JPH10152990A - Method for vertical placing joint, and embedded sheathing board therefor - Google Patents

Method for vertical placing joint, and embedded sheathing board therefor

Info

Publication number
JPH10152990A
JPH10152990A JP32915596A JP32915596A JPH10152990A JP H10152990 A JPH10152990 A JP H10152990A JP 32915596 A JP32915596 A JP 32915596A JP 32915596 A JP32915596 A JP 32915596A JP H10152990 A JPH10152990 A JP H10152990A
Authority
JP
Japan
Prior art keywords
concrete
board
weir
embedding
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32915596A
Other languages
Japanese (ja)
Inventor
Isao Aihara
功 相原
Takeshi Wakamatsu
岳 若松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP32915596A priority Critical patent/JPH10152990A/en
Publication of JPH10152990A publication Critical patent/JPH10152990A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with a roughening treatment such as chipping or the like in an additionally placing work. SOLUTION: Embedded sheathing plates in which structures sticking concrete are formed at both faces of the sheathing body, are arranged in a vertical placing joint in the state that reinforcements are forced to pierce the sheathing body, in this vertically placing joint (102-106). Then, concrete is placed in one side of the embedded sheathing and the other side thereof respectively (step 107, 108).

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄筋コンクリート
梁やスラブ等における鉛直打継方法及びそれに用いる埋
込みせき板に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vertical joint method for reinforced concrete beams, slabs, and the like, and an embedding board used for the method.

【0002】[0002]

【従来の技術】コンクリートに設けられた打継部は、該
打継部が欠陥部となって構造耐力や耐久性の低下を招き
やすい。したがって、コンクリートに打継部を設ける場
合には、該打継部が弱点とならないよう、先打ちコンク
リートと後打ちコンクリートとの一体性をできるだけ高
めることが重要であり、そのためには、後打ちコンクリ
ートの打設前に先打ちコンクリートの打継面を処理して
健全なコンクリートを露出させなければならない。
2. Description of the Related Art A joint portion provided in concrete is liable to cause a deterioration in structural strength and durability due to the joint portion becoming a defective portion. Therefore, when providing a joint in concrete, it is important to increase the integrity of the pre-cast concrete and the post-cast concrete as much as possible so that the joint does not become a weak point. Before casting, the joint surface of precast concrete must be treated to expose sound concrete.

【0003】ここで、鉄筋コンクリート梁、スラブ等に
おいて鉛直方向の打継部を設ける手順としては、まず、
打継部にせき板を取り付け、しかる後に先打ちコンクリ
ートを打設する。次に、養生期間が経過してからせき板
を取り外し、その露出面、すなわち打継面に対してチッ
ピングやワイヤブラシによる目荒らしを行い、該打継面
に形成された脆弱なコンクリートを除去する。
Here, the procedure for providing a vertical joint in a reinforced concrete beam, slab, or the like is as follows.
Attach a dam to the joint, and then pour first-cast concrete. Next, after the curing period has elapsed, the dam is removed, and the exposed surface, that is, the joint surface is roughened by chipping or wire brush to remove the fragile concrete formed on the joint surface. .

【0004】打継面において健全なコンクリートが露出
したならば、適宜吸水を行ってから後打ちコンクリート
を打設し、先打ちコンクリートとの一体化を図る。
[0004] When sound concrete is exposed on the joint surface, water is appropriately absorbed, and then post-cast concrete is cast to integrate the concrete with pre-cast concrete.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、打継面
に配置された多数の鉄筋が目荒らし処理の邪魔になる
上、水平方向の打継面とは異なって、先打ちコンクリー
トの硬化がかなり進んでいるため、打継面の目荒らし処
理には非常に手間がかかるという問題を生じていた。
However, a large number of rebars arranged on the joint surface hinder the roughening treatment, and unlike the horizontal joint surface, hardening of the precast concrete considerably progresses. Therefore, there has been a problem that the roughening processing of the joint surface is very troublesome.

【0006】本発明は、上述した事情を考慮してなされ
たもので、先打ちコンクリートの打継面に対しチッピン
グ等による処理が不要な鉛直打継方法及びそれに用いる
埋込みせき板を提供することを目的とする。
The present invention has been made in view of the above-mentioned circumstances, and provides a vertical joint method that does not require processing such as chipping on a joint surface of precast concrete, and an embedding dam used therefor. Aim.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するた
め、本発明の鉛直打継方法は請求項1に記載したよう
に、せき板本体の両面にコンクリート付着構造が設けら
れた埋込みせき板を前記せき板本体に鉄筋を貫通させた
状態でコンクリートの鉛直打継部に配置し、前記埋込み
せき板の一方の側と他方の側にそれぞれコンクリートを
打設するものである。
In order to achieve the above object, a vertical joint method according to the present invention comprises embedding a dam having a concrete adhering structure provided on both sides of a dam body. The rebar is penetrated into the vertical joint portion of concrete with the reinforcing bar penetrated through the main body of the weir, and concrete is poured on one side and the other side of the embedding board.

【0008】また、本発明の埋込みせき板は請求項2に
記載したように、鉄筋を挿通可能に形成されたせき板本
体の両面にコンクリート付着構造を設けてなり、該コン
クリート付着構造は、前記せき板本体の両側に打設され
たコンクリートとの付着強度を確保するようになってい
るものである。
Further, the embedding board of the present invention has a concrete adhering structure provided on both sides of a main body of the damping board formed so that a reinforcing bar can be inserted therein. This is to ensure the strength of adhesion to concrete cast on both sides of the weir board body.

【0009】また、本発明の埋込みせき板は、請求項2
のせき板本体を複数のせき板片から構成し、該せき板片
の接合縁部に形成された配筋溝内に前記鉄筋を嵌め込む
ようにしたものである。
Further, the embedding dam of the present invention is provided in claim 2 of the present invention.
The weir plate main body is composed of a plurality of weir plate pieces, and the reinforcing bar is fitted into a reinforcing groove formed in a joining edge portion of the weir plate piece.

【0010】本発明の鉛直打継方法及びそれに用いる埋
込みせき板においては、従来のせき板とは異なり、埋込
みせき板を脱型せずにそのままコンクリート内に残す。
このようにすると、埋込みせき板の両側に打設されたコ
ンクリートは、せき板本体及びそれに設けられたコンク
リート付着構造を介して相互に接合され一体化される。
そのため、従来の打継方法のように、先行打設されたコ
ンクリートの打継面をチッピングやワイヤブラシによっ
て目荒らしする必要がなくなる。
[0010] In the vertical joint method of the present invention and the embedding board used therein, unlike the conventional weir board, the embedding board is left in the concrete without being removed from the mold.
In this way, the concrete cast on both sides of the embedding board is joined and integrated with each other via the body of the board and the concrete adhering structure provided on the board.
Therefore, unlike the conventional joint method, it is not necessary to roughen the joint surface of the previously cast concrete by chipping or a wire brush.

【0011】なお、埋込みせき板は、例えばプレキャス
トコンクリート製品として製造することができるが、脱
型されずにそのままコンクリート中に埋設され、梁、床
スラブ等の構造部材の一部になるため、該構造部材と同
等若しくはそれ以上の強度となるように、必要に応じて
繊維補強し、あるいは鋼、繊維強化プラスチック等の材
料で構成する。
The embedding board can be manufactured, for example, as a precast concrete product. However, the embedding board is buried in the concrete without being removed from the mold and becomes a part of structural members such as beams and floor slabs. The fiber is reinforced as necessary so as to have a strength equal to or higher than that of the structural member, or is made of a material such as steel or fiber reinforced plastic.

【0012】鉛直打継部を設ける部位としては、梁、床
スラブ、壁等が考えられるが、いずれにしろ、打継部が
鉛直方向に延びるすべての場合に適用される。なお、こ
こで言う鉛直方向とは、厳密な意味での鉛直ではなく、
フレッシュコンクリートの水平流動を阻止するために設
けられる打継部であれば、一定の傾斜を持つものも含む
ものとする。
[0012] The portion where the vertical joint is provided may be a beam, a floor slab, a wall, or the like. In any case, the present invention is applied to all cases where the joint extends in the vertical direction. In addition, the vertical direction here is not a vertical in a strict sense,
Any joints provided to prevent the horizontal flow of fresh concrete include those having a certain slope.

【0013】埋込みせき板を鉛直打継部に取り付ける際
には、部位に応じて設置される梁筋、スラブ筋等の鉄筋
をせき板本体に貫通させる必要があるが、せき板本体を
複数のせき板片から構成し、該せき板片の接合縁部に形
成された配筋溝内に前記鉄筋を嵌め込むようにした場
合、せき板片と鉄筋とを交互に重ねていくことによって
容易に取付けが可能となる。
When the embedding board is attached to the vertical joint portion, it is necessary to penetrate a reinforcing bar such as a beam bar or a slab bar, which is installed in accordance with a part, through the bar body. In the case where the reinforcing bar is constituted by a weir plate and the reinforcing bar is fitted into a reinforcing groove formed at a joint edge of the weir plate, the reinforcing bar is easily overlapped with the reinforcing bar. Mounting becomes possible.

【0014】コンクリート付着構造をどのように構成す
るかは任意であり、例えば、せき板本体にさし筋、アン
カーボルト等の定着部材を貫通させて該本体の両側に突
出させる、せき板本体にリブ、溝等の凹凸を形成する、
せき板本体をプレキャストコンクリートで形成し該コン
クリートの骨材を露出させる等の構造が考えられる。
The construction of the concrete adhering structure is optional. For example, the concrete body is made to penetrate through a fixing member such as a penetrating bar, an anchor bolt or the like so as to protrude from both sides of the main body. Forming irregularities such as ribs and grooves,
A structure is conceivable in which the dam body is made of precast concrete and the aggregate of the concrete is exposed.

【0015】[0015]

【発明の実施の形態】以下、本発明に係る鉛直打継方法
及びそれに用いる埋込みせき板を鉄筋コンクリート梁に
適用した場合の実施形態について、添付図面を参照して
説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment in which a vertical joint method according to the present invention and an embedding board used for the method are applied to a reinforced concrete beam will be described below with reference to the accompanying drawings.

【0016】図1は、本実施形態に係る鉛直打継方法の
手順を示したフローチャートである。同図でわかるよう
に、本実施形態に係る鉛直打継方法においては、まず、
梁の型枠を設置し(ステップ101)、次いで、鉛直打
継部を設ける所定位置に本実施形態の埋込みせき板を設
置する(ステップ102〜106)。
FIG. 1 is a flowchart showing the procedure of the vertical joint method according to the present embodiment. As can be seen from the figure, in the vertical joint method according to the present embodiment, first,
A beam formwork is installed (Step 101), and then the embedding board of the present embodiment is installed at a predetermined position where a vertical joint is provided (Steps 102 to 106).

【0017】図2は、本実施形態に係る埋込みせき板1
を示した分解斜視図である。同図に示すように、埋込み
せき板1は、複数のせき板片としての下段せき板片2
a、中段せき板片2b及び上段せき板片2cからせき板
本体2を構成するとともに、コンクリート付着構造とし
てのアンカーボルト3を中段せき板片2bに貫通させて
その両側にそれぞれ突出させてなり、該アンカーボルト
3は、せき板本体2の両側に打設されたコンクリート内
に定着されて該コンクリートとの付着強度を確保するよ
うになっている。
FIG. 2 shows an embedding board 1 according to this embodiment.
FIG. As shown in the figure, the embedding dam 1 is composed of a lower dam 2 as a plurality of dams.
a, the main body 2 is composed of the middle step board piece 2b and the upper step board piece 2c, and the anchor bolt 3 as a concrete adhering structure is made to penetrate the middle step board piece 2b and protrude from both sides thereof, The anchor bolts 3 are fixed in concrete cast on both sides of the weir board main body 2 so as to secure an adhesive strength with the concrete.

【0018】下段せき板片2a、中段せき板片2b及び
上段せき板片2cは、例えばプレキャストコンクリート
製品として製造することができるが、後述するように、
脱型されずにそのまま鉄筋コンクリート梁の一部になる
ため、該梁と同等若しくはそれ以上の強度となるよう
に、必要に応じて炭素繊維等で繊維補強し、あるいはコ
ンクリートに代えて鋼、繊維強化プラスチック等の材料
で構成するのがよい。
The lower weir 2a, the middle weir 2b, and the upper weir 2c can be manufactured, for example, as a precast concrete product.
As it is part of the reinforced concrete beam as it is without being removed, it is reinforced with carbon fiber or the like as necessary so that it has the same or higher strength as this beam, or steel or fiber reinforced instead of concrete It is preferable to use a material such as plastic.

【0019】下段せき板片2a、中段せき板片2bの各
接合縁部にはそれぞれ配筋溝4、5が形成してあり、該
溝内に梁の下筋9を嵌め込むようになっている。同様
に、中段せき板片2b、上段せき板片2cの各接合縁部
にはそれぞれ配筋溝6、7が形成してあり、該溝内に梁
の上筋10を嵌め込むようになっている。
Reinforcing grooves 4 and 5 are formed at the joining edges of the lower weir 2a and the middle weir 2b, respectively, and lower braces 9 of the beams are fitted in the grooves. I have. Similarly, reinforcing joint grooves 6 and 7 are formed at the respective joining edges of the middle and upper weir plates 2b and 2c, and the upper strut 10 of the beam is fitted into the grooves. I have.

【0020】中段せき板片2bの両面にはリブ11を形
成してあり、アンカーボルト3とともにコンクリート付
着構造としての役割を果たすほか、中段せき板片2bの
曲げ剛性を高める補剛構造として兼用される。
Ribs 11 are formed on both sides of the middle wedging plate piece 2b, and serve as a concrete adhering structure together with the anchor bolt 3, and are also used as a stiffening structure for increasing the bending rigidity of the middle weeding plate piece 2b. You.

【0021】かかる埋込みせき板1を設置するには、ま
ず図3(a)、(b)に示すように、梁の型枠底部20に下段
せき板片2aを取り付ける(図1、ステップ102)。
In order to install the embedding dam 1, first, as shown in FIGS. 3A and 3B, the lower dam 2 a is attached to the bottom 20 of the beam form (step 102 in FIG. 1). .

【0022】次に、下段せき板片2aの配筋溝4内に接
着剤を塗布し該溝内に梁の下筋9を嵌め込む(ステップ
103)。なお、下筋9は、後述する上筋10とともに
図示しないあばら筋に予め通した状態で埋込みせき板1
の取付けを行うのがよい。
Next, an adhesive is applied to the inside of the reinforcing groove 4 of the lower weir 2a, and the lower line 9 of the beam is fitted into the groove (step 103). The lower muscle 9 is embedded in the embedding plate 1 in a state where the lower muscle 9 is passed through a stirrup (not shown) together with an upper muscle 10 described later.
It is good to attach.

【0023】次に、下段せき板片2aの接合面に接着剤
を塗布し、その上に図3(c)、(d)に示すように中段せき
板片2bを接合する。接合の際には、中段せき板片2b
の配筋溝5内に下筋9が嵌め込まれるように位置決めす
る(ステップ104)。なお、接着剤の塗布は、配筋溝
4への塗布と同時に行ってもよい。
Next, an adhesive is applied to the bonding surface of the lower weir 2a, and the middle weir 2b is bonded thereon as shown in FIGS. 3 (c) and 3 (d). At the time of joining, the middle step board piece 2b
Is positioned so that the lower muscle 9 is fitted into the groove 5 (step 104). The application of the adhesive may be performed simultaneously with the application to the reinforcing groove 4.

【0024】次に、ステップ103、104と同様、中
段せき板片2bの配筋溝6内に接着剤を塗布し該溝内に
梁の上筋10を嵌め込み(ステップ105)、続いて中
段せき板片2bの接合面に接着剤を塗布し、その上に上
段せき板片2cを接合する(ステップ106)。
Next, as in steps 103 and 104, an adhesive is applied to the reinforcing groove 6 of the middle weir plate piece 2b, and the upper bar 10 of the beam is fitted into the groove (step 105). An adhesive is applied to the joint surface of the plate piece 2b, and the upper weir plate piece 2c is joined thereon (step 106).

【0025】次に、図4(a)に示すように、組み立てら
れた埋込みせき板1の一方の側にコンクリート21を先
行打設し(ステップ107)、引き続いて同図(b)に示
すように反対側にコンクリート22を打設する(ステッ
プ108)。
Next, as shown in FIG. 4 (a), concrete 21 is pre-cast on one side of the assembled embedding board 1 (step 107), and subsequently, as shown in FIG. 4 (b). The concrete 22 is cast on the opposite side (step 108).

【0026】このようにすると、埋込みせき板1の両側
に打設されたコンクリート21、22は、各せき板片2
a、2b、2c及び中段せき板片2bに設けられたアン
カーボルト3を介して相互に接合され一体化される。
In this way, the concretes 21 and 22 cast on both sides of the embedding board 1 can be separated from the respective board pieces 2.
a, 2b, 2c and the intermediate step board piece 2b are joined and integrated with each other via an anchor bolt 3 provided on the middle step board piece 2b.

【0027】以上説明したように、本実施形態に係る鉛
直打継方法及びそれに用いる埋込みせき板によれば、埋
込みせき板1は、脱型されずにそのままコンクリート内
に残され、該埋込みせき板を介して両側のコンクリート
が一体化される。そのため、従来の打継方法のように、
先行打設されたコンクリートの打継面をチッピングやワ
イヤブラシによって目荒らしする必要がなくなる。
As described above, according to the vertical joint method according to the present embodiment and the embedding board used therein, the embedding board 1 is left in the concrete without being removed from the concrete, and the embedding board is removed. The concrete on both sides is integrated via the. Therefore, like the traditional method of connection,
There is no need to roughen the joint surface of the previously cast concrete by chipping or wire brush.

【0028】したがって、手間のかかるチッピング等の
作業が不要になる分だけ現場での作業が効率化されると
ともに、従来であれば、先行コンクリートの養生、せき
板の脱型及び目荒らし処理といった一連の手順を踏まな
ければ後行コンクリートの打設を行うことができず、か
かる打継処理の流れが全体工程でクリティカルになる場
合もあったが、本実施形態の鉛直打継方法によれば、先
行打設を終えてから後行打設を行うまでに一定の時間を
おく必要がなくなり、後行打設の準備が整い次第、場合
によっては同時進行で後行コンクリートの打設を行うこ
とができる。したがって、打継処理が全体工程に与える
影響はほとんどなくなり、全体の工期短縮に寄与する。
Therefore, the work on site is made more efficient by the amount of troublesome work such as chipping and the like, and conventionally, a series of steps such as curing of preceding concrete, demolding of dams and roughening are performed. Without following the procedure of the following concrete can not be poured, the flow of such a joint process may be critical in the entire process, but according to the vertical joint method of the present embodiment, There is no need to wait for a certain amount of time after the preceding placement is completed before the subsequent placement, and as soon as the preparation for the later placement is ready, the subsequent concrete placement can be performed simultaneously. it can. Therefore, the influence of the joining process on the entire process is almost negligible, which contributes to shortening the entire construction period.

【0029】また、せき板本体2を複数のせき板片2
a、2b、2cから構成し、該せき板片の接合縁部に形
成された配筋溝4、5、6、7内に梁の鉄筋9、10を
嵌め込むようにしたので、梁の型枠内にスペーサ等が交
錯していて、あるいはあばら筋がすでに配筋してあるた
めに埋込みせき板1の水平移動が困難な場合であって
も、鉄筋9、10の両側からせき板片2a、2b、2c
を挟み込むようにすることで埋込みせき板1の取付けを
容易に行うことができる。
Further, the weir board main body 2 is divided into a plurality of weir board pieces 2.
a, 2b, 2c, and the reinforcing bars 9, 10 of the beams are fitted into the reinforcing grooves 4, 5, 6, 7 formed at the joint edges of the weir plate pieces. Even when spacers and the like are intersected in the frame, or when the stirrups are already arranged, it is difficult to move the embedding board 1 horizontally. , 2b, 2c
The embedding board 1 can be easily mounted by sandwiching it.

【0030】また、梁の下筋9、上筋10がせき板片2
a、2b、2cの配筋溝4、5、6、7に位置決めされ
るので、配筋溝を設計上の配筋位置に合わせて正確に形
成しておくことにより、鉄筋のピッチやかぶり厚さを容
易に確保することが可能となる。
Further, the lower struts 9 and the upper struts 10 of the beam are
a, 2b, and 2c are positioned in the reinforcing grooves 4, 5, 6, and 7, so that the reinforcing grooves are accurately formed in accordance with the designed reinforcing arrangement position, so that the rebar pitch and cover thickness can be increased. Can be easily ensured.

【0031】また、複数のせき板片2a、2b、2c同
士を接着剤を介して接合するとともに、接合されたせき
板本体2をやはり接着剤を介して鉄筋9、10に固定す
るようにしたので、コンクリートの側圧を支持するため
の支保工を簡略化若しくは省略することが可能となる。
Further, the plurality of weir plates 2a, 2b, 2c are joined to each other via an adhesive, and the joined weir board main body 2 is fixed to the reinforcing bars 9, 10 also via the adhesive. Therefore, it is possible to simplify or omit the shoring for supporting the lateral pressure of the concrete.

【0032】本実施形態では、鉛直打継部を梁に設ける
例を説明したが、梁以外に床スラブ、や壁等に設ける場
合にも本発明を適用できることは言うまでもない。
In this embodiment, an example in which the vertical joint is provided on the beam has been described. However, it goes without saying that the present invention can be applied to a case where the vertical joint is provided on a floor slab, a wall, or the like in addition to the beam.

【0033】また、本実施形態では、せき板本体を複数
のせき板片で構成したが、かかる分割構成に代えて一体
構成としてもよい。図5は、かかる変形例に係る埋込み
せき板を示した斜視図である。同図でわかるように、本
変形例の埋込みせき板31は、一体型のせき板本体32
にアンカーボルト3を貫通させて該本体の両側に突出さ
せるとともに、梁の下筋9、上筋10をそれぞれ貫通さ
せる挿通孔33、34をせき板本体32に形成してあ
る。
Further, in the present embodiment, the main body of the weir plate is constituted by a plurality of pieces of the weir plate, but may be an integral structure instead of the divided structure. FIG. 5 is a perspective view showing an embedding board according to such a modification. As can be seen from the figure, the embedding board 31 of this modification is an integrated weir board body 32.
In addition, penetration holes 33 and 34 for penetrating the lower streaks 9 and the upper streaks 10 of the beam are formed in the dam body 32 while the anchor bolts 3 are penetrated to project from both sides of the main body.

【0034】かかる構成においても、両側に打設された
コンクリートを埋込みせき板31を介して一体化させる
とともに、先行コンクリートの打継面を処理する必要が
なくなることについては上述の実施形態とほぼ同様の効
果を奏する。
Also in this configuration, the concrete poured on both sides is integrated via the embedding plate 31, and the necessity of treating the joint surface of the preceding concrete is eliminated, which is almost the same as the above-described embodiment. Has the effect of

【0035】一体型の埋込みせき板31を使用する際
は、まず、例えば地上においてせき板本体32の挿通孔
33、34に梁の下筋9、上筋10をそれぞれ挿通した
後、あばら筋を巻いて鉄筋組立体とし、しかる後に該組
立体を梁型枠内に吊り降ろすようにするのがよい。
When the integrated embedding board 31 is used, first, for example, the lower streaks 9 and the upper streaks 10 of the beam are inserted into the insertion holes 33 and 34 of the weir board main body 32 on the ground, and then the stirrups are removed. Preferably, the assembly is wound into a rebar assembly, and the assembly is then suspended in the beam formwork.

【0036】また、本実施形態では、コンクリート付着
構造としてアンカーボルト及びリブを採用したが、設計
上の付着強度が得られるのであればこれらのいずれかを
省略してもよい。また、アンカーボルトに代えてさし筋
を用いてもよいし、せき板本体に凹凸を形成し、該凹凸
をコンクリート付着構造としてもよい。
In this embodiment, the anchor bolts and the ribs are used as the concrete attachment structure. However, any one of them may be omitted as long as the designed adhesion strength can be obtained. In addition, a cutting bar may be used in place of the anchor bolt, or irregularities may be formed on the weir board main body, and the irregularities may have a concrete adhering structure.

【0037】図6は、別の変形例に係る埋込みせき板4
1を示したものである。同図でわかるように、本変形例
の埋込みせき板41は、埋込みせき板1と同様、下段せ
き板片42a、中段せき板片42b及び上段せき板片4
2cからせき板本体42を構成してあるが、中段せき板
片42bの両面は、骨材43を露出させてコンクリート
付着構造とし、このような骨材あらわし仕上げ面にてコ
ンクリートとの付着を確保するようになっている。
FIG. 6 shows an embedding dam 4 according to another modification.
1 is shown. As can be seen from the figure, the embedding board 41 of this modification is similar to the embedding board 1 in that the lower weir 42a, the middle weir 42b, and the upper weir 4
The crevice board body 42 is formed from 2c, but the both surfaces of the middle step board piece 42b are exposed to the aggregate 43 to form a concrete adhesion structure, and the adhesion to concrete is ensured by such an aggregated finish surface. It is supposed to.

【0038】かかる構成においても、両側に打設された
コンクリートを埋込みせき板41を介して一体化させる
とともに、先行コンクリートの打継面を処理する必要が
なくなることについては上述の実施形態とほぼ同様の効
果を奏する。
In this structure, the concrete cast on both sides is integrated via the embedding plate 41, and the necessity of treating the joint surface of the preceding concrete is eliminated. Has the effect of

【0039】また、本実施形態では、中段せき板片にの
みコンクリート付着構造を設けたが、必要に応じて下段
せき板片や上段せき板片にもアンカーボルトやさし筋あ
るいは凹凸面等からなるコンクリート付着構造を設ける
ようにしてもよい。
Further, in this embodiment, the concrete adhering structure is provided only on the middle weir plate, but if necessary, the lower weir plate and the upper weir plate may be made of concrete made of anchor bolts, scissors, or irregular surfaces. An attachment structure may be provided.

【0040】[0040]

【発明の効果】以上述べたように、請求項1に係る本発
明の鉛直打継方法によれば、埋込みせき板が脱型されず
にそのままコンクリート内に残され、該埋込みせき板を
介して両側のコンクリートが一体化されるので、従来の
打継方法のように、先行打設されたコンクリートの打継
面をチッピングやワイヤブラシによって目荒らしする必
要がなくなる。そのため、現場での作業が効率化される
とともに、打継処理が全体工程に対してクリティカルに
なることがなくなり、全体の工期短縮に寄与する。
As described above, according to the vertical joint method according to the first aspect of the present invention, the embedding board is left in the concrete as it is without being removed from the mold, and the embankment is inserted through the embedding board. Since the concrete on both sides is integrated, there is no need to roughen the joint surface of the previously cast concrete by chipping or a wire brush unlike the conventional joint method. For this reason, work on site is made more efficient, and the joining process is not critical to the entire process, which contributes to shortening the overall construction period.

【0041】また、請求項2に係る本発明の埋込みせき
板によれば、脱型されずにそのままコンクリート内に残
り、両側のコンクリートを一体化するので、先行打設さ
れたコンクリートの打継面をチッピング等で目荒らしす
る必要がなくなる。そのため、現場での作業が効率化さ
れるとともに、打継処理が全体工程に対してクリティカ
ルになることがなくなり、全体の工期短縮に寄与する。
According to the embedding board of the present invention according to the second aspect, since it is not removed from the mold and remains in the concrete as it is, and the concrete on both sides is integrated, the joint surface of the previously cast concrete is installed. Does not need to be roughened by chipping or the like. For this reason, work on site is made more efficient, and the joining process is not critical to the entire process, which contributes to shortening the overall construction period.

【0042】また、請求項3に係る本発明の埋込みせき
板によれば、型枠内にスペーサ等が交錯していて、ある
いはせん断補強筋がすでに配筋してあるために埋込みせ
き板の水平移動が困難な場合であっても、型枠内への取
付けを容易に行うことができる。
According to the embedding board according to the third aspect of the present invention, since the spacers and the like are intersected in the formwork, or the shear reinforcing bars are already arranged, the embedding board is horizontal. Even if the movement is difficult, it can be easily mounted in the mold.

【0043】[0043]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本実施形態に係る鉛直打継方法の手順を示した
フローチャート。
FIG. 1 is a flowchart showing a procedure of a vertical joint method according to an embodiment.

【図2】本実施形態に係る埋込みせき板を示した分解斜
視図。
FIG. 2 is an exploded perspective view showing an embedding board according to the embodiment.

【図3】本実施形態に係る鉛直打継方法にしたがって一
連の作業を行っている様子を示した図であり、(a)は下
筋を配置したときの断面図、(b)は(a)のA―A線に沿う
断面図、(c)は上筋を配置したときの断面図、(d)は(c)
のB―B線に沿う断面図。
FIGS. 3A and 3B are views showing a state in which a series of operations are performed according to the vertical joint method according to the embodiment, wherein FIG. 3A is a cross-sectional view when a lower streak is arranged, and FIG. ) Is a cross-sectional view along the line AA, (c) is a cross-sectional view when the upper streak is arranged, and (d) is (c).
Sectional drawing which follows the BB line of FIG.

【図4】引き続いて一連の作業を示した図であり、(a)
は埋込みせき板の一方の側にコンクリートを打設したと
きの断面図、(b)は他方の側にコンクリートを打設した
ときの断面図。
FIG. 4 is a diagram showing a series of operations, and FIG.
2 is a cross-sectional view when concrete is cast on one side of the embedding board, and (b) is a cross-sectional view when concrete is poured on the other side.

【図5】変形例に係る埋込みせき板を示した全体斜視
図。
FIG. 5 is an overall perspective view showing an embedding board according to a modification.

【図6】別の変形例に係る埋込みせき板を示した分解斜
視図。
FIG. 6 is an exploded perspective view showing an embedding board according to another modification.

【符号の説明】[Explanation of symbols]

1、31、41 埋込みせき板 2、32、42 せき板本体 2a 下段せき板片(せき板片) 2b 中段せき板片(せき板片) 2c 上段せき板片(せき板片) 3 アンカーボルト(コンクリート付着
構造) 4、5、6、7 配筋溝 9、10 鉄筋 11 リブ(コンクリート付着構造) 21、22 コンクリート 42a 下段せき板片(せき板片) 42b 中段せき板片(せき板片) 42c 上段せき板片(せき板片)
1, 31, 41 Embedment board 2, 32, 42 Body of main board 2a Lower board piece (slit board piece) 2b Middle board piece (slit board piece) 2c Upper board piece (slit board piece) 3 Anchor bolt ( Concrete attachment structure) 4, 5, 6, 7 Reinforcement groove 9, 10 Reinforcing bar 11 Rib (Concrete attachment structure) 21, 22 Concrete 42a Lower crest plate piece (circular plate piece) 42b Middle crevice plate piece (circular plate piece) 42c Upper-stage crevice board piece (cough board piece)

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 せき板本体の両面にコンクリート付着構
造が設けられた埋込みせき板を前記せき板本体に鉄筋を
貫通させた状態でコンクリートの鉛直打継部に配置し、
前記埋込みせき板の一方の側と他方の側にそれぞれコン
クリートを打設することを特徴とする鉛直打継方法。
1. An embankment board having a concrete adhering structure provided on both sides of a dam body, and a reinforcing bar penetrating through the dam body, and disposed on a vertical joint of concrete.
A vertical joining method, wherein concrete is cast on one side and the other side of the embedding board.
【請求項2】 鉄筋を挿通可能に形成されたせき板本体
の両面にコンクリート付着構造を設けてなり、該コンク
リート付着構造は、前記せき板本体の両側に打設された
コンクリートとの付着強度を確保するようになっている
ことを特徴とする埋込みせき板。
2. A concrete adhering structure is provided on both sides of a main body of a baffle formed so that a reinforcing bar can be inserted therein, and the concrete adhering structure has a lower adhering strength with concrete cast on both sides of the main body of the weir. Embedded embankment characterized by being secured.
【請求項3】 前記せき板本体を複数のせき板片から構
成し、該せき板片の接合縁部に形成された配筋溝内に前
記鉄筋を嵌め込むようにした請求項2記載の埋込みせき
板。
3. The embedding device according to claim 2, wherein said weir plate main body is composed of a plurality of weir plate members, and said reinforcing bar is fitted into a reinforcing groove formed in a joint edge portion of said weir plate member. Cough board.
JP32915596A 1996-11-25 1996-11-25 Method for vertical placing joint, and embedded sheathing board therefor Pending JPH10152990A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32915596A JPH10152990A (en) 1996-11-25 1996-11-25 Method for vertical placing joint, and embedded sheathing board therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32915596A JPH10152990A (en) 1996-11-25 1996-11-25 Method for vertical placing joint, and embedded sheathing board therefor

Publications (1)

Publication Number Publication Date
JPH10152990A true JPH10152990A (en) 1998-06-09

Family

ID=18218262

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32915596A Pending JPH10152990A (en) 1996-11-25 1996-11-25 Method for vertical placing joint, and embedded sheathing board therefor

Country Status (1)

Country Link
JP (1) JPH10152990A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011017241A (en) * 2009-06-09 2011-01-27 Soyu:Kk Member with joint member for concrete structure and construction method for concrete structure
JP2017128980A (en) * 2016-01-22 2017-07-27 三井住友建設株式会社 PCa partial wall, PCa partial beam, RC building and RC building method
JP2018178497A (en) * 2017-04-11 2018-11-15 鹿島建設株式会社 Method of casting fiber reinforced concrete and boundary member
JP2023042601A (en) * 2021-08-26 2023-03-27 飛島建設株式会社 Concrete structure construction equipment
JP2024074098A (en) * 2022-11-18 2024-05-30 鹿島建設株式会社 Method for manufacturing precast plate and precast plate

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011017241A (en) * 2009-06-09 2011-01-27 Soyu:Kk Member with joint member for concrete structure and construction method for concrete structure
JP2017128980A (en) * 2016-01-22 2017-07-27 三井住友建設株式会社 PCa partial wall, PCa partial beam, RC building and RC building method
JP2018178497A (en) * 2017-04-11 2018-11-15 鹿島建設株式会社 Method of casting fiber reinforced concrete and boundary member
JP2023042601A (en) * 2021-08-26 2023-03-27 飛島建設株式会社 Concrete structure construction equipment
JP2024074098A (en) * 2022-11-18 2024-05-30 鹿島建設株式会社 Method for manufacturing precast plate and precast plate

Similar Documents

Publication Publication Date Title
JP2522714B2 (en) Construction method of building frame
KR100760393B1 (en) Precast concrete panel and slab construction method
JP3208530B2 (en) Precast concrete formwork and structure using the same
JPH11270146A (en) Reinforcement method of existing beam
JPH04334405A (en) Manufacture of precast concrete beam
JPH05106339A (en) Precast concrete formwork for concrete splicing
JPH0665973A (en) Construction method of reinforced concrete structures such as foundations and walls and the structures
JP3713192B2 (en) Foundation structure with anchor bolt and its construction method
JP3271810B2 (en) A method for manufacturing a heat-insulated half-PC plate.
JPH11166294A (en) Concrete beam with steel frame and floor construction method using it
JPH09221706A (en) Floor slab for road surface and layout method thereof
JPH11117333A (en) Construction method of concrete structure and formwork thereof
JP3029908B2 (en) Construction method of concrete structure
JP2000280229A (en) Bridge reinforced concrete floor system and its manufacture
JPH11303284A (en) Floor slab with steps
JP3047817B2 (en) Method of placing concrete so that it can be separated
KR200434622Y1 (en) Precast concrete panels
JP3245106B2 (en) Steel composite composite bridge using precast prestressed concrete slab
JP2749474B2 (en) Reverse construction method for underground structures
JP3191955B2 (en) Formwork of prefabricated steel frame formwork unit
JP3026058B2 (en) PC composite floor slab
JPH1150466A (en) Forming method of column leg part form and member for sheathing connection of the column leg form
JP3119117B2 (en) PC version driving formwork and formwork method
JP2942370B2 (en) Formwork method for vertical joints such as reinforced concrete beams and walls and guide metal fittings used in this method
JPS59177445A (en) Semi-pc slab construction method and semi-pc panel used therein

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050426

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050428

A521 Written amendment

Effective date: 20050622

Free format text: JAPANESE INTERMEDIATE CODE: A523

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050810