JPH10238010A - Half precast floor board and floor structure using it - Google Patents

Half precast floor board and floor structure using it

Info

Publication number
JPH10238010A
JPH10238010A JP9045628A JP4562897A JPH10238010A JP H10238010 A JPH10238010 A JP H10238010A JP 9045628 A JP9045628 A JP 9045628A JP 4562897 A JP4562897 A JP 4562897A JP H10238010 A JPH10238010 A JP H10238010A
Authority
JP
Japan
Prior art keywords
slab
precast
concrete
floor
present
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9045628A
Other languages
Japanese (ja)
Other versions
JP3028297B2 (en
Inventor
Ryoji Yamaki
良治 八巻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Y M K TECHNOL KK
Original Assignee
Y M K TECHNOL KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Y M K TECHNOL KK filed Critical Y M K TECHNOL KK
Priority to JP9045628A priority Critical patent/JP3028297B2/en
Publication of JPH10238010A publication Critical patent/JPH10238010A/en
Application granted granted Critical
Publication of JP3028297B2 publication Critical patent/JP3028297B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Panels For Use In Building Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce machining man-hours, save labor, and reduce the cost by using steel sheets as the main elements of drive members partially driven in a half precast board precast on a part of a reinforced concrete member cross section. SOLUTION: Drive members 20 using steel sheets 21 as main elements are partially driven into a precast concrete board 10 to form this half floor board. Two steel sheets 21 are assembled into a triangular shape, reinforcing bars 22a, 22b, 22c are welded at its apexes to form a unit drive member 20, multiple drive members 20 are arranged in parallel, and multiple reinforcing bars 22d are integrally welded at the lower ends. The steel sheet 21 is a member for mainly securing the integrity between the half board and cast-in-place concrete, and it does not require high strength so much. The steel sheet 21 is provided with opening sections 23 to improve the filling of concrete. Machining man-hours are reduced, labor is saved, and the cost can be reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、プレキャストコン
クリート工法のみならず在来工法や鉄骨構造などと組み
合わせて使用されるプレキャスト版に関し、詳しくは、
一般的な床,バルコニー床,廊下床等の施工に使用され
る型枠兼用のハーフプレキャスト床版に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast slab which is used in combination with a conventional method or a steel structure, as well as a precast concrete method.
The present invention relates to a half precast slab combined with a formwork used for construction of general floors, balcony floors, corridor floors, and the like.

【0002】[0002]

【従来の技術】近年、建築現場においては、一定品質の
確保、工期短縮、コストダウン等を目的とした現場作業
の合理化・システム化を進める様々な工法が導入されて
おり、その一つの工法としてプレキャスト工法がある。
かかるプレキャスト工法の最も大きな特徴は構造部材を
予め工場生産することであり、量産化による省力化やコ
スト面において大きなメリットがある。
2. Description of the Related Art In recent years, various construction methods have been introduced at a construction site for streamlining and systematizing on-site work for the purpose of ensuring a certain level of quality, shortening the construction period, reducing costs, and the like. There is a precast method.
The most significant feature of such a precast method is that the structural members are preliminarily produced in a factory, which has great advantages in terms of labor saving and cost due to mass production.

【0003】プレキャスト工法では特に床及び壁のプレ
キャスト化が進んでおり、中でも床は躯体工事の中で最
も広い作業範囲を有しており、非常に多くの種類の無支
保工・無型枠のプレキャスト床版が開発実用化されてい
る。
[0003] In the precast method, floors and walls are particularly precast, and the floor has the widest work area in the frame work, and a very large number of types of unsupported works and formless frames are used. Precast floor slabs have been developed and put to practical use.

【0004】プレキャスト床版を構造断面とする場合に
は、プレキャスト接合面における一体化確保のための接
合方法が品質確保のための重要なポイントとなる。例え
ば、床版全体をプレキャスト化したフルプレキャスト床
版を用いる場合には、床版相互の接合部がルーズである
と床剛性や強度が十分に確保できないとともに、遮音・
防水・耐火などに対する十分な性能を確保することが難
しくなる。このため、近年、特に集合住宅等ではハーフ
プレキャスト床板が盛んに用いられるようになった。
[0004] When a precast floor slab has a structural section, a joining method for ensuring integration at the precast joint surface is an important point for ensuring quality. For example, when using a full precast slab in which the entire slab is precast, if the joints between the slabs are loose, sufficient floor rigidity and strength cannot be ensured, and sound insulation and
It is difficult to ensure sufficient performance against water and fire. For this reason, in recent years, half precast floorboards have come into widespread use especially in apartment buildings and the like.

【0005】ハーフプレキャスト床版とは部材断面の一
部をプレキャスト化した床版であり、プレキャストコン
クリート版に部分的に打込材を打ち込んだ構造を有する
ものである。かかるハーフプレキャスト床版は、現場に
おいて梁間等に据付けた後、残りの断面に配筋し、コン
クリートを打設してスラブとして一体化されるもので、
大重量且つ構造的な一体性の確保が難しいというフルプ
レキャスト床版の短所を補うとともに、施工的な納まり
に関しても優れるものである。
[0005] The half precast slab is a slab in which a part of the cross section of the member is precast, and has a structure in which a driving material is partially driven into a precast concrete slab. Such half precast slabs are installed at the site between beams, etc., then laid out on the remaining cross section, cast concrete and integrated as a slab,
It compensates for the disadvantages of full precast slabs in that it is difficult to ensure a large weight and structural integrity, and is also excellent in terms of installation.

【0006】図12に従来から一般的に用いられている
ハーフプレキャスト床版を示す。なお、図12(a)は
斜視図、図12(b)は図12(a)中のA−A’面に
おける断面図、図12(c)は図12(a)中のB−
B’面における断面図である。
FIG. 12 shows a half precast slab generally used conventionally. 12 (a) is a perspective view, FIG. 12 (b) is a cross-sectional view taken along the line AA 'in FIG. 12 (a), and FIG.
It is sectional drawing in the B 'surface.

【0007】図12に示したように従来のハーフプレキ
ャスト床版は、プレキャストコンクリート版101内
に、スラブの上端筋となる鉄筋102と下端筋となる鉄
筋103とをトラス筋104に溶接したものを打ち込ん
で構成されている。
As shown in FIG. 12, a conventional half precast slab is obtained by welding a reinforcing steel 102 serving as an upper reinforcing bar and a reinforcing bar 103 serving as a lower reinforcing bar to a truss bar 104 in a precast concrete slab 101. It is configured to be driven.

【0008】[0008]

【発明が解決しようとする課題】しかしながら、上記従
来のハーフプレキャスト床版に打込材として用いられて
いるトラス筋は、多数の鉄筋を複雑に折り曲げ加工し、
これらを溶接してトラス状に組み上げて作製するため、
加工工数が非常に多く、量産化による省力化やコスト面
におけるメリットには限界があった。
However, the truss bar used as a driving material in the above-mentioned conventional half precast slab is formed by bending a large number of reinforcing bars in a complicated manner.
In order to make these by welding and assembling them into a truss shape,
The number of processing man-hours is very large, and there are limits to the merit in labor saving and cost in mass production.

【0009】本発明の主たる目的は、上記事情に鑑み、
さらなる省力化や低コスト化を可能にする新規なハーフ
プレキャスト床版を提供することである。
[0009] In view of the above circumstances, the main object of the present invention is to provide
It is an object of the present invention to provide a new half precast slab that enables further labor saving and cost reduction.

【0010】[0010]

【課題を解決するための手段】上記目的を達成すべく成
された本発明の構成は以下の通りである。
The configuration of the present invention which has been achieved to achieve the above object is as follows.

【0011】即ち、本発明第1は、鉄筋コンクリート部
材断面の一部をプレキャスト化したハーフプレキャスト
床版であって、プレキャストコンクリート版に部分的に
打ち込まれる打込材の主要素として鋼板を用いたことを
特徴とするハーフプレキャスト床版に関する。
That is, the first aspect of the present invention is a half precast slab in which a part of a cross section of a reinforced concrete member is precast, wherein a steel plate is used as a main element of a driving material partially driven into the precast concrete slab. And a half precast slab.

【0012】また、本発明第2は、上記本発明第1のハ
ーフプレキャスト床版を用いて施工された床構造に関す
る。
[0012] The second aspect of the present invention relates to a floor structure constructed using the half precast slab of the first aspect of the present invention.

【0013】本発明のハーフプレキャスト床版では、打
込材の主要素として、従来の鉄筋に代えて鋼板を用いた
ことにより、打込材の加工を単純化できるとともに、組
立工数を削減でき、量産化による更なる省力化や低コス
ト化を実現し得るものである。
In the half precast floor slab of the present invention, since the steel plate is used instead of the conventional reinforcing bar as the main element of the driving material, the processing of the driving material can be simplified and the number of assembling steps can be reduced. It is possible to realize further labor saving and cost reduction by mass production.

【0014】また、本発明のハーフプレキャスト床版
は、型枠兼用の床版であり、型枠サポートの合理化、若
しくは工法によってはノンサポート化も可能であるた
め、施工の合理化・省力化が図れる。
Further, the half precast slab of the present invention is a slab that also serves as a formwork. Since the formwork support can be rationalized or non-supported depending on the method of construction, the construction can be rationalized and labor-saving can be achieved. .

【0015】[0015]

【発明の実施の形態】以下、本発明の実施の形態例を図
面を参照して説明するが、言うまでもなく本発明はこれ
らの形態例に限定されるものではない。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described with reference to the drawings, but it is needless to say that the present invention is not limited to these embodiments.

【0016】図1は、本発明のハーフプレキャスト床版
(以下、「ハーフ床版」と記す)の代表的な例を示す斜
視図である。本発明のハーフ床版は、プレキャストコン
クリート版10に鋼板21を主要素とする打込材20を
部分的(その一部が外部に突出した状態を意味する)に
打ち込こんで構成される。
FIG. 1 is a perspective view showing a typical example of a half precast slab (hereinafter referred to as "half slab") of the present invention. The half-floor slab of the present invention is configured by partially (in a state where a part thereof projects outside) a precast concrete slab 10 into which a driving material 20 mainly composed of a steel plate 21 is driven.

【0017】打込材20の主要素である鋼板21は、主
としてハーフ床版と現場打ちコンクリートとの一体性を
確保するための部材でありさほど高い強度は要求される
ものではなく、一般に、現場に据え付けられた後のこの
上での配筋組みやコンクリート打ちの際に作業員の歩行
によって変形しない程度の剛性を有していれば良い。従
って、鋼板21としては、その加工形状によっても異な
るが、通常は1.0mm乃至2.0mm程度の厚さのも
のが用いられる。
The steel plate 21, which is the main element of the cast material 20, is a member for mainly securing the integrity of the half slab and the cast-in-place concrete, and does not require a very high strength. It is sufficient that the material has such a rigidity that it is not deformed by the walking of the worker when the reinforcing members are assembled or the concrete is poured after being installed. Therefore, the thickness of the steel sheet 21 is usually about 1.0 mm to 2.0 mm, although it depends on the processing shape.

【0018】図1のハーフ床版に用いている打込材20
は、図2に示されるように2枚の鋼板21を三角形状に
組み上げ、その各頂部に鉄筋22a,22b,22cを
溶接したものを一単位とし、これを複数並列に配置した
状態で、下端に複数の鉄筋22dを溶接して一体化した
ものである。ここで上記構成単位の寸法及び配列ピッチ
は、床強度に見合った寸法及びピッチに適宜設計される
ものである。なお、図2中にはプレキャストコンクリー
ト版10を2点鎖線で示してある。
The driving material 20 used for the half slab of FIG.
As shown in FIG. 2, two steel plates 21 are assembled in a triangular shape, and a reinforcing bar 22 a, 22 b, 22 c is welded to each of the tops as one unit. A plurality of rebars 22d are welded and integrated. Here, the dimensions and arrangement pitch of the structural units are appropriately designed to dimensions and pitches corresponding to the floor strength. In FIG. 2, the precast concrete slab 10 is indicated by a two-dot chain line.

【0019】前述のように、ハーフ床版の上面には現場
においてコンクリートが打設される。この際、図1及び
図2に示した例のように打込材20の主要素である鋼板
21によって特に長い半閉空間が形成される場合には、
かかる空間部分にコンクリートを充填することが困難に
なることもある。
As described above, concrete is cast on the upper surface of the half slab at the site. At this time, when a particularly long semi-closed space is formed by the steel plate 21 which is the main element of the driving material 20 as in the example shown in FIGS.
It may be difficult to fill such spaces with concrete.

【0020】このため、鋼板21には、開口部23(図
2参照)若しくは切欠部を設けておくことが好ましい。
すなわち、少なくともその一部がプレキャストコンクリ
ート版10から露出するような位置に開口部23を設け
ておくことにより、かかる開口部23がコンクリートの
流路となり、コンクリートの充填をスムーズに行うこと
ができる。また、ハーフ床版を製造する際のコンクリー
トの流動性も考慮すると、開口部23はプレキャストコ
ンクリート版10内から外部に跨がって、若しくはプレ
キャストコンクリート版10の内外に独立して形成する
ことが好ましい。
For this reason, the steel plate 21 is preferably provided with an opening 23 (see FIG. 2) or a notch.
That is, by providing the opening 23 at a position where at least a part thereof is exposed from the precast concrete slab 10, the opening 23 serves as a concrete flow path, and the concrete can be smoothly filled. In addition, in consideration of the fluidity of concrete when manufacturing a half-slab, the opening 23 may be formed to extend from the inside of the precast concrete slab 10 to the outside or independently of the inside and outside of the precast concrete slab 10. preferable.

【0021】また、上記のように鉄板21に開口部23
若しくは切欠部を設けることにより、ハーフ床板全体の
重量が軽量化され、運搬や現場における据付工事が容易
になるメリットもある。
Further, as described above, the opening 23 is formed in the iron plate 21.
Alternatively, the provision of the cutout portion also has the advantage that the weight of the entire half floor plate is reduced, and the transportation and installation work at the site are facilitated.

【0022】本発明のハーフ床版に用いられる打込材2
0の構成単位の別の例を図3乃至図10を用いて説明す
る。なお、これらの図においてもプレキャストコンクリ
ート版10を2点鎖線で示してある。
Driving material 2 used for half-slab of the present invention
Another example of the structural unit of 0 will be described with reference to FIGS. In these figures, the precast concrete slab 10 is indicated by a two-dot chain line.

【0023】図3及び図4は、図2に示したものと同様
に、開口部23を形成した2枚の鋼板21を組み合わせ
てその上下端に鉄筋22a,22bを溶接したものを一
単位とし、これを複数並列に配置した状態で、下端に複
数の鉄筋22dを溶接して一体化したものである。な
お、図3は図2と同様に鋼板21の曲げ加工をしないも
の、図4は鋼板21の曲げ加工を行うものである。
FIGS. 3 and 4 show a unit obtained by combining two steel plates 21 each having an opening 23 and welding rebars 22a and 22b to the upper and lower ends, as in FIG. A plurality of the reinforcing bars 22d are welded to the lower end and integrated with a plurality of the reinforcing bars arranged in parallel. FIG. 3 shows a case where the steel plate 21 is not bent similarly to FIG. 2, and FIG. 4 shows a case where the steel plate 21 is bent.

【0024】図5乃至図7は、開口部23を形成した1
枚の鋼板21を長尺方向に沿って折り曲げ加工し、その
下端に鉄筋22b,22cを溶接したものを一単位と
し、上記と同様にして一体化したものである。なお、図
5は鋼板21の1回曲げ、図6は2回曲げ、図7は3回
曲げによって曲げ加工を行っている。
FIG. 5 to FIG.
The steel plate 21 is bent along the longitudinal direction, and the lower end thereof is welded with the reinforcing bars 22b and 22c as one unit, and is integrated in the same manner as described above. Note that FIG. 5 shows bending of the steel plate 21 by bending once, FIG. 6 bending by twice, and FIG. 7 by bending three times.

【0025】図8は、開口部23を形成した1枚の鋼板
21を短尺方向に沿って折り曲げ加工し、その下端に鉄
筋22b,22cを溶接したものを一単位とし、上記と
同様にして一体化したものである。なお、この場合には
鋼板21の曲げ加工の工数が多くなるが、鋼板21への
穴開け加工の工数を減らすことができる。
FIG. 8 shows a single steel plate 21 having an opening 23 formed by bending along a short direction, and welding a reinforcing bar 22b, 22c to the lower end as one unit. It is a thing. In this case, the man-hour for bending the steel plate 21 increases, but the man-hour for drilling the steel plate 21 can be reduced.

【0026】図9は、1枚の鋼板21を短尺方向に沿っ
て曲げ加工することにより上記の開口部を有するものと
同様の機能を果たす形状とし、その下端に鉄筋22b,
22cを溶接したものを一単位とし、上記と同様にして
一体化したものである。このような構成によれば、鋼板
21への穴開け加工が不要となる(但し、曲げの加工の
工数が増えることになる。)。
FIG. 9 shows a shape obtained by bending a single steel plate 21 along the short direction so as to perform the same function as that having the above-mentioned opening.
22c is welded as one unit and integrated in the same manner as above. According to such a configuration, it is not necessary to form a hole in the steel plate 21 (however, the number of steps for bending is increased).

【0027】図10は、開口部の代わりに切欠部24を
形成した2枚の鋼板21を組み合わせてその上下端に鉄
筋22a,22bを溶接したものを一単位とし、上記と
同様にして一体化したものである。
FIG. 10 shows a combination of two steel plates 21 each having a notch 24 formed in place of an opening and welding rebars 22a and 22b to the upper and lower ends of the steel plate 21 as one unit. It was done.

【0028】以上例示したように、打込材20を構成す
る鋼板21としては、前述のように作業員の歩行によっ
て変形しない程度の剛性を有していれば様々な形状のも
のを適用することができるものである。
As exemplified above, as the steel plate 21 constituting the driving material 20, various shapes can be applied as long as the steel plate 21 has such a rigidity as not to be deformed by the walking of the worker as described above. Can be done.

【0029】本発明のハーフ床版において、打込材20
の上部の鉄筋22aはスラブの上端筋となるものであ
り、下部の鉄筋22b,22c,22dはスラブの下端
筋となるものである。これらの中でスラブの下端筋とな
る2方向の鉄筋(22b,22c,22d)はプレキャ
ストコンクリート版10内に予め設けられる。このた
め、本発明のハーフ床版に係るプレキャストコンクリー
ト版10の厚みは、通常60mm乃至100mm程度と
なる。
In the half slab of the present invention, the driving material 20
The upper reinforcing bar 22a serves as the upper reinforcing bar of the slab, and the lower reinforcing bars 22b, 22c, 22d serve as the lower reinforcing bar of the slab. Of these, two-directional reinforcing bars (22b, 22c, 22d) serving as lower end bars of the slab are provided in the precast concrete slab 10 in advance. For this reason, the thickness of the precast concrete slab 10 according to the half slab of the present invention is usually about 60 mm to 100 mm.

【0030】一方、スラブの上端筋となる鉄筋は必ずし
も予め一体化して設けられるものではなく、施工現場の
要求に応じて適宜設計される。すなわち、上端筋の付加
に伴うハーフ床版の重量増加による運搬・据付工事の困
難性等によるデメリットと、現場における上端筋の配筋
工事の簡略化等によるメリットを比較検討して決めるこ
とができる。
On the other hand, the reinforcing bar serving as the upper end bar of the slab is not necessarily provided integrally in advance, but is appropriately designed according to the requirements of the construction site. In other words, it is possible to determine the disadvantages due to the difficulty of transportation and installation work due to the increase in the weight of the half slab due to the addition of the top reinforcement, and the advantages due to simplification of the reinforcement work of the top reinforcement at the site, etc. .

【0031】なお、図2乃至図4の例では1方向の上端
筋(鉄筋22a)のみを設け、図5乃至図10の例では
上端筋を全く設けていないが、上述のように施工現場の
要求に応じてこれらのものに対しても上端筋となる2方
向の鉄筋を予め一体化して設けておくこともできる。
In the examples of FIGS. 2 to 4, only the upper reinforcing bar (rebar 22 a) in one direction is provided, and in the examples of FIGS. 5 to 10, no upper reinforcing bar is provided. If necessary, a two-way reinforcing bar serving as an upper reinforcing bar may be integrally provided in advance for these components.

【0032】本発明のハーフ床版は、一般的な床部分に
施工されるものに限らず、集合住宅等における廊下部分
に施工される廊下床版やバルコニー部分に施工されるバ
ルコニー床版としても用いることができるものである。
また、廊下部分やバルコニー部分は現場での作業効率が
特に悪い部位であるため、本発明のハーフ床版に手摺と
なる立ち上がり部を予め一体化しておくことにより、外
部足場等の仮設資材を削減できるとともに、全体の生産
性の向上を図ることもできる。また、本発明のハーフ床
版には、必要に応じて小梁を一体化して形成しておくこ
ともできる。
The half slab of the present invention is not limited to a slab constructed on a general floor, but may also be used as a slab constructed on a corridor or a balcony constructed on a balcony in an apartment house. It can be used.
In addition, corridors and balconies are sites with particularly poor work efficiency at the site, so by integrating in advance the half-slab of the present invention with a rising part that becomes a handrail, temporary materials such as external scaffolds are reduced. It is possible to improve the overall productivity. Further, in the half slab of the present invention, small beams can be integrally formed as necessary.

【0033】次に、本発明のハーフ床版を用いて施工さ
れる床構造の一例について図11を用いて説明する。
Next, an example of a floor structure constructed using the half-slab of the present invention will be described with reference to FIG.

【0034】本発明の床構造を施工に際しては、先ず本
発明のハーフ床版Aを梁(ハーフプレキャスト梁,プレ
キャスト梁,鉄骨梁であっても構わない)51間に据付
け、必要に応じて適宜サポート等(不図示)を設置す
る。次に、上端筋を一体化していないハーフ床版を用い
る場合には上端筋52a,52bを配筋し、さらに梁及
び隣接するハーフ床版等の鉄筋と連結する連結筋53を
配筋した後、床の残りの断面にコンクリート54を打設
する。
When constructing the floor structure of the present invention, first, the half slab A of the present invention is installed between beams (may be a half precast beam, a precast beam, or a steel beam) 51, and if necessary, appropriately. Supports (not shown) are installed. Next, in the case of using a half slab in which the upper reinforcement is not integrated, the upper reinforcements 52a and 52b are arranged, and furthermore, the connecting reinforcement 53 for coupling to the beam and the reinforcing steel such as the adjacent half slab is arranged. The concrete 54 is poured into the remaining section of the floor.

【0035】以上のようにして施工される本発明の床構
造は、プレキャストコンクリート版10と現場打ちコン
クリート54の一体構造であり、更には現場打ちコンク
リート54によって柱及び梁等とも一体的に施工するこ
とができるため、十分な剛性と耐力や遮音性能の確保が
可能となる。
The floor structure of the present invention constructed as described above is an integrated structure of the precast concrete slab 10 and the cast-in-place concrete 54, and furthermore, the cast-in-place concrete 54 is constructed integrally with columns and beams. Therefore, sufficient rigidity, proof strength and sound insulation performance can be ensured.

【0036】[0036]

【発明の効果】以上説明したように、本発明によれば以
下の効果を奏する。 (1)ハーフプレキャスト床版の打込材の主要素として
鋼板を用いたことにより、打込材の形状設計の自由度が
増し、打込材の加工を単純化できるとともに、組立工数
を削減でき、低コスト化が実現される。 (2)床の施工に際し、型枠サポートの合理化、若しく
はハーフプレキャスト床版の構造及び工法によってはノ
ンサポート化も可能であるため、施工の合理化・省力化
が図れる。 (3)本発明のハーフプレキャスト床版を用いた床構造
では、容易に且つ確実に柱及び梁と一体的に施工するこ
とができ、十分な剛性と耐力や遮音性能を有する床構造
が実現される。
As described above, according to the present invention, the following effects can be obtained. (1) By using steel plate as the main element of the driving material of the half precast slab, the degree of freedom in the shape design of the driving material can be increased, the processing of the driving material can be simplified, and the number of assembly steps can be reduced. Thus, cost reduction is realized. (2) When constructing the floor, it is possible to rationalize the formwork support or non-support depending on the structure and construction method of the half precast slab, so that the construction can be rationalized and labor-saving. (3) In the floor structure using the half precast floor slab of the present invention, the floor structure can be easily and reliably integrated with the columns and beams, and a floor structure having sufficient rigidity, proof strength and sound insulation performance is realized. You.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のハーフプレキャスト床版の一例を示す
斜視図である。
FIG. 1 is a perspective view showing an example of a half precast floor slab of the present invention.

【図2】本発明のハーフプレキャスト床版に用いられる
打込材の一構成例を説明するための図である。
FIG. 2 is a view for explaining one configuration example of a driving material used for the half precast slab of the present invention.

【図3】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 3 is a diagram for explaining another example of the configuration of the driving material used for the half precast floor slab of the present invention.

【図4】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 4 is a view for explaining another example of the configuration of the driving material used for the half precast slab of the present invention.

【図5】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 5 is a diagram for explaining another example of the configuration of the driving material used for the half precast slab of the present invention.

【図6】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 6 is a diagram for explaining another example of the configuration of the driving material used for the half precast floor slab of the present invention.

【図7】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 7 is a diagram for explaining another example of the configuration of the driving material used for the half precast slab of the present invention.

【図8】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 8 is a view for explaining another example of the configuration of the driving material used for the half precast floor slab of the present invention.

【図9】本発明のハーフプレキャスト床版に用いられる
打込材の別の構成例を説明するための図である。
FIG. 9 is a diagram for explaining another example of the configuration of the driving material used for the half precast floor slab of the present invention.

【図10】本発明のハーフプレキャスト床版に用いられ
る打込材の別の構成例を説明するための図である。
FIG. 10 is a view for explaining another example of the configuration of the driving material used for the half precast floor slab of the present invention.

【図11】本発明のハーフプレキャスト床版を用いて施
工される床構造を説明するための図である。
FIG. 11 is a diagram for explaining a floor structure constructed using the half precast floor slab of the present invention.

【図12】従来のハーフプレキャスト床版を説明するた
めの図である。
FIG. 12 is a view for explaining a conventional half precast floor slab.

【符号の説明】[Explanation of symbols]

10 プレキャストコンクリート版 20 打込材 21 鉄板 22a 上端筋 22b,22c,22d 下端筋 23 開口部 24 切欠部 51 梁 52a,52b 上端筋 53 連結筋 54 現場打ちコンクリート A ハーフ床版 DESCRIPTION OF SYMBOLS 10 Precast concrete slab 20 Casting material 21 Iron plate 22a Upper end bar 22b, 22c, 22d Lower end bar 23 Opening 24 Notch 51 Beam 52a, 52b Upper end bar 53 Connecting bar 54 Cast-in-place concrete A Half slab

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋コンクリート部材断面の一部をプレ
キャスト化したハーフプレキャスト床版であって、プレ
キャストコンクリート版に部分的に打ち込まれる打込材
の主要素に鋼板を用いたことを特徴とするハーフプレキ
ャスト床版。
1. A half precast slab obtained by precasting a part of a cross section of a reinforced concrete member, wherein a steel plate is used as a main element of a material to be partially driven into the precast concrete slab. Floor slab.
【請求項2】 前記鋼板に開口部若しくは切欠部が設け
られていることを特徴とする請求項1に記載のハーフプ
レキャスト床版。
2. The half precast floor slab according to claim 1, wherein an opening or a notch is provided in the steel plate.
【請求項3】 前記鋼板に設けられている開口部若しく
は切欠部の少なくとも一部がプレキャストコンクリート
版から露出していることを特徴とする請求項2に記載の
ハーフプレキャスト床版。
3. The half precast floor slab according to claim 2, wherein at least a part of the opening or the notch provided in the steel plate is exposed from the precast concrete slab.
【請求項4】 前記鋼板の上端部に鉄筋が溶接されてい
ることを特徴とする請求項1〜3のいずれかに記載のハ
ーフプレキャスト床版。
4. The half precast floor slab according to claim 1, wherein a reinforcing bar is welded to an upper end of the steel plate.
【請求項5】 請求項1〜4のいずれかに記載のハーフ
プレキャスト床版を用いて施工された床構造。
5. A floor structure constructed using the half precast floor slab according to claim 1.
JP9045628A 1997-02-28 1997-02-28 Half precast slab and floor structure using the same Expired - Fee Related JP3028297B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9045628A JP3028297B2 (en) 1997-02-28 1997-02-28 Half precast slab and floor structure using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9045628A JP3028297B2 (en) 1997-02-28 1997-02-28 Half precast slab and floor structure using the same

Publications (2)

Publication Number Publication Date
JPH10238010A true JPH10238010A (en) 1998-09-08
JP3028297B2 JP3028297B2 (en) 2000-04-04

Family

ID=12724646

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9045628A Expired - Fee Related JP3028297B2 (en) 1997-02-28 1997-02-28 Half precast slab and floor structure using the same

Country Status (1)

Country Link
JP (1) JP3028297B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104878876A (en) * 2015-05-19 2015-09-02 华南理工大学 Ultra-high performance concrete cover plate with optimized steel angles and production method of ultra-high performance concrete cover plate
WO2016183607A1 (en) * 2015-05-18 2016-11-24 Conrock Australia Pty Ltd Ultimate (eco) floor system
JP2019052507A (en) * 2017-09-19 2019-04-04 株式会社大林組 Concrete buried formwork and integration method of concrete buried formwork and post-cast concrete

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016183607A1 (en) * 2015-05-18 2016-11-24 Conrock Australia Pty Ltd Ultimate (eco) floor system
CN104878876A (en) * 2015-05-19 2015-09-02 华南理工大学 Ultra-high performance concrete cover plate with optimized steel angles and production method of ultra-high performance concrete cover plate
JP2019052507A (en) * 2017-09-19 2019-04-04 株式会社大林組 Concrete buried formwork and integration method of concrete buried formwork and post-cast concrete

Also Published As

Publication number Publication date
JP3028297B2 (en) 2000-04-04

Similar Documents

Publication Publication Date Title
CN1821501B (en) Column-beam connection structure of building and connection method thereof
KR100211534B1 (en) Connection structure between PC wall and PC slab of building and construction method
JPH10131516A (en) Reinforcing structure of existing building
EP0418216B1 (en) Frame-work for structural walls in multy-storey buildings
CN115596000B (en) Precast raft foundation components, prefabricated raft foundations, and houses
JP2977798B1 (en) Construction method of steel frame / RC composite structure building and formwork thereof
JP3074599B2 (en) Half precast slab and floor structure using the same
JP3028297B2 (en) Half precast slab and floor structure using the same
JP2001020376A (en) Sc beam construction method for building
JPS6314937A (en) Reinforced steel composite column
JPH11166294A (en) Concrete beam with steel frame and floor construction method using it
JP2697532B2 (en) How to build an architectural frame
JPH08135049A (en) Construction method of building using precast concrete wall member
CN220100204U (en) Prefabricated parapet and coincide floor connection structure
JPH0253576B2 (en)
JP2952778B2 (en) Wall type PC high-rise building
JPS5816410B2 (en) Building construction method using L-type and 1-type precast concrete independent load-bearing walls
JP2734946B2 (en) Construction method of concrete wall structure
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
CN115717445A (en) Connecting joint of prefabricated non-bearing outer wall and cast-in-place shear wall
JPH09273317A (en) Seismic retrofitting method for existing concrete structures
JP2781643B2 (en) Basement building block unit
JPH0427018A (en) Construction of concrete assembly-type basement
CN118881006A (en) A modular structural system of prefabricated room modules and steel-concrete combination
JPH045605Y2 (en)

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19991130

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees