JPS559967A - Method of constructing base for steel tower - Google Patents
Method of constructing base for steel towerInfo
- Publication number
- JPS559967A JPS559967A JP8322378A JP8322378A JPS559967A JP S559967 A JPS559967 A JP S559967A JP 8322378 A JP8322378 A JP 8322378A JP 8322378 A JP8322378 A JP 8322378A JP S559967 A JPS559967 A JP S559967A
- Authority
- JP
- Japan
- Prior art keywords
- blocks
- vertical hole
- steel tower
- ground
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title abstract 3
- 239000010959 steel Substances 0.000 title abstract 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 1
- 238000000465 moulding Methods 0.000 abstract 1
- 230000002093 peripheral effect Effects 0.000 abstract 1
Landscapes
- Foundations (AREA)
Abstract
PURPOSE: To plan to shorten working hours and save energy by constructing a slab portion for a base with a plurality of ready-made blocks.
CONSTITUTION: In case a base for a steel tower is constructed, a vertical hole 1 with a predetermined depth is digged first into the ground and ready-made blocks 2 are hang down to the predetermined positions at the bottom thereof. The block 2 is made of concrete and formed so as to be a tubular box with a square section and a metallic edge is mounted, if necessary, along the end of the opening thereof. Next, the block 2 are pushed into the peripheral ground at the bottom portion of the vertical hole 1 by a push-jack 5. This pushing work is effected against each one set of a pair of blocks 2 successively, and finally, a plurality of blocks are pushed into the ground in radial configuration. Next, a leg member 8 for the steel tower is installed at the center of the vertical hole 1 and reinforcing steel bars 9 are combine therewith, thereafter, a molding frame 10 is assembled and concrete is filled therewithin to construct a pillor portion 7.
COPYRIGHT: (C)1980,JPO&Japio
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8322378A JPS559967A (en) | 1978-07-07 | 1978-07-07 | Method of constructing base for steel tower |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8322378A JPS559967A (en) | 1978-07-07 | 1978-07-07 | Method of constructing base for steel tower |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS559967A true JPS559967A (en) | 1980-01-24 |
| JPS569618B2 JPS569618B2 (en) | 1981-03-03 |
Family
ID=13796307
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8322378A Granted JPS559967A (en) | 1978-07-07 | 1978-07-07 | Method of constructing base for steel tower |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS559967A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2013087481A (en) * | 2011-10-17 | 2013-05-13 | Chugoku Electric Power Co Inc:The | Structural member for steel tower foundation and steel tower foundation, and construction method for steel tower foundation |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS53111606A (en) * | 1977-03-09 | 1978-09-29 | Chubu Electric Power | Method of making foundation for steel tower* and cylinder for making base board of foundation for steel tower |
-
1978
- 1978-07-07 JP JP8322378A patent/JPS559967A/en active Granted
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS53111606A (en) * | 1977-03-09 | 1978-09-29 | Chubu Electric Power | Method of making foundation for steel tower* and cylinder for making base board of foundation for steel tower |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2013087481A (en) * | 2011-10-17 | 2013-05-13 | Chugoku Electric Power Co Inc:The | Structural member for steel tower foundation and steel tower foundation, and construction method for steel tower foundation |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS569618B2 (en) | 1981-03-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS57224A (en) | Protection work of slope and modified ruler used therefor | |
| JPS55114717A (en) | Combination method of support and foundation | |
| JPS57187427A (en) | Reinforcing work for slope | |
| JPS57193631A (en) | L-shaped concrete block to be integrally combined with ground and construction of retaining wall by block thereof | |
| JPS56135625A (en) | Construction of underwater structure | |
| JPS57178032A (en) | Constructing method for concrete wall | |
| JPS57225A (en) | Reinforcing work for natural ground | |
| JPS57112523A (en) | Substructure of building | |
| JPS5523242A (en) | Concrete foundation process | |
| JPS5595013A (en) | Construction of incinerator | |
| JPS5693916A (en) | Construction for water-surface structure | |
| JPS57184134A (en) | Construction of retaining wall by large-size blocks | |
| JPS5712730A (en) | Foundation work employing a precast reinforced concrete foundation beam | |
| JPS55161125A (en) | Foundation constructing method | |
| IT7949116A0 (en) | HOLLOW METALLIC POLE, FILLABLE WITH CONCRETE, FOR THE PRODUCTION OF A CAST IN PLACE POLE | |
| JPS55111528A (en) | Base formation method | |
| JPS57112521A (en) | Advanced single hole type underground foundation work | |
| JPS56425A (en) | Prefabricated box-type retaining wall | |
| JPS554461A (en) | Method of constructing plantable retaining wall and block for constituting the plantable retaining wall | |
| SU678146A1 (en) | Method of constructing a supporting monolithic reinforced-concrete slab of the foundation of a turbine-electric unit | |
| JPS5724734A (en) | Construction method for box culvert | |
| JPS6483716A (en) | Foundation work for building | |
| JPS57155424A (en) | Executing method for underground outer wall | |
| SE8107068L (en) | Building foundation component with V-section upper surface - has reinforcement bars held in groove of upper surface while concrete poured to raised level | |
| JPS5796136A (en) | Setting method of foundation |