0835209A (en) | Installation method for large structures | |
| JP3787971B2 (en) | How to install seismic isolation devices | |
| JPS6315415B2 (en) | ||
| JPH1060913A (en) | How to install machinery and equipment | |
| JPH062313A (en) | Level adjustment of bearing part | |
| JP3700096B2 (en) | Seismic isolation device installation method | |
| JPS62298794A (en) | Liner structure of container | |
| JP4120734B2 (en) | Column base structure of steel structure | |
| JP2662362B2 (en) | How to bury underground tanks | |
| JPH086374B2 (en) | Foundation bolt fixing structure | |
| JPH01284617A (en) | Method for constructing base plate | |
| JPH09301700A (en) | Positioning device | |
| JP7049961B2 (en) | How to add equipment mount | |
| JPS6349698Y2 (en) | ||
| JPH07217249A (en) | Fuel pool foundation construction method | |
| JP3017084U (en) | Jig for level adjustment of side form | |
| JP3006503B2 (en) | Installation method of modularized integrated leg unit | |
| JP3433007B2 (en) | Reinforced concrete containment vessel and its construction method | |
| JPH11125007A (en) | Concrete form bearing device | |
| JPH01176900A (en) | How to install a support for a structure | |
| JPH04231517A (en) | Placing of base concrete for silo | |
| JPH0771042A (en) | Method of installing packer plate for equipment installation | |
| JPH07180393A (en) | Anchor frame | |
| JP2761455B2 (en) | ALC external wall panel mounting method on the floor taken out | |
| JPH0444672Y2 (en) |