JPH09158317A - Joint structure of precast concrete beam - Google Patents

Joint structure of precast concrete beam

Info

Publication number
JPH09158317A
JPH09158317A JP32038195A JP32038195A JPH09158317A JP H09158317 A JPH09158317 A JP H09158317A JP 32038195 A JP32038195 A JP 32038195A JP 32038195 A JP32038195 A JP 32038195A JP H09158317 A JPH09158317 A JP H09158317A
Authority
JP
Japan
Prior art keywords
precast concrete
girder
double
beams
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32038195A
Other languages
Japanese (ja)
Inventor
Takao Kijima
隆夫 木島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP32038195A priority Critical patent/JPH09158317A/en
Publication of JPH09158317A publication Critical patent/JPH09158317A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

(57)【要約】 【課題】 プレキャストコンクリート部材による完全な
乾式化施工が行なわれ、工期が短縮され、大梁をダブル
梁化して二重壁化が可能となり、平面計画の自由度が増
大するプレキャストコンクリート柱梁の接合構造を提供
する。 【解決手段】 プレキャストコンクリート柱部材1にお
ける梁取付部から水平の梁取付部片3を一体に突設し、
同各梁取付部片を表裏一双のプレキャストコンクリート
大梁部材5で挟着するとともに、同一双の大梁部材と前
記梁取付部片3とをボルト6、ナット7によって剛結合
し、前記一双のプレキャストコンクリート大梁部材5に
よってダブル化大梁を構成した。
(57) [Abstract] [Problem] Precast concrete construction is carried out by completely dry-type construction, the construction period is shortened, and large beams can be converted into double beams to form double walls, increasing the degree of freedom in plan planning. Provide a joint structure of concrete columns and beams. SOLUTION: A horizontal beam mounting portion piece 3 is integrally projected from a beam mounting portion of a precast concrete pillar member 1,
The respective beam attachment parts are sandwiched between the front and back precast concrete girder members 5, and the same girder members and the beam attachment parts 3 are rigidly connected by bolts 6 and nuts 7. The girder member 5 constitutes a double girder.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明はプレキャストコンク
リート柱梁の接合構造に係るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint structure for precast concrete columns and beams.

【0002】[0002]

【従来の技術】従来のプレキャスト鉄筋コンクリート構
法は、柱ピースaと梁ピースbとの取合仕口部に現場打
ちコンクリートcを打設しなければならず、また大梁は
1本の断面である。(図7参照)
2. Description of the Related Art In the conventional precast reinforced concrete construction method, cast-in-place concrete c must be cast at the joint between the pillar piece a and the beam piece b, and the girder has one cross section. (See Fig. 7)

【0003】[0003]

【発明が解決しようとする課題】前記従来の工法におい
ては前記したように柱、梁ピースの取合仕口部に現場打
ちコンクリート打設の湿式工事が残っており、同打設コ
ンクリートが硬化して所要の強度を発現するまで、相当
の手待ち時間を要する。またプレキャストコンクリート
大梁は、単一部材より構成されているので、二重壁化が
不可能であるなどの問題点があった。
In the above-mentioned conventional construction method, as described above, the wet work of in-place concrete pouring remains at the joint portion of the pillar and beam pieces, and the pouring concrete hardens. It takes a considerable waiting time to develop the required strength. Further, since the precast concrete girder is composed of a single member, there is a problem that it cannot be made into a double wall.

【0004】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とするところは、プレ
キャストコンクリート部材による完全な乾式化施工が行
なわれ、工期が短縮され、大梁をダブル梁化して二重壁
の構築が可能になり、平面計画の自由度が増大するプレ
キャストコンクリート柱梁の接合構造を提供する点にあ
る。
The present invention has been proposed in view of the above-mentioned problems of the prior art. The object of the present invention is to perform a complete dry-type construction using a precast concrete member, shorten the construction period, and double the girder. The point is to provide a joint structure of precast concrete column beams that allows the construction of double walls by constructing beams and increases the degree of freedom in plan planning.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係るプレキャストコンクリート柱梁の接合
構造はプレキャストコンクリート柱部材における梁取付
部から、水平の梁取付部片を一体に突設し、同各梁取付
部片を表裏一双のプレキャストコンクリート大梁部材で
挟着するとともに、同一双の大梁部材と前記梁取付部片
とをボルト及びナットを介して剛結合し、前記一双のプ
レキャストコンクリート大梁部材によってダブル化大梁
を構成してなることを特徴とするものである。
In order to achieve the above-mentioned object, the joint structure of a precast concrete column beam according to the present invention has a horizontal beam mounting piece integrally projecting from a beam mounting portion of a precast concrete column member. The beam mounting parts are sandwiched between front and back precast concrete girder members, and the same girder members and the beam mounting parts are rigidly coupled with each other via bolts and nuts. It is characterized in that a double beam is formed by a large beam member.

【0006】また本発明はプレキャスト柱部材とプレキ
ャストコンクリート大梁部材を、三角形の頂点を占める
位置毎において、ボルト、ナットによって緊結して剛接
合したものである。
Further, according to the present invention, a precast column member and a precast concrete girder member are tightly joined together by bolts and nuts at respective positions occupying the vertices of a triangle.

【0007】[0007]

【発明の実施の形態】以下、本発明の最も良好な実施の
形態を図面について説明する。1はプレキャストコンク
リート柱部材で、柱梁接合部において同柱部材における
各梁部材に対する接合面にボルト取付孔2が貫通された
梁取付部片3が水平方向に突設されている。
BEST MODE FOR CARRYING OUT THE INVENTION The best mode for carrying out the present invention will be described below with reference to the drawings. Reference numeral 1 denotes a precast concrete column member, and a beam attachment portion piece 3 having a bolt attachment hole 2 penetrating through the joint surface of the column-beam joint portion with respect to each beam member in the column-beam joint portion is horizontally projected.

【0008】プレキャストコンクリート柱部材1の梁取
付部片3に設けられた、前記ボルト取付孔2の対応位置
に、夫々ボルト取付孔4が貫通された表裏一対のプレキ
ャストコンクリート大梁部材によって、図2に示すよう
に前記各梁取付部片3を挟着し、同梁取付部片3のボル
ト取付孔2と前記プレキャストコンクリート大梁部材5
のボルト取付孔4とに亘ってボルト6を貫挿してナット
7で緊締し、大梁をダブル化されたプレキャストコンク
リート梁とする。
As shown in FIG. 2, a pair of front and back precast concrete girder members are provided on the beam mounting portion 3 of the precast concrete pillar member 1 at positions corresponding to the bolt mounting holes 2 and through which bolt mounting holes 4 are respectively passed. As shown, the beam mounting pieces 3 are sandwiched, and the bolt mounting holes 2 of the beam mounting pieces 3 and the precast concrete girder member 5 are attached.
The bolt 6 is inserted through the bolt mounting hole 4 and tightened with the nut 7, and the large beam is made into a doubled precast concrete beam.

【0009】この際、柱ピースと梁ピースの取付に際し
ては、三角形の頂点を占める位置毎に前記ボルトも、ナ
ット7による三角形のピン接合として、前記梁取付部片
3とプレキャストコンクリート大梁部材5を剛接合す
る。図中8は上階床を示す。このようにプレキャストコ
ンクリート大梁をダブルプレキャストコンクリート梁と
することによって、建物の区画壁を二重にした専用壁を
設けることができ、同専用区画壁9に、自由に換気、吸
気等の開口10を設けたり、二重壁の中間に設備配管1
1、配線を行なうことができる。
At this time, when the pillar piece and the beam piece are mounted, the bolt mounting portion 3 and the precast concrete girder member 5 are also connected to each other at the positions occupying the apexes of the triangle by using the nut 7 to form the triangular pin connection. Make a rigid joint. In the figure, 8 indicates the upper floor. By thus forming the precast concrete girder as a double precast concrete beam, it is possible to provide a dedicated wall in which the partition wall of the building is doubled, and the dedicated partition wall 9 is provided with openings 10 for ventilation, intake, etc. freely. Install or install equipment pipe 1 in the middle of double wall
1. Wiring can be performed.

【0010】[0010]

【発明の効果】本発明は前記したように、プレキャスト
コンクリート柱部材における梁取付部から、水平の梁取
付部材を一体に突設し、同各梁取付部材を表裏一双のプ
レキャストコンクリート大梁部材で挟着するとともに、
同一双の大梁部材と前記梁取付部材とをボルト、ナット
を介して接合することによって、プレキャストコンクリ
ート柱部材と梁部材との取合仕口部をすべてボルトナッ
トによって取り付ける乾式構造とし、現場打ちコンクリ
ート施工部をなくしたことによって施工を著しく簡略化
し、工期を大幅に短縮しうるとともに、プレキャストコ
ンクリート大梁をダブル梁化し、同ダブル梁によって二
重壁化が可能になり、平面計画の自由度が増大し、二重
壁内を配管、換気設備等の空間に利用でき、またこれら
の設備のメンテナンスが容易に行なわれるとともに、前
記プレキャストコンクリート梁部材がダブル梁化された
ことによって構造性能が増大するものである。
As described above, according to the present invention, a horizontal beam mounting member is integrally projected from a beam mounting portion of a precast concrete column member, and each beam mounting member is sandwiched between front and back precast concrete girder members. As you wear
By joining the same large beam member and the beam mounting member with bolts and nuts, a dry structure in which all the joints of the precast concrete column member and the beam member are attached with bolts and nuts By eliminating the construction section, the construction can be significantly simplified and the construction period can be greatly shortened.In addition, the precast concrete large beam can be made into a double beam, and the double beam can be used as a double wall, increasing the degree of freedom in plan planning. However, the inside of the double wall can be used as a space for piping, ventilation equipment, etc., and the maintenance of these equipment is easily performed, and the structural performance is increased by the double beam of the precast concrete beam member. Is.

【0011】請求項2の発明は、プレキャストコンクリ
ート柱部材とプレキャストコンクリート大梁部材とを接
合するのに当り、三角形の頂点を占める位置毎において
ボルトナットによって緊結したことによって、前記大梁
部材と柱部材とが剛接合されるものである。
According to the second aspect of the present invention, when the precast concrete pillar member and the precast concrete girder member are joined, the girder member and the pillar member are connected by bolt nuts at positions occupying the vertices of a triangle. Are rigidly joined.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るプレキャストコンクリート柱梁の
接合構造の一実施例を示す正面図である。
FIG. 1 is a front view showing an embodiment of a joint structure for precast concrete column beams according to the present invention.

【図2】図1の平面図で、プレキャストコンクリート大
梁部材のプレキャストコンクリート柱部材に対する取付
状態を示す。
FIG. 2 is a plan view of FIG. 1 showing a mounting state of a precast concrete girder member to a precast concrete column member.

【図3】プレキャストコンクリート柱梁の接合直前の状
態を示す正面図である。
FIG. 3 is a front view showing a state immediately before joining the precast concrete column beams.

【図4】プレキャストコンクリート柱梁の接合部を示す
正面図である。
FIG. 4 is a front view showing a joint portion of a precast concrete column beam.

【図5】本発明によってダブル梁化された大梁を有する
構造体の縦断面図である。
FIG. 5 is a vertical cross-sectional view of a structure having a girder double-beamed according to the present invention.

【図6】本発明によって構成された柱梁接合部の斜視図
である。
FIG. 6 is a perspective view of a beam-column joint formed according to the present invention.

【図7】従来構造を示す斜視図である。FIG. 7 is a perspective view showing a conventional structure.

【符号の説明】[Explanation of symbols]

1 プレキャストコンクリート柱部材 2 ボルト取付孔 3 梁取付部片 4 ボルト取付孔 5 プレキャストコンクリート大梁部材 6 ボルト 7 ナット 8 上階床 9 専用区画壁 10 開口 11 設備配管 1 Precast concrete pillar member 2 Bolt mounting hole 3 Beam mounting piece 4 Bolt mounting hole 5 Precast concrete large beam member 6 Bolt 7 Nut 8 Upper floor 9 Exclusive partition wall 10 Opening 11 Facility piping

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 プレキャストコンクリート柱部材におけ
る梁取付部から、水平の梁取付部片を一体に突設し、同
各梁取付部片を表裏一双のプレキャストコンクリート大
梁部材で挟着するとともに、同一双の大梁部材と前記梁
取付部片とをボルト及びナットを介して剛結合し、前記
一双のプレキャストコンクリート大梁部材によってダブ
ル化大梁を構成してなることを特徴とするプレキャスト
コンクリート柱梁の接合構造。
1. A horizontal beam attachment piece is integrally projected from a beam attachment portion of a precast concrete column member, and each beam attachment portion piece is sandwiched between front and back precast concrete large beam members, and the same beam is attached. The joint structure of precast concrete column beams, characterized in that the girder member and the beam mounting portion are rigidly coupled to each other via bolts and nuts, and a double girder is constituted by the pair of precast concrete girder members.
【請求項2】 プレキャスト柱部材とプレキャストコン
クリート大梁部材を、三角形の頂点を占める位置毎にお
いて、ボルト、ナットによって緊結して剛接合してなる
請求項1記載のプレキャストコンクリート柱梁の接合構
造。
2. The precast concrete beam-column joining structure according to claim 1, wherein the precast column member and the precast concrete girder member are rigidly joined together by bolts and nuts at positions occupying the vertices of a triangle.
JP32038195A 1995-12-08 1995-12-08 Joint structure of precast concrete beam Pending JPH09158317A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32038195A JPH09158317A (en) 1995-12-08 1995-12-08 Joint structure of precast concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32038195A JPH09158317A (en) 1995-12-08 1995-12-08 Joint structure of precast concrete beam

Publications (1)

Publication Number Publication Date
JPH09158317A true JPH09158317A (en) 1997-06-17

Family

ID=18120845

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32038195A Pending JPH09158317A (en) 1995-12-08 1995-12-08 Joint structure of precast concrete beam

Country Status (1)

Country Link
JP (1) JPH09158317A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105971116A (en) * 2016-06-29 2016-09-28 中国建筑第七工程局有限公司 Connecting device for precast exterior wall panel and columns
CN109339233A (en) * 2018-11-21 2019-02-15 安徽建筑大学 A connection structure of a concrete frame assembled T-beam-column

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105971116A (en) * 2016-06-29 2016-09-28 中国建筑第七工程局有限公司 Connecting device for precast exterior wall panel and columns
CN105971116B (en) * 2016-06-29 2019-06-07 中国建筑第七工程局有限公司 A kind of prefabricated outer wall panel and column attachment device
CN109339233A (en) * 2018-11-21 2019-02-15 安徽建筑大学 A connection structure of a concrete frame assembled T-beam-column

Similar Documents

Publication Publication Date Title
JPH09158317A (en) Joint structure of precast concrete beam
JP2000234443A (en) Reinforcement structure for existing structures
JP2000273952A (en) Connecting device of structural material for building
JP3045034B2 (en) Structural method of RC building
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH09158318A (en) Precast reinforced concrete beam-column joint structure
JPS6347201Y2 (en)
JP2000212930A (en) Prefabricated caisson joint structure and prefabricated caisson
JPS62178634A (en) Frame construction method for structures
JP2574630Y2 (en) Half PC beam structure
JPH04140366A (en) Preceding erection method of prefabricated column bar and semi-pc girder in pc construction
JP3114024B2 (en) Frame joint structure
JPH11264189A (en) Constructing method of steel-framed and steel reinforced concrete composite building
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JP2699812B2 (en) Industrialized structure of middle- and high-rise houses
JPH11172758A (en) Concrete beam with steel frame for load-bearing wall, steel beam for load-bearing wall and construction method of load-bearing wall and floor using these
JPH1181694A (en) Seismic retrofitting of structures
JP2000110247A (en) Building unit without beam and its construction method
JPH0333336A (en) Structure for column/beam connection
JPH0781322B2 (en) Building unit connection structure
JPH0366852A (en) Construction method of composite structure using precast reinforced concrete columns and steel beams
JPH03187436A (en) Supporting member for construction pillar of reinforced concrete building
JPH0469259B2 (en)
JPH05148899A (en) Method of composite structural building structure