JPS59179902A - Bowed walking road block - Google Patents
Bowed walking road blockInfo
- Publication number
- JPS59179902A JPS59179902A JP5384783A JP5384783A JPS59179902A JP S59179902 A JPS59179902 A JP S59179902A JP 5384783 A JP5384783 A JP 5384783A JP 5384783 A JP5384783 A JP 5384783A JP S59179902 A JPS59179902 A JP S59179902A
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- sidewalk
- roadway
- overhanging
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 206010011224 Cough Diseases 0.000 claims 1
- 230000002262 irrigation Effects 0.000 description 6
- 238000003973 irrigation Methods 0.000 description 6
- 238000009434 installation Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 238000003780 insertion Methods 0.000 description 4
- 230000037431 insertion Effects 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 241000196324 Embryophyta Species 0.000 description 2
- 241000209094 Oryza Species 0.000 description 2
- 235000007164 Oryza sativa Nutrition 0.000 description 2
- 239000010426 asphalt Substances 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 239000000047 product Substances 0.000 description 2
- 235000009566 rice Nutrition 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 239000013067 intermediate product Substances 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 230000002747 voluntary effect Effects 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
この発明は、高架1■置1(敷設さ)また車道の縁部V
C造成する張出歩道プロ りに関する。DETAILED DESCRIPTION OF THE INVENTION The present invention provides a method for installing an elevated structure at the edge of a roadway.
Concerning the construction of overhang sidewalks to be constructed.
従来、用水路が橡を流ね、たり、1日の中にI!liは
hだ道路・/)縁部f歩道を造成するのIcは用水路や
田の31!めケてを行わなければなちなかった。し7か
し、こl)ような構造の歩道は、用水路!田を埋め1χ
てて造成を行うものであるため、f=間と費用が多くか
751ね、しかも用水路等が無用になる。Traditionally, irrigation canals have been used to drain water or water during the day. li is h, road//) Edge f is to create a sidewalk, Ic is for irrigation canals and rice fields 31! Arrangements had to be made. However, a sidewalk with a structure like this is actually an irrigation canal! Fill the field 1χ
Since it requires a lot of time and expense, it also eliminates the need for irrigation canals.
用水路、[月等を埋めヴてずに周囲より高く形成された
高架道路(車道)の縁部に歩道を張り出して造成する方
法としては、従来、例えば第1図に示す構造のものがあ
る。すなわち、略枠形のコンクリート環の基礎ブロック
人と、該基礎プロ、り人の上面に載置、固定されるコン
クリート環の張出桟材Bと、該張出桟材Bを前記基礎プ
ロ、り人の上面に植設ばれたアンカー・ボルトC,Dと
から形成きれる。As a method of constructing an irrigation canal, etc., by extending a sidewalk over the edge of an elevated road (roadway) that is higher than the surrounding area without burying it, there is a conventional method, such as the structure shown in Figure 1. That is, a substantially frame-shaped concrete ring foundation block person, the foundation professional, the concrete ring overhanging beam B placed and fixed on the upper surface of the foundation professional, and the overhanging beam B being the foundation professional, It is formed from anchor bolts C and D planted on the top surface of the person.
そして歩道Eを造成するの((は先ず、車道Fの縁部の
土を掘削して断回路り字状の掘削部Gを形成+る。次に
この掘削部GICコノクリート製の基礎プロ、りAを前
記車道Fに沿って順次、並設し、その後、前記基礎プロ
、りA内に生コンクリートHを打設(7て固化させるこ
とにより数本のアンカー・ボルトC,Dを植設する。Then, to create the sidewalk E ((First, excavate the soil at the edge of the roadway F to form an excavated section G in the shape of a disconnection line.Next, create a foundation professional made of GIC conocret for this excavated section. A are placed in parallel along the roadway F, and then fresh concrete H is poured into the foundation concrete A (after solidifying in Step 7, several anchor bolts C and D are planted). .
それから、張出桟材Bを基礎プロ、りAの上面に載置し
、その後、張出桟材Bの基部aに予め設けた数個のボル
ト挿通孔工、J内に基礎ブロック人に位置決めした後の
前記アンカー・ボルトG。Then, place the overhanging beam B on the top surface of the foundation block A, and then position the foundation block in the several bolt insertion holes previously provided at the base a of the overhanging beam B. The anchor bolt G after
Dを挿通して該ボルト挿通孔1.J内にモルタルhを打
設、固化する。そして、このアンカー・ポルトC,DV
CPl金を介してす、トを螺合させるととてより基礎プ
ロ、りムの1面に張出桟材Bを固定する。享らに張出桟
材Bの一側の表面板部すと、掘削部Gに埋め戻した土と
アスファル)K、Lを舗装して歩道Eを造成する。D through the bolt insertion hole 1. Place mortar h inside J and harden. And this anchor Porto C, DV
By screwing the two parts together through the CPl metal, the overhanging beam B is fixed to one surface of the base plate and rim. The surface plate on one side of the overhanging crosspiece B is paved with soil and asphalt (K and L) that have been backfilled into the excavated area G to create a sidewalk E.
!−7かし、第1図に示す上記従来品は、基礎ブロック
A iC’4EコンクリートHを打設することによって
アンカー・ボルトC,Dを挿通して核ボルト挿通孔I、
J内てモルタルh全打設、固化する。そして、このアン
カー・ボルトC,D;て座金を介してす、1・を螺合き
せること知より基礎プロ、りAの1面に張出桟材Bを固
定する。をら圧張出桟材Bの一側の表面板部すと、掘削
部Gに埋め戻した士とてアスファルトに、Lを舗装して
歩道Eを造成する。! -7 However, the above-mentioned conventional product shown in Fig. 1 is constructed by placing the foundation block A iC'4E concrete H and inserting the anchor bolts C and D into the core bolt insertion hole I.
Place the mortar h completely in J and let it harden. Then, by screwing together the anchor bolts C and D through the washers, the projecting beam B is fixed to one side of the base plate A. After removing the surface plate on one side of the stretched crosspiece B, the excavated part G is backfilled with asphalt and L is paved to create a sidewalk E.
しかし、第1図に示す上記従中品は、基礎ブロック人に
生コンクリートHを打設することによってアンカー・ボ
ルトCIDを基礎ブ「フック人に現場で植設するもので
あるから、生コンクリートHの打設作業Cc手間取ると
ともにアンカー・ボルトC,Dの取付位置出しを測らな
ければならないのでその計測に手間がががり、アンカー
・ボルトC。However, in the above-mentioned intermediate product shown in Fig. 1, the anchor bolt CID is placed in the foundation block by placing the ready-mixed concrete H on the foundation block. The casting work Cc is time consuming, and the installation position of anchor bolts C and D must be measured, which takes time and effort.
Dの取付位置が基礎プロ、りA毎に不揃になっていた。The mounting position of D was uneven for each basic pro and RIA.
また順次、車道Fに沿って並設された基礎ブロックAの
E面に張出桟材Bを取付けるのにも手間がかかっていた
。従ってこの従来品は、歩道El!i−造成するのに工
期が長くなる欠点があった。It also took time and effort to sequentially attach the projecting beams B to the E surfaces of the foundation blocks A that were arranged side by side along the roadway F. Therefore, this conventional product is the sidewalk El! There was a drawback that it took a long time to construct i-.
しかも、基礎プロ、りAt上面に張出桟材Bを植設する
のに基礎プロ、りAに植設したアンカー・ポル)[、D
の取付位置が基礎プロ、りム毎にばらつきが生じるため
、張出桟材B相互の間隙が手元と数百m先て置かれたも
のとでは内側(車道)と外側(歩道側)とで不揃になり
、車道に沿ってIE確知知歩道造成を行うことはできな
かった。Moreover, in order to plant the overhanging beam B on the top surface of the basic pro, the anchor pole (pol) [,D
Because the installation position of the base plate varies depending on the frame, the gap between the projecting beams B and the one placed several hundred meters away from each other may differ between the inside (roadway) and the outside (sidewalk side). Due to the unevenness of the road, it was not possible to construct an IE Chichichi walkway along the road.
本発明は、ヒ述の如き点に鑑みてなされたものであり、
その目的とするところは、短い工期で狭い置所を利用し
て歩道を造成でき、しがも張出桟部相互の間隔が手元の
ものと先方に配置された表面板相互の内側と外側との間
隔が不揃になることがなく一様な間隔で敷設できる張出
歩道プロ、りを提供するの如ある。The present invention has been made in view of the points mentioned above,
The purpose of this is to make it possible to create a sidewalk in a narrow space in a short construction period, and to make sure that the distance between the overhanging crosspieces is the same as the one at hand and the one on the outside of the surface board. We would like to provide a professional overhang walkway that can be laid at uniform intervals without causing irregular intervals.
以下本発明の一実施例を第2図I″J至第4図に従って
説明する。An embodiment of the present invention will be described below with reference to FIGS. 2I"J to 4.
1は例えばその縁部に用水路が流れたり、田の中ζτ流
てれる等、高架に造成され、歩道2を縁部に造成すべき
東肴、3 +d東通道1縁部のモを掘削した掘削部で、
この間前部3のヒ方及び外側は開口さハ、て所面略り字
状(て形成される。4は前記掘削部3に収容ざ)して固
定さ力、るべきコンクリート製の基礎フコ、りであり、
この基礎プロ、り4は、川向した俣]財部5.5の1司
のF方に2本の伐利6゜6と、また1−万てjま・?を
側に延出さハるよつな2本の張トB桟部γ、7を介j7
て形成きれる。なお、第2図シこ/];す基礎プロ、〃
4ば、市道1とVE 、@ 2とが略=1− ’l’而
、亮さの7う7ト型の基礎プロ、りであり、第51g1
で示−を基礎ブロック4は歩道22屯道1に高低をもた
せたマウント・ノ°ノブタイプのものゝである。8はA
iJ記$礎プロ、り4の2本の張出@C都7,7のヒ司
に載Ia1 ・、11定さねる表面板で、この表面板8
を2木の前記張出桟部7,7の一ヒ面に載置、固定する
手段としては例えば張出桟部77の一上面に植設した数
本のボルト9を前記?
表面板8の対応位置に設けたボルト挿通孔10内に挿通
した後に座金を介1.てナツト11で固定する。12は
前記表面板8の一側に形成烙れた地覆で、13はこの地
覆12に設けられた取付穴で、この取付穴13はその1
り部にガイド柵14の支柱15のド端を挿入してコンク
リートを充填して固化することにより前記支柱15を取
付け、ケ役するだめのものである。16はガイド・レー
ル、1γはその支柱である。1. For example, an irrigation canal flows along the edge of the elevated road, or a rice field ζτ flows, etc., and a walkway 2 is to be built on the edge of the elevated road. At the excavation department,
During this time, the front and outer sides of the front part 3 are opened and formed in an oval shape. , is ri,
This basic pro, Ri 4, has two cuttings on the F side of the 1st Tsukasa of Kawamukai Shitamata] Takarabe 5.5, and 1-10,000 tejma? The two tension B crosspieces γ and 7 that extend to the side are connected to j7.
It can be formed completely. In addition, Figure 2 is a basic professional.
4, city road 1 and VE, @ 2 are abbreviations = 1- 'l', and Ryo's 7-7 type basic professional, ri, the 51st g1
The foundation block 4, shown in , is of the mount knob type, with the height of the sidewalk 22 and the road 1 being raised and lowered. 8 is A
iJki $ Foundation Pro, the two overhangs of Ri 4 @ C capital 7, 7 on the surface plate Ia1 ・, 11 fixed surface plate, this surface plate 8
As a means for placing and fixing the above-mentioned two wooden projecting crosspieces 7, 7 on one surface of the two wooden projecting crosspieces 7, several bolts 9 planted on one upper surface of the overhanging crosspieces 77 can be used, for example. After inserting the bolt into the bolt insertion hole 10 provided at the corresponding position on the surface plate 8, insert the washer 1. and fix it with nut 11. 12 is a cover formed on one side of the surface plate 8; 13 is a mounting hole provided in this cover 12;
The supports 15 are attached and serve by inserting the ends of the supports 15 of the guide fence 14 into the grooves and filling and solidifying concrete. 16 is a guide rail, and 1γ is its support.
本発明の一実施例はト述のような構成からなり、以F作
用ふともて敷設工法を説明する。One embodiment of the present invention has the structure as described in (T) below, and the laying method for the operation (F) will be explained below.
歩道2を造成するには、先ず車道1の縁部に断面路り字
状の掘削部3を形成する。To construct the sidewalk 2, first, an excavated portion 3 having a cross-section with a cross-section is formed at the edge of the roadway 1.
次(lこ歩道2を造成するには、先ず車道1の縁部に断
面路り字状の掘削部3に基礎プロ、り4を収容[7、車
道1に沿って多数、並設した後て基礎プロ2り4の対向
した脚材部5,5間に配筋を施し、それから主コンクリ
ート11を基礎プロ、り4の対向i〜だ脚材部5.5の
間の空隙に連続して打設、固化烙せることにより基礎プ
ロ、り4を前記掘削部3に固定して前記市道1の縁部に
基礎プロ、り4の北面に形成された張出桟部1を片持、
支持する。Next (In order to create the sidewalk 2, first, the foundation blocks 4 are installed in the excavated section 3 with a cross-section shaped like a cross section on the edge of the roadway 1. Reinforcement is placed between the opposing leg parts 5 and 5 of the foundation pro 2 and 4, and then the main concrete 11 is continued into the gap between the opposing leg parts 5 and 5 of the foundation pro and the girder 4. The foundation plate 4 is fixed to the excavated portion 3 by pouring and hardening, and the overhanging crosspiece 1 formed on the north face of the foundation plate 4 is cantilevered on the edge of the city road 1. ,
To support.
ざらに前記掘削部3の間隙をt18で埋め戻す。The gap in the excavated portion 3 is roughly backfilled at t18.
そして前記基礎プロ、り4の上面に形成きれた2本の張
出桟部γ、7の長面に表(苗根8をボルト9、ナツト1
1で固定する。Then, on the long side of the two overhanging crosspieces γ and 7 formed on the upper surface of the basic protrusion 4,
Fixed at 1.
その慢、掘削部3の間隙を埋め戻しだ±18と表面板8
の−E面にγスフマルト19.20を敷設、固化するこ
とによって車道1と歩道2とを造成する。The arrogance is to backfill the gap in the excavated part 3 with ±18 and surface plate 8.
A roadway 1 and a sidewalk 2 are created by laying and solidifying γ Sfumalt 19.20 on the -E side of the road.
埒らε・こ、表面板8 r)−1!il+に形成した地
復12の取付穴13内て支柱15の下端を挿入してコノ
クリートを充填、固化することにより、支柱15を立設
してガイド柵14を形成する。埒らε・こ、Surface plate 8 r) -1! The lower end of the post 15 is inserted into the mounting hole 13 of the ground foundation 12 formed at il+, and conocrete is filled and solidified to erect the post 15 and form the guide fence 14.
また車道1側にも同様11Cシて支柱17を−rててガ
イド・レール16を形成する。なお(−記発明について
は2本の張出桟部γを基礎プロ、り4の北面に設けてい
るけれども、これに限らず数本、設けてもよい。Similarly, on the roadway 1 side, a guide rail 16 is formed by extending the pillars 17 through 11C. Note that (in the invention described in -), two projecting beams γ are provided on the north face of the base plate 4, but the invention is not limited to this, and several pieces may be provided.
ト述のように本発明は、コンクリート製の基礎プロ、り
の上面(C張出桟部を形成したことてよって基礎ブロッ
クの側面が開口された構造であるから、基礎プロ2りが
軽量化されるとともに市道の縁部に史削した掘削部に並
設置、た基礎プロ、りの対向した脚利部に生コンクリー
トを連続して打設するだけで基礎プロ、りを掘削部に強
固に固定でさ、快い楊所を利用[7て車道の縁部に歩道
を造成できる。このように生コンクリートを連続して打
設することによって基礎プロ7りを強固VC堀削部に内
定したから、基礎ブロックの傾倒は防IEできる。As mentioned above, the present invention has a structure in which the side surface of the foundation block is opened by forming the upper surface (C overhanging crosspiece) of the concrete foundation block, so that the foundation block 2 is lighter. At the same time, it was installed parallel to the excavated part on the edge of the city road, and the foundation pro was firmly attached to the excavated part by simply pouring ready-mixed concrete continuously on the legage part facing the base pro. It is possible to create a sidewalk at the edge of the roadway by fixing it to the concrete surface and making use of the convenient slope.By pouring ready-mixed concrete continuously in this way, the foundation projector was established as a strong VC excavation area. Therefore, the tilting of the foundation block can be prevented from IE.
このため、従来と異なって基礎プロ、り内に生コノクリ
ートを打設、固化させてアノカー・ゲルトに植設する手
間と之に要する位置決め作業と、をらには基礎ブロック
に対する張出桟部の取付作業が省略化されるので工期が
短縮きれ、造成費用は低置になる。For this reason, unlike in the past, it took a lot of time and effort to pour raw conocrete inside the foundation block, solidify it, and then plant it in the anokur/gelt. Since the installation work is simplified, the construction period can be shortened and construction costs can be reduced.
まだ前述のように基礎ブロックの上面に張出桟部が形成
孕れているから、高架な車道に沿って基礎プロ、りを並
設置−るだ番すで手7Cと先ηの張出桟部相互の間隙が
内側と外側では一様になり、市道に向ってIE確に歩1
6の造成が行える。As mentioned above, the overhanging pier is still formed on the top surface of the foundation block, so the foundation protrusions are installed side by side along the elevated roadway. The gap between the parts is uniform on the inside and outside, and it is exactly 1 step toward the city road.
6 can be created.
4、図面、17)簡を曽な説明
第1図は従来の張出歩道ブL+、りの敷設状報を示1.
た1斬11図、第2図は本発明の基礎プロ、りと羨面板
とを示17た分解斜面図、第3図は同じく車道の片側に
設けた掘削部に基ノぬプロ、りを並役しrc次状態一面
図、第41図11同じく本発明の敷設状的を示したi折
面・図、第5図は本発明の基礎ブワ。4.Drawings, 17) Simple explanation Figure 1 shows the installation status of the conventional overhang walkway block L+ and RI.1.
Fig. 11 and Fig. 2 are exploded slope views showing the basic projector of the present invention, and the horizontal board, and Fig. 3 is an exploded slope view showing the basic projector of the present invention, and the horizontal plate. Fig. 41 is a side view of the RC-order state; Fig. 5 is an i-fold view showing the installation state of the present invention; Fig. 5 is a basic blower of the present invention.
りの変形り11を示17た斜1111図である。FIG. 17 is a diagonal 1111 view showing the deformation 11 of FIG.
1・ 車道、2 ・車道、3・・俤r11部、4 基礎
プロ2.り、5・・脚材部、6・・・桟部、7 ・偏重
桟部、8・・表面板。1. Roadway, 2. Roadway, 3.. R11 Division, 4. Basic Pro 2. 5. Leg portion, 6. Crosspiece portion, 7. Unbalanced crosspiece portion, 8. Surface plate.
峙1Yキ出願人 昧式会社西友
第2■
第3図
第5図
手続補正書(自発)
昭和58年 5 月 4 日
特許庁長官 若 杉 和 夫 殿
1′1[件の表示 昭和58年 1.1許願 第538
47825と明の名称
3 補正をする者
事イ′1との関イ 持、″「出u1人名(′:
□ 株式会社 西 友
4代理人
明細書の「発明の詳細な説明」の柵j
がろるのを1生コンクリ−)21,1IcFIlt圧す
る。1 Yki Applicant Seiyu No. 2 Figure 3 Figure 5 Procedural Amendment (Voluntary) May 4, 1980 Commissioner of the Patent Office Kazuo Wakasugi 1'1 [Indication of Item 1988 .1 Application No. 538
47825 and Ming's name 3 The person making the amendment A'1 The name of the person who made the amendment (': □ Seiyu Co., Ltd. 4 The fence of the ``detailed description of the invention'' in the agent specification Pressure the rolling concrete to 21,1 IcFilt.
Claims (1)
のトガには外側く紙出シれるような数個の張出桟部とを
介して形成される基礎プrj2り入1、咳張出枚部の上
面に固定きれる水道用の表面板とから)1yることを特
徴と17た張出S着プロ、り。A basic prism 2 is formed by several crosspieces below the opposing leg parts and several overhanging crosspieces that extend outward from the togs of the leg parts. The 17-piece protrusion is characterized by a surface plate for water supply that can be fixed to the upper surface of the cough bulge.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5384783A JPS59179902A (en) | 1983-03-31 | 1983-03-31 | Bowed walking road block |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP5384783A JPS59179902A (en) | 1983-03-31 | 1983-03-31 | Bowed walking road block |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59179902A true JPS59179902A (en) | 1984-10-12 |
| JPS6315401B2 JPS6315401B2 (en) | 1988-04-05 |
Family
ID=12954159
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP5384783A Granted JPS59179902A (en) | 1983-03-31 | 1983-03-31 | Bowed walking road block |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59179902A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0386105U (en) * | 1989-12-25 | 1991-08-30 |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4716229U (en) * | 1971-03-24 | 1972-10-25 | ||
| JPS4844607U (en) * | 1971-09-25 | 1973-06-11 |
-
1983
- 1983-03-31 JP JP5384783A patent/JPS59179902A/en active Granted
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4716229U (en) * | 1971-03-24 | 1972-10-25 | ||
| JPS4844607U (en) * | 1971-09-25 | 1973-06-11 |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0386105U (en) * | 1989-12-25 | 1991-08-30 |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6315401B2 (en) | 1988-04-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2000144769A (en) | Method of landslide protection work for preparing housing lot | |
| JPS59179902A (en) | Bowed walking road block | |
| JPS609178B2 (en) | How to install garden or boundary wall panels | |
| JPS6250601B2 (en) | ||
| JPS6054459B2 (en) | Slope protection method | |
| JP2775668B2 (en) | Wide-area slope protection method | |
| JP2002227410A (en) | Forming unit for building foundation, construction method of building foundation and building foundation | |
| JPS59220501A (en) | Expanded walking road block and production thereof | |
| JPH07279184A (en) | Floating underground beam foundation for building | |
| JP3138129B2 (en) | Reverse beam construction method and driving beam side formwork | |
| JPH0885959A (en) | Execution of work for foundation of building | |
| JPS6290445A (en) | Block for foundation and its manufacture | |
| JPS6123092Y2 (en) | ||
| JPS6312161Y2 (en) | ||
| JPS6315402B2 (en) | ||
| JPS61261528A (en) | Retaining wall with sheathing plate | |
| JPH0321709A (en) | Revetment retaining wall block body with road plate and road widening method using block body | |
| JPS6332164Y2 (en) | ||
| JP3629684B2 (en) | Sound insulation wall foundation block | |
| JPH03260222A (en) | Construction of slope frame and block structure | |
| JPH0978892A (en) | Fence and erection thereof | |
| JPH02248527A (en) | Constructing foundation structure | |
| JPH0317301A (en) | Widening of road | |
| JPH05125739A (en) | Constructing method for slope-face retaining wall and retaining-wall concrete block | |
| JPH06212644A (en) | Foundation construction method |