JPH09201747A - Extraction method of delay process - Google Patents
Extraction method of delay processInfo
- Publication number
- JPH09201747A JPH09201747A JP8013493A JP1349396A JPH09201747A JP H09201747 A JPH09201747 A JP H09201747A JP 8013493 A JP8013493 A JP 8013493A JP 1349396 A JP1349396 A JP 1349396A JP H09201747 A JPH09201747 A JP H09201747A
- Authority
- JP
- Japan
- Prior art keywords
- time
- work
- work process
- scheduled
- computer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Multi-Process Working Machines And Systems (AREA)
Abstract
(57)【要約】
【課題】複数の工作機械に割り付けた作業工程の中の遅
延工程を自動的に抽出することができる新規な方法を提
供すること。
【解決手段】各作業工程の開始時刻、現在時刻の進捗状
況、完了時刻(実行状態にある場合は現在時刻)及び作
業完了部品数(実行状態にある場合は現在時刻までの作
業完了部品数)を実績情報として電子計算機に入力して
おき、作業工程を管理する必要が生じた場合は、個々の
作業工程の進捗状況を電子計算機に判定させ、完了状態
にある場合は、完了時刻と完了予定時刻を電子計算機に
比較させて遅延工程を抽出し、かつ、実行状態にある場
合は、現在時刻までの作業完了部品数に基づいて当該工
程の完了見込時刻を電子計算機に算出させるとともに、
当該見込時刻と完了予定時刻を電子計算機に比較させて
遅延工程を抽出する。
(57) [Abstract] [PROBLEMS] To provide a novel method capable of automatically extracting a delay process among work processes assigned to a plurality of machine tools. SOLUTION: The start time of each work process, the progress status at the current time, the completion time (current time if in the execution state), and the work completed part number (the work completion part number up to the current time in the execution state) Is entered in the computer as record information, and when it becomes necessary to manage the work process, the computer determines the progress status of each work process, and when it is in the completed state, the completion time and the scheduled completion Extract the delay process by comparing the time with the electronic computer, and, if in the execution state, with the electronic computer to calculate the expected completion time of the process based on the number of work completed parts up to the current time,
The delay process is extracted by making the computer compare the estimated time and the scheduled completion time.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、数多くの自動工作
機械を使用する生産ラインに適用して好適な遅延工程の
抽出方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of extracting a delay process which is suitable for a production line using many automatic machine tools.
【0002】[0002]
【従来の技術】同一又は異なる機能の複数の自動工作機
械を選択的に使用することによって各種の部品加工(例
えば、プレス、切削、成形、鍛造など)を行なう生産ラ
インでは、計画に対して遅延している作業工程を探し出
して管理する必要がある。この種の管理は、市販のパー
ソナルコンピュータやワークステーションによって構成
した電子計算機システムを用いて行なうことが可能であ
り、既に幾つかの方法が提案されている。その代表例
は、個々の作業工程の計画情報及び実績情報を電子計算
機のディスプレイ上にガントチャートとして表示し、当
該チャートを観察して遅延工程を見付け出す方法であ
る。2. Description of the Related Art In a production line where various parts are machined (for example, press, cutting, forming, forging, etc.) by selectively using a plurality of automatic machine tools having the same or different functions, a delay is caused against a plan. It is necessary to find out and manage the work processes that are being performed. This kind of management can be performed by using an electronic computer system configured by a commercially available personal computer or workstation, and some methods have already been proposed. A typical example thereof is a method in which plan information and actual result information of each work process are displayed as a Gantt chart on a display of an electronic computer, and the chart is observed to find a delay process.
【0003】ガントチャートでは、ディスプレイの時間
軸に沿って延長する複数の矩形時間帯枠の形で個々の作
業工程を表示するのが普通である。時間帯枠の始端は、
作業工程の開始時刻又は開始予定時刻を示しており、か
つ、その終端は、作業工程の完了時刻又は完了予定時刻
を示している。従って、各作業工程について、計画情報
を表わす時間帯枠と実績情報を表わす時間帯枠を作成
し、両者を並べて配置することによって遅延工程を見つ
け出すことが可能となる。In the Gantt chart, it is usual to display individual work processes in the form of a plurality of rectangular time frame frames extending along the time axis of the display. The beginning of the time frame is
The start time or the scheduled start time of the work process is shown, and the end thereof shows the completion time or the scheduled completion time of the work process. Therefore, for each work process, it is possible to find a delay process by creating a time frame representing the plan information and a time frame representing the actual result information and arranging them side by side.
【0004】しかし、数多くの工作機械を使用する生産
ラインでは、ガントチャート上における時間帯枠の数が
非常に多くなるため、視覚による遅延工程の抽出が困難
になることが多い。しかも、完了状態にある作業工程の
場合は、その工程が遅延しているか否かの判別が可能で
あるが、実行状態にある作業工程の場合は、この種の判
別が困難である点でも問題がある。However, in a production line using a large number of machine tools, the number of time frame on the Gantt chart is very large, and it is often difficult to visually detect the delay process. Moreover, in the case of a work process in the completed state, it is possible to determine whether or not the process is delayed, but in the case of a work process in the execution state, this type of determination is difficult. There is.
【0005】[0005]
【発明が解決しようとする課題】本発明の目的は、従来
技術の前記問題点を解消し、遅延工程を自動的に抽出す
ることができる新規な方法を提供することにある。SUMMARY OF THE INVENTION An object of the present invention is to solve the above problems of the prior art and to provide a novel method capable of automatically extracting a delay step.
【0006】[0006]
【課題を解決するための手段】前記課題を解決するた
め、本発明にあっては、各作業工程の開始予定時刻、完
了予定時刻及び作業予定部品数を計画情報として電子計
算機に予め登録しておくとともに、各作業工程の開始時
刻、現在時刻における進捗状況、完了時刻(その作業工
程が実行状態にある場合は現在時刻)及び作業完了部品
数(その作業工程が実行状態にある場合は現在時刻まで
の作業完了部品数)を実績情報として電子計算機に入力
する。そして、作業工程を管理する必要が生じたときに
は、当該実績情報に基づいて各作業工程の進捗状況を電
子計算機に判定させ、いずれかの作業工程が完了状態に
ある場合は、その作業工程の完了時刻と完了予定時刻を
電子計算機に比較させて遅延工程を抽出し、一方、いず
れかの作業工程が実行状態にある場合は、現在時刻まで
の作業完了部品数に基づいて当該工程の完了見込時刻を
電子計算機に算出させ、かつ、当該見込時刻とその作業
工程の完了予定時刻を電子計算機に比較させることによ
って遅延工程を抽出する。実績情報は、生産ラインの作
業者が個別に収集した結果を利用することもできるが、
個々の工作機械に所定のセンサを配設した場合は、必要
な実績情報を自動的に収集して電子計算機に入力するこ
とができて好都合である。In order to solve the above problems, according to the present invention, a scheduled start time, a scheduled completion time and a scheduled work number of each work process are registered in advance in a computer as plan information. In addition, the start time of each work process, the progress status at the current time, the completion time (current time when the work process is in the execution state), and the work completed part number (the current time when the work process is in the execution state) The number of completed parts up to) is input to the computer as performance information. Then, when it becomes necessary to manage the work process, the computer is made to judge the progress status of each work process based on the record information, and when any work process is in the completed state, the work process is completed. The delay process is extracted by comparing the time and the scheduled completion time with an electronic computer. On the other hand, if any work process is in the execution state, the expected completion time of the process based on the number of work completed parts up to the current time. Is calculated by the electronic computer, and the delay process is extracted by making the electronic computer compare the estimated time and the scheduled completion time of the work process. For the actual information, the results collected individually by the workers on the production line can be used,
When a predetermined sensor is provided on each machine tool, it is convenient because necessary performance information can be automatically collected and input to the electronic computer.
【0007】[0007]
【発明の実施の形態】抽出した遅延工程の識別は、ガン
トチャート上における該当の時間帯枠の配色を他の時間
帯枠と変えることによって容易に行なうことができるほ
か、遅延工程の一覧表をディスプレイに描画するか、プ
リンタ等によって印字出力することによっても容易に行
なうことができる。以下、本発明に係る遅延工程の抽出
方法を図面に示した実施例を参照して更に詳細に説明す
る。BEST MODE FOR CARRYING OUT THE INVENTION The identification of the extracted delay process can be easily performed by changing the color scheme of the relevant time frame on the Gantt chart to another time frame, and a list of the delay processes can be displayed. It can be easily performed by drawing on a display or printing out by a printer or the like. Hereinafter, a method of extracting a delay process according to the present invention will be described in more detail with reference to the embodiments shown in the drawings.
【0008】[0008]
【実施例】本実施例において使用した電子計算機システ
ムの一例を図1に示す。本システムのハードウェア構成
それ自体は既に公知であり、市販のパーソナルコンピュ
ータ、ワークステーション等を用いて構成することがで
きる。電子計算機のディスク装置4には、作業工程計画
テーブル5(以下単に「計画テーブル」という)及び作
業工程実績テーブル6(以下単に「実績テーブル」とい
う)が登録されている。中央処理装置1は、同装置のメ
モリ2に格納されている作業工程管理プログラム3の制
御のもとで動作し、計画テーブル5及び実績テーブル6
を読み出して必要な演算処理を行なった後、その結果を
ディスプレイ7上にガントチャートとして表示する。EXAMPLE FIG. 1 shows an example of an electronic computer system used in this example. The hardware configuration itself of this system is already known and can be configured using a commercially available personal computer, workstation, or the like. A work process planning table 5 (hereinafter simply referred to as “planning table”) and a work process actual result table 6 (hereinafter simply referred to as “actual result table”) are registered in the disk device 4 of the electronic computer. The central processing unit 1 operates under the control of the work process management program 3 stored in the memory 2 of the same device, and has a plan table 5 and a performance table 6
Is read out and necessary arithmetic processing is performed, and the result is displayed on the display 7 as a Gantt chart.
【0009】計画テーブルの一例を図2に示す。テーブ
ルの各行には、各作業工程について予め設定された計画
がエントリされており、例えば第1行は、工作機械BP
−1により、1995年4月1日9時から同日の11時
までの時間帯に、2個の部品P−MR−101に対して
穴あけ加工を行なう計画であることを示す。計画テーブ
ルの編集(必要なデータの入力等)は、管理者がマウス
やキーボードを用いて行なうことが可能である。An example of the plan table is shown in FIG. A preset plan for each work process is entered in each row of the table. For example, the first row indicates the machine tool BP.
-1 indicates that there is a plan to perform drilling on the two parts P-MR-101 in the time zone from 9:00 on April 1, 1995 to 11:00 on the same day. The administrator can edit the plan table (input required data, etc.) using a mouse or a keyboard.
【0010】実績テーブルの一例を図3に示す。テーブ
ル第1列の「進捗状況」欄は、現在時刻における各作業
工程の進捗状況を記録するための欄であり、現在時刻に
おいて完了状態にある場合は例えば記号“1”を入力
し、現在時刻において実行状態にある場合は例えば記号
“3”を入力する。第5列の「開始時刻」欄には、各作
業工程の実際の開始時刻を入力する。第6列の「完了時
刻」欄には、各作業工程の実際の完了時刻(実行状態に
ある作業工程の場合は現在時刻)を入力する。第6列の
「作業完了部品数」欄には、各工程での作業が完了した
部品数(実行状態にある作業工程の場合は現在時刻まで
の作業完了部品数)を入力する。実績テーブルの編集
も、計画テーブルと同様、管理者がマウスやキーボード
を用いて行なうことができる。An example of the performance table is shown in FIG. The “progress status” column in the first column of the table is a column for recording the progress status of each work process at the current time, and when it is in the completed state at the current time, for example, enter the symbol “1” In the case of being in the execution state, the symbol "3" is input, for example. The actual start time of each work process is input in the “start time” column of the fifth column. In the “completion time” column of the sixth column, the actual completion time of each work process (current time in the case of a work process in the execution state) is entered. In the “work completed parts number” column of the sixth column, the number of parts for which the work in each process is completed (in the case of a work process in the execution state, the work completed parts number up to the current time) is entered. Similar to the plan table, the administrator can edit the result table using the mouse or keyboard.
【0011】図3に例示した実績テーブルの第1行は、
予定時刻(4月1日11時)までに予定通り2個の部品
について穴あけ作業が完了したことを表わしている。第
2行は、予定通り2個の部品について切削作業が完了し
たが、その完了時刻は予定時刻(4月1日14時)より
も1時間遅い4月1日15時であったことを表わしてい
る。第3行は、現在時刻(4月1日13時30分)まで
に6個の部品について成形作業を行ない、なお実行状態
にあることを表わしている。第4行は、予定時刻(4月
1日12時)よりも30分早い4月1日11時30分ま
でに予定通り2個の部品について組立作業を完了したこ
とを表わしている。The first row of the performance table illustrated in FIG. 3 is
This means that the drilling work has been completed for the two parts as scheduled by the scheduled time (11:00 on April 1). The second line shows that the cutting work was completed for the two parts as planned, but the completion time was 15:00 on April 1st, which was one hour later than the scheduled time (14:00 on April 1st). ing. The third line indicates that the molding work has been performed on the six parts by the current time (13:30 on April 1) and is still in the execution state. The fourth line indicates that the assembly work for the two parts has been completed as scheduled by 11:30 on April 1 30 minutes earlier than the scheduled time (12:00 on April 1).
【0012】工程管理プログラムの制御のもとで中央処
理装置が作成したガントチャートの一例を図4に示す。
このチャートの縦軸には、使用した工作機械のコードが
表示されており、かつ、横軸には、各工作機械による作
業工程が矩形の時間帯枠として表示されている。なお、
本実施例の場合、各作業工程は、計画時間帯枠401が
上側に位置し、実績時間帯枠402が下側に位置するよ
うに配列されている。An example of a Gantt chart created by the central processing unit under the control of the process control program is shown in FIG.
The vertical axis of this chart shows the code of the machine tool used, and the horizontal axis shows the work process by each machine tool as a rectangular time frame. In addition,
In the case of the present embodiment, the work processes are arranged such that the planned time frame 401 is located on the upper side and the actual time frame 402 is located on the lower side.
【0013】遅延工程の抽出手順を図5を用いて説明す
ると、中央処理装置は、作業工程管理プログラムの制御
のもとで動作し、いずれかの一つの作業工程を選択する
(ステップ51)。そして、実績テーブルの進捗状況欄
を参照し、当該工程が完了状態にあるか実行状態にある
かを判定する(ステップ52)。完了状態にある場合
は、実績テーブルに入力された作業完了部品数と、計画
テーブルに入力された作業予定部品数とを比較する(ス
テップ53)。完了部品数が予定数に満たない場合は、
当該工程を遅延工程と判定し、図4のガントチャート上
における複数の実績時間帯枠402のうち、該当の時間
帯枠の配色を変えることより、その作業工程を抽出して
警告する(ステップ54)。作業完了部品数が予定数に
達している場合は、実績テーブルに入力された完了時刻
と、計画テーブルに入力された完了予定時刻とを比較す
る(ステップ55)。そして、完了時刻が予定時刻より
遅い場合は、当該工程を遅延工程と判定し、前記の場合
と同様、その作業工程を抽出して警告する(ステップ5
4)。一方、完了時刻が予定時刻と一致するか予定時刻
より早い場合は、未チェックの作業工程が残っているか
否かを判定する(ステップ56)。未チェックの作業工
程がある場合は、ステップ51に戻って同様の処理を繰
り返し、未チェックの作業工程がない場合は、処理を終
了する。The procedure for extracting the delay process will be described with reference to FIG. 5. The central processing unit operates under the control of the work process management program and selects any one work process (step 51). Then, it is determined whether the process is in the completed state or the executed state by referring to the progress column of the achievement table (step 52). If it is in the completed state, the number of work completed parts input in the actual result table is compared with the number of scheduled work parts input in the plan table (step 53). If the number of completed parts is less than the planned number,
The process is determined to be a delay process, and the work process is extracted and a warning is issued by changing the color scheme of the relevant time slot frame among the plurality of actual time slot frames 402 on the Gantt chart in FIG. 4 (step 54). ). If the number of work-completed parts has reached the planned number, the completion time input in the actual result table is compared with the scheduled completion time input in the plan table (step 55). When the completion time is later than the scheduled time, the process is determined to be a delay process, and the work process is extracted and a warning is issued as in the case described above (step 5).
4). On the other hand, if the completion time matches the scheduled time or is earlier than the scheduled time, it is determined whether or not there are unchecked work steps (step 56). If there is an unchecked work process, the process returns to step 51 and the same process is repeated. If there is no unchecked work process, the process ends.
【0014】ステップ52において、選択した作業工程
がまだ実行状態にあると判定した場合は、その作業工程
の実績情報が実績テーブルにエントリされているかどう
かを判定し(ステップ57)、エントリされていない場
合はステップ56に進む。一方、実績情報が実績テーブ
ルにエントリされている場合は、当該工程の開始時刻か
ら現在時刻までの作業時間を算出するとともに、その時
間を作業完了部品数で割ることによって1個の部品の作
業に必要とする時間を算出し、その結果に基づいて当該
工程の完了見込時刻を算出する(ステップ58)。そし
て、当該見込時刻を計画テーブルに入力された完了予定
時刻と比較し(ステップ59)、見込時刻が予定時刻よ
り遅い場合は、その作業工程を遅延工程と判定し、前記
の場合と同様、当該工程を抽出して警告する(ステップ
54)。一方、見込時刻が予定時刻と一致するか予定時
刻より早い場合はステップ56に進む。When it is judged in step 52 that the selected work process is still in the execution state, it is judged whether or not the record information of the work process is entered in the record table (step 57), and it is not entered. If so, go to step 56. On the other hand, when the record information is entered in the record table, the work time from the start time of the process to the current time is calculated, and the time is divided by the number of work-completed parts to work on one part. The required time is calculated, and the expected completion time of the process is calculated based on the result (step 58). Then, the estimated time is compared with the scheduled completion time input in the plan table (step 59), and when the estimated time is later than the scheduled time, the work process is determined to be the delay process, and the same as the above case, A process is extracted and a warning is given (step 54). On the other hand, if the estimated time matches the scheduled time or is earlier than the scheduled time, the process proceeds to step 56.
【0015】図2に例示した計画テーブル及び図3に例
示した実績テーブルによれば、第2行の作業工程及び第
3行の作業工程が現に遅延しているか、遅延する可能性
がある。これらの作業工程は、図4のガントチャートに
おいて交差斜線で示したように、該当の実績時間帯枠4
02の配色が変えられており、管理者は、極めて容易に
遅延工程を識別することができる。According to the plan table illustrated in FIG. 2 and the performance table illustrated in FIG. 3, the work process of the second row and the work process of the third row are actually delayed or may be delayed. These work steps are shown in the Gantt chart of FIG.
The color scheme of 02 is changed so that the administrator can identify the delay process very easily.
【0016】[0016]
【発明の効果】本発明によれば、複数の工作機械のそれ
ぞれに割り付けた作業工程のうち、現に遅延しているも
の又は遅延する可能性があるものを自動的に抽出するこ
とができるので、作業計画の修正を効率良く実行するこ
とが可能となる。As described above, according to the present invention, it is possible to automatically extract, from the work processes assigned to each of a plurality of machine tools, a work process that is currently delayed or may be delayed. It is possible to efficiently execute work plan correction.
【図1】本発明の実施例において使用した電子計算機シ
ステムを示す系統図FIG. 1 is a system diagram showing an electronic computer system used in an embodiment of the present invention.
【図2】本発明の実施例において採用した作業工程計画
テーブルの一例を示す配列図。FIG. 2 is an array diagram showing an example of a work process plan table adopted in the embodiment of the present invention.
【図3】本発明の実施例において採用した作業工程実績
テーブルの一例を示す配列図。FIG. 3 is an array diagram showing an example of a work process result table adopted in the embodiment of the present invention.
【図4】本発明によって遅延工程を抽出した結果を表示
したガントチャートの一例を示す配列図。FIG. 4 is an array diagram showing an example of a Gantt chart displaying a result of extracting a delay process according to the present invention.
【図5】本発明に係る遅延工程抽出方法の手順を説明す
るためのフローチャート。FIG. 5 is a flowchart for explaining a procedure of a delay process extraction method according to the present invention.
1:中央処理装置 2:メモリ 3:工程管理プログラム 4:ディスク装置 5:作業工程計画テーブル 6:作業工程実績テーブル 7:ディスプレイ 401:計画時間帯枠 402:実績時間帯枠 1: Central Processing Unit 2: Memory 3: Process Management Program 4: Disk Device 5: Work Process Planning Table 6: Work Process Actual Table 7: Display 401: Planned Time Frame 402: Actual Time Frame
───────────────────────────────────────────────────── フロントページの続き (72)発明者 大山 晃弘 神奈川県横浜市都筑区加賀原二丁目2番 株式会社日立製作所ビジネスシステム開発 センタ内 (72)発明者 木橋 智徳 神奈川県川崎市幸区鹿島田890番地の12 株式会社日立製作所情報システム事業部内 (72)発明者 酒谷 正人 神奈川県川崎市幸区鹿島田890番地の12 株式会社日立製作所情報システム事業部内 (72)発明者 金井 周一 神奈川県川崎市幸区鹿島田890番地の12 株式会社日立製作所情報システム事業部内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Akihiro Oyama Inventor Akihiro Oyama 2-2 Kagahara, Tsuzuki-ku, Yokohama, Kanagawa Inside Hitachi Business System Development Center (72) Inventor Tomonori Kihashi 890 Kashimada, Saiwai-ku, Kawasaki-shi, Kanagawa No. 12 Hitachi Ltd. Information Systems Division (72) Inventor Masato Sakata 890 Kashimada, Kawasaki City, Kanagawa Prefecture 12 No. 12 Hitachi Information Systems Division (72) Inventor Shuichi Kanai Sachi-ku, Kawasaki City, Kanagawa Prefecture 12 890 Kashimada, Information Systems Division, Hitachi, Ltd.
Claims (1)
及び作業予定部品数を計画情報として電子計算機に予め
登録しておくとともに、各作業工程の開始時刻、現在時
刻における進捗状況、完了時刻(その作業工程が実行状
態にある場合は現在時刻)及び作業完了部品数(その作
業工程が実行状態にある場合は現在時刻までの作業完了
部品数)を実績情報として電子計算機に入力しておき、
作業工程を管理する必要が生じたときは、実績情報に基
づいて各作業工程の進捗状況を電子計算機に判定させ、
いずれかの作業工程が完了状態にある場合は、当該工程
の完了時刻と完了予定時刻を電子計算機に比較させて遅
延工程を抽出し、一方、いずれかの作業工程が実行状態
にある場合は、現在時刻までの作業完了部品数に基づい
て当該工程の完了見込時刻を電子計算機に算出させ、か
つ、当該見込時刻とその作業工程の完了予定時刻を電子
計算機に比較させて遅延工程を抽出することを特徴とす
る遅延工程の抽出方法。1. A scheduled start time, scheduled completion time, and scheduled work number of each work process are registered in a computer in advance as plan information, and the start time of each work process, the progress status at the current time, and the completion time. (When the work process is in the execution state, the current time) and the number of work completed parts (when the work process is in the execution state, the number of work completed parts up to the current time) are input to the computer as record information. ,
When it becomes necessary to manage work processes, let the computer determine the progress status of each work process based on actual information,
If any work process is in the completed state, the delay time is extracted by comparing the completion time and the scheduled completion time of the process with the electronic computer, while if any work process is in the executed state, To have the electronic computer calculate the expected completion time of the process based on the number of work completed parts up to the current time, and to compare the expected time and the scheduled completion time of the work process with the electronic computer to extract the delay process. And a method for extracting a delay step.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8013493A JPH09201747A (en) | 1996-01-30 | 1996-01-30 | Extraction method of delay process |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8013493A JPH09201747A (en) | 1996-01-30 | 1996-01-30 | Extraction method of delay process |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH09201747A true JPH09201747A (en) | 1997-08-05 |
Family
ID=11834651
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8013493A Pending JPH09201747A (en) | 1996-01-30 | 1996-01-30 | Extraction method of delay process |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH09201747A (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2001075541A1 (en) * | 2000-04-04 | 2001-10-11 | Fujitsu Limited | Production control network system, production control method, and recorded medium on which production control program is recorded |
| WO2019017061A1 (en) * | 2017-07-18 | 2019-01-24 | 株式会社日立製作所 | Progress/operation monitoring system and method |
| KR20200127085A (en) * | 2019-04-30 | 2020-11-10 | 한국조선해양 주식회사 | Auto formation apparatus and method for curved plates in ship |
| KR20200127086A (en) * | 2019-04-30 | 2020-11-10 | 한국조선해양 주식회사 | Auto formation system of curved plates in ship having work log function |
| JP2021130479A (en) * | 2020-02-19 | 2021-09-09 | 日本電気株式会社 | Control device, control method, and program |
| JP2021189766A (en) * | 2020-05-29 | 2021-12-13 | 京セラ株式会社 | Production system |
| US11567709B2 (en) | 2018-07-25 | 2023-01-31 | Fujifilm Business Innovation Corp. | Print management device and computer readable medium |
| US11704075B2 (en) | 2018-07-25 | 2023-07-18 | Fujifilm Business Innovation Corp. | Print management device and computer readable medium |
| WO2025057893A1 (en) * | 2023-09-13 | 2025-03-20 | 株式会社牧野フライス製作所 | Production system |
-
1996
- 1996-01-30 JP JP8013493A patent/JPH09201747A/en active Pending
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2001075541A1 (en) * | 2000-04-04 | 2001-10-11 | Fujitsu Limited | Production control network system, production control method, and recorded medium on which production control program is recorded |
| US6694202B2 (en) | 2000-04-04 | 2004-02-17 | Fujitsu Limited | Production management network system, production management method and recording medium having recorded production management program |
| WO2019017061A1 (en) * | 2017-07-18 | 2019-01-24 | 株式会社日立製作所 | Progress/operation monitoring system and method |
| JP2019021014A (en) * | 2017-07-18 | 2019-02-07 | 株式会社日立製作所 | System and method for monitoring progress/operation |
| CN110832415A (en) * | 2017-07-18 | 2020-02-21 | 株式会社日立制作所 | Progress operation monitoring system and method |
| US11567709B2 (en) | 2018-07-25 | 2023-01-31 | Fujifilm Business Innovation Corp. | Print management device and computer readable medium |
| US11704075B2 (en) | 2018-07-25 | 2023-07-18 | Fujifilm Business Innovation Corp. | Print management device and computer readable medium |
| US12093581B2 (en) | 2018-07-25 | 2024-09-17 | Fujifilm Business Innovation Corp. | Management device that displays processing information for multiple processing devices |
| KR20200127086A (en) * | 2019-04-30 | 2020-11-10 | 한국조선해양 주식회사 | Auto formation system of curved plates in ship having work log function |
| KR20200127085A (en) * | 2019-04-30 | 2020-11-10 | 한국조선해양 주식회사 | Auto formation apparatus and method for curved plates in ship |
| JP2021130479A (en) * | 2020-02-19 | 2021-09-09 | 日本電気株式会社 | Control device, control method, and program |
| JP2021189766A (en) * | 2020-05-29 | 2021-12-13 | 京セラ株式会社 | Production system |
| WO2025057893A1 (en) * | 2023-09-13 | 2025-03-20 | 株式会社牧野フライス製作所 | Production system |
| JP2025041389A (en) * | 2023-09-13 | 2025-03-26 | 株式会社牧野フライス製作所 | Production System |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH07251356A (en) | Operation results display analysis system | |
| JPH09201747A (en) | Extraction method of delay process | |
| US20130030781A1 (en) | Processing stimulation method, device for the same, and program for causing a computer to execute the method | |
| JPH1110400A (en) | Automatic programming method for punch press and device therefor | |
| JPH09212555A (en) | Schedule / actual data display system | |
| US20010046068A1 (en) | Print schedule planning method, print schedule planning system and print schedule planning program storage medium | |
| CN107247846A (en) | A kind of cut-parts screening technique, method of cutting out and system | |
| JPH09330110A (en) | Numerical control information generating device | |
| JP2001184112A (en) | Method and device for automatically blanking parts and computer readable recording medium recording program for executing automatic blanking of parts | |
| JP2003280715A (en) | Production planning support method and device, and production management system | |
| JP2677827B2 (en) | Bending die automatic selection method | |
| JPH0643920A (en) | Tool control system | |
| JP3412346B2 (en) | Work assignment support device | |
| JPH05290053A (en) | Providing method for flowing information in production management system of small scale many kinds | |
| JPH06110530A (en) | Result data managing device for numerical controller | |
| JP2006164128A (en) | Production simulation equipment | |
| JP2006048385A (en) | NC program input device | |
| JPH06262436A (en) | Moving locus display device for electric discharge machine | |
| JPH08215986A (en) | Cutting tool life management method | |
| JPH09319419A (en) | Processing method for working graphic | |
| JP2003280711A (en) | Automatic creation of single axis operation | |
| JPH079301A (en) | How to create a tool unit shape | |
| JP3111984B2 (en) | Printed wiring board data analysis apparatus and printed wiring board data analysis method | |
| JP3684887B2 (en) | Solid model generation method | |
| JP3175686B2 (en) | Process flow check system and process flow check method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080110 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20090110 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100110 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100110 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 8 Free format text: PAYMENT UNTIL: 20110110 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 9 Free format text: PAYMENT UNTIL: 20120110 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130110 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 10 Free format text: PAYMENT UNTIL: 20130110 |