JPH108457A - Core linked body used for underground wall and method of building core - Google Patents
Core linked body used for underground wall and method of building coreInfo
- Publication number
- JPH108457A JPH108457A JP16760296A JP16760296A JPH108457A JP H108457 A JPH108457 A JP H108457A JP 16760296 A JP16760296 A JP 16760296A JP 16760296 A JP16760296 A JP 16760296A JP H108457 A JPH108457 A JP H108457A
- Authority
- JP
- Japan
- Prior art keywords
- core
- core material
- members
- ground
- short
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
(57)【要約】
【課題】 建込みの際に捻じれること無く、また良好な
精度で建込むことができる地中壁用の芯材および芯材の
建込み方法を提供すること。
【解決手段】 所定間隔でほぼ平行に配置した複数の芯
材11,12,21,22,31,32と、該複数の芯
材を一体に連結する連結部材13a,23a,23b,
33aとを備え、これにより該複数の芯材を同時に地中
に建込み可能にした。
(57) [Summary] [PROBLEMS] To provide a core material for an underground wall and a method for installing the core material, which can be built with good accuracy without being twisted at the time of building. SOLUTION: A plurality of core members 11, 12, 21, 22, 31, 32 arranged substantially in parallel at predetermined intervals, and connection members 13a, 23a, 23b, which integrally connect the plurality of core members.
33a, whereby the plurality of cores can be simultaneously built in the ground.
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地中壁に用いる芯
材および芯材の建込み方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a core used for an underground wall and a method for installing the core.
【0002】[0002]
【従来の技術】従来の地中壁、例えば、山留め壁や止水
壁としてのソイルセメント柱列壁は、ミキシング装置の
先端から地盤中にセメント系の注入液を注入しながら、
原位置土と撹拌混合してソイルセメント柱を形成し、こ
のソイルセメント柱が硬化する前に鉄骨や鋼矢板等の芯
材を一本ずつ建込んで形成していた。2. Description of the Related Art A conventional underground wall, for example, a soil cement column wall as a retaining wall or a water blocking wall is formed by injecting a cement-based injection liquid into the ground from the tip of a mixing device.
The soil cement column was formed by stirring and mixing with the in-situ soil, and a core material such as a steel frame or a steel sheet pile was erected one by one before the soil cement column hardened.
【0003】[0003]
【発明が解決しようとする課題】上記ソイルセメント柱
列壁において、芯材の寸法や配設間隔は、従来、床付け
付近の曲げ応力の大きさに応じて設計している。しかし
ながら、図4の設計側圧図で地下水位が−5.5mと示
されているように、地下水位が比較的低い場合や、表層
がローム層等の良質な粘性土の場合、地表面近傍での土
圧は床付け付近の土圧よりも相当に小さくなる。したが
って、図4の芯材割付け図に示したように、所定深度よ
りも上方では芯材間隔を大きく、所定深度よりも下方で
は芯材間隔を狭くして密に、設計できれば理想的であ
る。すなわち、図4の芯材割付け図では、長さ15,000mm
の長尺芯材52と長さ10,000mmの短尺芯材51とを交互
に割り付けて、長尺芯材52はその上端が地表面に位置
し、短尺芯材51はその上端が地表面下5,000mmに位置
し、これにより深度5,000mmよりも上方では芯材間隔が9
00mmになり、深度5,000mmよりも下方では芯材間隔が450
mmになるように設計している。In the above-mentioned soil cement column walls, the dimensions of the core material and the interval between the core materials have conventionally been designed according to the magnitude of the bending stress near the floor. However, when the groundwater level is relatively low, as shown in the design lateral pressure map of Fig. 4 as -5.5m, or when the surface layer is a high-quality cohesive soil such as a loam layer, Is significantly lower than that near the floor. Therefore, as shown in the core material layout diagram of FIG. 4, it is ideal if the space between the core materials is larger than the predetermined depth and the space between the core materials is narrower below the predetermined depth, so that the design is ideal. That is, in the core material layout diagram of FIG.
The long core 52 and the short core 51 having a length of 10,000 mm are alternately arranged, and the upper end of the long core 52 is located on the ground surface, and the upper end of the short core 51 is 5,000 below the ground surface. mm, which allows for a core spacing of 9 mm above a depth of 5,000 mm.
00mm, core spacing 450 below 5,000mm depth
It is designed to be mm.
【0004】しかしながら、上述したように長短の芯材
を割り付けて地中壁を設計しても、かようなソイルセメ
ント柱列壁の施工は非常に困難であり、以下のような問
題が生じる。 芯材を地表面下に建て込むと、芯材の天端の設計位置
からの誤差を把握するのが困難になり、また捻じれて挿
入される可能性が高くなる。 その結果、建て込み精度が低下し、捻じれにより芯材
間の距離が大きくなることで、ソイルセメント柱列壁に
亀裂が入ったり、また芯材間からの漏水が生じ易くな
る。However, even if the underground wall is designed by allocating the long and short core members as described above, it is very difficult to construct such a soil cement column wall, and the following problems occur. When the core material is erected below the ground surface, it is difficult to grasp an error from the design position of the top end of the core material, and the possibility that the core material is twisted and inserted increases. As a result, the installation accuracy is reduced, and the distance between the core materials is increased by twisting, so that cracks are formed in the soil cement column walls, and water leaks between the core materials are likely to occur.
【0005】本発明は上記従来技術の欠点に着目し、こ
れを解決せんとしたものであり、その目的は、芯材を所
望の割付けで配置することができて、しかも建込みの際
に捻じれること無く、また良好な精度で建込むことがで
きる地中壁用の芯材および芯材の建込み方法を提供する
ことにある。The present invention has been made to solve the above-mentioned drawbacks of the prior art and to solve the problem. The purpose of the present invention is to make it possible to arrange a core material in a desired layout and to twist the core material at the time of installation. It is an object of the present invention to provide a core material for an underground wall and a method of installing the core material, which can be built with good accuracy without being damaged.
【0006】[0006]
【課題を解決するための手段】本発明は上記の目的に鑑
みてなされたものであり、その要旨は、所定間隔でほぼ
平行に配置した複数の芯材と、該複数の芯材を一体に連
結する連結部材とを備え、これにより該複数の芯材を同
時に地中に建込み可能にしたことを特徴とする地中壁に
用いる芯材連結体にある。SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned object, and the gist of the present invention is to integrate a plurality of core members arranged substantially in parallel at a predetermined interval with the plurality of core members. And a connecting member for connecting the plurality of cores so that the plurality of cores can be simultaneously built in the ground.
【0007】本発明の別の要旨は、複数の芯材を所定間
隔でほぼ平行に配置し、該複数の芯材を一体に連結して
芯材連結体を形成し、該芯材連結体を吊り上げた後に地
中に建込む芯材の建込み方法にある。Another gist of the present invention is that a plurality of core members are arranged substantially in parallel at predetermined intervals, and the plurality of core members are integrally connected to form a core member connected body. There is a method of building a core material to be built in the ground after being lifted.
【0008】また本発明の別の要旨は、二種類以上の長
さの複数の芯材を所定間隔でほぼ平行に配置し、該複数
の芯材を一体に連結して芯材連結体を形成し、該芯材連
結体を吊り上げた後に地中に建込む芯材の建込み方法で
あって、前記芯材連結体を形成する際に、該複数の芯材
のうちの短い芯材を地中の土圧の大きな区間に位置する
ように配置したことを特徴とする芯材の建込み方法にあ
る。ここで、芯材の長さが三種類以上の場合には、最も
土圧の大きな地中区間に最も短い芯材を割付けて、次に
土圧の大きな地中区間に次に短い芯材を割付け、同様に
して順次芯材を割り付けてから芯材連結体を形成する。Another aspect of the present invention is that a plurality of core members having two or more types of lengths are arranged substantially in parallel at predetermined intervals, and the plurality of core members are integrally connected to form a connected core member. And a method of building a core material to be buried in the ground after lifting the connected core material, wherein a short core material of the plurality of core materials is ground when forming the connected core material. There is provided a method of building a core material, wherein the core material is arranged so as to be located in a section having a large earth pressure. Here, when the length of the core material is three or more types, the shortest core material is allocated to the underground section having the highest earth pressure, and the next short core material is assigned to the underground section having the next highest earth pressure. After allocating and sequentially arranging the core materials in the same manner, a connected core material is formed.
【0009】本発明の芯材連結体及び芯材の建込み方法
において、複数の芯材は複数種類の長さに形成し、適当
な順番でほぼ平行に配置して形成しても良い。例えば、
複数の芯材を長尺芯材及び短尺芯材の二種類の芯材と
し、これらの長尺及び短尺芯材を交互に配置し、その下
端部はほぼ同じ位置に揃え、これにより上端部では長尺
芯材どうしが隣あって芯材間隔が大きくなり、これ以下
では長尺芯材と短尺芯材とが隣あって芯材間隔が密にな
るように、芯材連結体を形成することができる。要する
に、適当種類の長さの異なる芯材を使用することによ
り、地盤の土質や地下水位等により異なる土圧分布に応
じて、芯材間隔が密になったり、あるいは疎になるよう
に割付けた芯材連結体を形成すれば良い。In the method for assembling the core material and the core material according to the present invention, the plurality of core materials may be formed in a plurality of kinds of lengths and arranged in a suitable order and substantially parallel to each other. For example,
A plurality of cores are used as two types of cores, a long core and a short core, and the long and short cores are alternately arranged, and the lower ends thereof are aligned at substantially the same position. The core material link is formed so that the long core materials are adjacent to each other and the core material interval is large, and below this, the long core material and the short core material are adjacent and the core material interval is dense. Can be. In short, by using core materials of different lengths of appropriate types, according to the soil pressure and ground pressure distribution depending on the soil quality and groundwater level of the ground, etc., the core materials are allocated so as to be dense or sparse. What is necessary is just to form a core material connection body.
【0010】[0010]
【実施例】以下、添付図面に基づいて実施例を説明する
が、本発明はこれに限定されるものではない。図1(a)
〜(c)は本発明の芯材連結体を示す正面図であり、図2
は図1(b)のII−II線に沿った断面図であり、図3は本
発明の芯材連結体を吊上げた際の斜視図である。DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments will be described below with reference to the accompanying drawings, but the present invention is not limited to these embodiments. Fig. 1 (a)
FIGS. 2A to 2C are front views showing the connected core material of the present invention, and FIG.
FIG. 2 is a sectional view taken along the line II-II of FIG. 1 (b), and FIG. 3 is a perspective view when the connected core material of the present invention is lifted.
【0011】図1(a)において、本発明の芯材連結体1
0は、I形鋼からなる一本の短尺芯材11と、この短尺
芯材11よりも長いI形鋼からなる一本の長尺芯材12
とを均等間隔でほぼ平行に配置し、これら短尺芯材11
及び長尺芯材12とを、背面側フラットバー13a及び
躯体側フラットバー(図示せず)で連結して形成する。
また図1(b)において、本発明の芯材連結体20は、I
形鋼からなる一本の短尺芯材21を、この短尺芯材21
よりも長いI形鋼からなる二本の長尺芯材22,22の
間に均等間隔でほぼ平行に配置し、これら短尺芯材21
及び長尺芯材22,22とを背面側フラットバー23a
及び躯体側フラットバー23bで連結して形成する。さ
らに図1(c)において、本発明の芯材連結体30は、I
形鋼からなる二本の短尺芯材31,31と、この短尺芯
材31よりも長いI形鋼からなる二本の長尺芯材32,
32とを、交互に均等間隔でほぼ平行に配置し、これら
短尺芯材31,31及び長尺芯材32,32とを背面側
フラットバー33a及び躯体側フラットバー(図示せ
ず)で連結して形成する。Referring to FIG. 1 (a), a core material connected body 1 according to the present invention is shown.
Reference numeral 0 denotes one short core 11 made of I-shaped steel and one long core 12 made of I-shaped steel longer than the short core 11.
Are arranged substantially in parallel at equal intervals, and these short core materials 11
And the long core material 12 are connected to each other by a back side flat bar 13a and a skeleton side flat bar (not shown).
Further, in FIG. 1 (b), the core material connecting body 20 of the present invention
One short core 21 made of a shaped steel is
The two long cores 22 made of I-shaped steel longer than each other are arranged almost in parallel at equal intervals, and these short cores 21 are formed.
And the long core members 22, 22 are connected to the back side flat bar 23a.
And it connects and is formed by the frame side flat bar 23b. Further, in FIG. 1 (c), the core material connected body 30 of the present invention
Two short core members 31, 31 made of shaped steel, and two long core members 32, made of I-shaped steel longer than the short core material 31.
32 are arranged alternately and substantially in parallel at equal intervals, and these short core members 31, 31 and long core members 32, 32 are connected by a back side flat bar 33a and a frame side flat bar (not shown). Formed.
【0012】図1(c)に示したように、前記芯材連結体
30において、短尺芯材31,31及び長尺芯材32,
32はそれぞれ一端(建込み時には下端になる端部)の位
置を揃えて配置する。これにより、他端側のA区間(建
込み時には上端になる端部)には長尺芯材32,32ど
うしが隣あって短尺芯材31が無い、芯材密度が疎な区
間が形成される。なお、芯材連結体10,20において
も、同様に一端の位置を揃えて配置して、他端側に芯材
密度が疎な区間を形成する。かように形成した芯材間隔
が密な区間は、地中に建込んだ際に土圧が大きな区間に
割付け、芯材間隔が疎な区間は、地中に建込んだ際に土
圧が小さな区間に割付ける。As shown in FIG. 1 (c), in the core connecting member 30, short cores 31, 31 and long cores 32,
Numerals 32 are arranged so that the positions of the ends (the ends that become the lower ends when built) are aligned. As a result, in the section A on the other end side (the end that becomes the upper end at the time of building), a section where the long cores 32 and 32 are adjacent to each other and there is no short core 31 and the core density is low is formed. You. Similarly, also in the core material connected bodies 10 and 20, one end is arranged at the same position, and a section having a low core material density is formed on the other end side. Sections with dense cores formed in this way are allocated to sections with high earth pressure when built in the ground, and sections with sparse cores are allocated with soil pressure when built in the ground. Assign to a small section.
【0013】また図2に示したように、前記芯材連結体
20では、背面側フラットバー23aは全てのI形鋼2
2(芯材22)に連続して延設できる長さに形成し、躯
体側フラットバー23bは隣あうI形鋼22のフランジ
間を連結できる長さに形成する。そして、背面側フラッ
トバー23aはI形鋼22のフランジ外側に溶接し、躯
体側フラットバー23bはI形鋼22のフランジ内側に
溶接する。この背面側フラットバーと躯体側フラットバ
ーは、芯材連結体10,30でも同様に配置する。かよ
うに背面側フラットバーをフランジ外側に配置すること
によって、背面側から躯体側に向かう土圧に対し、良好
に対抗することができ、また躯体側フラットバーをフラ
ンジ内側に配置することにより、躯体との間のクリアラ
ンスに余裕を与えることができる。As shown in FIG. 2, the back flat bar 23a in the core material linking body 20
2 (core member 22) is formed to have a length that can be continuously extended, and the skeleton side flat bar 23b is formed to have a length that can connect the flanges of the adjacent I-shaped steel 22. Then, the rear side flat bar 23a is welded to the outside of the flange of the I-shaped steel 22, and the skeleton side flat bar 23b is welded to the inside of the flange of the I-shaped steel 22. The flat bar on the back side and the flat bar on the skeleton side are arranged in the same manner in the core material linked bodies 10 and 30. By arranging the rear side flat bar outside the flange in this way, it is possible to satisfactorily counter the earth pressure from the back side to the skeleton side, and by arranging the skeleton side flat bar inside the flange, It is possible to give a margin to the clearance between the skeleton.
【0014】さらに、図1に示した芯材連結体10,2
0,30では、長尺芯材と短尺芯材とを交互に配置する
ことにより、結果として、長尺芯材が一方の外側に配置
されたが、例えば、複数の短尺芯材と一本の長尺芯材と
を使用して図1(a)〜(c)以外の芯材連結体を形成する場
合にも、同様に、一本の長尺芯材が短尺芯材の間に配置
されることの無いように、必ず長尺芯材を一方の外側に
配置する。かように長尺芯材を一方の外側に配置し、長
尺芯材の上端が地表面に目視可能に現われるように、芯
材連結体をソイルセメント柱に建て込めば、次工程での
芯材連結体の建て込み作業時には、長尺芯材の上端を目
印にすることができ、芯材連結体相互の間隔を正確に建
て込むことができる。[0014] Further, the core member connected body 10, 2 shown in FIG.
At 0 and 30, the long core material and the short core material are alternately arranged, and as a result, the long core material is arranged on one outer side. For example, a plurality of short core materials and one In the case of using the long core material to form a core material connected body other than those shown in FIGS. 1A to 1C, similarly, one long core material is disposed between the short core materials. Be sure to place the long core material on one outside so that it does not occur. If the long core material is placed on one of the outsides and the upper end of the long core material is erected on the soil surface so that the upper end of the long core material can be seen on the ground surface, the core in the next process can be used. At the time of erection work of the linked material, the upper end of the long core material can be used as a mark, and the interval between the linked material members can be accurately set.
【0015】更にまた短尺芯材11,21,31及び長
尺芯材12,22,32のうち、それぞれ少なくとも2
本の芯材の上端にはワイヤー連結孔(図示せず)を形成す
る。Further, at least two of the short core members 11, 21, 31 and the long core members 12, 22, 32 are respectively provided.
A wire connection hole (not shown) is formed at the upper end of the book core.
【0016】次に、芯材連結体の建込み方法について図
4を参照して説明する。建込みに先立って、ソイルセメ
ント柱列壁を構築する予定箇所には、ミキシング装置の
先端から地盤中にセメント系の注入液を注入しながら、
原位置土と注入液とを撹拌混合してソイルセメントの壁
体を形成しておく。Next, a method of assembling the core material connected body will be described with reference to FIG. Prior to the construction, a cement-based injection liquid was injected into the ground from the tip of the mixing device at the location where the soil cement column wall was to be constructed.
The in-situ soil and the infusate are stirred and mixed to form a soil cement wall.
【0017】次いで、クレーン等の揚重機(図示せず)
から吊り具50を吊り降ろす。この吊り具50は、揚重
機等から懸吊された吊りワイヤー45,45と、この吊
りワイヤー45,45に繋止された吊り金物46と、こ
の吊り金物46に繋止されて吊り下げられた吊りワイヤ
ー47,47とを備える。Next, a hoist such as a crane (not shown)
The hanging tool 50 is hung down. The suspending device 50 is suspended by suspending wires 45, 45 suspended from a hoist, etc., suspending hardware 46 secured to the suspending wires 45, 45, and suspended by the suspending hardware 46. And hanging wires 47, 47.
【0018】かような吊り具50の吊りワイヤー47,
47下端を、長尺芯材42の上端に形成されたワイヤー
連結孔に繋止して、揚重機で芯材連結体40を吊り上げ
る。そして、吊り上げた芯材連結体40を、地中に予め
施工された上記ソイルセメントのなかに吊り降ろせば、
芯材連結体40は建込むことができる。なお、建込時
に、芯材連結体40は、その自重によってソイルセメン
ト中に沈下していくため、杭打機等により外力を加える
必要はない。The hanging wire 47 of the hanging tool 50,
The lower end of 47 is connected to a wire connection hole formed at the upper end of the long core material 42, and the core material connected body 40 is lifted by a hoist. Then, if the suspended core material linking body 40 is suspended in the soil cement pre-constructed in the ground,
The core material linking body 40 can be erected. At the time of building, the core material linking body 40 sinks into the soil cement by its own weight, so that it is not necessary to apply external force using a pile driver or the like.
【0019】[0019]
【発明の効果】本発明では、所定間隔でほぼ平行に配置
した複数の芯材を、連結部材によって予め一体に連結し
て芯材連結体を形成し、この芯材連結体をソイルセメン
ト柱列壁のような地中壁中に建て込むようにしたので、
建込み時に芯材連結体に土圧が作用しても、芯材どうし
が連結部材で相互に保持されて、芯材に捻じれが生じる
のを防止することができる。したがって、従来のよう
に、芯材を一本ずつ建て込んで形成する地中壁と比較し
て、芯材の建込み精度が格段に向上し、故に、地中壁の
亀裂発生を防止すると共に漏水発生も防止することがで
きる。また、従来の芯材を一本ずつ建て込む施工方法と
比較すると、本発明の芯材連結体や芯材の建込み方法で
は、複数の芯材を同時に建て込むことができるので、芯
材建て込み施工の工期短縮が可能になる。According to the present invention, a plurality of core members arranged substantially in parallel at predetermined intervals are connected together in advance by a connecting member to form a core member connected body. Because it was built in the underground wall like a wall,
Even when earth pressure acts on the core material connected body at the time of building, the core materials are mutually held by the connecting member, and it is possible to prevent the core material from being twisted. Therefore, as compared with the underground wall which is formed by laying the core material one by one as in the related art, the accuracy of the core material is significantly improved, and thus, the occurrence of cracks in the underground wall is prevented. Water leakage can also be prevented. Also, in comparison with the conventional method of constructing the core material one by one, the method of constructing the core material connected body and the core material according to the present invention allows a plurality of core materials to be simultaneously constructed. The construction period can be shortened.
【0020】さらに本発明では、予め芯材連結体を形成
し、この芯材連結体をソイルセメント柱列壁のような地
中壁中に建て込むので、一部の芯材の上端が地表面下に
埋設される芯材割付け、例えば、比較的土圧が小さい地
表面近傍では芯材間隔を大きく形成し、比較的土圧が大
きい床付け部近傍では芯材間隔を狭く密にするといった
芯材割付けも可能になる。故に、芯材量を減少させるこ
とができて、材料コストの削減が可能になる。Further, according to the present invention, a core material connected body is formed in advance and this core material connected body is erected in an underground wall such as a soil cement column wall, so that the upper end of a part of the core material is A core material to be buried underneath, for example, a core material with a large core spacing near the ground surface where the earth pressure is relatively low, and a narrow core density near the flooring part where the earth pressure is relatively large. Material allocation is also possible. Therefore, the amount of the core material can be reduced, and the material cost can be reduced.
【図1】(a)〜(c)は本発明の芯材連結体を示す正面図で
ある。FIGS. 1 (a) to 1 (c) are front views showing a core material connected body of the present invention.
【図2】図1(b)のII−II線に沿った断面図である。FIG. 2 is a sectional view taken along the line II-II of FIG. 1 (b).
【図3】本発明の芯材連結体を吊上げた際の斜視図であ
る。FIG. 3 is a perspective view showing a state in which the linked core material of the present invention is lifted.
【図4】従来の設計図であって、山留め壁の断面図、芯
材割付け図及び設計側圧図である。FIG. 4 is a conventional design drawing, which is a cross-sectional view of a retaining wall, a layout of core materials, and a design side pressure diagram.
10,20,30 芯材連結体 11,21,31 短尺芯材(芯材) 12,22,32 長尺芯材(芯材) 13a,23a,33a 背面フラットバー(連結部
材) 23b 躯体側フラットバー(連結部材)10, 20, 30 Core material connection body 11, 21, 31 Short core material (core material) 12, 22, 32 Long core material (core material) 13a, 23a, 33a Back flat bar (connection member) 23b Body side flat Bar (connecting member)
Claims (3)
材と、該複数の芯材を一体に連結する連結部材とを備
え、 これにより該複数の芯材を同時に地中に建込み可能にし
たことを特徴とする地中壁に用いる芯材連結体。1. A plurality of core members arranged substantially in parallel at predetermined intervals, and a connecting member for integrally connecting the plurality of core members, whereby the plurality of core members can be simultaneously built in the ground. A linked core material used for an underground wall, characterized in that:
し、該複数の芯材を一体に連結して芯材連結体を形成
し、該芯材連結体を吊り上げた後に地中に建込む芯材の
建込み方法。2. A plurality of core members are arranged substantially in parallel at predetermined intervals, and the plurality of core members are integrally connected to form a core member connected body. How to build the core material to be built.
隔でほぼ平行に配置し、該複数の芯材を一体に連結して
芯材連結体を形成し、該芯材連結体を吊り上げた後に地
中に建込む芯材の建込み方法であって、 前記芯材連結体を形成する際に、該複数の芯材のうちの
短い芯材が地中の土圧の大きな区間に位置するように配
置したことを特徴とする芯材の建込み方法。3. A plurality of core materials having two or more kinds of lengths are arranged substantially in parallel at a predetermined interval, and the plurality of core materials are integrally connected to form a core material connected body. A method of building a core material to be built in the ground after lifting the core material, wherein when forming the core material connected body, a short core material of the plurality of core materials is a section where the earth pressure in the ground is large. A method for installing a core material, wherein the core material is disposed so as to be located at a position.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16760296A JPH108457A (en) | 1996-06-27 | 1996-06-27 | Core linked body used for underground wall and method of building core |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16760296A JPH108457A (en) | 1996-06-27 | 1996-06-27 | Core linked body used for underground wall and method of building core |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH108457A true JPH108457A (en) | 1998-01-13 |
Family
ID=15852820
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16760296A Pending JPH108457A (en) | 1996-06-27 | 1996-06-27 | Core linked body used for underground wall and method of building core |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH108457A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002138465A (en) * | 2000-11-01 | 2002-05-14 | Seiko Kogyo Kk | Steel pipe column earth retaining wall construction method |
-
1996
- 1996-06-27 JP JP16760296A patent/JPH108457A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002138465A (en) * | 2000-11-01 | 2002-05-14 | Seiko Kogyo Kk | Steel pipe column earth retaining wall construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2215316B1 (en) | A block wall system | |
| US6240700B1 (en) | Constructing method for underground continuous double-row walls and the structure of continuous double-row walls | |
| JP2000352108A (en) | Precast block method | |
| CN210369031U (en) | Slurry anchor lap joint type prefabricated retaining wall unit and prefabricated retaining wall | |
| CN110093980A (en) | Beam-column node structure, the construction method of beam-column node structure and assembled architecture | |
| US4976087A (en) | Method of forming footing and laying first course of block | |
| EP0245407B1 (en) | Casing for constructing a rigid structure upon the bottom of a body of water as well as a method of constructing a rigid structure upon the bottom of a body of water | |
| JPH108457A (en) | Core linked body used for underground wall and method of building core | |
| KR101314764B1 (en) | Retaining wall and corrugation method using corrugated steel | |
| CN219240553U (en) | Sprayed concrete thickness and base bonding strength controller | |
| JPH0833005B2 (en) | Construction method of soil pile row mountain retaining wall | |
| CN218894091U (en) | Utilize integrated cantilever pile supporting construction of hardening road | |
| CN216108526U (en) | Underground continuous wall structure for foundation pit support | |
| KR101168803B1 (en) | The Method for constructing Underground Structure | |
| KR102229028B1 (en) | Hybrid foundation combined with the precast and cast-in-place concrete and its manufacturing method | |
| CN111395324A (en) | Mixed pile construction method and mixed pile structure | |
| JP3094329B2 (en) | Joint reinforcement and construction method of block building using this joint reinforcement | |
| CN220666601U (en) | Wet-type connection structure of laminated slab and integral partition plate | |
| CN220908715U (en) | Installation structure of assembled wall | |
| KR20090084273A (en) | Block type rock retaining wall method using steel rod | |
| JPH07292857A (en) | Pc member with irregular-shaped steel pipe for joint, and connecting method thereof | |
| JPH04347283A (en) | Construction method of reinforced concrete fence | |
| JP2018135658A (en) | Building structure | |
| CN104878939B (en) | The construction method of vertical reinforcement in the xoncrete structure of heavy in section | |
| JPS63181831A (en) | Underground construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20000822 |