JPH1011502A - Production plan evaluation system - Google Patents

Production plan evaluation system

Info

Publication number
JPH1011502A
JPH1011502A JP15942196A JP15942196A JPH1011502A JP H1011502 A JPH1011502 A JP H1011502A JP 15942196 A JP15942196 A JP 15942196A JP 15942196 A JP15942196 A JP 15942196A JP H1011502 A JPH1011502 A JP H1011502A
Authority
JP
Japan
Prior art keywords
parts
schedule
plan
small
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15942196A
Other languages
Japanese (ja)
Inventor
Taiji Tsurumi
大治 鶴見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu General Ltd
Original Assignee
Fujitsu General Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu General Ltd filed Critical Fujitsu General Ltd
Priority to JP15942196A priority Critical patent/JPH1011502A/en
Publication of JPH1011502A publication Critical patent/JPH1011502A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

(57)【要約】 【課題】 小日程計画に同期した部品の欠品状況をシミ
ュレーションし、前記小日程計画を評価する。 【解決手段】 資材管理システムから部品の在庫数量
と、納入数量及び納入日などの部品情報及び製品出荷計
画を入手するステップ1と、生産ラインの稼働状況と、
前記部品情報とからラインの小日程計画を作成するステ
ップ2と、例えば、10日間の在庫部品の数量及び納入
予定日から、前記小日程計画上の生産日程順に製品使用
部品として在庫部品を引き当て、シミュレーションを実
行するステップ3と、前記シミュレーションで得た結果
を表示するステップ4と、前記小日程計画に基づく生産
が可能か否かの判定するステップ5と、可能(YES )の
場合ラインの小日程計画に沿った、出材日、部品の調整
をするステップ6と、不可能(NO)の場合前記小日程計
画の修正を行うステップ7とでなる。
(57) [Summary] [PROBLEMS] To simulate a shortage situation of parts synchronized with a small schedule plan and evaluate the small schedule plan. [MEANS FOR SOLVING PROBLEMS] Step 1 of obtaining a part inventory quantity, a part quantity such as a delivery quantity and a delivery date, and a product shipment plan from a material management system;
Step 2 of creating a small-schedule plan of the line from the parts information and, for example, from a stock part quantity and a scheduled delivery date for 10 days, assigning stock parts as product use parts in the order of production schedule on the small-schedule plan; Step 3 of executing the simulation, Step 4 of displaying the result obtained by the simulation, Step 5 of determining whether or not production based on the small schedule is possible, and if possible (YES), small schedule of the line A step 6 for adjusting the delivery date and parts in accordance with the plan, and a step 7 for correcting the small-schedule plan if impossible (NO).

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は生産管理技術に係わ
り、詳しくは小日程計画での欠品状況をシミュレーショ
ンして評価するようにした生産計画評価システムに関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production management technique, and more particularly, to a production plan evaluation system for simulating and evaluating a shortage situation in a small schedule plan.

【0002】[0002]

【従来の技術】従来、工場で製品を生産する場合、その
製品の出荷期日に合わせて作成された大日程計画から工
場の生産ラインの状況等に応じた所要の小日程計画を作
成し、この小日程計画に基づき生産ラインに、部品、人
及びツール等を投入して物を生産する。
2. Description of the Related Art Conventionally, when a product is produced in a factory, a necessary small schedule plan according to the situation of the production line of the factory is created from a large schedule plan created in accordance with the shipping date of the product. Parts, people, tools, etc. are put into the production line based on the small schedule plan to produce products.

【0003】ところで生産ラインの稼働状況と、部品在
庫などとを勘案して作成した上記小日程計画は、納入予
定部品の納入遅延等のため発生する欠品状況により修正
が必要となることが普通である。部品a1、a2及びa
3で構成される製品Aを100個生産する小日程計画に
ついて、図4を参照して具体的に説明する。先ず第一例
は、図4に示したように、部品が予定どうりに納入さ
れ、生産開始予定日における構成部品a1の在庫数が9
0個で受注残数10個、構成部品a2の在庫数が100
個で受注残数0個、構成部品a3の在庫数が60個で受
注残数40個であるとする。この生産計画を実施するこ
とにより、製品Aを60個作ることが可能である。ま
た、製品Aの仕掛かり品(a3が不足の状態の品)が3
0個できる。ここで、他の例として、部品a1は生産開
始日までに50個しか納入されず、部品a1の在庫数が
50個である場合、今度は製品Aは50個だけ作ること
が可能となり、仕掛かり品は50個となる。また、他の
例として、生産開始日を2日遅延するようにした場合、
例えば、構成部品a3の受注残数40個がこの2日の間
に納入され、在庫数が60個から100個に増加するの
で、製品Aは90個作ることが可能で、仕掛かり品は1
0個となる。通常、工場では上記各例に示したように、
部品の納入状況を見極めながら、仕掛かり品を少なくす
るように、未納入部品の督促、納期の確認をしたり、生
産日程を遅延させたり或いは製品製造の日程を組み替え
たり等の生産計画の修正を行って最も都合の良い計画を
実施するようにしている。
[0003] The above-mentioned small-schedule plan created in consideration of the operation status of the production line and the stock of parts usually needs to be corrected due to a shortage situation that occurs due to a delay in delivery of parts to be delivered. It is. Parts a1, a2 and a
The small schedule plan for producing 100 products A constituted by the three items will be specifically described with reference to FIG. First, in the first example, as shown in FIG. 4, the parts are delivered according to schedule, and the inventory number of the component a1 on the scheduled production start date is nine.
0 pieces, 10 backorders, and 100 parts a2 in stock
It is assumed that the number of order backlogs is 0, the number of components a3 in stock is 60, and the number of order backlogs is 40. By implementing this production plan, it is possible to produce 60 products A. In addition, the number of in-process products (products with insufficient a3) of product A is 3
You can do zero. Here, as another example, if only 50 parts a1 are delivered by the production start date and the number of parts a1 in stock is 50 pieces, then only 50 pieces of product A can be manufactured. The number of hanging products is 50 pieces. As another example, if the production start date is delayed by two days,
For example, the order backlog of the component a3 is delivered in the last two days, and the stock increases from 60 to 100. Therefore, 90 products A can be manufactured, and the number of products in process is 1
It becomes zero. Normally, as shown in the above examples,
Revise the production plan, such as urging undelivered parts, confirming the delivery date, delaying the production schedule, or changing the schedule of product production, so as to reduce the work-in-progress while checking the delivery status of parts. To implement the most convenient plan.

【0004】実際には、部品の発注等の管理に付いては
購買部門の資材管理システムがあり、この資材管理シス
テムで大日程計画により製品毎の大まかな部品納期に基
づき、部品の発注及び納期管理を行っている。
In practice, there is a material management system of a purchasing department for managing the ordering of parts and the like. The material management system uses a large schedule to order and deliver parts based on a rough part delivery time for each product. Managing.

【0005】ところで、従来工場の生産管理部門では生
産計画の実施にあたり、上記資材管理システムの出力リ
ストを参照して、納期、納入部品及び在庫状況等を把握
して、上述したように小日程計画(生産計画)の修正等
を行っていた。
[0005] By the way, when the production management department of the conventional factory implements the production plan, the delivery schedule, the parts to be delivered, the stock status, and the like are grasped by referring to the output list of the material management system, and as described above, the small schedule planning is performed. (Production plan) was revised.

【0006】しかし、上記出力リストの内容は、大日程
計画に基づいた大まかなものであり、実際の生産に使用
する小日程計画とは日程が必ずしも同期していない。通
常は1週間程度の誤差を含んでいることが多い。そのた
め、工場の生産管理部門では前記出力リストに基づき出
材指示を行うと、小日程計画の実施日以前に部品が出材
されることがある。従って、例えば、生産工程の後段で
使用される梱包材などが工程の最初に出庫されたような
場合の、場所を塞ぐなどの問題、また、必要数に満たな
い部品(欠品部品)の出材が指示されることにより、仕
掛かり品の在庫が発生する問題、さらに、小日程計画の
作成時に予想される欠品部品の把握が困難であるなどの
問題があった。
However, the contents of the output list are rough based on the large schedule, and the schedule is not always synchronized with the small schedule used for actual production. Usually, it often includes an error of about one week. Therefore, if the production management department of the factory issues a material output instruction based on the output list, parts may be output before the execution date of the small schedule plan. Therefore, for example, when packing materials used in a later stage of the production process are delivered at the beginning of the process, there is a problem such as blockage of a place, and a required number of parts (missing parts) are output. There is a problem that the designation of the material causes the stock of the work-in-progress to occur, and furthermore, it is difficult to grasp the missing parts expected at the time of creating the small schedule plan.

【0007】[0007]

【発明が解決しようとする課題】本発明は上記問題点に
鑑みなされたもので、小日程計画に同期した部品の欠品
状況をシミュレーションし、同小日程計画で生産を行う
か或いは同小日程計画を修正するかを判定するようにし
た生産計画評価システムを提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and simulates a situation in which parts are out of stock in synchronization with a small schedule. It is an object of the present invention to provide a production plan evaluation system configured to determine whether to modify a plan.

【0008】[0008]

【課題を解決するための手段】上記目的を達成するため
に、部品の在庫データを記憶する在庫データ部と、部品
の納期管理データを記憶する納期データ部と、製品毎に
部品構成表データを記憶する部品表データ部と、製品出
荷計画データを記憶する出荷計画データ部と、部品の在
庫数、納入数、発注残数及び引き当て数に基づき生産日
毎の欠品数を算定するシミュレーション実行部と、製品
出荷計画及びラインの稼働状況に基づき小日程計画を作
成する小日程作成部と、算定した欠品数及び所要基準に
基づき前記小日程計画を実行するか否かを判定する判定
部と、シミュレーション結果を表示する表示部と、シス
テム動作のアルゴリズムを記述したプログラム及び前記
所要基準を記憶するメモリ部と、各部を制御する制御部
とで構成し、上記小日程計画の日毎に欠品シミュレーシ
ョンを実施し、欠品部品の状況により前記小日程計画を
修正するか若しくはそのまま実行するかを判断するよう
にした。
In order to achieve the above object, in order to achieve the above object, an inventory data section for storing inventory data of parts, a delivery date data section for storing delivery date management data of parts, and a parts configuration table data for each product. A parts list data part to store, a shipping plan data part to store product shipping plan data, and a simulation execution part for calculating the number of missing parts for each production day based on the number of parts in stock, the number of deliveries, the number of remaining orders and the number of reserves, A small-schedule creating unit that creates a small-schedule plan based on the product shipment plan and the operation status of the line; a determining unit that determines whether to execute the small-schedule plan based on the calculated number of missing parts and a required standard; and a simulation result. , A memory unit for storing a program describing the algorithm of the system operation and the required reference, and a control unit for controlling each unit. The shortage simulations carried out daily schedule was to determine whether or directly run to correct the small scheduling by the situation of shortage parts.

【0009】また、資材管理システムの大日程計画に基
づく生産日程を記述した小日程計画を作成する第一ステ
ップと、前記資材管理システムから所要の期間に付き在
庫部品の数及び納入予定日を取得して、前記小日程計画
上の製品毎に在庫部品を引き当てることにより、同製品
と欠品部品の数及び納入予定日とを関連付けする第二ス
テップと、前記第二ステップで関連付けした欠品部品の
数と納入予定日とを表示する第三ステップと、前記表示
した欠品部品の状況から前記小日程計画を修正するか或
いは前記小日程計画をそのままとするかの判断を行う第
四ステップとで構成した。
A first step of preparing a small schedule describing a production schedule based on the large schedule of the material management system, and acquiring the number of stock parts and the scheduled delivery date for a required period from the material management system Then, a second step of associating the product with the number of missing parts and the scheduled delivery date by assigning stock parts to each product on the small-schedule plan, and a missing part associated with the second step A third step of displaying the number of items and the expected delivery date, and a fourth step of determining whether to correct the small-schedule plan or leave the small-schedule plan unchanged from the status of the displayed missing parts. It consisted of.

【0010】[0010]

【発明の実施の形態】以上のように構成したので、資材
管理システムから所要期間に付き欠品部品の数と納入予
定日と製品出荷日とを取得し、小日程計画上の生産日程
順に製品に在庫部品を引き当てるようにして、前記所要
期間の日毎に製品と欠品部品の数、発注残数及び納入予
定日とを関連付けることにより、欠品部品の数と、該欠
品部品の部品ランクから生産日程が妥当か否かの判定を
行う。
DESCRIPTION OF THE PREFERRED EMBODIMENTS With the above configuration, the number of missing parts, the scheduled delivery date, and the product shipping date are acquired from the material management system for a required period, and the products are ordered in the production schedule in the small schedule plan. By associating the product with the number of missing parts, the number of remaining parts, and the expected delivery date for each day of the required period, the number of missing parts and the part rank of the missing parts Then, it is determined whether or not the production schedule is appropriate.

【0011】[0011]

【実施例】以下、本発明による生産計画評価システムに
ついて、図を用いて詳細に説明する。図1は本発明によ
る生産計画評価システムの実施例を示すブロック図であ
る。1は部品の在庫データを記憶する、例えば、RAM
(Random Access Memory)で構成した在庫データ部であ
る。2は部品の納期管理データを記憶する、例えば、R
AMで構成した納期データ部である。3は製品の部品構
成表データを記憶する、例えば、RAMで構成した部品
表データ部である。4は、例えば、生産開始日以降の1
0日間の在庫数、納入数、発注残数及び引き当て数に基
づき、生産日毎に欠品数を算定するようにしたシミュレ
ーション実行部である。5は製品出荷計画及びラインの
稼働状況に基づき小日程計画を作成する小日程作成部で
ある。6は算定した欠品数及び所要基準に基づき前記小
日程計画を実行するか否かを判定する判定部である。7
はシミュレーション結果を表示する、例えば、パソコン
等のディスプレイで構成した表示部である。8はシステ
ム動作のアルゴリズムを記述したプログラム及び前記所
要基準を記憶するメモリ部である。9は各部を制御する
制御部である。10は、資材管理システムから得た製品
出荷計画の所要データ、例えば、製品出荷日等を記憶す
る出荷計画データ部である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A production plan evaluation system according to the present invention will be described below in detail with reference to the drawings. FIG. 1 is a block diagram showing an embodiment of a production plan evaluation system according to the present invention. 1 stores part inventory data, for example, RAM
(Random Access Memory). 2 stores delivery date management data of parts, for example, R
This is a delivery date data section configured by AM. Reference numeral 3 denotes a parts bill data section configured to store parts bill data of a product, for example, a RAM. 4 is, for example, 1 after the production start date.
A simulation execution unit that calculates the number of missing parts for each production day based on the number of stocks, the number of deliveries, the number of remaining orders, and the number of reserves in 0 days. Reference numeral 5 denotes a small schedule creation unit that creates a small schedule based on the product shipment plan and the operation status of the line. Reference numeral 6 denotes a determination unit that determines whether or not to execute the small-schedule plan based on the calculated number of missing parts and a required standard. 7
Is a display unit that displays a simulation result, for example, a display such as a personal computer. A memory unit 8 stores a program describing an algorithm of a system operation and the required standard. A control unit 9 controls each unit. Reference numeral 10 denotes a shipment plan data section for storing required data of a product shipment plan obtained from the material management system, for example, a product shipment date.

【0012】図2は本発明による生産計画評価システム
の実施例の動作を示すフローチャートである。このフロ
ーチャート及び図1を参照して本発明による生産計画評
価システムの生産計画評価動作を説明する。生産計画評
価システムでは、ステップ1(STP1) は資材管理システ
ムの製品生産の大日程計画から、部品の在庫数と、納入
数及び納入日などの部品情報と、製品出荷計画の製品出
荷日等を入手し、それぞれ在庫データ部1、納期データ
部2及び出荷計画データ部10に記憶させる。ステップ
2(STP2) は、小日程作成部5で生産ラインの稼働状況
と、前記部品情報と、製品出荷日等から工場ラインで生
産のための小日程計画を作成する。ステップ3(STP3)
は、シミュレーション実行部4で、前記在庫データ部1
及び納期データ部2に記憶させた生産開始日以降、例え
ば、10日間に付き在庫部品の数、納入予定日及び製品
出荷日等に基づき、前記小日程計画上の生産日程順に、
部品表データ部3の製品生産使用部品に在庫部品を引き
当て、その結果、在庫部品が不足した、所謂、欠品部品
の数及び納入予定日を製品に関連付けて欠品状況を明ら
かにする(シミュレーションの実行)。
FIG. 2 is a flowchart showing the operation of the embodiment of the production plan evaluation system according to the present invention. The production plan evaluation operation of the production plan evaluation system according to the present invention will be described with reference to this flowchart and FIG. In the production plan evaluation system, step 1 (STP1) is to calculate the parts information such as the number of parts, the number of parts delivered, the delivery date, etc., Obtained and stored in the inventory data section 1, the delivery date data section 2, and the shipment plan data section 10, respectively. In step 2 (STP2), the small schedule creation unit 5 creates a small schedule plan for production on the factory line based on the operation status of the production line, the component information, the product shipping date, and the like. Step 3 (STP3)
Is the simulation execution unit 4 and the inventory data unit 1
After the production start date stored in the delivery date data unit 2, for example, based on the number of stock parts per 10 days, the scheduled delivery date, the product shipping date, etc., in the order of the production schedule in the small schedule plan,
The stock parts are allocated to the parts used for product production in the parts table data part 3, and as a result, the stock shortage state is clarified by associating the so-called number of missing parts and the expected delivery date with the product with a shortage of stock parts (simulation). Run).

【0013】ステップ4(STP4) は、前記ステップ3
(STP3) のシミュレーションで得た製品と、関連付けた
欠品部品と、その数及び納入予定日とを表示部8に表示
する。ステップ5(STP5) は判定部6で、例えば、欠品
部品の数と、メモリ部7に記憶している同欠品部品の生
産工程上の重要度を示す部品ランク及び欠品許容数とか
らステップ2の小日程計画に基づく生産が可能か否かの
判定をする。例えば、部品Lが組立予定日に30個欠品
となる等で、部品Lは重要度を示す部品ランクは低い
上、欠品許容数が100個であった場合、判定部6は生
産が可能と判断する。そして、実際には部品Lが後に納
入された時点で、後組立を実施して対処することにす
る。前記テップ5で可能(YES )の場合、ステップ6
(STP6) は、前記小日程作成部5でラインの小日程計画
に沿った、出材日、部品の調整を行う。また、前記テッ
プ5で不可能(NO)の場合、ステップ7(STP7) は前記
小日程作成部5でステップ2の小日程計画を、例えば、
製品の生産順番を変える、生産開始日を遅延する等の修
正を行う。
Step 4 (STP4) is the same as step 3
The display unit 8 displays the product obtained by the simulation of (STP3), the associated missing parts, the number thereof, and the scheduled delivery date. In step 5 (STP5), the determination unit 6 determines, for example, the number of missing parts, the component rank stored in the memory unit 7 indicating the importance of the same missing part in the production process, and the allowable number of missing parts. It is determined whether or not production based on the small schedule plan in step 2 is possible. For example, if the part L has a shortage of 30 parts on the scheduled assembly date, the part L has a low part rank indicating the importance, and if the allowable number of missing parts is 100, the determination unit 6 can produce. Judge. Then, in practice, when the part L is delivered later, post-assembly is performed to deal with it. If it is possible in step 5 (YES), step 6
In (STP6), the small-schedule creating unit 5 adjusts the delivery date and parts according to the small-schedule plan of the line. If it is impossible (NO) in step 5, step 7 (STP7) executes the small schedule plan in step 2 by the small schedule creation unit 5, for example,
Modify the production order of products, delay production start date, etc.

【0014】本発明による生産計画評価システムの欠品
シミュレーションについて図3に従い動作の説明を行
う。図3は本発明による生産計画評価システムの小日程
計画に基づいた欠品状況のシミュレーション結果を示す
図である。図3(イ)は計画案1の表示画面と、同計画
案1におけるシミュレーション結果の表示画面である。
詳細に説明する。計画案1は製品Aと製品Bとをこの順
に各々200個、400個づつ製造する場合の、6月1
日の製造開始日から10日分の小日程計画を線表形式で
表している。また、シミュレーション結果は最初に生産
する製品Aの構成部品の所要数に対する在庫を引き当て
ることにより、不足数/所要数及び納入予定日を表す。
尚、製品Bの不足数/所要数及び納入予定日は次ページ
以降に順次表示するようにする(図示せず)。
The operation of the out-of-stock simulation of the production plan evaluation system according to the present invention will be described with reference to FIG. FIG. 3 is a diagram showing a simulation result of a stockout situation based on the small schedule plan of the production plan evaluation system according to the present invention. FIG. 3A shows a display screen of the plan 1 and a display screen of a simulation result in the plan 1.
This will be described in detail. Plan 1 is June 1 when 200 and 400 products A and B are manufactured in this order.
A small schedule plan for 10 days from the production start date of the day is shown in a line table format. Further, the simulation result represents the shortage / required number and the scheduled delivery date by allocating stock for the required number of components of the product A to be produced first.
Note that the shortage / required number of the product B and the expected delivery date are sequentially displayed on the next page and thereafter (not shown).

【0015】シミュレーション結果から欠品状況は6月
1日の時点で部品a1は「0」、a2は「50」、a3
は「150」である。但し、a2は6月9日に納入予定
があり、a3は10日以内の納入予定が無いことを示
す。従って、この計画案1の欠品状況から、例えば、6
月1日から製造を開始し、6月4日に終了するために
は、上述したように部品a2と、a3が不足することが
容易に分かる。
According to the simulation results, the stockout situation is "0" for part a1, "50" for a2, and "a3" as of June 1.
Is “150”. However, a2 indicates that the delivery is scheduled for June 9, and a3 indicates that the delivery is not scheduled within 10 days. Therefore, based on the shortage situation of this plan 1, for example, 6
In order to start the production on the 1st of the month and finish on the 4th of June, it is easily understood that the parts a2 and a3 are insufficient as described above.

【0016】図3(ロ)は計画案2の表示画面と、同計
画案2におけるシミュレーション結果の表示画面であ
る。詳細に説明する。計画案2は製品Bと製品Aとをこ
の順に各々400個、200個づつ製造する場合の、6
月1日の製造開始日から10日分の小日程計画を線表形
式で表している。また、シミュレーション結果は最初に
生産する製品Bの構成部品の所要数に対する在庫を引き
当てることにより、不足数/所要数及び納入予定日を表
す。尚、製品Aの不足数/所要数及び納入予定日は次ペ
ージ以降に順次表示するようにする(図示せず)。シミ
ュレーション結果から欠品状況は6月1日時点で部品b
1は「0」、b2は「20」、b3は「100」であ
る。但し、b2は6月5日に、b3は6月1日に納入予
定があることを示す。
FIG. 3B shows a display screen of the plan 2 and a display screen of a simulation result in the plan 2. This will be described in detail. The plan 2 is for manufacturing 400 and 200 products B and A in this order, respectively.
The small schedule plan for 10 days from the production start date of the first month is shown in a line table format. In addition, the simulation result represents the shortage / required number and the scheduled delivery date by allocating stock for the required number of components of the product B to be produced first. In addition, the shortage / required number of the product A and the expected delivery date are sequentially displayed on the subsequent pages (not shown). From the simulation results, the shortage situation is as of June 1 for parts b
1 is “0”, b2 is “20”, and b3 is “100”. However, b2 indicates that the delivery is scheduled for June 5, and b3 indicates that the delivery is scheduled for June 1.

【0017】従って、この計画案2の欠品状況のシミュ
レーションから6月1日から製造を開始し、6月9日に
終了するためには、当初は不足があるものの、生産期間
中に上述のように納入予定があるので、前記不足が解消
されることになり、この計画案2による生産ではほとん
ど問題が無いことが分かる。尚、本発明による生産計画
評価システムは、上述した動作アルゴリズムを実現する
ソフトを開発してパソコン或いはワークステーション等
で構築することができるので、自動的に資材管理システ
ムから部品情報を得て複数の小日程計画を作成し、それ
ぞれの欠品状況を生産日毎にシミュレーションして、デ
ィスプレイに表示するとともに、該小日程計画で生産可
能か否かの判断を行うものである。また、製品組立上等
の部品の重要度を示す部品ランクを設定し、この部品ラ
ンクと欠品許容数とを対照表にしてメモリ部7に記憶さ
せておくことにより、欠品が存在する場合も生産が可能
か否の判断ができるようにしても良い。また、上述した
ように、欠品状況を把握するためのシミュレーション期
間は、経験上から1週間乃至、10日程度が妥当であ
る。
Therefore, in order to start the production from June 1 and finish on June 9 based on the simulation of the shortage situation of the plan 2, there is a shortage at the beginning, but the above-mentioned during the production period. As described above, the shortage will be resolved, and it can be seen that there is almost no problem in the production according to the plan 2. Note that the production plan evaluation system according to the present invention can be constructed on a personal computer or a workstation by developing software for realizing the above-described operation algorithm. A small schedule plan is created, the shortage status is simulated for each production day, displayed on a display, and it is determined whether or not production is possible with the small schedule plan. Also, by setting a part rank indicating the importance of parts for assembling a product, and storing the part rank in the memory unit 7 as a comparison table with the permissible number of missing parts, it is possible to determine whether parts are missing. It may also be possible to determine whether or not production is possible. Also, as described above, the simulation period for grasping the out-of-stock condition is appropriately from one week to 10 days from experience.

【0018】[0018]

【発明の効果】以上説明したように、本発明は小日程計
画に同期した部品の欠品状況をシミュレーションし、同
小日程計画で生産を行うか或いは同小日程計画を修正す
るかを判定するようにした生産計画評価システムを提供
する。従って、工場の生産管理部門では本発明による生
産計画評価システムを利用して小日程計画を簡易に評価
できる。さらに、修正した小日程計画に基づき、実際の
生産に則した出材指示を行うことができる効果を奏す
る。
As described above, the present invention simulates the shortage situation of parts synchronized with the small schedule plan, and determines whether to perform the production according to the small schedule plan or to modify the small schedule plan. Thus, a production plan evaluation system is provided. Therefore, the production management department of the factory can easily evaluate the small schedule plan using the production plan evaluation system according to the present invention. Further, there is an effect that it is possible to issue a material output instruction in accordance with actual production based on the modified small schedule plan.

【0019】また、修正した小日程計画に基づき、欠品
部品が発生しないように出材指示を行うことにより、仕
掛かり品の在庫を無くすことができる大きな効果を奏す
る。
Further, by issuing a command to output materials based on the modified small schedule plan so as to prevent the occurrence of missing parts, there is a great effect that the stock of in-process products can be eliminated.

【0020】また、パソコン等の画面に欠品状況のシミ
ュレーション結果が分かり易く表示されるので、欠品部
品の把握が容易であり、部品管理がし易い効果を奏す
る。
Further, since the simulation result of the out-of-stock situation is displayed on the screen of a personal computer or the like in an easy-to-understand manner, it is easy to grasp the out-of-stock parts and to easily manage the parts.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明による生産計画評価システムの実施例を
示すブロック図である。
FIG. 1 is a block diagram showing an embodiment of a production plan evaluation system according to the present invention.

【図2】本発明による生産計画評価システムの実施例の
動作を示すフローチャートである。
FIG. 2 is a flowchart showing an operation of the embodiment of the production plan evaluation system according to the present invention.

【図3】本発明による生産計画評価システムの小日程計
画に基づいた欠品状況のシミュレーション結果を示す図
である。
FIG. 3 is a diagram showing a simulation result of a stockout situation based on a small schedule in the production plan evaluation system according to the present invention.

【図4】製品の構成部品の必要数と、在庫の関係を示す
図である。
FIG. 4 is a diagram showing the relationship between the required number of component parts of a product and inventory.

【符号の説明】[Explanation of symbols]

1 在庫データ部 2 納期データ部 3 部品表データ部 4 シミュレーション実行部 5 小日程作成部 6 判定部 7 表示部 8 メモリ部 9 制御部 10 出荷計画データ部 Reference Signs List 1 stock data part 2 delivery date data part 3 parts list data part 4 simulation execution part 5 small schedule creation part 6 judgment part 7 display part 8 memory part 9 control part 10 shipping plan data part

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】 部品の在庫データを記憶する在庫データ
部と、部品の納期管理データを記憶する納期データ部
と、製品毎に部品構成表データを記憶する部品表データ
部と、製品出荷計画データを記憶する出荷計画データ部
と、部品の在庫数、納入数、発注残数及び引き当て数に
基づき生産日毎の欠品数を算定するシミュレーション実
行部と、製品出荷計画及びラインの稼働状況に基づき小
日程計画を作成する小日程作成部と、算定した欠品数及
び所要基準に基づき前記小日程計画を実行するか否かを
判定する判定部と、シミュレーション結果を表示する表
示部と、システム動作のアルゴリズムを記述したプログ
ラム及び前記所要基準を記憶するメモリ部と、各部を制
御する制御部とで構成し、 上記小日程計画の日毎に欠品シミュレーションを実施
し、欠品部品の状況により前記小日程計画を修正するか
若しくはそのまま実行するかを判断するようにした生産
計画評価システム。
1. An inventory data section for storing parts inventory data, a delivery date data section for storing delivery date management data for parts, a parts table data section for storing parts configuration table data for each product, and product shipping plan data. And a simulation execution unit that calculates the number of missing parts for each production day based on the number of parts in stock, the number of deliveries, the number of remaining orders and the number of reserves, and a small schedule based on the product shipment plan and line operation status A small-schedule creating unit for creating a plan, a determining unit for determining whether to execute the small-schedule plan based on the calculated number of missing parts and a required standard, a display unit for displaying a simulation result, and an algorithm of a system operation. A memory unit for storing the described program and the required standard, and a control unit for controlling each unit, and a shortage simulation is performed for each day of the small schedule. Applied, production planning evaluation system so as to determine whether to perform either or as it is modifying the small scheduling by the situation of shortage parts.
【請求項2】 上記所要基準を部品ランク及び欠品許容
数で構成することを特徴にした請求項1記載の生産計画
評価システム。
2. The production plan evaluation system according to claim 1, wherein said required standard is constituted by a part rank and an allowable number of missing parts.
【請求項3】 部品毎に部品ランク及び欠品数を対照表
にしてメモリ部に記憶させるようにした請求項1記載の
生産計画評価システム。
3. The production plan evaluation system according to claim 1, wherein the rank and the number of missing parts for each part are stored in a memory as a comparison table.
【請求項4】 上記在庫データ部と、納期データ部と、
部品表データ部と、出荷計画データ部とをRAMで構成
するようにした請求項1記載の生産計画評価システム。
4. The inventory data section, a delivery date data section,
2. The production plan evaluation system according to claim 1, wherein the parts table data section and the shipping plan data section are configured by a RAM.
【請求項5】 資材管理システムの大日程計画に基づく
生産日程を記述した小日程計画を作成する第一ステップ
と、前記資材管理システムから所要の期間に付き在庫部
品の数及び納入予定日を取得して、前記小日程計画上の
製品毎に在庫部品を引き当てることにより、同製品と欠
品部品の数及び納入予定日とを関連付けする第二ステッ
プと、前記第二ステップで関連付けした欠品部品の数と
納入予定日とを表示する第三ステップと、前記表示した
欠品部品の状況から前記小日程計画を修正するか或いは
前記小日程計画をそのままとするかの判断を行う第四ス
テップとで構成した生産計画評価システム。
5. A first step of preparing a small schedule describing a production schedule based on a large schedule of the material management system, and acquiring the number of stock parts and a scheduled delivery date for a required period from the material management system. Then, a second step of associating the product with the number of missing parts and the scheduled delivery date by assigning stock parts to each product on the small-schedule plan, and a missing part associated with the second step A third step of displaying the number of items and the expected delivery date, and a fourth step of determining whether to correct the small-schedule plan or leave the small-schedule plan unchanged from the status of the displayed missing parts. A production plan evaluation system composed of
【請求項6】 上記製品毎に在庫部品を引き当てる場
合、生産日程上の早いものから順に製品の構成部品に在
庫部品を引き当てるようにした請求項5記載の生産計画
評価システム。
6. The production plan evaluation system according to claim 5, wherein when allocating the inventory parts for each product, the inventory parts are allocated to the component parts of the product in order from the earliest production schedule.
【請求項7】 上記小日程計画を線表形式で表現した請
求項5記載の生産計画評価システム。
7. The production plan evaluation system according to claim 5, wherein said small schedule plan is represented in a line table format.
【請求項8】 複数の上記小日程計画毎に、製品の欠品
部品と、その数及び納入予定日とを関連付けるようにし
た請求項5記載の生産計画評価システム。
8. The production plan evaluation system according to claim 5, wherein for each of the plurality of small schedule plans, a missing part of a product is associated with a number and a scheduled delivery date.
【請求項9】 上記表示を端末ディスプレイ上に表示す
るようにした請求項5記載の生産計画評価システム。
9. The production plan evaluation system according to claim 5, wherein said display is displayed on a terminal display.
【請求項10】 上記所要の期間をほぼ10日とする請
求項5記載の生産計画評価システム。
10. The production plan evaluation system according to claim 5, wherein said required period is approximately 10 days.
JP15942196A 1996-06-20 1996-06-20 Production plan evaluation system Pending JPH1011502A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15942196A JPH1011502A (en) 1996-06-20 1996-06-20 Production plan evaluation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15942196A JPH1011502A (en) 1996-06-20 1996-06-20 Production plan evaluation system

Publications (1)

Publication Number Publication Date
JPH1011502A true JPH1011502A (en) 1998-01-16

Family

ID=15693386

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15942196A Pending JPH1011502A (en) 1996-06-20 1996-06-20 Production plan evaluation system

Country Status (1)

Country Link
JP (1) JPH1011502A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1387231A4 (en) * 2001-05-08 2006-05-10 Daikin Ind Ltd APPARATUS AND METHOD FOR SUPPLYING PIECES
JP2007323680A (en) * 2007-09-10 2007-12-13 Hitachi Ltd Management decision support system
JP2018049578A (en) * 2016-09-23 2018-03-29 充広 藤田 ΔtLot control method product management system, ΔtLot control method product management program, and ΔtLot control method information processing program
WO2018061083A1 (en) * 2016-09-27 2018-04-05 株式会社日立製作所 Order parameter generation assistance device and order parameter generation method
JP2020057341A (en) * 2018-09-28 2020-04-09 フジキンソフト株式会社 Production management device and production management method
WO2023068052A1 (en) * 2021-10-19 2023-04-27 カシオ計算機株式会社 Inventory management method, program, and inventory management device
WO2024176489A1 (en) * 2023-02-22 2024-08-29 三菱電機株式会社 Production planning work assistance device, production planning work assistance system, production planning work assistance method, and program
WO2026011405A1 (en) * 2024-07-12 2026-01-15 苏州微源石信息科技有限公司 Mes-based production line control system and control method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1387231A4 (en) * 2001-05-08 2006-05-10 Daikin Ind Ltd APPARATUS AND METHOD FOR SUPPLYING PIECES
JP2007323680A (en) * 2007-09-10 2007-12-13 Hitachi Ltd Management decision support system
JP2018049578A (en) * 2016-09-23 2018-03-29 充広 藤田 ΔtLot control method product management system, ΔtLot control method product management program, and ΔtLot control method information processing program
WO2018061083A1 (en) * 2016-09-27 2018-04-05 株式会社日立製作所 Order parameter generation assistance device and order parameter generation method
JPWO2018061083A1 (en) * 2016-09-27 2018-11-01 株式会社日立製作所 Order parameter generation support apparatus and order parameter generation method
JP2020057341A (en) * 2018-09-28 2020-04-09 フジキンソフト株式会社 Production management device and production management method
WO2023068052A1 (en) * 2021-10-19 2023-04-27 カシオ計算機株式会社 Inventory management method, program, and inventory management device
JP2023061312A (en) * 2021-10-19 2023-05-01 カシオ計算機株式会社 Inventory management method, program, and inventory management device
WO2024176489A1 (en) * 2023-02-22 2024-08-29 三菱電機株式会社 Production planning work assistance device, production planning work assistance system, production planning work assistance method, and program
WO2026011405A1 (en) * 2024-07-12 2026-01-15 苏州微源石信息科技有限公司 Mes-based production line control system and control method

Similar Documents

Publication Publication Date Title
US8175733B2 (en) Modeling manufacturing processes to include defined markers
WO2002091094A1 (en) Parts procurement method and apparatus
JPH0425357A (en) Indication device for input
US20070219929A1 (en) Planning granularity in manufacturing computing systems
US7123977B2 (en) Production planning system
JPH1011502A (en) Production plan evaluation system
JP2013122733A (en) Production planning program and production planning device
US8494893B2 (en) Production plan making program, device, and method
JP3419216B2 (en) Production plan creation device
JP4177234B2 (en) Production planning device and production planning method
JP3640900B2 (en) Component management system, component management method, component management program, and recording medium recording component management program
JP7783067B2 (en) Warehouse work management system, warehouse work management method and program
US8027857B2 (en) Rough-cut manufacturing operations for use in planning
JP3671809B2 (en) Inventory management support device
US20050065833A1 (en) Production scheduling management method and production scheduling management program
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JP2798299B2 (en) Inventory simulation system
JPH0675975A (en) Production schedule method
JP2002006933A (en) Built-to-order manufacturing method and built-to-order manufacturing system
JPH11126221A (en) Production planning scheduling device
JP2004021891A (en) Production schedule creation system, parts delivery instruction system, production schedule creation method, and production schedule plan creation support method
JP3786029B2 (en) Material requirements planning processing system and method and material requirements planning processing program
JPH05342241A (en) Mrp system for securing parts for order accepted
JPH086997A (en) How to create an arrow diagram master for each model
JP2002351524A (en) Process scheduler system