JPH0835596A - Water retention method for water retention buried pipe - Google Patents

Water retention method for water retention buried pipe

Info

Publication number
JPH0835596A
JPH0835596A JP6174130A JP17413094A JPH0835596A JP H0835596 A JPH0835596 A JP H0835596A JP 6174130 A JP6174130 A JP 6174130A JP 17413094 A JP17413094 A JP 17413094A JP H0835596 A JPH0835596 A JP H0835596A
Authority
JP
Japan
Prior art keywords
water
pipe
buried pipe
ground
blocking material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6174130A
Other languages
Japanese (ja)
Other versions
JP3430300B2 (en
Inventor
Yoji Mori
洋司 森
Katsutoshi Kato
勝利 加藤
Tomoyoshi Nakao
朋由 中尾
Masanori Akita
政則 秋田
Kazuhiro Hosono
一弘 細野
Takayuki Kurobe
高之 黒部
Yasuo Miyazaki
康雄 宮崎
Akira Kamiide
明 神出
Katsuhisa Minami
勝久 南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Gas Co Ltd
Osaka Bousui Construction Co Ltd
Toho Gas Co Ltd
Original Assignee
Osaka Gas Co Ltd
Osaka Bousui Construction Co Ltd
Toho Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Osaka Gas Co Ltd, Osaka Bousui Construction Co Ltd, Toho Gas Co Ltd filed Critical Osaka Gas Co Ltd
Priority to JP17413094A priority Critical patent/JP3430300B2/en
Publication of JPH0835596A publication Critical patent/JPH0835596A/en
Application granted granted Critical
Publication of JP3430300B2 publication Critical patent/JP3430300B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pipe Accessories (AREA)

Abstract

(57)【要約】 【目的】管内が満水状態にある横方向延出の低所管部を
含む水滞留埋設管の止水を施工容易に安定確実に行うこ
とを可能にする。 【構成】満水状態にある低所管部の欠損部において管内
滞留水と止水材との置換を行い、次いで置換された止水
材の地盤内への注入充填を行う。
(57) [Summary] [Purpose] It is possible to easily and stably stop water in a water retention buried pipe including a laterally extending low-place pipe where the pipe is full of water. [Structure] The accumulated water in the pipe is replaced with the water blocking material at the defective portion of the low-place pipe section in a full water state, and then the replaced water blocking material is injected and filled into the ground.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は水滞留埋設管の止水工法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a water stopping method for a water retention buried pipe.

【0002】[0002]

【従来技術とその問題点】地下に埋設された電力管、ガ
ス本管等の既設埋設管においては、老朽化してくるとど
うしても管継手部、腐食孔、亀裂部等から地下水の浸入
が起こり、地下水位より低い管内低所においては満水状
態になることがある。
[Prior art and its problems] In existing buried pipes such as power pipes and gas mains buried underground, groundwater inevitably enters from pipe joints, corrosion holes, cracks, etc. A low water level below the groundwater level may cause full water.

【0003】このような水滞留埋設管の内面に、例えば
各種ライニング工法を適用してライニングを施す場合に
は、前処理工程として管内滞留水の排出、漏水箇所の止
水及び管内クリーニングを行うことが必要になる。
When lining is applied to the inner surface of such a water retention buried pipe, for example, by applying various lining construction methods, drainage of accumulated water in the pipe, stopping of water leakage and cleaning inside the pipe are performed as pretreatment steps. Will be required.

【0004】本出願人は先に、工事対象の水滞留埋設管
の両端に形成された作業口より上記埋設管の全長に亘り
チューブを遊挿し、埋設管とチューブ間の周隙内に管内
滞留水を一時的に収容する第1工程、埋設管とチューブ
間の上記周隙内に止水材を一端から他端に向けて注入充
填することにより、上記周隙内の滞留水の全量を管外に
排出すると共に止水材の一部を管継手部、腐食孔等に注
入充填して止水処理する第2工程、上記止水材の固化後
に、止水材固化層を埋設管内面に残したままでチューブ
を固化層より剥離して回収する第3工程及び、上記固化
層を埋設管内面の錆等の付着物とともに除去し管内クリ
ーニングする第4工程を含む水滞留埋設管の前処理工法
を提案した(例えば特開平3−106479号公報参
照)。
The applicant firstly loosely inserted a tube over the entire length of the above-mentioned buried pipe from the work openings formed at both ends of the water-retained buried pipe to be constructed, and stayed inside the pipe between the buried pipe and the tube. The first step of temporarily containing water is to fill the gap between the buried pipe and the tube with a water-stopping material from one end to the other end so that the total amount of the accumulated water in the gap is piped. The second step of discharging the water to the outside and injecting and filling a part of the water blocking material into the pipe joint portion, the corrosion hole, etc. to perform the water blocking treatment. Pretreatment method for water retention buried pipe, including a third step of peeling and collecting the tube from the solidified layer while leaving it, and a fourth step of removing the solidified layer together with deposits such as rust on the inner surface of the buried pipe and cleaning the inside of the tube (See, for example, Japanese Patent Laid-Open No. 3-106479).

【0005】上記工法によれば、管内滞留水の排出を管
の止水処理作業を利用して、また止水処理後に残る止水
材固化層の除去を管内クリーニング作業を利用してそれ
ぞれ行い得るので、滞留水排出、止水処理及び管内クリ
ーニングを個別に行う場合よりも作業能率を遥かに向上
できるが、チューブの管内挿入並びに管内よりの剥離回
収に手数がかかり、より一層の改善が望まれていた。
According to the above-mentioned construction method, the accumulated water in the pipe can be discharged by using the water-stopping process of the pipe, and the solidified layer of the water-stopping material remaining after the water-stopping process can be removed by using the in-pipe cleaning work. Therefore, the work efficiency can be improved much more than the case where the accumulated water is discharged, the water stoppage treatment and the pipe cleaning are individually performed, but it takes time to insert the pipe into the pipe and recover the peeling from the pipe, and further improvement is desired. Was there.

【0006】本出願人は上記第1発明の問題を解消する
べく、工事対象の水滞留埋設管の両端に形成された作業
口より上記埋設管の全長に亘り通線材を挿通する通線工
程、上記通線工程に引続き上記埋設管内に一端から他端
に向けてホモゲルタイプの止水材を注入充填して行くと
共に、この注入充填につれ上記止水材を介し管内滞留水
を埋設管の他端に向け押出しつつ管外に排出して行く滞
留水排出工程、管内滞留水の排出後、管内充填の止水材
を加圧して該止水材の一部を管内止水個所に注入充填す
る止水工程、及び上記止水材の固化後に、該止水材を上
記通線材に取付けたクリーニング手段の適用により管外
に排出するクリーニング工程、を含む水滞留埋設管の前
処理工法、を提案した(特願昭5−68396号参
照)。
In order to solve the problem of the first invention, the applicant of the present invention has a wire-passing step of inserting a wire rod over the entire length of the buried pipe from work ports formed at both ends of the water retention buried pipe to be constructed, Subsequent to the wire passing step, a homogel-type water blocking material is injected and filled into the buried pipe from one end to the other, and the accumulated water in the pipe is transferred to the buried pipe through the water blocking material as well as the buried pipe. After the accumulated water is discharged to the outside of the pipe while extruding toward the end, the accumulated water in the pipe is discharged, and then the waterproof material for filling the pipe is pressurized to inject and fill a part of the waterproof material in the pipe. A pretreatment method for a water retention buried pipe, including a water-stopping step and a cleaning step in which the water-stopping material is solidified and then discharged outside the pipe by applying a cleaning means attached to the wire. (See Japanese Patent Application No. 5-68396).

【0007】この第2発明によれば、上記第1発明の問
題点を解消し得るが、次の点で尚一層の改良を必要とす
ることが判明した。
According to this second invention, the problems of the first invention can be solved, but it has been found that further improvement is required in the following points.

【0008】(イ)滞水量が多い場合には、止水材が滞
留水により希釈されるため、充分な止水効果が得られな
い場合がある。
(A) When the amount of water staying is large, the water-stopping material is diluted with the accumulated water, so that a sufficient water-stopping effect may not be obtained.

【0009】(ロ)第2発明の実施例に示されているよ
うに管内移動のピグにより管内からの排水を行うように
すれば止水材の希釈の問題はなくなるが、水滞留部分の
両側には多くの場合管曲部があるためにピグの管内移動
が困難になる場合がある。
(B) As shown in the embodiment of the second aspect of the invention, if the pig for moving in the pipe is used for draining water from the inside of the pipe, the problem of dilution of the water blocking material is eliminated, but both sides of the water retention portion are eliminated. In many cases, there is a bend in the pipe, which may make it difficult to move the pig in the pipe.

【0010】本発明は上記第2発明の問題点を一掃する
ことを目的としてなされたものである。
The present invention has been made for the purpose of eliminating the problems of the second invention.

【0011】[0011]

【問題点を解決するための手段】本発明は、管内が実質
的に満水状態にある横方向延出の低所管部を含む水滞留
埋設管の止水工法であって、上記埋設管の両端に作業口
を形成し、該作業口を通じ上記埋設管の全長に亘って通
線材を通線する第1工程、上記埋設管内にテレビカメラ
を設置し、該カメラを上記通線材を利用して低所管部内
を移動することにより管内欠損部の位置確認を行う第2
工程、及び上記第2工程により位置確認された欠損部近
傍の底所管部内に地上からホモゲルタイプの止水材を供
給して行くことにより、欠損部を中心にしてその両側領
域の管内滞留水を上記止水材と実質的に置換して行く第
3工程、とを含み、注入ノズルから上記置換部に供給さ
れる止水材を管内外の圧力差を利用して欠損部を通じ該
欠損部より外側の地盤内に注入充填して行く、ことを特
徴とする水滞留埋設管の止水工法に係る。
DISCLOSURE OF THE INVENTION The present invention is a water stop construction method for a water retention buried pipe including a laterally extending low-place pipe portion in which the inside of the pipe is substantially full, and the both ends of the buried pipe are First step of forming a work opening in the buried pipe, and passing the running wire through the work opening along the entire length of the buried pipe, a television camera is installed in the buried pipe, and the camera is installed using the above-mentioned running wire. The second to confirm the position of the defect in the tube by moving inside the tube.
By supplying a homogel-type water-stopping material from the ground into the bottom pipe part near the defect part confirmed in the step and the above-mentioned second step, the accumulated water in the pipe in both sides of the defect part as a center is supplied. And a third step of substantially replacing the water-stopping material with the water-stopping material, and passing the water-stopping material supplied from the injection nozzle to the replacing portion through the defect portion through the defect portion by utilizing the pressure difference between the inside and the outside of the pipe. The present invention relates to a water stoppage construction method for a water retention buried pipe, which comprises injecting and filling into the ground on the outer side.

【0012】[0012]

【実施例】以下に本発明工法の1実施例を添付図面に基
づき説明すると次の通りである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The following will describe one embodiment of the method of the present invention with reference to the accompanying drawings.

【0013】図1は工事対象の埋設管1の滞水状況を示
し、埋設管1内は欠損部2から浸入した浸入水3により
横方向に延出する低所管部1a並びに該管部1aの両端
に接続する立上り管部1b,1bの途中まで満水状態に
なっている。尚、満水に達していない場合には水を補充
して満水にする。図中、aは地下水位を示している。
FIG. 1 shows a state of water retention in a buried pipe 1 to be constructed. Inside the buried pipe 1, a low-place pipe portion 1a extending laterally by infiltrated water 3 that has infiltrated from a defect portion 2 and the pipe portion 1a. The rising pipe portions 1b, 1b connected to both ends are filled with water halfway. If the water is not full, add water to fill it. In the figure, a indicates the groundwater level.

【0014】図2は本発明工法の第1工程の状況を示し
ている。この第1工程において、水滞留埋設管1の両端
に作業口4,4が形成され、該作業口4,4を通じて埋
設管1の全長に亘り通線材5が挿通される。
FIG. 2 shows the state of the first step of the method of the present invention. In this first step, working ports 4 and 4 are formed at both ends of the water retention buried pipe 1, and the wire 5 is inserted through the working ports 4 and 4 over the entire length of the buried pipe 1.

【0015】図3は上記第1工程に引続き行われる第2
工程の状況を示している。第2工程においては埋設管1
の低所管部1a内にテレビカメラ6が設置され、該カメ
ラ6を上記通線材5を利用して管内移動しつつ管内欠損
部2の位置確認が行われる。管内移動中、上記カメラ6
が欠損部2をとらえると、該カメラ6はその位置で停止
され、カメラの管内引込み長さ並びに地上のモニタテレ
ビ(図示せず)に映し出された映像等をもとにして欠損
部2の位置が割り出され記録される。
FIG. 3 shows a second step that follows the first step.
The process status is shown. Buried pipe 1 in the second step
A television camera 6 is installed in the low-place pipe portion 1a, and the position of the defective portion 2 in the pipe is confirmed while moving the camera 6 in the pipe by using the above-mentioned wire rod 5. The above camera 6 while moving in the pipe
When the defective portion 2 is caught, the camera 6 is stopped at that position, and the position of the defective portion 2 is determined based on the drawing length of the camera in the pipe, the image displayed on the monitor TV (not shown) on the ground, and the like. Is calculated and recorded.

【0016】図4,5は上記第2工程に引続き行なわれ
る第3工程の状況が示されている。第3工程において
は、最初に図4に示すように第2工程で位置確認された
欠損部2の位置まで、先端に注入ノズル7を備えた注入
ホース8が挿入される。注入ホース8の管内挿入は通線
材5の牽引により行われ、該ホース8の挿入長さを測長
機9により計測することにより、注入ノズル7と欠損部
2との位置合せを行うことができる。
4 and 5 show the situation of the third step which is carried out subsequent to the second step. In the third step, first, as shown in FIG. 4, the injection hose 8 having the injection nozzle 7 at the tip is inserted up to the position of the defect portion 2 whose position has been confirmed in the second step. The injection hose 8 is inserted into the pipe by pulling the wire 5. The length of the hose 8 is measured by the length measuring machine 9, so that the injection nozzle 7 and the defective portion 2 can be aligned with each other. .

【0017】注入ノズル7は低所管部1aの管半径方向
に開口する吐出口7aを備えている。
The injection nozzle 7 is provided with a discharge port 7a which opens in the pipe radial direction of the low-place pipe portion 1a.

【0018】注入ノズル7の低所管部1a内への挿入設
置を終えると、図5に示すように埋設管1の両端の作業
口4,4が蓋体10,10により密閉される。
After the insertion and installation of the injection nozzle 7 into the low-place pipe portion 1a is completed, the working ports 4 and 4 at both ends of the buried pipe 1 are sealed by the lids 10 and 10 as shown in FIG.

【0019】図5に示す状態で止水材がその供給部12
からこれに接続する注入ホース8を経てその先端の注入
ノズル7に向けて送られる。
In the state shown in FIG.
Then, it is sent toward the injection nozzle 7 at its tip via the injection hose 8 connected thereto.

【0020】止水材供給部12は主剤ポンプ12aと硬
化剤ポンプ12bとを備え、これらポンプ12a,12
bの作動をして主剤と硬化剤とが所定の割合で混合さ
れ、所定のゲルタイムの止水材が調製される。
The water blocking material supply unit 12 is provided with a main agent pump 12a and a hardening agent pump 12b, and these pumps 12a, 12
By operating b, the main agent and the curing agent are mixed at a predetermined ratio to prepare a water blocking material having a predetermined gel time.

【0021】上記供給部12より注入ホース8を経て注
入ノズル7に送られた止水材は該ノズル7の吐出口7a
より低所管部1a内に欠損部2と略々一致する位置で管
半径方向に向けて吐出されていく。この止水材の管半径
方向への吐出は、吐出された止水材の管軸方向への移動
拡散をできるだけ抑制するためである。
The water-stopping material sent from the supply unit 12 to the injection nozzle 7 through the injection hose 8 is the discharge port 7a of the nozzle 7.
It is discharged in the pipe radial direction at a position in the lower pipe portion 1a which substantially coincides with the defect portion 2. The discharge of the water blocking material in the radial direction of the pipe is for suppressing the movement and diffusion of the discharged water blocking material in the pipe axis direction as much as possible.

【0022】注入ノズル7からの止水材の吐出を継続す
ると、欠損部2を中心に管内の止水材濃度は徐々に上昇
して行きいずれ高濃度となり、この高濃度領域は吐出時
間の経過につれて管軸方向に拡がって行き、いずれ欠損
部2付近の管内滞留水は止水材とほぼ置換される。
When the discharge of the water blocking material from the injection nozzle 7 is continued, the concentration of the water blocking material in the pipe gradually increases around the defective portion 2 and eventually becomes high. In this high concentration region, the discharge time elapses. Along with this, the water spreads in the axial direction of the pipe, and eventually the accumulated water in the pipe in the vicinity of the defect portion 2 is almost replaced with the water blocking material.

【0023】図5に止水材置換部13が概略的に示さ
れ、止水材は欠損部2を中心とする領域が最も高濃度と
なり、これより両側領域は管軸方向に向けて止水材濃度
を漸進的に低下する。
FIG. 5 schematically shows the water-stopping material replacing portion 13, in which the water-stopping material has the highest concentration in the region centered on the defective portion 2, and the water-stopping material in the regions on both sides from this is water-stopping in the axial direction of the pipe. The wood concentration is gradually decreased.

【0024】一方管内への止水材の供給につれて立上り
管部1b,1b内の水位が上昇して行くと共にこの水位
上昇につれて管内気相部14内の空気が圧縮されて行く
ので、この水位上昇と空気圧縮とにより止水材置換部1
3の水圧が上昇し、この水圧上昇は注入ホース8の途中
に備えた圧力計15に表示される。
On the other hand, as the water-stopping material is supplied into the pipes, the water level in the rising pipe portions 1b, 1b rises and the air in the pipe gas phase portion 14 is compressed as the water level rises. And water compression part 1
The water pressure of No. 3 rises, and this water pressure rise is displayed on the pressure gauge 15 provided in the middle of the injection hose 8.

【0025】止水材置換部13の圧力上昇により、欠損
部2より外側の地盤16側との間に圧力差が生じ、この
圧力差は止水材の管内供給を継続するに従い次第に増大
して行く。この圧力差がある程度大きくなると、止水材
の地盤16内への注入充填が自然に開始される。
Due to the increase in the pressure of the waterproof material replacement portion 13, a pressure difference is generated between the defective portion 2 and the ground 16 side, and this pressure difference gradually increases as the supply of the waterproof material in the pipe is continued. go. When this pressure difference becomes large to some extent, the injection and filling of the water blocking material into the ground 16 is naturally started.

【0026】地盤16内への止水材の注入充填は欠損部
2を通じて行なわれ、この注入充填の開始と同時に止水
材置換部13の水圧上昇は実質的に停止し、以後地盤内
で止水材の固化が始まるまでの間は略々一定圧力とな
る。このような置換部13での圧力変化は、上記圧力計
15に表示されるので、地上においても止水材の注入充
填の開始を確認できる。
The filling and filling of the waterproofing material into the ground 16 is carried out through the defective portion 2, and at the same time when the filling and filling is started, the increase in the water pressure of the waterproofing material replacing portion 13 is substantially stopped, and thereafter, it is stopped in the ground. The pressure is almost constant until the water material begins to solidify. Since such a pressure change in the replacement portion 13 is displayed on the pressure gauge 15, it is possible to confirm the start of the injection and filling of the water blocking material even on the ground.

【0027】尚、立上り管部1b,1b内の水位が低い
場合など施工条件によっては、止水材の地盤内への注入
充填に必要な圧力差を得るまでに、管内に相当量の止水
材を供給しなければならないときがある。このような時
は、止水材の供給量更には供給時間の削減を目的とし
て、止水材の管内供給前又は供給中に、蓋体10,10
に備えられている補給口11,11を通じ管内に水及び
/又は空気を補給するようにしてもよい。
Depending on the construction conditions, such as when the water level in the riser pipes 1b, 1b is low, a considerable amount of water still remains in the pipe before the pressure difference required for injecting and filling the water stop material into the ground is obtained. Sometimes it is necessary to supply lumber. In such a case, the lids 10, 10 may be supplied before or during the supply of the waterproof material in the pipe for the purpose of reducing the amount of the waterproof material and further the supply time.
Water and / or air may be replenished into the pipe through replenishment ports 11 and 11 provided in the.

【0028】止水材置換部13への止水材供給ひいては
欠損部2からの地盤16内への止水材注入充填を継続す
ると、いずれ地盤16内で止水材の固化がはじまり、こ
れにより注入充填抵抗ひいては注入充填圧が上昇する。
この注入充填圧の上昇は止水終了を示すシグナルとして
地上に設置の圧力計15に送られ表示されるので、これ
により止水材注入充填の終了を地上で確認できる。
When the water-stopping material is supplied to the water-stopping material replacing portion 13, and further, the water-stopping material is continuously injected and filled from the defect portion 2 into the ground 16, solidification of the water-stopping material begins in the ground 16 at some point. The injection-filling resistance and thus the injection-filling pressure rises.
This rise in the injection and filling pressure is sent to the pressure gauge 15 installed on the ground as a signal indicating the end of the water stoppage and is displayed, so that the end of the waterstopping material injection and filling can be confirmed on the ground.

【0029】本発明において、止水材としては施工条件
にも左右されるが、通常は1〜20分、好ましくは2〜
15分程度のゲルタイムのものが使用される。止水材の
ゲルタイルは主剤と硬化剤との混合比率を変えることに
より自由に調整できる。
In the present invention, the waterproof material is usually 1 to 20 minutes, preferably 2 to, although it depends on the working conditions.
A gel time of about 15 minutes is used. The gel tile of the water blocking material can be freely adjusted by changing the mixing ratio of the main agent and the curing agent.

【0030】低所管部1a内における管内滞留水と止水
剤との置換工程においては、置換さらには地盤内への止
水材注入充填に必要な圧力を得るまでに、ゲルタイムを
超える時間が経過することが考えられるが、この置換工
程においては止水材は管内滞留水によりどうしても多少
は希釈され従ってゲルタイムは遅延されることになるの
で、置換工程中における管内での止水材のゲル化は殆ん
ど生ずる虞れはない。ちなみに置換工程に要する時間は
施工条件などにより異なるが、およそ2〜15分程度で
ある。置換工程に限っていえば、置換工程中だけ、比較
的ゲルタイムの長いもの、例えば15〜30分程度のも
のを用いるようにしてもよい。
In the process of replacing the accumulated water in the pipe in the low-place pipe portion 1a with the waterproofing agent, a time exceeding the gel time elapses until the pressure necessary for the replacement and the filling and filling of the ground with the waterproofing material is obtained. However, in this replacement step, the water blocking material is inevitably diluted to some extent by the accumulated water in the pipe, and the gel time is delayed, so gelation of the water blocking material in the pipe during the replacement step is prevented. There is almost no danger of this occurring. By the way, the time required for the replacement step is about 2 to 15 minutes, although it depends on the construction conditions. As long as the replacement step is limited, it is possible to use one having a relatively long gel time, for example, about 15 to 30 minutes only during the replacement step.

【0031】地盤16内への止水材の注入充填開始後、
止水材が地盤16内で固化を始めるまでの時間は、地盤
16の地質、地下水位の高さなど施工条件によって異な
るが、例えば2〜15分のゲルタイムのものを用いた場
合で、およそ20〜60分程度である。
After the injection and filling of the waterproofing material into the ground 16 is started,
The time until the water blocking material begins to solidify in the ground 16 varies depending on the construction conditions such as the geology of the ground 16 and the height of the groundwater level, but is about 20 when using the gel time of 2 to 15 minutes, for example. It is about 60 minutes.

【0032】地盤16内への止水材注入充填の間は、注
入ノズル7と欠損部2とをむすぶ線上では、次々と新し
い止水材が供給されてくるので止水材の固化は起らず従
って止水材流路13aが確保されるが、この流路13a
の両側では少なくとも高濃度領域13b,3bで止水材
の固化が生ずる。
During the filling of the waterproof material into the ground 16, new waterproof material is supplied one after another on the line joining the injection nozzle 7 and the defective portion 2, so that the solid material does not solidify. Therefore, the water blocking material flow path 13a is secured, but this flow path 13a
On both sides of the water blocking material, solidification of the water blocking material occurs at least in the high concentration regions 13b and 3b.

【0033】地盤16内への止水材の注入充填が継続さ
れている間は、流路13a内の圧力はほぼ安定している
が、地盤13内の止水材充填部17で止水材の固化がは
じまると急激に上昇する。この圧力上昇は注入ノズル7
及び注入ホース8を経て圧力計15に送られるので、こ
れにより止水材の注入充填作業を直ちに終了することが
できる。
While the filling and filling of the waterproofing material into the ground 16 is continued, the pressure in the flow path 13a is almost stable, but the waterproofing material is filled at the waterproofing material filling portion 17 in the ground 13. The temperature rises sharply when the solidification begins. This pressure increase is due to the injection nozzle 7
Also, since it is sent to the pressure gauge 15 via the injection hose 8, the injection and filling operation of the water blocking material can be immediately completed.

【0034】止水材の注入充填作業を終えた後は図7に
示すように、管内クリーニング機17を適用して管内ク
リーニングが行なわれる。管内には止水材残渣が固化物
として残るので、この固化物の除去を容易に行うため、
止水材としては、固化後の強度が小さいホモゲルタイプ
のものが使用される。
After the work of injecting and filling the water blocking material is completed, as shown in FIG. 7, a pipe cleaning machine 17 is applied to perform pipe cleaning. Since the waterproofing material residue remains in the pipe as a solidified product, in order to easily remove this solidified product,
As the water blocking material, a homogel type material having low strength after solidification is used.

【0035】この管内クリーニングにより、次工程で行
なわれる管内ライニング施工に備えることができる。
By this cleaning of the inside of the pipe, it is possible to prepare for the inside lining work to be performed in the next step.

【0036】[0036]

【発明の効果】本発明工法によれば、低所管部の欠損部
の付近で管内滞留水と止水材との置換を行った後に、止
水材を欠損部を通じ地盤内に注入充填するようにしたの
で、地盤内に止水材を高濃度のもとに注入充填すること
ができ、満水状態下での欠損部の止水を施工容易に安定
確実に行うことが可能になる。さらに止水材は管内滞留
水と部分的に置換されるにすぎないので、全体置換する
場合に比較し止水材の消費量を少なくできると共に、施
工後の管内クリーニングが容易になる。
According to the method of the present invention, after the accumulated water in the pipe and the waterproof material are replaced in the vicinity of the defective portion of the low-place pipe portion, the waterproof material is injected and filled into the ground through the defective portion. Therefore, it is possible to inject and fill the water blocking material into the ground at a high concentration, and it is possible to easily and stably carry out water blocking of the defective portion under a full water condition. Further, since the water blocking material is only partially replaced with the accumulated water in the pipe, the consumption amount of the water blocking material can be reduced as compared with the case where the water is completely replaced, and the pipe cleaning after the construction becomes easy.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明工法が適用される埋設管の管内滞水状況
を概略的に示す縦断面図である。
FIG. 1 is a vertical cross-sectional view schematically showing a situation of water retention in a buried pipe to which the method of the present invention is applied.

【図2】本発明工法における通線工程の状況を概略的に
示す縦断面図である。
FIG. 2 is a vertical sectional view schematically showing a situation of a wire passing step in the method of the present invention.

【図3】同、欠損部の位置確認工程の状況を概略的に示
す縦断面図である。
FIG. 3 is a vertical cross-sectional view schematically showing the situation of the position confirmation process of the defective portion.

【図4】同、注入ノズルと欠損部との位置合せ状況を概
略的に示す縦断面図である。
FIG. 4 is a vertical sectional view schematically showing the alignment of the injection nozzle and the defective portion.

【図5】同、管内滞留水と止水材との置換工程の状況を
概略的に示す縦断面図である。
FIG. 5 is a vertical cross-sectional view schematically showing the state of the process of replacing the accumulated water in the pipe with the water blocking material.

【図6】同、止水材の地盤への注入充填工程の状況を概
略的に示す縦断面図である。
FIG. 6 is a vertical cross-sectional view schematically showing the state of the step of injecting and filling the water blocking material into the ground.

【図7】同、管内のクリーニング工程の状況を概略的に
示す縦断面図である。
FIG. 7 is a vertical cross-sectional view schematically showing a situation of a cleaning process in the tube.

【符号の説明】[Explanation of symbols]

1 埋設管 2 欠損部 3 管内滞留水 4 作業口 5 通線材 6 テレビカメラ 7 注入ノズル 8 注入ホース 9 測長機 10 蓋体 11 補供口 12 止水材供給部 13 止水材置換部 14 気相部 15 圧力計 16 地盤 17 止水材注入充填部 18 管内クリーニング機 1 buried pipe 2 missing part 3 stagnant water in pipe 4 working port 5 wire rod 6 TV camera 7 injection nozzle 8 injection hose 9 length measuring machine 10 lid 11 supplementary port 12 water stop material supply part 13 water stop material replacement part 14 air Phase part 15 Pressure gauge 16 Ground 17 Water-stopping material injection filling part 18 Pipe cleaning machine

フロントページの続き (72)発明者 加藤 勝利 大阪府大阪市中央区平野町四丁目1番2号 大阪瓦斯株式会社内 (72)発明者 中尾 朋由 大阪府大阪市中央区平野町四丁目1番2号 大阪瓦斯株式会社内 (72)発明者 秋田 政則 愛知県海部郡甚目寺町下萱津未見取1130 (72)発明者 細野 一弘 愛知県春日井市岩野町118−2 (72)発明者 黒部 高之 愛知県名古屋市天白区天白町平釘住宅8− 85 (72)発明者 宮崎 康雄 大阪府大阪市東成区大今里南2−16−6 (72)発明者 神出 明 大阪府東大阪市西岩田1−10−21 (72)発明者 南 勝久 奈良県奈良市中登美ケ丘1−4162−1−E 30−4Front page continued (72) Inventor Kato Satoru 4-1-2, Hirano-cho, Chuo-ku, Osaka-shi, Osaka Prefecture Osaka Gas Co., Ltd. (72) Tomoyuki Nakao 4--1, Hirano-cho, Chuo-ku, Osaka-shi, Osaka No. 2 Osaka Gas Co., Ltd. (72) Inventor Masanori Akita 1130 Shiomigatsu, Jinmeji-cho, Kaifu-gun, Aichi (72) Inventor Kazuhiro Hosono 118-2, Iwano-cho, Kasugai-shi, Aichi (72) Inventor Takayuki Kurobe Aichi 8-85 (72) Inventor, Yasuo Miyazaki, Tenpaku-cho, Tenpaku-ku, Nagoya-shi, Nagoya, Japan 2-16-6 Oimazari Minami, Higashinari-ku, Osaka-shi, Osaka (72) Akira Kamide 1 Nishi-Iwata, Higashi-Osaka, Osaka −10−21 (72) Inventor Katsuhisa Minami 1-4162-1-E 30-4 Nakatomigigaoka, Nara City, Nara Prefecture

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】管内が実質的に満水状態にある横方向延出
の低所管部を含む水滞留埋設管の止水工法であって、 上記埋設管の両端に作業口を形成し、該作業口を通じ上
記埋設管の全長に亘って通線材を通線する第1工程、 上記埋設管内にテレビカメラを設置し、該カメラを上記
通線材を利用して低所管部内を移動することにより管内
欠損部の位置確認を行う第2工程、及び上記第2工程に
より位置確認された欠損部近傍の底所管部内に地上から
ホモゲルタイプの止水材を供給して行くことにより、欠
損部を中心にしてその両側領域の管内滞留水を上記止水
材と実質的に置換して行く第3工程、とを含み、 注入ノズルから上記置換部に供給される止水材を管内外
の圧力差を利用して、欠損部を通じ該欠損部より外側の
地盤内に注入充填して行く、ことを特徴とする水滞留埋
設管の止水工法。
1. A water-stopping method for a water retention buried pipe including a laterally extending low-place pipe part in which the inside of the pipe is substantially full, wherein work ports are formed at both ends of the buried pipe. First step of passing a wire through the mouth over the entire length of the buried pipe, installing a TV camera in the buried pipe, and moving the camera in the low-place pipe portion using the wire to cause a defect in the pipe. By supplying the homogel-type water stopping material from the ground into the second step of confirming the position of the part and the bottom pipe part near the defect part confirmed in the second step, the defect part is mainly focused. And a third step of substantially replacing the accumulated water in the pipes in both sides thereof with the water blocking material, and utilizing the pressure difference between the inside and outside of the water blocking material supplied from the injection nozzle to the replacement portion. Then, through the deficient portion, fill and inject into the ground outside the deficient portion. Waterproofing construction method of water retention buried pipe, characterized in that.
JP17413094A 1994-07-26 1994-07-26 Water stoppage method for buried water retention pipe Expired - Fee Related JP3430300B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17413094A JP3430300B2 (en) 1994-07-26 1994-07-26 Water stoppage method for buried water retention pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17413094A JP3430300B2 (en) 1994-07-26 1994-07-26 Water stoppage method for buried water retention pipe

Publications (2)

Publication Number Publication Date
JPH0835596A true JPH0835596A (en) 1996-02-06
JP3430300B2 JP3430300B2 (en) 2003-07-28

Family

ID=15973188

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17413094A Expired - Fee Related JP3430300B2 (en) 1994-07-26 1994-07-26 Water stoppage method for buried water retention pipe

Country Status (1)

Country Link
JP (1) JP3430300B2 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5431623A (en) * 1977-08-16 1979-03-08 Osaka Gas Co Ltd Sealing-up of conduit installed
JPS54142621A (en) * 1978-04-28 1979-11-07 Yasushi Nakashin Leakage repair method of pipes laid underground
JPS59147189A (en) * 1983-02-10 1984-08-23 株式会社竹中工務店 Device for repairing leakage of duct and method of repair construction of leakage
JPS6376987A (en) * 1986-09-20 1988-04-07 那須 基仁 Drilling cut-off construction method of leakage section of sewer pipe
JPS63294973A (en) * 1987-01-28 1988-12-01 Three Bond Co Ltd Method for lining underground pipe and water absorptive resin composition for lining pretreatment
JPH01176895A (en) * 1987-12-29 1989-07-13 Kansui Kogyo Kk Method and device for repairing water leaked/water intruded section
JPH03106479A (en) * 1989-09-18 1991-05-07 Osaka Bosui Constr Co Ltd Pretreatment construction method of water stagnation embedded pipe
JPH06281066A (en) * 1993-03-31 1994-10-07 Shinwa Sangyo Kk Coupling device for piping

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5431623A (en) * 1977-08-16 1979-03-08 Osaka Gas Co Ltd Sealing-up of conduit installed
JPS54142621A (en) * 1978-04-28 1979-11-07 Yasushi Nakashin Leakage repair method of pipes laid underground
JPS59147189A (en) * 1983-02-10 1984-08-23 株式会社竹中工務店 Device for repairing leakage of duct and method of repair construction of leakage
JPS6376987A (en) * 1986-09-20 1988-04-07 那須 基仁 Drilling cut-off construction method of leakage section of sewer pipe
JPS63294973A (en) * 1987-01-28 1988-12-01 Three Bond Co Ltd Method for lining underground pipe and water absorptive resin composition for lining pretreatment
JPH01176895A (en) * 1987-12-29 1989-07-13 Kansui Kogyo Kk Method and device for repairing water leaked/water intruded section
JPH03106479A (en) * 1989-09-18 1991-05-07 Osaka Bosui Constr Co Ltd Pretreatment construction method of water stagnation embedded pipe
JPH06281066A (en) * 1993-03-31 1994-10-07 Shinwa Sangyo Kk Coupling device for piping

Also Published As

Publication number Publication date
JP3430300B2 (en) 2003-07-28

Similar Documents

Publication Publication Date Title
KR101359448B1 (en) Entire repairing method for pipe lines with non-excavation
CN113668897B (en) A low-pressure supplementary irrigation treatment method for the leakage of slurry from the communicating cavity at the bottom of the prefabricated shear wall
JP3776831B2 (en) Groundwater level lowering device
KR102014460B1 (en) Diagnosis of the depression amount of the back of the pipeline and filler injection device and diagnosis of the backside depression of the pipeline using the same and filling method
KR101847131B1 (en) Medium and large diameter pipeline inner diameter around the president and grout repair and reinforcement
CN111733823A (en) Grouting pipe burying structure and broken pile processing method in cast-in-situ bored pile pouring process
CN113137081A (en) Deformation joint acrylate grouting plugging construction method
JP3430300B2 (en) Water stoppage method for buried water retention pipe
CN113668776B (en) Filling and repairing method for sleeve grouting defect under condition that slurry outlet channel is bent pipe
CN102330868B (en) Total environmentally-friendly trenchless repairing method
JP6144541B2 (en) Grout reinjection method and cap member
CN109056734A (en) Diaphram wall defect grouting mending construction method
CN114775913A (en) Visual grout supplementing method for sleeve grouting defects
CN111519631B (en) Repairing structure and repairing method of foundation pit support
CN213898998U (en) A kind of anti-void grouting device for secondary lining vault of hydraulic tunnel
JP2520360B2 (en) Pretreatment method for water retention buried pipe
JP4541483B2 (en) Rehabilitation method of miscellaneous drain pipes in apartment houses.
CN116427442A (en) A three-dimensional drainage and rapid plugging method for post-casting belts on basement floors
JP3761983B2 (en) Replacement method for buried pipes
JPH08135032A (en) Construction method of concrete joint water stop hose
JP7824809B2 (en) Watertight method for anchor hole opening
CN113217019B (en) Test method for testing effectiveness of drain pipe of quick-installation water stop
CN115288732A (en) Tunnel defect processing method
CN109488338B (en) Rock crevice anti-seepage method
CN121853811A (en) Negative pressure grouting system for crack plugging and construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees