Sand embankment method

Info

Publication number
JPS5937370B2
JPS5937370B2 JP4886279A JP4886279A JPS5937370B2 JP S5937370 B2 JPS5937370 B2 JP S5937370B2 JP 4886279 A JP4886279 A JP 4886279A JP 4886279 A JP4886279 A JP 4886279A JP S5937370 B2 JPS5937370 B2 JP S5937370B2
Authority
JP
Japan
Prior art keywords
sand
float
embankment
discharge port
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4886279A
Other languages
Japanese (ja)
Other versions
JPS55142813A (en
Inventor
英樹 瀬戸
正夫 倉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
UOTAMAN KK
Original Assignee
UOTAMAN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by UOTAMAN KK filed Critical UOTAMAN KK
Priority to JP4886279A priority Critical patent/JPS5937370B2/en
Publication of JPS55142813A publication Critical patent/JPS55142813A/en
Publication of JPS5937370B2 publication Critical patent/JPS5937370B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

【発明の詳細な説明】 人工島の建設、特に埋立地に放置されたヘドロ地等の軟
弱な地盤の上に建造物を建設する場合そのままの地盤上
に建設することは不可能なので盛砂工法を行ったのち建
設を始めることをしている。
[Detailed description of the invention] When constructing an artificial island, especially when constructing a structure on soft ground such as sludge left in a reclaimed land, it is impossible to construct on the ground as it is, so the sand embankment method is used. After that, construction will begin.

すなわち地盤が盛砂した盛砂の載荷圧密により強度が増
加し、よって地盤の強化を図るものである。
In other words, the strength of the ground is increased by loading and compacting the sand filled with sand, thereby strengthening the ground.

しかしながら地盤が硬い場所では盛砂が不均等に行われ
たとしてもその後ブルドーザ−で平担に地ならしすれば
よいが、軟弱地盤上に盛砂する場合は均厚に行わないと
盛砂の厚い部分は自重により軟弱地盤中に沈下し、他方
沈下により排除された軟泥は盛砂の薄い部分を下方から
持ち上げることとなり、これを修正しなければ建設物を
建設することはできないので沈下した部分に砂を入れる
ことによってその修正を行う必要があり、そのための作
業日数、人件費そして盛砂等に非常に多くの費用を必要
とすることとなった。
However, in places where the ground is hard, even if the sand is filled unevenly, it is possible to level the ground with a bulldozer, but when sand is placed on soft ground, it must be done evenly in the thick areas. The soil sinks into the soft ground due to its own weight, and the soft mud removed by the sinking lifts the thin part of the embankment from below, and since it is not possible to construct a structure unless this is corrected, sand is added to the sunken part. It was necessary to make corrections by adding the following, which required a large amount of work days, labor costs, and sand embankment.

本発明はこのような現状に鑑みて平担に盛砂することに
より後の修正作業を不必要としたものである。
In view of the current situation, the present invention eliminates the need for subsequent correction work by laying sand flatly.

以下本発明の盛砂工法の一実施例を図面にもとづきなが
ら説明する。
An embodiment of the sand embankment method of the present invention will be described below based on the drawings.

1は浚渫船で、盛砂用砂を浚渫している。1 is a dredger that is dredging sand for embankment.

2は、浚渫した砂を運ぶ排送パイプである。2 is a discharge pipe that carries the dredged sand.

3は、任意個所に打設したスパッドである。3 is a spud placed at an arbitrary location.

4は、水面に浮かせているフロートで、前記スパッドを
中心として回動するように設けている。
4 is a float floating on the water surface, and is provided so as to rotate around the spud.

5は、前記水上可撓管と連通している排砂管で、前記フ
ロート4上に固定している。
Reference numeral 5 denotes a sand discharge pipe that communicates with the floating flexible pipe and is fixed on the float 4.

6は、前記排砂管5の吐出口である。6 is a discharge port of the sand discharge pipe 5.

7はウィンドラスで、吐出口6側のフロート4上に固定
している。
7 is a windlass, which is fixed on the float 4 on the discharge port 6 side.

8はワイヤーロープで、前記ウィンドラスに巻きつけ、
両端にはアンカー9.9を継いでいる。
8 is a wire rope, wrapped around the windlass,
Anchors 9.9 are connected to both ends.

本発明の工法はこのような装置を用いて実施するもので
ある。
The construction method of the present invention is carried out using such equipment.

すなわちフロート4を水面に浮かすことができるように
スパッド3を任意の個所に打設し、他方盛砂用砂を浚渫
する浚渫船1の排送パイプ2の一端を前記フロート4上
に載置している排砂管5の一端と連通し、吐出口6上あ
るいは吐出口6側のフロート4上に固定されたウィンド
ラス7にワイヤーロープ8を巻きつけ、ワイヤーロープ
8の両端に緊縛されたアンカー9,9を水中に適当な位
置に投錨してフロート4を一方向に一定速度で索引する
と排砂管5の吐出口6からの砂の吐出量が一定であれば
吐出口6を画く軌跡下に均厚の盛砂が行え、そしてフロ
ート4のスイングを一定盛砂厚になると盛砂幅だけ吐出
口6を移動させると均厚に盛砂し地盤の強化を図ること
ができるのである。
That is, a spud 3 is placed at an arbitrary location so that the float 4 can float on the water surface, and one end of the discharge pipe 2 of the dredger 1 for dredging sand for filling is placed on the float 4. A wire rope 8 is wound around a windlass 7 that communicates with one end of the sand discharge pipe 5 and is fixed on the discharge port 6 or on the float 4 on the side of the discharge port 6, and anchors 9 are tied to both ends of the wire rope 8. , 9 is anchored in the water at an appropriate position and the float 4 is indexed in one direction at a constant speed.If the amount of sand discharged from the discharge port 6 of the sand discharge pipe 5 is constant, it will be placed under the trajectory that marks the discharge port 6. Sand can be laid to a uniform thickness, and when the float 4 is swung to a certain thickness, the discharge port 6 is moved by the width of the pile, and the sand can be piled evenly and the ground can be strengthened.

この際吐出口6の移動は吐出口6を分割可能とし一つづ
つ外していくと同時にウィンドラス7の位置もずらせて
いく必要があることはもちろんである。
At this time, it goes without saying that the movement of the discharge ports 6 requires that the discharge ports 6 be divided into parts and removed one by one, while at the same time shifting the position of the windlass 7.

なお、吐出口6側のウィンドラス7に巻きつけたワイヤ
ーロープ8はアンカー9,9を緊縛し水中に投錨する方
法ではなく、スパッド3の上端からロープを引っばりウ
ィンドラスγに巻きつける方法等吐出口6が正確にスイ
ングすることができることが可能であれば如何なる方法
でもよいことはもちろんである。
Note that the wire rope 8 wound around the windlass 7 on the side of the discharge port 6 is not tied to the anchors 9 and anchored in the water, but is pulled from the upper end of the spud 3 and wound around the windlass γ. Of course, any method may be used as long as the discharge port 6 can swing accurately.

以上のように本発明工法は均厚盛砂が一度に行うことが
できるので作業能率のアップを図ることができ、ひいて
は作業費の低減化も可能となるものである。
As described above, in the construction method of the present invention, sand of uniform thickness can be carried out at one time, so it is possible to improve work efficiency, and in turn, it is possible to reduce work costs.

そして本発明工法は軟弱地盤上はもちろんのことどのよ
うな地盤上にも均厚な盛砂が行え地上でも利用できるの
でその応用範囲は非常に広いものである。
The method of the present invention can be used not only on soft ground, but also on any type of ground, and can be used even above ground, so its range of applications is very wide.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の実施例を示すもので、第1図は平面図、
第2図は側面図である。 2は排送パイプ、3はスパッド、4はフロート、5は排
砂管、6は吐出口、7はウィンドラス。
The drawings show an embodiment of the present invention, and FIG. 1 is a plan view;
FIG. 2 is a side view. 2 is a discharge pipe, 3 is a spud, 4 is a float, 5 is a sand discharge pipe, 6 is a discharge port, and 7 is a windlass.

Claims (1)

【特許請求の範囲】[Claims] 1 水中地盤中に打ち込んだ抗に回転自在にフロートを
設け、フロート上には常時排砂量が一定である吐出口を
設けた排砂管を載設し、前記フロートを任意の角度スイ
ングさせ一定厚の盛砂を行うと吐出口を盛砂幅だけ移動
することによって水底に均厚な盛砂を行うことを特徴と
する盛砂工法。
1. A float is installed on a shaft driven into the underwater ground so that it can rotate freely. A sand discharge pipe with a discharge port that constantly discharges a constant amount of sand is mounted on the float, and the float is swung at an arbitrary angle to maintain a constant amount of sand discharge. A sand embankment method that is characterized in that when performing thick sand embankment, the discharge port is moved by the width of the embankment, thereby creating an even thickness of sand embankment on the water bottom.
JP4886279A 1979-04-20 1979-04-20 Sand embankment method Expired JPS5937370B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4886279A JPS5937370B2 (en) 1979-04-20 1979-04-20 Sand embankment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4886279A JPS5937370B2 (en) 1979-04-20 1979-04-20 Sand embankment method

Publications (2)

Publication Number Publication Date
JPS55142813A JPS55142813A (en) 1980-11-07
JPS5937370B2 true JPS5937370B2 (en) 1984-09-10

Family

ID=12815077

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4886279A Expired JPS5937370B2 (en) 1979-04-20 1979-04-20 Sand embankment method

Country Status (1)

Country Link
JP (1) JPS5937370B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60238512A (en) * 1984-05-10 1985-11-27 Toa Harbor Works Co Ltd Carrying and spreading method of soil and sand
JPS6153921A (en) * 1984-08-21 1986-03-18 Unyusho Daisan Kowan Kensetsu Kyokucho Reclaiming method and reclaimer ship

Also Published As

Publication number Publication date
JPS55142813A (en) 1980-11-07

Similar Documents

Publication Publication Date Title
GB2106572A (en) Marine structures
JPS5937370B2 (en) Sand embankment method
CN107165121A (en) Shallow slotting formula steel cylinder bank protection structure construction method
JPH08170343A (en) Finishing method for underwater rubble mound
JPH07292648A (en) Artificial island construction method
JP2815492B2 (en) How to build an underwater foundation
JPH08165652A (en) Foundation construction method of maritime structure
JPS5934331A (en) How to build a sewage treatment facility
JPH06257163A (en) Drought barge for shallow water foundation work
JP2652026B2 (en) Quay construction method
JPH07300835A (en) Formation method of toe of slope of outer peripheral bank in reclamation work
JPS6124797A (en) Coffering immersed tunnel of subaqueous tunnel
Ridehalgh THE RECONSTRUCTION OF GREENWELL'S NO. 1 DRY DOCK AND ANCILLARY WORKS AT SUNDERLAND.
JPH07305322A (en) Construction method of control type revetment
Griffin TAIKOO DOCKYARD, HONG KONG.(INCLUDING PLATE).
JP3069822B2 (en) Installation method of intake water discharge pipe
JPH06286688A (en) Method for building dock submerged for ship entering moat
JPS5955908A (en) Construction of quaywall
JPS6134534B2 (en)
JPS6245827A (en) Formation of rubble-mound under water
Fowler Ordinary Foundations: Including The Coffer-dam Process for Piers
ALLISON et al. CORRESPONDENCE ON HARBOUR WORKS AT MOMBASA AND AT ST HELIER, JERSEY.
Malcolm et al. CIVIL ENGINEERING CONSTRUCTION UNDER WATER.
BERTLIN CONSTRUCTION OF THE NEW ENTRANCE TO TRANMERE DOCK.
Wang Construction of Su-Ao Harbor Project, Taiwan