JPH09268588A - Seismic retrofitting method for submerged tunnel - Google Patents
Seismic retrofitting method for submerged tunnelInfo
- Publication number
- JPH09268588A JPH09268588A JP8112885A JP11288596A JPH09268588A JP H09268588 A JPH09268588 A JP H09268588A JP 8112885 A JP8112885 A JP 8112885A JP 11288596 A JP11288596 A JP 11288596A JP H09268588 A JPH09268588 A JP H09268588A
- Authority
- JP
- Japan
- Prior art keywords
- submerged tunnel
- tunnel
- submerged
- sides
- existing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
(57)【要約】
【課題】 既設の沈埋トンネルを耐震補強する方法と、
既設の場合と同様な手段で新設の沈埋トンネルを耐震補
強する方法の提供。
【解決手段】 第1の方法では、既設の沈埋トンネル1
の両側を掘削して、この掘削部に、地震時に作用する水
平力で容易に変形もしくは破壊される緩衝ブロック2を
設置する。第2の方法では、沈埋トンネルの新設時に、
その両側に前述の緩衝ブロックを設置する。第3の方法
では、既設の沈埋トンネルの両側と上側を沈埋トンネル
の継ぎ目部を除いて、コンクリートで被覆し、剛性を高
める。
(57) [Abstract] [Problem] Method for retrofitting an existing submerged tunnel with earthquake resistance,
Providing seismic retrofitting methods for new buried tunnels using the same means as for existing ones. According to a first method, an existing buried tunnel 1 is used.
Both sides are excavated, and buffer blocks 2 that are easily deformed or destroyed by the horizontal force that acts during an earthquake are installed in the excavated portion. In the second method, when a new submerged tunnel is built,
The above-mentioned buffer blocks are installed on both sides thereof. In the third method, both sides and the upper side of the existing submerged tunnel are covered with concrete excluding the joint portion of the submerged tunnel to increase rigidity.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、沈埋トンネルの耐
震補強方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a seismic retrofitting method for a submerged tunnel.
【0002】[0002]
【従来の技術】阪神大震災以降、特に、土木構造物や建
築物を耐震補強する要望が高まっているが、従来の沈埋
トンネルに対する耐震補強は、主として新設時になされ
ており、既設のものに対してはトンネルの内部から小規
模に行われているに過ぎず、大型の地震に十分に対応で
きるものでないのが実情である。2. Description of the Related Art Since the Great Hanshin Earthquake, there has been an increasing demand for seismic retrofitting of civil engineering structures and buildings, but seismic retrofitting of conventional submerged tunnels has been done mainly at the time of new construction, and it has been The fact is that it is only carried out on a small scale from inside the tunnel, and it is not enough to deal with a large earthquake.
【0003】[0003]
【発明が解決しようとする課題】本発明が解決しようと
する課題、すなわち、本発明の目的は、第1に、前述の
実情に鑑み、既設の沈埋トンネルを大型の地震にも十分
に耐えうるように補強する新規方法を提供することにあ
り、第2に、既設の場合と同様な手段で新設のものを耐
震補強する方法を提供することにある。DISCLOSURE OF THE INVENTION The problem to be solved by the present invention, that is, the object of the present invention is, firstly, in view of the above-mentioned circumstances, the existing submerged tunnel can sufficiently withstand a large earthquake. The second purpose is to provide a method for seismic strengthening a new construction by the same means as the existing construction.
【0004】[0004]
【課題を解決するための手段】前記第1の目的を達成す
るために、本発明の第1の方法では、既設の沈埋トンネ
ルの両側を掘削し、この掘削部に、地震時に作用する水
平力で簡単に変形もしくは破壊される緩衝ブロックを設
置している。In order to achieve the above first object, in the first method of the present invention, both sides of an existing submerged tunnel are excavated, and a horizontal force acting on the excavated portion during an earthquake is applied. A buffer block that can be easily deformed or destroyed is installed.
【0005】前記第2の目的を達成するために、、本発
明の第2の方法では、沈埋トンネルを新設する際に、底
面の巾が沈埋トンネルの巾よりも広いトレンチを掘削
し、その中央部に沿って沈埋トンネルを構築するとも
に、その両側に、地震時に作用する水平力で簡単に変形
もしくは破壊される緩衝ブロックを設置している。In order to achieve the above-mentioned second object, in the second method of the present invention, when a submerged tunnel is newly installed, a trench whose bottom width is wider than that of the submerged tunnel is excavated, and the center of the trench is excavated. In addition to constructing a submerged tunnel along the section, buffer blocks that are easily deformed or destroyed by the horizontal force acting during an earthquake are installed on both sides of the tunnel.
【0006】本発明の第1の発明と同じ目的を達成する
ために、、本発明の第3の方法では、既設の沈埋トンネ
ルの両側に適宜間隔を明けて山留め矢板を打設し、その
内側を掘削して沈埋トンネルを露出させ、両側の山留め
矢板の上端部間に頂鈑を架設した後、山留め矢板および
頂版と沈埋トンネルとの間の間隙部に、沈埋トンネルの
継ぎ目部を除いて、コンクリートを充填している。In order to achieve the same object as the first invention of the present invention, in the third method of the present invention, mountain retaining sheet piles are driven on both sides of an existing submerged tunnel at appropriate intervals, and the inside thereof. After excavating the burial tunnel to expose the submerged tunnel, and erected the top plate between the upper ends of the mountain retaining sheet piles on both sides, remove the seam portion of the burial tunnel in the gap between the mountain retaining sheet pile and the slab and the burial tunnel. , Filled with concrete.
【0007】なお、本発明の第1と第2の方法で用いる
緩衝ブロックの材質は任意であるが、コンクリート製に
するのが一般的である。The material of the buffer block used in the first and second methods of the present invention is arbitrary, but is generally made of concrete.
【0008】[0008]
【発明の実施の形態】本発明の第1の方法は、既設の沈
埋トンネルに作用する水平地震力を低減させることを意
図してなされるものであって、図1に例示する態様で実
施される。BEST MODE FOR CARRYING OUT THE INVENTION The first method of the present invention is intended to reduce the horizontal seismic force acting on an existing submerged tunnel, and is carried out in the mode illustrated in FIG. It
【0009】図1において、(1)は既設の沈埋トンネ
ル1の両側を掘削した段階、(2)は掘削部に、地震時
に作用する水平力で簡単に変形もしくは破壊される緩衝
ブロック2を設置した段階、(3)は埋め戻しの段階を
それぞれ示している。In FIG. 1, (1) is a stage in which both sides of an existing submerged tunnel 1 are excavated, and (2) is a buffer block 2 which is easily deformed or destroyed by horizontal force acting at the time of an earthquake in the excavated portion. And the step (3) shows the step of backfilling.
【0010】なお、図中、3は沈埋トンネル1の一側に
掘削に先立って打設した土留め矢板であり、このような
土留め矢板3を、図示のように沈埋トンネル1の一側に
打設するか、両側に打設するか、もしくは、全く打設し
ないかはその何れでも良い。In the figure, reference numeral 3 denotes an earth retaining sheet pile placed on one side of the submerged tunnel 1 prior to excavation. Such an earth retaining sheet pile 3 is provided on one side of the submerged tunnel 1 as shown in the figure. It does not matter whether it is set, it is set on both sides, or it is not set at all.
【0011】緩衝ブロック2の材質は任意であるが、コ
ンクリート製とするのが一般的であり、図2には、空洞
4,5を備えた直方形状で無筋コンクリート製の2種類
の緩衝ブロックが例示されている。Although the material of the buffer block 2 is arbitrary, it is generally made of concrete. In FIG. 2, two types of buffer blocks made of non-reinforced concrete having cavities 4 and 5 are made of unreinforced concrete. Is illustrated.
【0012】次に、本発明の第2の方法は、前述の第1
の方法と同様な手段で新設の沈埋トンネルに作用する水
平地震力を低減させることを意図しているものであっ
て、図1の(1)が、この方法における、底面の巾が沈
埋トンネルの巾よりも広いトレンチを掘削し、その中央
部に沿って沈埋トンネルを構築している段階を示してお
り、それ以後の作業は第1の方法の場合と同様である。Next, the second method of the present invention is the above-mentioned first method.
It is intended to reduce the horizontal seismic force acting on the new submerged tunnel by the same method as in the method of (1). It shows the step of excavating a trench wider than the width and constructing a submerged tunnel along the central part of the trench, and the subsequent work is similar to that of the first method.
【0013】なお、この第2の方法の場合、新設の沈埋
トンネルの函体の底面および両側面に予め、摩擦力低減
用のシート(例えば、塩化ビニールシート)を貼着して
おくと、耐震効果が増大する。In the case of the second method, if a sheet for reducing frictional force (for example, a vinyl chloride sheet) is previously attached to the bottom surface and both side surfaces of the box body of the new submerged tunnel, the seismic resistance will be improved. The effect increases.
【0014】次に、本発明の第3の方法は、既設の沈埋
トンネルの剛性を高めて地震力に対する耐力を向上させ
ることを意図してなされるものであって、図3に例示す
る態様で実施される。Next, the third method of the present invention is intended to enhance the rigidity of the existing submerged tunnel to improve the proof stress against seismic force. In the embodiment illustrated in FIG. Be implemented.
【0015】図3において、(1)は既設の沈埋トンル
6の両側に山留め矢板7,7を打設した段階、(2)は
山留め矢板7,7の内側を掘削して沈埋トンネル6を露
出させた段階、(3)は山留め矢板7,7の上端部間に
頂版8を架設した後、山留め矢板7,7および頂版8と
沈埋トンネル6の函体9との間の間隙部に水中打設のコ
ンクリート10を施し、函体9をコンクリート10で包
んでその剛性を大にした段階を示している。In FIG. 3, (1) is a stage in which pile retaining sheet piles 7, 7 are placed on both sides of the existing buried tunnel 6, and (2) is an excavation inside the pile retaining sheet piles 7, 7 to expose the buried tunnel 6. In the step (3), after the top plate 8 was installed between the upper ends of the mountain retaining sheet piles 7, 7, the mountain retaining sheet piles 7, 7 and the space between the top plate 8 and the box body 9 of the submerged tunnel 6 were installed. This shows a stage in which the concrete 10 for underwater casting is applied and the box 9 is wrapped with the concrete 10 to increase its rigidity.
【0016】そして、図3の(4)は前述の(3)の段
階における沈埋トンネル6の継ぎ目部11(函体9の接
続部)の断面を示しており、この図から明らかなよう
に、この部分にはコンクリートを充填しないので、その
剛性は小であり、補強後もフレキシブルジョイントとし
ての性能を保持する。FIG. 3 (4) shows a cross section of the seam portion 11 (connection portion of the box 9) of the submerged tunnel 6 at the above-mentioned step (3). As is clear from this figure, Since this part is not filled with concrete, its rigidity is small and the performance as a flexible joint is maintained even after reinforcement.
【0017】山留め矢板7と頂版8には剛性の確保とコ
ンクリート10との一体的付着のための手段を施すのが
好ましく、また、函体9は軸力が伝達されないようにコ
ンクリート10と一体化させないのが良いが、その手段
の一例として、露出させた函体9の表面に塩化ビニール
シートを貼り付けることが考えられる。It is preferable that the mountain retaining sheet pile 7 and the top plate 8 are provided with means for securing rigidity and integrally adhering with the concrete 10, and the box 9 is integrated with the concrete 10 so that axial force is not transmitted. Although it is better not to turn it into vinyl, as an example of such means, it is conceivable to attach a vinyl chloride sheet to the exposed surface of the box 9.
【図1】本発明の第1の方法と第2の方法の説明図であ
る。FIG. 1 is an explanatory diagram of a first method and a second method of the present invention.
【図2】本発明の第1の方法と第2の方法で使用する緩
衝ブロックの2例の斜視図である。FIG. 2 is a perspective view of two examples of buffer blocks used in the first method and the second method of the present invention.
【図3】本発明の第3の方法の説明図である。FIG. 3 is an explanatory diagram of a third method of the present invention.
1:沈埋トンネル、2:緩衝ブロック、3:土留め矢
板、4:空洞、5:空洞、6:沈埋トンネル、7:土留
め矢板、8:頂版、9:函体、10:コンクリート、1
1:継ぎ目部。1: Submerged tunnel, 2: Buffer block, 3: Earth retaining sheet pile, 4: Hollow, 5: Hollow, 6: Submerged tunnel, 7: Earth retaining sheet pile, 8: Top plate, 9: Box, 10: Concrete, 1
1: Seam part.
Claims (4)
の掘削部に、地震時に作用する水平力で簡単に変形もし
くは破壊される緩衝ブロックを設置することを特徴とす
る沈埋トンネルの耐震補強方法。1. A seismic retrofitting method for a submerged tunnel, which comprises excavating both sides of an existing submerged tunnel, and installing a buffer block in the excavated portion that is easily deformed or destroyed by a horizontal force acting during an earthquake. .
が沈埋トンネルの巾よりも広いトレンチを掘削し、その
中央部に沿って沈埋トンネルを構築するとともに、その
両側に、地震時に作用する水平力で簡単に変形もしくは
破壊される緩衝ブロックを設置することを特徴とする沈
埋トンネルの耐震補強方法。2. When newly constructing a submerged tunnel, a trench whose bottom width is wider than that of the submerged tunnel is excavated, a submerged tunnel is constructed along the center of the trench, and both sides act on an earthquake. A seismic reinforcement method for submerged tunnels, characterized by installing a buffer block that can be easily deformed or destroyed by horizontal force.
請求項1または請求項2記載の沈埋トンネルの耐震補強
方法。3. The seismic reinforcement method for a submerged tunnel according to claim 1, wherein a concrete buffer block is used.
明けて山留め矢板を打設し、その内側を掘削して沈埋ト
ンネルを露出させ、両側の山留め矢板の上端部間に頂鈑
を架設した後、山留め矢板および頂版と沈埋トンネルと
の間の間隙部に、沈埋トンネルの継ぎ目部を除いて、コ
ンクリートを充填することを特徴とする沈埋トンネルの
耐震補強方法。4. An embankment sheet pile is struck on both sides of an existing submerged tunnel at appropriate intervals, the inside is excavated to expose the submerged tunnel, and a top plate is erected between the upper ends of the mountain pile sheet piles on both sides. A seismic reinforcement method for the submerged tunnel, characterized in that after that, the gap between the mountain retaining sheet pile and the top plate and the submerged tunnel is filled with concrete excluding the seam of the submerged tunnel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8112885A JPH09268588A (en) | 1996-04-01 | 1996-04-01 | Seismic retrofitting method for submerged tunnel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8112885A JPH09268588A (en) | 1996-04-01 | 1996-04-01 | Seismic retrofitting method for submerged tunnel |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH09268588A true JPH09268588A (en) | 1997-10-14 |
Family
ID=14597964
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8112885A Pending JPH09268588A (en) | 1996-04-01 | 1996-04-01 | Seismic retrofitting method for submerged tunnel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH09268588A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2011026942A (en) * | 2009-06-25 | 2011-02-10 | Shimizu Corp | Seismic strengthening structure for box culvert |
| CN114961763A (en) * | 2021-02-26 | 2022-08-30 | 宝山钢铁股份有限公司 | A sheltered tunnel in an underwater soft soil foundation and its construction method |
| CN114960755A (en) * | 2021-02-26 | 2022-08-30 | 宝山钢铁股份有限公司 | Shielding type tunnel on underwater rock foundation and construction method thereof |
-
1996
- 1996-04-01 JP JP8112885A patent/JPH09268588A/en active Pending
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2011026942A (en) * | 2009-06-25 | 2011-02-10 | Shimizu Corp | Seismic strengthening structure for box culvert |
| CN114961763A (en) * | 2021-02-26 | 2022-08-30 | 宝山钢铁股份有限公司 | A sheltered tunnel in an underwater soft soil foundation and its construction method |
| CN114960755A (en) * | 2021-02-26 | 2022-08-30 | 宝山钢铁股份有限公司 | Shielding type tunnel on underwater rock foundation and construction method thereof |
| CN114960755B (en) * | 2021-02-26 | 2024-06-04 | 宝山钢铁股份有限公司 | Masking tunnel on underwater rock foundation and construction method thereof |
| CN114961763B (en) * | 2021-02-26 | 2025-10-17 | 宝山钢铁股份有限公司 | Masking tunnel in underwater soft soil foundation and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2899670B2 (en) | Excavation for underground structures | |
| JP3185190B2 (en) | Construction method of PC hollow pile and underground structure | |
| JP2697558B2 (en) | Independent mountain retaining wall method | |
| JPH0762436B2 (en) | Open shield method | |
| JP2969607B1 (en) | Method for constructing box culvert without pulling out pile retaining pile and panel member used in this method | |
| JPH0613770B2 (en) | Method of constructing mountain retaining wall with parent pile | |
| JP3012896B2 (en) | Reverse cutting method combined with advance cutting | |
| JP3520358B2 (en) | Connection structure between horizontal shaft structure and vertical shaft structure | |
| JP4322688B2 (en) | Construction method of large section tunnel | |
| JP3114093B2 (en) | Concrete box used for open shield method | |
| JP4117209B2 (en) | Bridge pier / Abutment base combined reinforcement structure | |
| JP2520036B2 (en) | Construction method of large section underground cavity and large section tunnel | |
| JP2565452B2 (en) | Construction method of self-supporting retaining wall | |
| JPH07300845A (en) | Liquefaction countermeasure method for underground linear structures | |
| JPS5851092B2 (en) | Earth retaining installation method using advance shoring frame | |
| JPH10298976A (en) | Foundation structure of building with soil cement pillar row retaining wall tied to frame | |
| JP2897666B2 (en) | Reaction receiving structure for starting a shield machine | |
| JP3147437B2 (en) | Construction method of underground diaphragm wall | |
| JP2000220374A (en) | How to build a shaft | |
| JP2828786B2 (en) | Casing shaft | |
| JP2898577B2 (en) | Starting shaft of shield machine and start method of shield machine | |
| JPS584021A (en) | Underground wall construction work | |
| JP2988516B2 (en) | Construction method of shield excavation wall | |
| JPH0133610B2 (en) | ||
| JPS58199925A (en) | Construction of underground wall and underground foundation pile with brace |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20040622 |