JPH1122373A - Building method for arrival or starting manhole in advancing method - Google Patents

Building method for arrival or starting manhole in advancing method

Info

Publication number
JPH1122373A
JPH1122373A JP17823397A JP17823397A JPH1122373A JP H1122373 A JPH1122373 A JP H1122373A JP 17823397 A JP17823397 A JP 17823397A JP 17823397 A JP17823397 A JP 17823397A JP H1122373 A JPH1122373 A JP H1122373A
Authority
JP
Japan
Prior art keywords
casing
ground
manhole
forming member
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17823397A
Other languages
Japanese (ja)
Inventor
Taizou Masumi
泰三 枡見
Hiroshi Koyama
浩史 小山
Shinji Nakamura
信児 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP17823397A priority Critical patent/JPH1122373A/en
Publication of JPH1122373A publication Critical patent/JPH1122373A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To build a manhole without building timbering for earth retaining. SOLUTION: When an impermeable impervious layer 12 is formed in a given depth position in a ground 10 of the an arrival manhole building schemed ground, a penetration work of a casing 14 is effected from the ground side. A casing 14 excavates earth in water and excavation is effected as excavated earth is discharged to an external part and when occasion needs, the casing 14 is rotational driven. When the tip of the casing 14 reaches the impervious layer 12, the surface side of the impervious layer 12, the surface side of the impervious layer 12 is excavated by approximate 1 m to prevent inflow of underground water to the casing 14. Water in the casing 14 is discharged. Thereafter, a manhole forming member is arranged in the casing 14 and the casing 14 is pulled out.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、推進工法における
到達ないしは発進人孔の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a reaching or starting human hole in a propulsion method.

【0002】[0002]

【従来の技術】下水道などの地下管路の敷設工事におい
ては、敷設位置が、例えば、河川の横断個所や、地中埋
設物との関係などにより深くなる場合がある。このよう
な条件下での管路の敷設工事には、通常、推進工法が採
用される。
2. Description of the Related Art When laying an underground conduit such as a sewer, the laying position may be deeper due to, for example, a crossing point of a river or a relationship with an underground object. For the construction work of the pipeline under such conditions, a propulsion method is usually employed.

【0003】推進工事で管路の敷設を行う場合には、発
進人孔から到達人孔に向けて、管路の推進が行われる。
このような推進工法においては、コンクリートの2次製
品を用いて人孔構造物を構築することが行われている。
[0003] When laying a pipeline in propulsion work, the pipeline is propelled from the starting manhole to the reaching manhole.
In such a propulsion method, a manhole structure is constructed using a secondary product of concrete.

【0004】この場合の人孔の構築方法としては、土留
め用の支保工を施して、地盤を所定深度まで掘削した後
に、ブロック状に分割した人孔形成部材を、下方から順
巻き工法により積み重ねて構築する方法が一般的に採用
されている。
[0004] In this case, as a method of constructing a human hole, a method for constructing a human hole is carried out from below by forming a human hole forming member divided into blocks after excavating the ground to a predetermined depth by providing a support for earth retaining. The method of stacking and building is generally adopted.

【0005】しかしながら、このような人孔の構築方法
には、以下に説明する技術的な課題があった。
[0005] However, such a method for constructing a human hole has the following technical problems.

【0006】[0006]

【発明が解決しようとする課題】すなわち、前述した人
孔の構築方法では、掘削深度が大きくなると、支保工の
架設および撤去作業に、手間がかかるとともに、深い地
下での積み重ね作業を行うことになり、作業環境も良好
なものとは言えない。
That is, according to the above-described method for constructing a human hole, when the excavation depth becomes large, it takes time and effort to erection and removal of the shoring, and it is necessary to perform a deep underground stacking operation. Therefore, the working environment is not good.

【0007】また、支保工を撤去する際に、これを引き
抜くと、そのときの衝撃や振動に伴って、構築した人孔
構造物や周辺地盤への悪影響が懸念される。
[0007] Further, if the support is removed when the support is removed, there is a concern that the impact or vibration at that time may have an adverse effect on the constructed human hole structure and the surrounding ground.

【0008】本発明は、このような従来の問題点に鑑み
てなされたものであって、その目的とするところは、土
留め用の支保工が不要になるとともに、周辺地盤に悪影
響を及ぼすことが非常に少なくなる推進工法における到
達ないしは発進人孔の構築方法を提供することにある。
[0008] The present invention has been made in view of such conventional problems, and an object of the present invention is to eliminate the need for shoring for earth retaining and adversely affect the surrounding ground. It is an object of the present invention to provide a method for constructing a reaching or starting human hole in a propulsion method in which the number of people is extremely reduced.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するた
め、本発明は、推進工法における到達ないしは発進人孔
の構築方法において、前記人孔の構築位置の地盤中に必
要に応じて不透水性の遮水層を形成する工程と、地上か
ら地盤を掘削しながら下端が前記遮水層に到達するケー
シングを貫入する工程と、前記ケーシング内部に下端が
閉止された人孔形成部材を挿入設置する工程と、前記ケ
ーシングを回転させながら引き抜いた後に、前記人孔形
成部材の外方に到達防護工を施す工程とを順に行うよう
にした。この構成によれば、ケーシングにより土留めを
行うことができるので、掘削に伴う土留め支保工を設置
する必要がない。また、ケーシングの貫入,引き抜き、
人孔形成用部材の挿入設置などの作業は、地上側からで
きるので、環境の悪い条件下で作業がなくなる。さら
に、ケーシングを引き抜く際には、これを回転させなが
ら行うので、周辺地盤や構築された人孔に対する影響が
非常に少なくなる。前記ケーシングを貫入する工程で、
当該ケーシング内に注水して、水中掘削を行うととも
に、前記人孔形成部材を挿入設置する前に、前記ケーシ
ング内の水を排水してもよい。このような構成を採用す
ると、ケーシングとその内部に注水された水とにより周
囲の土水圧に対抗することができるので、より深い人孔
の構築が可能になる。前記遮水層は、深層混合工法など
による地盤改良により形成することができる。 この構
成を採用すると、地上側からの作業で比較的簡単に遮水
層の形成を行える。本発明では、前記ケーシングを引き
抜く前に、前記人孔形成部材に載加荷重を加えることが
できる。この場合の載加荷重は、人孔形成部材内に水を
注水することなどより行われ、載加荷重を人孔形成部材
に加えておくと、ケーシングの引き抜き時に発生する負
圧や浮力に対して、人孔形成部材を安定させることが可
能になる。
In order to achieve the above object, the present invention relates to a method for constructing a reaching or starting manhole in a propulsion method, wherein the manhole is impermeable as required in the ground at the construction position of the manhole. Forming the impermeable layer, excavating the ground from the ground, and penetrating a casing whose lower end reaches the impermeable layer, and inserting and installing a human hole forming member having a closed lower end inside the casing. The step and the step of performing the protective work outside the human-hole forming member after the casing is pulled out while rotating the casing are sequentially performed. According to this configuration, earth retaining can be performed by the casing, and thus it is not necessary to install earth retaining supports associated with excavation. In addition, penetration of casing, pulling out,
Work such as insertion and installation of a member for forming a human hole can be performed from the ground side, so that work is not performed under adverse environmental conditions. Furthermore, when the casing is pulled out, it is performed while rotating, so that the influence on the surrounding ground and the constructed human hole is extremely reduced. In the step of penetrating the casing,
Water may be injected into the casing to perform underwater excavation, and the water in the casing may be drained before inserting and installing the human hole forming member. When such a configuration is adopted, the casing and the water injected into the casing can counter the surrounding earth water pressure, so that a deeper human hole can be constructed. The water impermeable layer can be formed by ground improvement by a deep mixing method or the like. When this configuration is adopted, the formation of the impermeable layer can be relatively easily performed from the ground side. In the present invention, a loading load can be applied to the human-hole forming member before the casing is pulled out. The loading load in this case is performed by, for example, pouring water into the human hole forming member, and if the loading load is applied to the human hole forming member, the negative pressure and buoyancy generated when the casing is pulled out are reduced. Thus, the human hole forming member can be stabilized.

【0010】[0010]

【発明の実施の形態】以下、本発明の好ましい実施の形
態について添付図面を参照して詳細に説明する。図1か
ら図6は、本発明にかかる推進工法における到達ないし
は発進人孔の構築方法の一実施例を示している。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIGS. 1 to 6 show an embodiment of a method for constructing a reaching or starting human hole in the propulsion method according to the present invention.

【0011】同図に示した構築方法は、本発明を到達人
孔に適用した場合を示しており、到達人孔を構築する際
には、まず、図1に示すように、到達人孔の構築予定地
の地盤10中の所定深度位置に不透水性の遮水層12が
形成される。
The construction method shown in FIG. 1 shows a case where the present invention is applied to a reaching manhole. When constructing a reaching manhole, first, as shown in FIG. An impermeable impermeable layer 12 is formed at a predetermined depth position in the ground 10 at the construction site.

【0012】遮水層12の大きさは、後述するケーシン
グ14の直径よりも大きく形成されるとともに、その厚
みは、例えば、数m程度に設定される。この遮水層12
の形成は、例えば、同図に示すように、地上から地盤中
に注入管13を貫入し、注入管13の先端側から、紛体
ないしは液状の固結材を噴射して、地盤改良を行うこと
により形成することができる。
The size of the water-impervious layer 12 is formed to be larger than the diameter of a casing 14 described later, and its thickness is set to, for example, about several meters. This impermeable layer 12
To form the ground, for example, as shown in the figure, the injection pipe 13 penetrates into the ground from the ground, and a powder or liquid consolidating material is sprayed from the tip side of the injection pipe 13 to perform the ground improvement. Can be formed.

【0013】地盤改良の方法は、図1に示した方法に限
ることはなく、例えば、深層混合法などであってもよ
い。また、地盤10の性状が良好である場合には、遮水
層12は、必ずしも形成する必要はなく、地盤10の性
状を考慮して必要に応じて設ければよい。遮水層12の
形成が終了すると、図2に示すように、地上側からケー
シング14の貫入作業が行われる。
The method of ground improvement is not limited to the method shown in FIG. 1, and may be, for example, a deep mixing method. In addition, when the properties of the ground 10 are good, the impermeable layer 12 does not necessarily need to be formed, and may be provided as necessary in consideration of the properties of the ground 10. When the formation of the water-blocking layer 12 is completed, the casing 14 is penetrated from the ground side as shown in FIG.

【0014】ケーシング14は、例えば、その直径が2
m程度の大きさのものであり、地上に設置されたガイド
15により案内しながら、内部に水を満たして、土砂を
水中掘削して、掘削土砂を外部に排出しながら行われ、
必要に応じて、ケーシング14を回転駆動して、周辺土
砂との間の摩擦を低減する。
The casing 14 has, for example, a diameter of 2
m, while being guided by a guide 15 installed on the ground, filling the inside with water, excavating earth and sand underwater, and discharging the excavated earth and sand to the outside,
If necessary, the casing 14 is rotationally driven to reduce friction between the surrounding earth and sand.

【0015】なお、このケーシング14の貫入に際し
て、地盤10の性状が非常に悪い場合には、例えば、ケ
ーシング14の貫入予定地域の地盤を石灰などにより地
盤改良して行ってもよいし、地盤10の性状が良好な場
合には、ケーシング14内に水を注入することなく、ド
ライな状態で行ってもよい。
If the properties of the ground 10 are very poor when the casing 14 is penetrated, for example, the ground in the area where the casing 14 is to be penetrated may be improved with lime or the like, or the ground 10 may be used. If the properties are good, the drying may be performed without injecting water into the casing 14.

【0016】ケーシング14の先端が遮水層12に到達
すると、遮水層12の表面側を、1m程度掘り込み、地
下水がケーシング14内に流入することを防止する。次
いで、図3に示すように、水中ポンプ16をケーシング
14内に設置し、ケーシング14内の水を排出する。
When the tip of the casing 14 reaches the impermeable layer 12, the surface of the impermeable layer 12 is dug about 1 m to prevent groundwater from flowing into the casing 14. Next, as shown in FIG. 3, the submersible pump 16 is installed in the casing 14, and the water in the casing 14 is discharged.

【0017】ケーシング14内から水が排出されると、
図4に示すように、ケーシング14の底部に、ケーシン
グ14の引き抜きが可能な程度の厚みを有する底盤コン
クリート層17を必要に応じて形成する。
When water is discharged from the casing 14,
As shown in FIG. 4, a bottom concrete layer 17 having a thickness that allows the casing 14 to be pulled out is formed on the bottom of the casing 14 as necessary.

【0018】そして、ケーシング14内に人孔形成部材
18を吊り下げて設置する。この人孔形成部材18は、
底部18aと、底部18aの外周縁に一体形成された筒
状壁18bとから構成されていて、下端が閉止されると
ともに、上端が開口した有底円筒状のものである。
Then, the human hole forming member 18 is suspended and installed in the casing 14. This human hole forming member 18
It has a bottom portion 18a and a cylindrical wall 18b integrally formed on the outer peripheral edge of the bottom portion 18a, and has a closed-bottom cylindrical shape with a closed lower end and an open upper end.

【0019】このような人孔形成部材18は、コンクリ
ートの2次製品として、販売されており、ユニホールと
呼ばれている。人孔形成部材18は、到達人孔の場合に
は、到達してくる推進機の頭部を解体撤去するスペース
が必要なので、筒状壁18bの内径が、例えば、1.5
m程度のものを使用する。
Such a human hole forming member 18 is sold as a secondary product of concrete and is called a uni-hole. In the case of a reaching manhole, the manhole forming member 18 needs a space for dismantling and removing the head of the arriving propulsion machine. Therefore, the inner diameter of the cylindrical wall 18b is, for example, 1.5 mm.
Use a material of about m.

【0020】人孔形成部材18の設置が終了すると、図
5に示すように、ケーシング14の引き抜き作業が行わ
れる。この場合、ケーシング14の引き抜き作業に先立
って、人孔形成部材18内に水を注入して、載加荷重が
加えられる。
When the installation of the human hole forming member 18 is completed, the casing 14 is pulled out as shown in FIG. In this case, prior to the operation of pulling out the casing 14, water is injected into the human hole forming member 18 to apply a load.

【0021】また、ケーシング14を引き抜く際には、
ケーシング14に回転が加えられるとともに、ケーシン
グ14の引き抜きによって人孔形成部材18の外周に発
生する空隙には、注入管20を介して、セメントベント
ナイトなどの固化剤が充填される。
When the casing 14 is pulled out,
As the casing 14 is rotated, voids formed on the outer periphery of the human hole forming member 18 due to withdrawal of the casing 14 are filled with a solidifying agent such as cement bentonite via an injection pipe 20.

【0022】空隙にこのような固化剤を充填すると、空
隙の発生に伴う、周辺地盤の崩落などを防ぐことができ
る。また、ケーシング14を回転させながら引き抜く
と、地盤10との間の摩擦が少なくなり、引き抜きが容
易になるだけでなく、周辺地盤に与える影響が大幅に低
減する。
When the voids are filled with such a solidifying agent, the collapse of the surrounding ground due to the voids can be prevented. Further, when the casing 14 is pulled out while being rotated, the friction between the casing 14 and the ground 10 is reduced, so that the pulling out becomes easy and the influence on the surrounding ground is greatly reduced.

【0023】ケーシング14の引き抜き撤去が終了する
と、図6に示すように、人孔形成部材18の頭部側に、
地上に連通する壁体22を形成し、人孔形成部材18の
外方に到達防護工24を形成する。
When the removal of the casing 14 is completed, as shown in FIG.
The wall body 22 communicating with the ground is formed, and the reach protection member 24 is formed outside the human hole forming member 18.

【0024】この到達防護工24は、地上側から注入管
26を地盤10中に貫入し、薬液を注入することにより
行われ、到達防護工24が形成されると、到達人孔の構
築が完了する。
The reaching protection work 24 is performed by injecting an injection pipe 26 into the ground 10 from the ground side and injecting a chemical solution. When the reaching protection work 24 is formed, the construction of the reaching manhole is completed. I do.

【0025】さて、以上のようにして構築される到達人
孔の構築方法によれば、ケーシング14の貫入により土
留めを行うことができるので、掘削に伴う土留め支保工
を設置する必要がなく、土留め用支保工を設けないの
で、その分だけ掘削土砂の量も少なくなる。
According to the method for constructing the reaching manhole constructed as described above, earth retaining can be performed by penetrating the casing 14, so that it is not necessary to install an earth retaining support accompanying the excavation. Since there is no earth retaining support, the amount of excavated earth and sand is reduced by that much.

【0026】また、ケーシング14の貫入,引き抜き、
人孔形成用部材18の挿入設置などの作業は、地上側か
らできるので、環境の悪い条件下で作業がなくなる。
Further, the casing 14 is penetrated and pulled out,
Work such as insertion and installation of the human hole forming member 18 can be performed from the ground side, so that work is not performed under adverse environmental conditions.

【0027】さらに、ケーシング14を引き抜く際に
は、これを回転させながら行うので、周辺地盤や構築さ
れた到達人孔に対する影響が非常に少なくなる。
Furthermore, since the casing 14 is pulled out while rotating, the influence on the surrounding ground and the constructed manhole is extremely reduced.

【0028】また、本実施例の場合には、遮水層12
は、深層混合工法などによる地盤改良により形成するの
で、地上側からの作業で比較的簡単に遮水層12を形成
することができる。
Further, in the case of this embodiment, the impermeable layer 12
Is formed by ground improvement by a deep mixing method or the like, so that the impermeable layer 12 can be formed relatively easily by work from the ground side.

【0029】さらに、本実施例の場合には、ケーシング
14を引き抜く前に、人孔形成部材18に注水して載加
荷重を加えるので、ケーシング14の引き抜き時に発生
する負圧や浮力に対して、人孔形成部材18を安定させ
ることができる。
Further, in the case of the present embodiment, before the casing 14 is pulled out, a water load is applied to the human hole forming member 18 to apply a load, so that a negative pressure and a buoyancy generated when the casing 14 is pulled out. Thus, the human hole forming member 18 can be stabilized.

【0030】なお、上記実施例では、本発明を到達人孔
の構築に適用した場合を例示したが、本発明は、推進工
法の発進人孔の構築にも適用することができる。
In the above-described embodiment, the case where the present invention is applied to the construction of the reaching manhole is illustrated. However, the present invention can also be applied to the construction of the starting manhole of the propulsion method.

【0031】[0031]

【発明の効果】以上、実施例で詳細に説明したように、
本発明にかかる推進工法における到達ないしは発進人孔
の構築工法によれば、土留め用支保工の設置撤去に伴う
作業が不要になり、人力作業が低減するため、省力化が
図られるとともに、作業環境も改善され、安全性も向上
する。
As described above in detail in the embodiments,
According to the construction method of the reaching or starting manhole in the propulsion method according to the present invention, the work associated with the installation and removal of the earth retaining shoring becomes unnecessary, and the human labor is reduced. The environment is improved and safety is improved.

【0032】また、掘削土量も少なくなるので、工期の
短縮および低コスト化が達成される。さらに、周辺地盤
に与える影響も非常に少なくすることができる。
Further, since the amount of excavated soil is reduced, the construction period is shortened and the cost is reduced. Further, the influence on the surrounding ground can be extremely reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる到達人孔の構築方法の最初の工
程を示す断面説明図である。
FIG. 1 is an explanatory cross-sectional view showing a first step of a method for constructing an attainment manhole according to the present invention.

【図2】図1の工程に引き続いて行われる工程の断面説
明図である。
FIG. 2 is an explanatory cross-sectional view of a step performed subsequent to the step of FIG. 1;

【図3】図2の工程に引き続いて行われる工程の断面説
明図である。
FIG. 3 is an explanatory cross-sectional view of a step performed subsequent to the step of FIG. 2;

【図4】図3の工程に引き続いて行われる工程の断面説
明図である。
FIG. 4 is an explanatory cross-sectional view of a step performed subsequent to the step of FIG. 3;

【図5】図4の工程に引き続いて行われる工程の断面説
明図である。
FIG. 5 is an explanatory cross-sectional view of a step performed subsequent to the step of FIG. 4;

【図6】図5の工程に引き続いて行われる工程の断面説
明図である。
FIG. 6 is an explanatory cross-sectional view of a step performed subsequent to the step of FIG. 5;

【符号の説明】[Explanation of symbols]

10 地盤 12 遮水層 14 ケーシング 16 水中ポンプ 18 人孔形成部材 24 到達防護工 Reference Signs List 10 ground 12 impermeable layer 14 casing 16 submersible pump 18 human hole forming member 24 reaching protection

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 推進工法における到達ないしは発進人孔
の構築方法において、 前記人孔の構築位置の地盤中に必要に応じて不透水性の
遮水層を形成する工程と、 地上から地盤を掘削しながら下端が前記遮水層に到達す
るケーシングを貫入する工程と、 前記ケーシング内部に下端が閉止された人孔形成部材を
挿入設置する工程と、 前記ケーシングを回転させながら引き抜いた後に、前記
人孔形成部材の外方に到達防護工を施す工程とを順に行
うことを特徴とする推進工法における到達ないしは発進
人孔の構築方法。
1. A method for constructing a reaching or starting manhole in a propulsion method, comprising the steps of: forming an impermeable impermeable layer in the ground at a position where the manhole is constructed, if necessary, excavating the ground from the ground A step of penetrating a casing whose lower end reaches the impermeable layer while inserting and installing a human hole forming member having a closed lower end inside the casing; and And a step of performing an arrival protection work outside of the hole forming member in order.
【請求項2】 前記ケーシングを貫入する工程で、当該
ケーシング内に注水して、水中掘削を行うとともに、前
記人孔形成部材を挿入設置する前に、前記ケーシング内
の水を排水することを特徴とする請求項1記載の推進工
法における到達ないしは発進人孔の構築方法。
2. In the step of penetrating the casing, water is injected into the casing to perform underwater excavation, and the water in the casing is drained before inserting and installing the human hole forming member. 2. A method for constructing a reaching or starting human hole in the propulsion method according to claim 1.
【請求項3】 前記遮水層は、深層混合工法などによる
地盤改良で形成することを特徴とする請求項1記載の推
進工法における到達ないしは発進人孔の構築方法。
3. The method according to claim 1, wherein the water-impervious layer is formed by ground improvement by a deep mixing method or the like.
【請求項4】 前記ケーシングを引き抜く前に、前記人
孔形成部材に載加荷重を加えることを特徴とする請求項
1記載の推進工法における到達ないしは発進人孔の構築
方法。
4. The method according to claim 1, wherein a load is applied to the human hole forming member before the casing is pulled out.
JP17823397A 1997-07-03 1997-07-03 Building method for arrival or starting manhole in advancing method Pending JPH1122373A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17823397A JPH1122373A (en) 1997-07-03 1997-07-03 Building method for arrival or starting manhole in advancing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17823397A JPH1122373A (en) 1997-07-03 1997-07-03 Building method for arrival or starting manhole in advancing method

Publications (1)

Publication Number Publication Date
JPH1122373A true JPH1122373A (en) 1999-01-26

Family

ID=16044931

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17823397A Pending JPH1122373A (en) 1997-07-03 1997-07-03 Building method for arrival or starting manhole in advancing method

Country Status (1)

Country Link
JP (1) JPH1122373A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018105030A (en) * 2016-12-27 2018-07-05 鹿島建設株式会社 Ground excavation method
KR101953192B1 (en) * 2018-10-22 2019-02-28 주식회사 진평 semi-shield method with improved directionality for recycle of casing

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018105030A (en) * 2016-12-27 2018-07-05 鹿島建設株式会社 Ground excavation method
KR101953192B1 (en) * 2018-10-22 2019-02-28 주식회사 진평 semi-shield method with improved directionality for recycle of casing

Similar Documents

Publication Publication Date Title
CN106545005B (en) A kind of reinforcing body and reinforcement means of subway tunnel shield end
JP2022502586A (en) Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles
JP5282541B2 (en) How to prevent lifting of the lining body
JP5502538B2 (en) Pile construction method and pile construction device
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
CN109208594A (en) Processing method, steel pile casting structure and the drilled pile of sinking steel protecting canister chance boulder
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
CN105350544B (en) For water-stop curtain and its construction method containing block stone region
CN115853024B (en) Anti-seepage wall structure and cofferdam anti-seepage construction method
CN106087995A (en) The method of stake is built in a kind of boring
CN218439314U (en) Prospecting hole plugging device
JP5282542B2 (en) Ground deformation prevention method and ground deformation prevention structure
JP2874906B2 (en) Shaft construction method
JP2003138584A (en) Construction method of underground skeleton
CN220890190U (en) Pipe jacking working well
JP3941429B2 (en) Water stoppage / Yamadome construction method for rebuilding existing buildings
JPS63223215A (en) In-situ concrete piling work
KR102505449B1 (en) Casing for retaining wall construction and method for retaining wall construction using the same
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPH0325121A (en) Sinking of pile in inner drilling pile method
JP2002115259A (en) Extension method for basement
JP2024086373A (en) How to build a water barrier
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPS61113924A (en) Method of forming pileform body