JPH0923583A - Distribution system operation device - Google Patents
Distribution system operation deviceInfo
- Publication number
- JPH0923583A JPH0923583A JP7168390A JP16839095A JPH0923583A JP H0923583 A JPH0923583 A JP H0923583A JP 7168390 A JP7168390 A JP 7168390A JP 16839095 A JP16839095 A JP 16839095A JP H0923583 A JPH0923583 A JP H0923583A
- Authority
- JP
- Japan
- Prior art keywords
- power transmission
- distribution line
- switch
- power
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
(57)【要約】
【目的】 配電系統開閉器の融通送電処理時に送電損失
が最小となる開閉器操作手順を作成し設備効率を良くす
る。
【構成】 配電線事故時あるいは作業停電時に生じた健
全停電区間又は過負荷解消操作を行うために過負荷量に
見合う負荷を持つ区間等の融通対象区間に対して、配電
線から融通送電を行うに際し、開閉器操作手順作成手段
6により融通対象区間に連係する開閉器、配電線しゃ断
器を連係する電気所母線に至る1つ以上の送電ルートを
求め、さらにこの各送電ルートの中から電圧降下量が設
定値以内の送電ルートを選び、この手段6で選ばれた送
電ルートの中から送電損失の最小のものを送電損失判定
手段5により選び、更にこの手段5で選んだ送電ルート
上の各開閉器に対して開閉器操作指示手段7により開閉
操作指示を出力する。
(57) [Summary] [Purpose] To improve equipment efficiency by creating a switch operating procedure that minimizes transmission loss during flexible transmission processing of distribution system switches. [Structure] Flexible power transmission from a distribution line to a flexible power supply segment that occurs during a distribution line accident or a work power outage or a section that has a load commensurate with the amount of overload to perform overload elimination operations. At this time, one or more power transmission routes to the electric power station bus linking the switch and the distribution line breaker linked to the interchange target section are obtained by the switch operating procedure creating means 6, and the voltage drop is further made from each of these power transmission routes. The power transmission route whose amount is within the set value is selected, the one with the smallest power transmission loss is selected from the power transmission routes selected by this means 6 by the power transmission loss determination means 5, and each of the power transmission routes selected by this means 5 is selected. The switch operation instruction means 7 outputs an open / close operation instruction to the switch.
Description
【0001】[0001]
【産業上の利用分野】本発明は配電系統における事故時
の復旧操作、作業計画操作、過負荷解消操作などの制御
を行う場合に融通操作を行う配電系統操作装置に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a power distribution system operation device for performing flexible operation when performing control such as recovery operation, work planning operation and overload elimination operation in case of accident in the power distribution system.
【0002】[0002]
【従来の技術】配電系統には通常配電系統操作装置を設
けており、この配電系統操作装置は概ね次の3つの制御
を行う機能を備えている。先ず第一に配電区間に事故が
発生した場合、事故発生の検出、事故区間の検出および
被融通区間(融通対象区間)を判断し、この被融通区間
に対して他の配電線から融通送電を行う事故時の復旧操
作の制御、第二は、任意の配電区間を作業停電させる場
合、作業停電指令に基づいて被融通区間を判定し、この
被融通区間に対して他の配電線から融通送電を行う作業
計画操作の制御、第三に、過負荷状態となった配電線の
負荷を解消する場合、他の配電線から過負荷を解消させ
るに見合う負荷を融通送電する過負荷解消操作の制御で
ある。配電系統操作装置が被融通区間への送電を行う融
通処理に関し送電ルートを決定する条件として従来、次
の3つの条件が必要とされている。(1)過負荷が発生
しないこと。(2)良質な電気(電圧降下量が許容値
内)が融通出来ること。(3)融通後の配電線の予備力
が残ること。しかしながら、従来の装置では送電元から
融通区間までの送電損失は考慮されていなかった。2. Description of the Related Art A power distribution system operating device is usually provided in a power distribution system, and this power distribution system operating device has a function of performing the following three controls. First of all, when an accident occurs in a power distribution section, detection of the occurrence of an accident, detection of the accident section and judgment of the concession section (accommodation target section) and transmission of the concession transmission from other distribution lines to this concession section. Second, control of recovery operation at the time of an accident, secondly, when a work power outage occurs in an arbitrary power distribution section, the concession section is judged based on the work power outage command, and the concession transmission from another distribution line to this concession section. Control of the work plan operation that performs the third, and thirdly, when the load on the distribution line that has become overloaded is eliminated, the control of the overload elimination operation that exchanges the load commensurate with eliminating the overload from other distribution lines Is. Conventionally, the following three conditions are required as conditions for the power transmission route operating device to determine the power transmission route regarding the accommodation process for transmitting power to the concession section. (1) No overload occurs. (2) Good quality electricity (the amount of voltage drop is within the allowable value) can be accommodated. (3) The reserve capacity of the distribution line after the accommodation is left. However, in the conventional device, the transmission loss from the transmission source to the interchange section has not been taken into consideration.
【0003】近年の電力需要に対する社会情勢は、電力
供給の逼迫から効率のよい電気の供給が求められている
が、上述のような従来方式では、送電元から融通された
電気の送電損失が考慮されていないため、設備効率のよ
い融通送電が提供出来ないという課題を残していた。In recent years, the social situation against the demand for power demands efficient power supply due to the tight power supply. In the conventional system as described above, the power transmission loss accommodated by the power source is taken into consideration. Since it has not been done, the problem remains that flexible power transmission with good equipment efficiency cannot be provided.
【0004】[0004]
【発明が解決しようとする課題】本発明は上記事情に鑑
みてなされたものであり、融通処理時に送電損失が小さ
くなるような処理を行うことにより経済的にメリットの
ある設備効率のよい電気の供給の可能な配電系統操作装
置を提供することを目的としている。SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and it is economically advantageous to perform electricity-efficient electricity processing by performing processing that reduces transmission loss during accommodation processing. It is an object of the present invention to provide a distribution system operation device that can be supplied.
【0005】[0005]
【課題を解決するための手段】本発明は上記目的を達成
するため、配電線を導出する配電線しゃ断器の開閉情報
や配電線を複数の区間に区分したり連係する各種開閉器
の開閉状態情報、更には各配電線の負荷電流情報、各区
間相互がどのように接続されているかを示すつながり情
報等を用いて検出された配電線の事故区間もしくは過負
荷状態になっている配電線の過負荷量に見合う負荷を持
つ区間、または設備の増設・撤去等の設備変更計画によ
り予め定めてある配電線の作業停電区間等の融通対象区
間に対し、他の配電線から融通送電を行うようにした配
電系統操作装置において、前記融通対象区間から開閉
器、配電線しゃ断器を経て電気所母線に至る一つ以上の
送電ルートを求め、更にこの各送電ルートの中から電圧
降下量が設定値以内の送電ルートを開閉器操作手順作成
手段5により選び、この開閉器操作手順作成手段5によ
り選ばれた送電ルートの中から送電損失の最小の送電ル
ートを送電損失判定手段6で選び、この送電損失判定手
段6で選んだ送電ルート上の前記各開閉器に対して開閉
操作指示出力手段7により開閉操作指示を出力するよう
にしたものである。In order to achieve the above object, the present invention provides opening / closing information of a distribution line breaker for deriving a distribution line and opening / closing states of various switches for dividing or linking the distribution line into a plurality of sections. Information, load current information of each distribution line, connection information indicating how each section is connected, etc. of the distribution line detected using the fault section or distribution line in the overloaded state. Transfer power from another distribution line to a section with a load commensurate with the amount of overload, or to a concession target section such as a work power outage section of a distribution line that has been determined in advance by a facility change plan such as facility expansion / removal. In the distribution system operation device, the one or more power transmission routes from the interchange target section to the electric power station bus through the switch and the distribution line breaker are obtained, and the voltage drop amount from each of the power transmission routes is set to a set value. Within The power transmission route is selected by the switch operation procedure creating means 5, the power transmission route having the minimum power transmission loss is selected by the power transmission loss determining means 6 from the power transmission routes selected by the switch operating procedure creating means 5, and this power transmission loss determination is performed. The opening / closing operation instruction output means 7 outputs an opening / closing operation instruction to each of the switches on the power transmission route selected by the means 6.
【0006】[0006]
【作用】融通対象区間から開閉器、配電線しゃ断器を経
て電気所母線に至る各送電ルート毎に送電距離と通過電
流とから送電損失を算出し、更にこの中から送電損失が
最小の送電ルートを選び、この損失が最小の送電ルート
上の開閉器に対して、開閉操作指示を出力するようにし
て、融通処理時に送電損失が小さくなるような処理を行
う。[Operation] The transmission loss is calculated from the transmission distance and the passing current for each transmission route from the interchange target section to the electric power station bus through the switch, the distribution line breaker, and the transmission route with the minimum transmission loss. Is selected, and a switching operation instruction is output to the switch on the power transmission route with the minimum loss, so that the power transmission loss is reduced during the accommodation process.
【0007】[0007]
【実施例】以下図面を参照して実施例を説明する。図1
は、配電系統を構成する配電線の一部と共に表した本発
明による配電系統操作装置の一実施例の構成図であり、
配電線TLを導出する配電線用しゃ断器CBと、この配
電線TLを適宜の区間に区分する開閉器群SW1,SW
2,…SW4で構成された配電系統から配電線の電流値
および開閉器の開閉状態信号を伝送するTC子局1-1…
1-4と、これらTC子局を統括するTC親局2と、更に
演算装置3とから構成される。この演算装置3は次の手
段4〜8により構成されている。先ず、融通対象区間検
出手段4は周知の機能であり、配電線の事故に基づいて
配電線用しゃ断器CBがしゃ断し、再閉路した後、順次
開閉器を投入してゆき、投入した直後に再び事故電流が
流れてしゃ断器CBが再しゃ断したことをもって事故区
間を検出するものである。例えば、区間a2 に事故が発
生すると、図示しない保護リレーの働きによりしゃ断器
CBがしゃ断し、所定時間後再閉路する。すると手段4
は、電源側に近い区分開閉器から順次投入してゆく。開
閉器SW2 が投入した直後、しゃ断器CBの再しゃ断が
あれば、区間a2 が事故区間として検出されしゃ断器C
Bの再々閉路後開閉器SW2 の投入がロックされる。こ
れにより事故区間a2 に隣接する負荷側区間a3 が健全
停電区間となり、図示左側の配電線から連係開閉器SW
4 を介して送電が融通される対象となる。本発明ではこ
のような区間a3 を被融通区間又は融通対象区間と呼ぶ
ことにする。An embodiment will be described below with reference to the drawings. FIG.
Is a configuration diagram of an embodiment of a distribution system operation device according to the present invention represented together with a part of a distribution line constituting a distribution system,
Distribution line breaker CB for deriving the distribution line TL, and switch groups SW1, SW for dividing the distribution line TL into appropriate sections
2, ... TC slave station 1-1 that transmits the current value of the distribution line and the switching status signal of the switch from the distribution system configured by SW4
1-4, a TC master station 2 that controls these TC slave stations, and an arithmetic unit 3. This arithmetic unit 3 is composed of the following means 4-8. First, the interchange target section detection means 4 has a well-known function, and the distribution line breaker CB is cut off based on an accident of the distribution line and closed again, and then the switches are sequentially turned on, and immediately after turning on. The fault section is detected when the fault current flows again and the circuit breaker CB re-blocks. For example, if an accident occurs in the section a2, the breaker CB is cut off by the action of a protection relay (not shown), and the circuit is closed again after a predetermined time. Then means 4
Turn on sequentially from the division switch near the power supply side. If the circuit breaker CB is re-cut immediately after the switch SW2 is turned on, the section a2 is detected as the accident section and the circuit breaker C is detected.
After B is closed again, switch SW2 is closed. As a result, the load side section a3 adjacent to the accident section a2 becomes a sound power failure section, and the link switch SW is connected from the distribution line on the left side in the figure.
Power transmission will be interchanged via the four. In the present invention, such a section a3 is referred to as a concession section or a concession target section.
【0008】次に送電損失判定手段5について説明す
る。送電損失判定手段5は、配電系統に発生した融通操
作により決定された変電所から融通対象区間に至る送電
ルートから求める送電損失を、当該送電ルート毎に予め
設定した許容値と比較判定する。なお、送電損失は、送
電ルート上の各区間の距離が予めわかっており、又単位
長さ当りのインピーダンスも既知であるので、送電ルー
トが決定され、かつ各区間に流れる電流の大きさがわか
れば、容易に求めることができる。前記比較判定の詳細
は図4に示した様に、送電損失が許容値内か?、かつ既
出の候補の中で最小か否か?を判定する。この判定結果
により送電損失を最小とするように求められた送電ルー
トを通じて電気を融通するように開閉器の操作手順を開
閉器操作手順作成手段6により作成する。開閉器操作指
示手段7は、前記開閉器操作手順作成手段6で作成した
手順をTC親局2、TC子局1を介して実行させる手段
である。そして、通知手段は前記送電損失判定手段5に
よる比較結果が許容値を越えた場合、その旨出力するも
のである。Next, the power transmission loss determining means 5 will be described. The power transmission loss determination means 5 compares and determines the power transmission loss obtained from the power transmission route from the substation determined by the power exchange operation that has occurred in the distribution system to the interchange target section, with a preset allowable value for each power transmission route. In addition, since the distance between each section on the power transmission route is known in advance and the impedance per unit length is also known, the power transmission loss is determined if the power transmission route is determined and the magnitude of the current flowing in each section is known. , Easy to find. As for details of the comparison judgment, as shown in FIG. 4, is the transmission loss within the allowable value? And is it the smallest of the existing candidates? Is determined. The switch operating procedure creating means 6 creates the operating procedure of the switch so as to exchange electricity through the power transmission route determined to minimize the power transmission loss based on this determination result. The switch operation instruction means 7 is means for executing the procedure created by the switch operation procedure creating means 6 via the TC master station 2 and the TC slave station 1. Then, when the comparison result by the power transmission loss determining means 5 exceeds the allowable value, the notifying means outputs that effect.
【0009】図2は本発明装置が適用される4つの配電
線a,b,c,およびdから成る配電線系統を表したも
のである。図2において、配電線用しゃ断器CB−a〜
CB−d(四角のシンボル)、区分開閉器SW1 〜SW
10(三角のシンボル)、及び他の配電系統と連係する目
的で設置され、常時開路状態にある連係開閉器SWC1
〜SWC4 (マルに×のシンボル)から構成されてい
る。ここで配電線aは、連係開閉器SWC2 を経て配電
線bと連係し、また連係開閉器SWC1 を経て配電線c
と連係している。同様に配電線bは、連係開閉器SWC
2 を経て前記配電線aと連係し、また連係開閉器SWC
4 を経て配電線dと連係している。配電線cは、連係開
閉器SWC1 を経て配電線aと連係し、また連係開閉器
SWC3 を経て配電線dと連係している。そして配電線
dは、連係開閉器SWC3 を経て配電線cと連係し、ま
た連係開閉器SWC4 を経て配電線bと連係している。FIG. 2 shows a distribution line system including four distribution lines a, b, c and d to which the device of the present invention is applied. In FIG. 2, a circuit breaker CB-a for distribution line
CB-d (square symbol), section switches SW1 to SW
10 (triangular symbol), and a link switch SWC1 installed for the purpose of linking with other power distribution systems and always open.
~ SWC4 (marked with a circle). Here, the distribution line a is linked to the distribution line b via the link switch SWC2, and the distribution line c is linked via the link switch SWC1.
Is associated with. Similarly, the distribution line b is a link switch SWC.
Via 2 and the distribution line a, and also the switch SWC
It is linked to the distribution line d via 4. The distribution line c is linked to the distribution line a via the link switch SWC1 and is linked to the distribution line d via the link switch SWC3. The distribution line d is linked to the distribution line c via the link switch SWC3, and is linked to the distribution line b via the link switch SWC4.
【0010】次に本発明装置の作用の概略について、図
1,図2を用いて説明する。このような系統状態におい
て、事故発生もしくは、作業計画により区間a−2(ハ
ッチングで示した領域)に停電が発生した場合、区分開
閉器SW2 以降SWC1 までの区間a−3,a−4が健
全な停電区間となる。この健全区間に電力融通出来る連
係開閉器をTC子局−TC親局を介して得られる開閉器
のオンライン情報により求め、融通元の配電線の予備力
を考慮し融通手順を作成する。このケースでは健全な停
電区間a−3,a−4にある連係開閉器は2個即ち、S
WC1,SWC2 存在する。一方の連係開閉器SWC1
から融通出来る送電ルートは、次の3ルートが考えられ
る。区間a−4を基点として先ず1つは連係開閉器SW
C1 →SWC3 →SWC4 →しゃ断器CB-b→配電線b
に至るルート即ち、SWC1 →SW8 →SWC3 →SW
10→SWC4 →SW6 →SW5 →SW4 →CB-bであ
り、2番目のルートは配電線cに連係するルート即ち、
SWC1 →SW8 →SW7 →CB-cであり、残りのルー
トはSWC3 を通って配電線dに至るルート即ち、SW
C1 →SW8 →SWC3 →SW9 →CB-dである。他方
の連係開閉器SWC2 から融通出来る送電ルートもSW
C1 と同様に配電線b,c,dへの合計3ルートが考え
られる。このように作成された送電ルート毎に当該の配
電線用しゃ断器から融通対象区間に連係する送電操作開
閉器までの送電距離に基づくインピーダンスおよびしゃ
断器近傍で検出した送出電流を用いて送電損失を算出
し、この算出値を予め送電ルート毎に設定した許容値と
送電損失判定手段5で比較し、送電損失が最小となる手
順を求める。なお、判定手段5により全ての算出値が許
容値を越えていると判定した場合、他系統との連係開閉
器を用いて融通する手順を開閉器操作手順作成手段6に
より作成する。その後、開閉器操作指示手段7が開閉器
操作手順に従い、操作実行指示をTC親局2へ出力す
る。Next, the outline of the operation of the device of the present invention will be described with reference to FIGS. In such a system condition, when an accident occurs or a power failure occurs in the section a-2 (hatched area) due to the work plan, the sections a-3 and a-4 from the switch SW2 to the switch SWC1 are sound. It becomes a blackout section. A link switch capable of accommodating electric power in this healthy section is obtained from the online information of the switch obtained via the TC slave station-TC master station, and the accommodating procedure is created in consideration of the reserve capacity of the distribution line of the concession source. In this case, there are two linked switches in the sound interruption sections a-3 and a-4, that is, S
There are WC1 and SWC2. One linked switch SWC1
The following three routes are considered as the power transmission routes that can be accommodated. First of all, based on the section a-4, the first one is the link switch SW.
C1 → SWC3 → SWC4 → Circuit breaker CB-b → Distribution line b
Route to SW, ie SWC1 → SW8 → SWC3 → SW
10 → SWC4 → SW6 → SW5 → SW4 → CB-b, and the second route is the route linked to the distribution line c, that is,
SWC1 → SW8 → SW7 → CB-c, and the remaining route is the route to the distribution line d through SWC3, that is, SW
C1 → SW8 → SWC3 → SW9 → CB-d. The transmission route that can be interchanged from the other link switch SWC2 is also SW
Similar to C1, a total of 3 routes to distribution lines b, c, d can be considered. For each transmission route created in this way, the transmission loss is determined using the impedance based on the transmission distance from the distribution line breaker to the transmission operation switch linked to the interchange target section and the sending current detected near the breaker. The calculated value is calculated, and the calculated value is compared with the allowable value set in advance for each power transmission route by the power transmission loss determining means 5 to obtain the procedure for minimizing the power transmission loss. When the determination unit 5 determines that all the calculated values exceed the allowable values, the switch operation procedure creation unit 6 creates a procedure for accommodating using a switch that is linked to another system. Then, the switch operation instruction means 7 outputs an operation execution instruction to the TC master station 2 in accordance with the switch operation procedure.
【0011】次に、演算装置3で行う処理内容の詳細に
ついて、図3,図4,図5,図6のフローチャートを用
いて説明する。まず、図3を用いて開閉器操作手順作成
手段6から説明する。ステップ3S−1は、配電系統に
停電が発生した場合、すでに求めてある健全な停電区間
a−3,a−4に連係している開閉器群(K)SWC1
,SWC2 を求める。次にステップ3S−2は、上述
のステップで求めた開閉器群SWC1 ,SWC2 (K)
を経て連係している配電線を検索し、配電線の予備力を
考慮し、融通候補の配電線群(H)b,c,dを求め
る。次にステップ3S−3は、この融通候補配電線群
(H)のうち電気品質が良好(電圧降下量が許容値内)
である開閉器操作手順の組み合わせ(h)を求め、送電
ルート毎に保存する複数存在した場合それらを記憶手段
に格納しておく。Next, the details of the processing performed by the arithmetic unit 3 will be described with reference to the flowcharts of FIGS. 3, 4, 5, and 6. First, the switch operation procedure creating means 6 will be described with reference to FIG. Step 3S-1 is a group of switchgear (K) SWC1 linked to the already-acquired sound power failure sections a-3 and a-4 when a power failure occurs in the distribution system.
, SWC2 is calculated. Next, step 3S-2 is the switch group SWC1, SWC2 (K) obtained in the above step.
Then, the distribution lines linked with each other are searched, and the distribution line groups (H) b, c, d of the interchange candidates are obtained in consideration of the reserve capacity of the distribution lines. Next, in step 3S-3, the electrical quality of the interchange candidate distribution line group (H) is good (the voltage drop amount is within the allowable value).
The combination (h) of the switch operating procedures is calculated, and if there are a plurality of storages for each power transmission route, these are stored in the storage means.
【0012】次に、図4を用いて送電損失判定手段5に
ついて説明する。ステップ4S−1は、上記により求め
られた一組の送電ルート(開閉器操作手順の組み合わせ
たもの)を取り出す、ステップ4S−2は複数の送電ル
ートに対して送電損失をチェック済みか否かを判定す
る。全ての組みについてチェックが完了し(Y)、かつ
次のステップ4S−3で送電ルートが未決定の場合、当
該の停電区間を融通する手順の内送電損失を満足する手
順が存在しないことを示している。ステップ4S−2で
全ての組みについてチェックが完了し、かつステップ4
S−3で送電ルートが決定していれば、その送電ルート
を用いる融通手順を後述する開閉器操作指示手段7に引
き継ぐ。次にステップ4S−4は送電ルート内に存在す
る全区間の恒長の総和と、当該配電線の送出電流(しゃ
断器近傍の電流もしくは各区間毎の電流)により送電損
失を求める。ステップ4S−5は4S−4により求めら
れた送電損失が予め設定した許容値内にありかつ最小
か、つまり既算出のhの一つの組みより、より小さいか
否かを判定する。判定の結果許容値を越えるまたは最小
でない場合、ステップ4S−6において次の手順の組み
を取り出す。また許容値内にありかつ最小の場合、ステ
ップ4S−7は取り出した手順を送電損失手順として保
存する。Next, the transmission loss determining means 5 will be described with reference to FIG. Step 4S-1 takes out a set of power transmission routes (combined of switch operating procedures) obtained above, and step 4S-2 determines whether or not transmission loss has been checked for a plurality of power transmission routes. judge. When the check is completed for all the sets (Y) and the power transmission route is not determined in the next step 4S-3, it indicates that there is no procedure satisfying the power transmission loss in the procedure for accommodating the power failure section. ing. The check is completed for all the combinations in step 4S-2, and step 4
If the power transmission route is determined in S-3, the interchange procedure using the power transmission route is taken over by the switch operation instruction means 7 described later. Next, in step 4S-4, the transmission loss is obtained from the sum of the constant lengths of all the sections existing in the power transmission route and the sending current (current near the breaker or current in each section) of the distribution line. In step 4S-5, it is determined whether or not the power transmission loss obtained in 4S-4 is within a preset allowable value and is minimum, that is, is smaller than one set of already calculated h. If the result of determination is that the allowable value is not exceeded or not the minimum value, the next set of procedures is taken out in step 4S-6. If it is within the allowable value and is the minimum value, step 4S-7 stores the extracted procedure as a transmission loss procedure.
【0013】次に、図5を用いて開閉器操作指示手段7
について説明する。ステップ5S−1は決定された融通
手順のうち一つの操作手順を取り出す。ステップ5S−
2は、操作される対象の手順が全て実行済みか否かの判
定を行う。この判定結果、操作される手順が全て実行済
みでない場合ステップ5S−3により、1操作手順毎に
TC親局2へ制御指示を与える。Next, the switch operation instruction means 7 will be described with reference to FIG.
Will be described. In step 5S-1, one operation procedure is taken out from the determined interchange procedures. Step 5S-
2 determines whether or not all procedures to be operated have been executed. As a result of this determination, if all the procedures to be operated have not been executed, a control instruction is given to the TC master station 2 for each operation procedure in step 5S-3.
【0014】次に図6を用いて警報通知手段8について
説明する。ステップ6S−1はステップ4S−3で融通
手順が未決定と判断された場合許容値以下の送電損失を
満足しないことを示しており、操作者に警報の通知を行
う。Next, the alarm notification means 8 will be described with reference to FIG. Step 6S-1 indicates that if the accommodation procedure is determined to be undecided in step 4S-3, the power transmission loss equal to or less than the allowable value is not satisfied, and the operator is notified of the alarm.
【0015】以上説明した実施例は、本発明装置を配電
線の事故時に健全区間に対して融通送電を行う場合につ
いてであるが、本発明はこれのみに限定されるものでは
なく、作業停電時の融通操作処理にも適用できる。また
配電区間が過負荷となった場合の、過負荷解消操作につ
いても適用できる。The embodiment described above is a case in which the device of the present invention is used for flexible power transmission to a healthy section in the event of a distribution line accident, but the present invention is not limited to this, and during a work power failure. It is also applicable to the flexible operation processing of It can also be applied to overload elimination operation when the distribution section is overloaded.
【0016】図7は、過負荷発生時の配電系統を示す。
なお、しゃ断器、区分開閉器、連係開閉器の接続状態は
図2の場合と同じなので、接続関係の説明は省略する。
図7の系統状態において、配電線bに過負荷状態が発生
した場合、過負荷を解消する為に配電線bを構成してい
る区間b−1,b−2,b−3,b−4から過負荷を解
消するのに見合う量を求める。区間b−4(ハッチング
部分)が過負荷解消に見合う量に相当した場合を例に説
明する。FIG. 7 shows the power distribution system when an overload occurs.
Since the connection state of the breaker, the division switch, and the link switch is the same as in the case of FIG. 2, the description of the connection relationship is omitted.
In the system state of FIG. 7, when an overload condition occurs on the distribution line b, sections b-1, b-2, b-3, b-4 forming the distribution line b to eliminate the overload. Find the amount that is appropriate to eliminate the overload from. An example will be described in which the section b-4 (hatched portion) corresponds to an amount commensurate with overload elimination.
【0017】次にこの区間負荷を連係する配電線に預け
る為の融通手順を作成する為に、融通対象区間に連係す
る開閉器と送電ルートを求める。連係開閉器はSWC4
1個のみ存在し、この連係開閉器SWC4 から融通出来
る送電ルートは、次の3ルートが考えられ、配電線a
(SWC4 →SW10→SWC3 →SW8 →SWC1 →S
W3 →SW2 →SW1 →CB-a)と配電線c(SWC4
→SW10→SWC3 →SW7 →CB-c)と配電線d(S
WC4 →SW10→SW9 →CB-d)からなる。このよう
に送電ルートが求められると、この後の処理は前記事故
もしくは作業計画により健全停電区間の復旧操作と同様
の処理となる。Next, in order to prepare an accommodation procedure for depositing this section load on the associated distribution line, a switch and a power transmission route associated with the accommodation target section are obtained. Link switch is SWC4
There is only one power transmission route that can be interchanged from this link switch SWC4, and the following three routes are considered.
(SWC4 → SW10 → SWC3 → SW8 → SWC1 → S
W3 → SW2 → SW1 → CB-a) and distribution line c (SWC4
→ SW10 → SWC3 → SW7 → CB-c) and distribution line d (S
WC4 → SW10 → SW9 → CB-d). When the power transmission route is obtained in this way, the subsequent processing is the same processing as the restoration operation of the sound power failure section due to the accident or the work plan.
【0018】[0018]
【発明の効果】以上説明したように、本発明によれば配
電系統の融通処理時に、融通対象区間である健全な停電
区間へ電力を供給する送電ルートの送電損失が小さくな
るように、開閉器操作手順を作成するようにしたので配
電線の効率の良い運用が可能な配電系統操作装置を提供
できる。As described above, according to the present invention, at the time of accommodation processing of a distribution system, a switch is provided so that transmission loss of a transmission route for supplying power to a healthy blackout section, which is an accommodation section, is reduced. Since the operation procedure is created, it is possible to provide a distribution system operation device capable of operating the distribution line efficiently.
【図1】本発明による配電操作装置の一実施例の構成
図、FIG. 1 is a configuration diagram of an embodiment of a power distribution operating device according to the present invention,
【図2】配電系統を示す図、FIG. 2 is a diagram showing a distribution system,
【図3】開閉器操作手順作成手段の処理内容を示すフロ
ーチャート、FIG. 3 is a flowchart showing the processing contents of a switch operating procedure creating means,
【図4】送電損失判定手段の処理内容を示すフローチャ
ート、FIG. 4 is a flowchart showing the processing contents of transmission loss determination means,
【図5】開閉器操作指示手段の処理内容を示すフローチ
ャート、FIG. 5 is a flowchart showing the processing contents of the switch operation instruction means,
【図6】通知手段の処理内容を示すフローチャート、FIG. 6 is a flowchart showing the processing contents of the notification means,
【図7】過負荷解消操作を説明するための配電系統図、FIG. 7 is a distribution system diagram for explaining overload elimination operation,
CB…配電線用しゃ断器 SW1 ,SW2 ,SW3 …区分開閉器 SW4…連係開閉器 1…TC子局 2…TC親局 3…演算装置 4…融通対象区間検出手段 5…送電損失判定手段 6…開閉器操作手順作成手段 7…開閉器操作指示手段 8…通知手段 CB ... Distributor breaker SW1, SW2, SW3 ... Differential switch SW4 ... Coupling switch 1 ... TC slave station 2 ... TC master station 3 ... Computing device 4 ... Interchange target section detection means 5 ... Transmission loss determination means 6 ... Switch operation procedure creating means 7 ... Switch operation instruction means 8 ... Notification means
Claims (2)
しゃ断器の開閉情報および前記配電線を複数の区間に区
分あるいは連係する各種開閉器の開閉状態情報、各配電
線の負荷電流情報、各区間相互がどのように接続されて
いるかを示すつながり情報等を用いて検出された配電線
の事故区間もしくは過負荷状態になっている配電線の過
負荷量に見合う負荷を持つ区間、または予め定めてある
配電線の作業停電区間等の融通対象区間に対し、これに
連係する他の配電線から融通送電を行うようにした配電
系統操作装置において、 前記融通対象区間から開閉器および配電線しゃ断器を経
て電気所母線に至る一つ以上の送電ルートを求め、さら
にこの各送電ルートの中から電圧降下量が設定値以内の
送電ルートを選ぶ開閉器操作手順作成手段と、 この開閉器操作手順作成手段により選ばれた各送電ルー
ト毎に送電距離に基づくインピーダンスおよび電流情報
から送電損失を求め、この求められた送電損失の中で最
小の送電損失になる送電ルートを選ぶ送電損失判定手段
と、 この送電損失判定手段で選んだ送電ルート上の前記各開
閉器に対して開閉操作指示を出力する開閉操作指示出力
手段とを備えた配電系統操作装置。1. Information on switching of a distribution line breaker for deriving a distribution line from an electric power station bus, switching state information of various switches dividing or linking the distribution line into a plurality of sections, load current information of each distribution line, A faulty section of a distribution line detected using connection information that shows how each section is connected, or a section with a load commensurate with the overload amount of the distribution line in an overloaded state, or in advance In a distribution system operation device configured to perform interchange power transmission from a specified power distribution line, such as a work power failure section, from another power distribution line linked to this, a switch and a distribution line cutoff And one or more power transmission routes to the electric power station bus via the switch, and a switch operating procedure creation means for selecting a power transmission route with a voltage drop amount within a set value from each of these power transmission routes, and Transmission loss is calculated from impedance and current information based on the transmission distance for each transmission route selected by the switch operating procedure creation means, and the transmission route that has the smallest transmission loss among the calculated transmission losses is selected. A distribution system operation device comprising: a determination unit; and an opening / closing operation instruction output unit that outputs an opening / closing operation instruction to each of the switches on the power transmission route selected by the power transmission loss determination unit.
送電ルートの送電損失が予め設定した許容値を上回る場
合、その旨出力する通知手段を設けたことを特徴とする
請求項1に記載の配電系統操作装置。2. When the transmission loss of the transmission route selected by the switch operating procedure creating means exceeds a preset allowable value, a notification means is provided to output that effect. Distribution system operation device.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7168390A JPH0923583A (en) | 1995-07-04 | 1995-07-04 | Distribution system operation device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7168390A JPH0923583A (en) | 1995-07-04 | 1995-07-04 | Distribution system operation device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0923583A true JPH0923583A (en) | 1997-01-21 |
Family
ID=15867232
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7168390A Pending JPH0923583A (en) | 1995-07-04 | 1995-07-04 | Distribution system operation device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0923583A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009225534A (en) * | 2008-03-14 | 2009-10-01 | Toshiba Corp | Distribution system operation device |
| JP2013169025A (en) * | 2012-02-14 | 2013-08-29 | Tokyo Electric Power Co Inc:The | Power distribution system recovery device |
-
1995
- 1995-07-04 JP JP7168390A patent/JPH0923583A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009225534A (en) * | 2008-03-14 | 2009-10-01 | Toshiba Corp | Distribution system operation device |
| JP2013169025A (en) * | 2012-02-14 | 2013-08-29 | Tokyo Electric Power Co Inc:The | Power distribution system recovery device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101911421B (en) | Method for electric power rehabilitation in electric power distribution systems | |
| JP2003299263A (en) | Monitoring and control system | |
| CN106160187A (en) | Middle pressure power transmission and distribution automatic switching control system and control method | |
| JPH0923583A (en) | Distribution system operation device | |
| JP4969340B2 (en) | Supervisory control system | |
| Teo | A computer aided system to automate the restoration of electrical power supply | |
| JP3577540B2 (en) | Power system accident facility estimation method | |
| JPS6367417B2 (en) | ||
| JP2908219B2 (en) | Distribution line load accommodation calculation constraint relaxation method | |
| JPS63316617A (en) | Faulty facility judging system | |
| JP2004015970A (en) | Power system restoration method and device | |
| JP2007159188A (en) | Power distribution monitoring control system and method | |
| JP2645003B2 (en) | Distribution system operating device | |
| JP2577394B2 (en) | Power system accident equipment judgment device | |
| JP2680466B2 (en) | Distribution system controller | |
| JP2645013B2 (en) | Power system accident recovery system | |
| JPS6016141A (en) | Power distributing operation monitoring device | |
| JP3167166B2 (en) | Load selective cut-off device | |
| JPH067731B2 (en) | Automatic creation method of system operation command procedure in electric power system | |
| JPH08163779A (en) | Distribution system control system | |
| JPH0145822B2 (en) | ||
| Hu et al. | An Intelligent Distributed Feeder Automatic Strategy for Active Distribution Network and Its Implementation | |
| CN117791590A (en) | A method, device and structure for self-healing of distribution network lines without power interruption | |
| JPH05292665A (en) | Power system operation method | |
| JPH01144325A (en) | Plant automatic bus switching control method |