JPS5983204A - Controller for operation of power plant - Google Patents
Controller for operation of power plantInfo
- Publication number
- JPS5983204A JPS5983204A JP57193338A JP19333882A JPS5983204A JP S5983204 A JPS5983204 A JP S5983204A JP 57193338 A JP57193338 A JP 57193338A JP 19333882 A JP19333882 A JP 19333882A JP S5983204 A JPS5983204 A JP S5983204A
- Authority
- JP
- Japan
- Prior art keywords
- power generation
- load
- change rate
- plant
- units
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/38—Arrangements for feeding a single network from two or more generators or sources in parallel; Arrangements for feeding already energised networks from additional generators or sources in parallel
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Feedback Control In General (AREA)
Abstract
Description
【発明の詳細な説明】
〔発明の技術分野〕
本発明は複数台の発電ユニットで構成される発電プラン
トの運転制御装置に関する。DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to an operation control device for a power generation plant composed of a plurality of power generation units.
最近、発電効率の向上を目的として複合サイクル発電ユ
ニットが開発された。この発電ユニットはガスタービシ
と蒸気タービンを結合し、ガスタービンを駆動し終えた
排ガスを利用して蒸気タービンを駆動することによシ、
熱エネルギーの有効利用を図るようにしたものである。Recently, combined cycle power generation units have been developed with the aim of improving power generation efficiency. This power generation unit combines a gas turbine and a steam turbine, and uses the exhaust gas that has driven the gas turbine to drive the steam turbine.
This is designed to make effective use of thermal energy.
しかし、この発電ユニットは単機容量が小さいため、系
統運用上は複数台で一つの発MJ、プラントを構成する
必要がある。−1,た、この発電プラントは開発されて
間もないため、その運転制御方式は完全には確立されて
いないが、従来のものとはかなシ異なった制御形態をと
ることが予測される。例えば、個々の発電ユニットは起
動、停止が簡単となることから、この発電プラントが負
荷FA整幅の大きい運転制御に使われることもその一つ
である。However, since this power generation unit has a small single unit capacity, it is necessary to configure a single generating MJ or plant with multiple units for system operation. -1. Since this power generation plant was recently developed, its operation control system has not been completely established, but it is predicted that it will take a control form that is slightly different from conventional ones. For example, since individual power generation units are easy to start and stop, this power generation plant is used for operational control with a large load FA adjustment.
ところで、一般に発電プラントを系統運用する場合には
、電力系統の安定化のため、中央給電指令に対する追従
性を良くすることが必振となる。By the way, in general, when operating a power generation plant in a system, it is essential to improve followability to the central power supply command in order to stabilize the power system.
前記複数発電ユニットから成る発電プラントの運転制御
Fil方式は上述したように未だ開発段階にあるが、中
央給電指令に対する追従性を良くするには、各発電ユニ
ットを取り得る最大負荷変化率で運転制御することか考
えられる。As mentioned above, the FIL system for controlling the operation of a power generation plant consisting of multiple power generation units is still in the development stage, but in order to improve the ability to follow the central power supply command, it is necessary to control the operation at the maximum load change rate that each power generation unit can take. I can think of something to do.
例えは、今、この発電プラントの定格負荷を100%、
この発電プラントにおける各発電ユニットの最大負荷変
化率をに格負荷換算で1%/分、6発11)、ユニット
が運転継続可能な最低負荷を同じく定格負荷換算で14
%、現在の定格負荷運転中の発電ユニット運転台数を5
台、目標の発’tFL fラント負荷を50%とし、こ
れを3台の発電ユニットにて運転するものとする。この
条件の下に、第1図の曲線Aで示すように、5台の発電
ユニットを同時に最大変化率で定格負荷100%(時刻
t1)から70%負荷(時刻tz)まで降下させる。各
発電ユニットの最低負荷は14%であるから発電プラン
トが70%負荷まで降下したのちは、同図曲線Bに示す
ように3台の発電ユニットを14%負荷運転し、同図曲
線Cで示すように残シ2台の発電ユニットを最大負荷変
化率で負荷降下させる。For example, if the rated load of this power plant is now 100%,
The maximum load change rate of each power generation unit in this power generation plant is 1%/min (converted to rated load), 6 shots (11), and the minimum load at which the unit can continue operating is 14% (converted to rated load).
%, the number of operating power generation units currently operating at rated load is 5.
Assume that the target power generation unit load is 50%, and three power generation units are used to operate this. Under these conditions, as shown by curve A in FIG. 1, the five power generation units are simultaneously lowered from 100% rated load (time t1) to 70% load (time tz) at the maximum rate of change. The minimum load of each power generation unit is 14%, so after the power generation plant drops to 70% load, the three power generation units are operated at 14% load as shown in curve B in the figure, and as shown in curve C in the figure. The remaining two power generation units are reduced in load at the maximum load change rate.
その2台の発電ユニットが各4%負狗に達したとき(時
刻t3)、発電プラント負荷が50%となる。When the two power generation units each reach 4% capacity (time t3), the power generation plant load becomes 50%.
以後は、停止予定となる2台の発電ユニットをそれぞれ
0%まで負荷降下させ、残シ3台の発電ユニットは16
.7%まで上昇させる。このようにすれば、発電プラン
ト負荷を定格の100%から50%へと最大負荷率で降
下させることができるように々る。尚、第1図中、曲&
!Bは停止しない発電ユニット1台分の負荷変化状態、
曲線Cは停止する発電ユニット1台分の負荷変化状態を
表わしている。After that, the load of the two power generation units scheduled to be shut down will be reduced to 0%, and the remaining three power generation units will be reduced to 16%.
.. Increase to 7%. In this way, the power plant load can be reduced from 100% of the rated value to 50% at the maximum load factor. In addition, in Figure 1, songs &
! B is the load change state for one power generation unit that does not stop;
Curve C represents the load change state for one power generation unit that is stopped.
しかしながら上記方法によると、第1図の時刻t2前後
における発電プラントの負荷変化率が一定でなくなシ、
系統運用に支障を及はす間顧点が生じる。即ち、中央給
電(旨令所では予め各発電プラントの負荷変化率を知シ
、これに基づき各発電プラントに負荷増減指令を出し、
系統における需給のバランスを保つようにしている。従
って、発電プラントが負荷を増減する途中でその負荷変
化率か変化すると、需給のバランスがくずれ、系統の安
定運転が保てなくなる問題点が生じる。However, according to the above method, the load change rate of the power generation plant around time t2 in FIG. 1 is not constant;
There will be issues that will hinder system operation. In other words, the central power supply system (the power supply office) knows the load change rate of each power generation plant in advance, and issues load increase/decrease instructions to each power generation plant based on this information.
We try to maintain a balance between supply and demand in the grid. Therefore, if the load change rate changes while the power generation plant is increasing or decreasing the load, the balance of supply and demand will be disrupted, causing the problem that stable operation of the system cannot be maintained.
本発明は負荷変化率を一定に保った上、複数台の発電ユ
ニットから成る発電プラントが最大変化率で負荷を増減
運転できる発電プラントの運転制御装置を提供すること
を目的とする。SUMMARY OF THE INVENTION It is an object of the present invention to provide an operation control device for a power generation plant that allows a power generation plant including a plurality of power generation units to increase or decrease the load at the maximum rate of change while keeping the rate of load change constant.
このため、本発明は起動、停止すべき発電ユニットは最
大負荷変化率で起動、停止させる一方、残シの運転中の
発電ユニットは、発電プラントの最大負荷変化率RM(
%/分)が、下式を満足するような変化率で負荷調整運
転させるようにしたことを特徴とする。Therefore, in the present invention, the power generation units to be started and stopped are started and stopped at the maximum load change rate, while the remaining operating power generation units are started and stopped at the maximum load change rate RM (
%/min) satisfies the following formula.
但し、Ll:負荷変化開始時発電プラント負荷(%)L
F:目標発電プラント負荷(%)
1、:負荷変化開始時発電ユニット負荷(%)tf:目
標発電プラント負向到達時の最低発電ユニット負荷(%
)
r詰発電ユニットの紐大発電ユニット負荷変化率(%/
分)
〔発明の実施例〕
(6)
第2ジ1は本発明の一実施例に係る発電プラントの運転
制御装置の構成図を示しだもので、1は目標負荷発電ユ
ニット目標値設定器、2は負荷変化率制御装置、3は負
荷制御装置、4は発電プラントである。However, Ll: Power plant load at the start of load change (%) L
F: Target power generation plant load (%) 1: Power generation unit load at the start of load change (%) tf: Minimum power generation unit load when the target power generation plant reaches negative direction (%)
) Load change rate (%/
(min) [Embodiment of the invention] (6) 2nd page 1 shows a configuration diagram of an operation control device for a power generation plant according to an embodiment of the present invention, in which 1 is a target load power generation unit target value setter; 2 is a load change rate control device, 3 is a load control device, and 4 is a power generation plant.
負荷変化率制御装置2は入力処理部21、最大負荷変化
率針9部22、パラメータ配憶部23および出力処理部
24よ多構成される。入力処理部21へ1、目標負荷発
電ユニット目標値打9足器1より発止、ユニット目標運
転台数を表わすデータd1、発電プラントの目椙′負荷
を衣ゎすデータd2および発電ユニット起動、停止指定
データd3が、また、負荷制御装置3からは発′t1.
fランド現在負荷データd4が、更に、制餉j対象とす
る発電プラント4からは発1にユニット現在運転台数を
表わすデータd5が入力される。最大負荷変化率計算部
22へは、入力処理部21よシ発電プラントの目標負荷
データd2、発電ユニット目標運転台数データd1、発
電プラント現在負荷データd4および発1、ユニット現
在運転台数データd5が伝送され、A’ラメータ記憶部
23よシ発電ユニット最大負荷変化率データd6および
発電ユニット最大、最小負荷制限値データd7が伝達さ
れる。これによシ、最大負荷変化率計算部22は出力処
理部24へ発電プラントの目標負荷データd2、発電ユ
ニット目標運転台数データd1、発電プラント現在負荷
データd4、発電ユニット現在運転台数データd5、発
電ユニット最大負荷変化率データd6および発電プラン
ト最大負荷変化率プ゛−タd8が伝送する。The load change rate control device 2 includes an input processing section 21, a maximum load change rate needle 9 section 22, a parameter storage section 23, and an output processing section 24. To the input processing unit 21, input 1, target load power generation unit target value, start from device 1, data d1 representing the target number of operating units, data d2 representing the estimated load of the power generation plant, and power generation unit start/stop designation. Data d3 is also output from the load control device 3 't1.
Land f current load data d4 is inputted, and furthermore, data d5 representing the number of units currently in operation is inputted to the power generation plant 1 from the power generation plant 4 targeted for control. The input processing unit 21 transmits target load data d2 of the power generation plant, target number of power generation units in operation d1, current power generation plant load data d4, generator 1, and current number of units in operation data d5 of the power generation plant to the maximum load change rate calculation unit 22. Then, power generation unit maximum load change rate data d6 and power generation unit maximum and minimum load limit value data d7 are transmitted to the A' parameter storage unit 23. Accordingly, the maximum load change rate calculation section 22 sends the output processing section 24 to the target load data d2 of the power generation plant, the target power generation unit operating number data d1, the power generation plant current load data d4, the power generation unit current operation number data d5, and the power generation Unit maximum load change rate data d6 and power plant maximum load change rate data d8 are transmitted.
出力処理部24は、負荷制御装置3の目標負荷設定器3
1へ発電プラント目標負荷設定データd9および発電プ
ラント負荷変化率設定データdlOを出力すると共に、
発電ユニット増減負荷制御切替器33へ発電ユニット増
減負荷指令dllおよび発電ユニット増減負荷制御切替
指令d12を出力する。このとき、発電ユニット起動、
停止指定データd3が入力処理部21から出力処理部2
4へ伝送される。The output processing unit 24 is a target load setter 3 of the load control device 3.
1 outputs power plant target load setting data d9 and power plant load change rate setting data dlO,
A power generation unit increase/decrease load control switching command dll and a power generation unit increase/decrease load control switching command d12 are output to the power generation unit increase/decrease load control switch 33. At this time, the power generation unit starts,
The stop designation data d3 is transferred from the input processing unit 21 to the output processing unit 2.
4.
負荷制御装置3は目標負荷設定器31、比例積分器32
、複数の発電ユニット増減負荷側側1切替器33および
2つの加算器34.35よ多構成され、目標負荷発電ユ
ニット目標値設定器1よυ与えられる発5hプラント目
標狛荷設定データd9および負荷変化率設定データdl
oの通υに、発電プラント4の出力である現在負荷を制
御するように構成されている。即ち、目標負荷設定器3
1は与えられる発電プラント目標負荷設定データd9お
よび負荷変化率設定データdloから発電グランド負荷
指令d13を生成する。発電プラント現在負荷データd
4を発電プラント負荷指令d13に青しくするため、加
算器34において差演鍔が行なわれ、発電プラント制御
偏差データd14を発生する。この偏差データd14は
、比例積分器32に−おいて積分され、発電ユニット制
御指令d15を生成し、この発電ユニット制御指令dl
Sによシ複数の発電ユニット41の出力d16を制御し
、発電ユニット負荷データd16の加算器35によシ加
算された発電プラント出力即ち発電プラント現在貴石デ
ータd4を前記の目標負荷設定器31の出力である発電
プラント貴石指令d13に追従させる。発電ユニット増
減負荷制御切替器33は、発電ユニット増減負荷指令d
ll側に切替えられた場合、対応する発電ユニット41
の出力負荷d16は、発電ユニット増減負荷指令dll
によシ制御される。The load control device 3 includes a target load setter 31 and a proportional integrator 32.
, a plurality of power generation units increase/decrease load side 1 switch 33 and two adders 34, 35, and the target load power generation unit target value setting device 1 is provided with power generation unit target load setting data d9 and load. Change rate setting data dl
It is configured to control the current load, which is the output of the power generation plant 4, in accordance with o. That is, the target load setter 3
1 generates a power generation ground load command d13 from the given power generation plant target load setting data d9 and load change rate setting data dlo. Power plant current load data d
4 as the power plant load command d13, a subtraction operation is performed in the adder 34 to generate power plant control deviation data d14. This deviation data d14 is integrated in the proportional integrator 32 to generate a power generation unit control command d15, and this power generation unit control command dl
S controls the outputs d16 of the plurality of power generation units 41, and the power generation plant outputs added by the adder 35 of the power generation unit load data d16, that is, the power generation plant current precious stone data d4, is sent to the target load setter 31. It is made to follow the power generation plant precious stone command d13 which is the output. The power generation unit increase/decrease load control switch 33 outputs a power generation unit increase/decrease load command d.
When switched to the ll side, the corresponding power generation unit 41
The output load d16 is the power generation unit increase/decrease load command dll
controlled by
以上の構成で、目標値設定器1の発電グランド目標負荷
データd2は、中央給電指令所の指令によって自動まだ
は手動で設定される。発電ユニット目標運転台数データ
d1は一般に発電ノラントの総合効率が最大となるよう
に、発電グランドの部分負荷効率曲線、発電ユニット起
動、停止損失、発電プラントの負荷曲線によって決定−
g tlる。With the above configuration, the power generation ground target load data d2 of the target value setting device 1 is set automatically or manually by a command from the central power dispatch center. The data d1 for the target number of power generation units in operation is generally determined based on the partial load efficiency curve of the power generation ground, the power generation unit start-up and stop loss, and the load curve of the power generation plant so that the overall efficiency of the power generation unit is maximized.
g tlru.
第3図は複数台発電ユニット構成発電プラントの部分負
荷効率曲線を示す。同一の発電ユニットが複数台ある場
合、最小運転発電ユニット数で均等負荷配分とした場合
が最高効率になることは知られでいる。同図は、発電プ
ラントが5台の発1Lユニットよ多構成されるとした。FIG. 3 shows a partial load efficiency curve of a power generation plant composed of multiple generating units. It is known that when there are multiple identical power generation units, the highest efficiency is achieved when the minimum number of operating power generation units is used and the load is distributed evenly. The figure assumes that the power generation plant is composed of five 1L generating units.
第4図は発電プラント負荷曲線の一例を示す。FIG. 4 shows an example of a power plant load curve.
同図は時刻t!からtl まで負荷は100%から70
%に変化し、また時刻t3からt4 まで負荷は70%
から再び100%に変化すると仮定した。この場合、1
00%運転の最大効率の発電ユニットの運転台数が5台
で、70%運転の最大効率の発電ユニットの運転台数が
4台としよう。100%から70%までの負荷降−下(
tl−+ta )をするとき、(1)発11Lユニット
;5→4台(発電ユニット1台停止)(2)発電ユニッ
ト;5→5台(発電ユニット1台停止しない)
上記のとれかのケースを選択するかは、70%において
ケース(1)とケース(2)との効率の比較、t2→t
3の時間および発電ユニットの起動、停止損失によ−る
。1台発電ユニットヲ停止することによって、t2→t
3の運転効率向上による利得が発14Lプラントの起動
、停止損失を超えたときケース(1)を選択する方がよ
く、逆の場合ではケース(2)を選択する方がよい。こ
のようにして、発電プラント出力負荷変化に伴う発電ユ
ニットの目標台数が算出される。The figure shows time t! From tl the load is 100% to 70
%, and the load is 70% from time t3 to t4.
It was assumed that the value changes from 100% to 100% again. In this case, 1
Let us assume that the number of power generating units in operation with maximum efficiency of 00% operation is five, and the number of power generating units in operation with maximum efficiency of 70% operation is four. Load drop from 100% to 70% (
tl-+ta), (1) Generator 11L unit; 5 → 4 units (one generator unit stops) (2) Power generator unit; 5 → 5 units (one generator unit does not stop) Any of the above cases The choice is based on the efficiency comparison between case (1) and case (2) at 70%, t2 → t
3 due to time and start-up and stop losses of the power generation unit. By stopping one power generation unit, t2 → t
It is better to select case (1) when the gain from the improved operating efficiency in step 3 exceeds the startup and shutdown losses of the 14L plant, and in the opposite case, it is better to select case (2). In this way, the target number of power generation units is calculated as the output load of the power generation plant changes.
発11Lユニット起動、停止指定データd3は、発電プ
ラント増(減)負荷時において発電ユニット現在運転台
数が目標運転台数より少ない(多い)場合、即ち発電ユ
ニットの起動(停止)が必要とする場合、どの発電ユニ
ットを起動(停止)するかを指定するものでめる。どの
発電ユニットの起動(停止)を選択するかは、発電ユニ
ットの運転積算時間、保守点検作業中、起動停止回数な
どによって決まる。The generator 11L unit start/stop designation data d3 is specified when the number of power generating units currently in operation is less (more) than the target number of operating units when the power generating plant is increased (decreased) in load, that is, when it is necessary to start (stop) the power generating units. Specify which power generation unit to start (stop). Which power generation unit is selected to be started (stopped) is determined by the cumulative operating time of the power generation unit, maintenance and inspection work, the number of times the power generation unit is started and stopped, and so on.
発電プラントの目標負荷データd2、発電ユニット現在
運転台数データd1、発電グランド現在負荷ガータd4
および発電ユニット現在運転台数データd5は最大負荷
変化率計算部22において処理されやすいように、入力
処理部21にふ・い1情号処理された後、前記の計算部
22へ伝送される。また、発電ユニット起動、停止指定
データd3は出力処理部24において処理もれやすいよ
うに、入力処理部21において信号処理された後、前記
の出力処理部24へ伝送される。Power generation plant target load data d2, power generation unit current operating number data d1, power generation ground current load gutter d4
The data d5 on the number of currently operating power generating units is subjected to F-1 information processing in the input processing section 21 so that it can be easily processed in the maximum load change rate calculation section 22, and then transmitted to the calculation section 22. Further, the power generation unit start/stop designation data d3 is signal-processed in the input processing section 21 so as to be easily omitted in the output processing section 24, and then transmitted to the output processing section 24.
パラメータ記憶部23の発電ユニット最大変化率データ
d6は発電ユニット4】の最大負荷変化率運転によって
決まる。発電ユニットはこの豚化率以内に運転される。The power generation unit maximum rate of change data d6 in the parameter storage section 23 is determined by the maximum load change rate operation of the power generation unit 4. The power generation unit is operated within this conversion rate.
また、この記憶部23の発電ユニット最大、最小負荷制
限値データd’7は、発10、ユニットの容I3i、達
転効率、安全運転しく−よって法定いれる。発電ユニッ
トの定常9術運転eよ、この負荷制r8M蝕データd7
範囲において行なわ!しる。Further, the maximum and minimum load limit value data d'7 of the power generation unit in the storage unit 23 are included in the power generation unit 10, unit capacity I3i, delivery efficiency, and safe operation. Steady operation of the power generation unit, this load control r8M eclipse data d7
Do it within range! Sign.
ノ1を大負荷変化率計u部22は入力処理部21から人
力なれろうj′、電ユニット目標運転台数dl、発電グ
ランドの目標負荷データd2、発−ブラント現在負荷デ
ータd4、発電ユニット現在運転台数データd5および
パラメータ記憶部23から入力される発■モユニット最
大負荷変化率データd6、発電ユニット最大、最小負荷
制限値データd7を基に下記(1)式で与えらJする最
大負荷変化率RMを計算する。The large load change rate meter u section 22 inputs from the input processing section 21 human power j', the target operating number of power units dl, the target load data of the power generation ground d2, the current load data of the generator brand d4, and the current operation of the power generation unit. The maximum load change rate RM is given by the following equation (1) based on the number of units data d5, generator unit maximum load change rate data d6, and power generation unit maximum and minimum load limit value data d7 input from the parameter storage unit 23. Calculate.
但し、LI:負荷変化開始時発電グランド負荷0)LF
:目標発′%、7″ランド負荷@)t、:負荷変化開始
時発電ユニット負荷C%)tf:目標発電プラントj’
((i?到i″h時の最低発電ユニット負荷(%)
rm:発π1ユニットの最大発′f、Jユニット負荷変
化率(%/分)
ここで、L1+LF+tf+tf+r、、についての帽
14方法について説明する。However, LI: Generation ground load at the start of load change 0) LF
:Target power generation '%, 7''land load @)t, :Generation unit load at the start of load change C%)tf:Target power generation plant j'
((minimum power generation unit load (%) at i?i''h) rm: Maximum power generation 'f of 1 unit, J unit load change rate (%/min) Here, L1 + LF + tf + tf + r, 14 methods for explain.
(i) L、:負荷変化しトI始時発M)、プラント
fi荷(%)Llは即ち泥2図の発電、プラント現在員
荀データd4であり、同図の入九処理部21をAしで負
荷制御装に3から入力される。(i) L: load change (to I start M), plant fi load (%) Ll is the power generation in Figure 2, current plant staff data d4, and input processing section 21 in the same figure. A is input to the load control device from 3.
(++)L、:目標発電プラント負荷0)L、はRIJ
ち第2図の発電プラントの目標角vノデータd2であシ
、同図の入力処理部21を介して目標負荷、発電ユニッ
ト目標値設定器lから入力される。(++)L, :Target power plant load 0)L, is RIJ
Specifically, the target angle v data d2 of the power generation plant shown in FIG. 2 is inputted from the target load and power generation unit target value setter l via the input processing section 21 shown in the same figure.
o++)tl:負荷変化開始時発電ユニット負荷(%)
X
N1
但し、Ll:負荷変化開始時発電、プラント負荷(%)
N1:負荷変化開始時発電ユニット運転台数N1は即ち
第2図の発電ユニット現在運転台数データd5であシ、
同図の入力処理部21を介して発電グランド4から入力
される。o++) tl: Generation unit load at the start of load change (%)
X N1 However, Ll: Power generation at the start of load change, plant load (%)
N1: The number of power generation units in operation at the start of load change N1 is the current number of power generation units in operation data d5 in FIG.
It is input from the power generation ground 4 via the input processing section 21 shown in the figure.
(IV) Lf:目標発′IIL 7’ラント負荷到
達時の最低発7jj、ユニット負荷(%)
LF
(イ)−≧(≦) trntn (tmax )の場合
N。(IV) Lf: Minimum output 7jj when target output 'IIL 7' runt load is reached, unit load (%) LF (A) - ≧ (≦) N if trntn (tmax).
1′ ・・・ (・)
1、 =可
但し、LF:目標発電プラント負荷(%)N1:負荷変
化間kj時発電ユニット運転台数tmin”maρ:発
電ユニット最小(最大)負荷制限値(%)
tmい(tmax)は即ち第2図の発電ユニット最大、
最小負荷制限値データd7であり、パラメータ記憶し、
L2:目標発1;グランド負荷(%)trrl、n(t
man)二 発電ユニット最小(最大)負荷制御装置
)
N1;負荷変化開始時発電ユニット運転台数NF:発電
ユニット目標運転台数
Nは即ち第2図の発電ユニット目標運転台数デ−タd1
であシ、同図の入力処理部21を介して目標負荷、発電
ユニット目標値設定器1から入力される。1' ... (・) 1, = Possible, LF: Target power generation plant load (%) N1: Number of power generation units in operation during kj hours between load changes tmin"maρ: Power generation unit minimum (maximum) load limit value (%) tm (tmax) is the maximum power generation unit in Figure 2,
Minimum load limit value data d7, parameters stored,
L2: Target emission 1; Ground load (%) trrl, n(t
(man) 2 Minimum (maximum) load control device for power generation units) N1; Number of power generation units in operation at the start of load change NF: Target number of power generation units in operation N is the target number of power generation units in operation d1 in Fig. 2
The target load and power generation unit target value setter 1 are inputted via the input processing section 21 shown in the figure.
また、発電プラント減(増)−負荷において、LF/N
1< (> ) tmin(tman)とい、う条件が
成立すれば、必ず発電ユニットを1台以上停止(起動)
する必要があるので、N1−N、笑Oとなる。In addition, at power plant decrease (increase) - load, LF/N
1 <(>) tmin (tman), if the condition is met, one or more power generation units will be stopped (started).
Since it is necessary to do so, it becomes N1-N, lol.
(V)r:発電ユニットの最大発電ユニット負荷変化率
(%/m1n)
rは即ち第1図の発電ユニット最大負荷変化率データd
6であり、同図のパラメータ記憶部23に記憶されてい
る。(V) r: Maximum power generation unit load change rate of power generation unit (%/m1n) r is the power generation unit maximum load change rate data d in Figure 1
6, and is stored in the parameter storage section 23 in the figure.
以上(1) 〜(V)によF> LX+Lr+Z1 r
’(およびr が求まシ、前記(1)式が算出される。According to (1) to (V) above, F> LX+Lr+Z1 r
'(and r is determined, and the above equation (1) is calculated.
第5図はこのときの処理をフローチャートにまとめだも
のである。FIG. 5 is a flowchart summarizing the processing at this time.
次に、出力処理部24は最大負荷変化率計算部22から
の発電グランドの目標9荷データd2および発電ユニッ
ト最大負荷変化率データd8により、発電シラ/ト目標
負荷設定データd9ふ・よび発′i、ゾラント負荷変化
率設定データdiOを負荷制御装置3の目標負荷設定器
31へ出ブノし、発電プラントの出力負荷を最大負荷変
化率ヒ率で運転させる。また、入力処理部21からの発
電ユニット起動、停止指定データd3によシ、起動、停
止となる発電ユニット41に対応した発電ユニット増減
負荷制御切替器33を発電ユニット増減負荷指令データ
dll側へ切替えるように、出力処理11s24から前
記の発電ユニット増減負荷制御切替器33へ発電ユニッ
ト増減負荷制御切替指令データd12を出力する。次い
で、出力処理部24は発電ユニット起動、停止指定デー
タd3に対応した発電ユニッ)41に対して発電ユニッ
ト増減負荷指令データdllを出力し、発電ユニット4
1を発電ユニット最大負荷変化率データd6に従って起
重ム、停止する。Next, the output processing unit 24 uses the power generation ground target load data d2 and the power generation unit maximum load change rate data d8 from the maximum load change rate calculation unit 22 to generate the power generation schedule/t target load setting data d9 and output'. i. Output the Zolant load change rate setting data diO to the target load setter 31 of the load control device 3 to operate the output load of the power generation plant at the maximum load change rate. Further, according to the power generation unit start/stop designation data d3 from the input processing unit 21, the power generation unit increase/decrease load control switch 33 corresponding to the power generation unit 41 to be started, started, or stopped is switched to the power generation unit increase/decrease load command data dll side. As such, the power generation unit increase/decrease load control switching command data d12 is output from the output processing 11s24 to the power generation unit increase/decrease load control switch 33. Next, the output processing unit 24 outputs power generation unit increase/decrease load command data dll to the power generation unit) 41 corresponding to the power generation unit start/stop designation data d3, and the power generation unit 4
1 is hoisted and stopped in accordance with the power generation unit maximum load change rate data d6.
例えtよ、前記第1図で説明したのと同じ条件で発電プ
ラント4を運転制御する場合について説明すると、負荷
変化率制御装置2には、目標負荷発電ユニット目標値設
定器1から発電ユニット目標運転台数データd1として
3台、発電プラントの目標負荷データd2として50%
、発電ユニット起動、停止指令データd3として2台の
発電ユニット41を停止指定すべきデータが与えられる
。For example, to explain the case where the operation of the power generation plant 4 is controlled under the same conditions as explained in FIG. The number of operating units data d1 is 3 units, and the power plant target load data d2 is 50%.
, data to designate the two power generation units 41 to be stopped is given as the power generation unit start/stop command data d3.
同時に発15.プラント4からは発′〜、コーニット現
在台数データd5として5台、更に、負荷制御装置3か
ら発電プラント現在負荷データd4が与えられる。At the same time 15. From the plant 4, 5 units are supplied as the current number of Kornit units data d5, and furthermore, the current power generation plant load data d4 is provided from the load control device 3.
負荷変化率制御装置2はこれらのデータd1〜d5およ
びパラメータ記憶部23に予め記憶されている発電ユニ
ット最大負荷変化率データd6として1%/分、発電ユ
ニット最大、最/」・負荷制限値データd7として14
%最小負荷制限値から、先ず、前記(1)式に基つき最
大負荷変化率RMを初出し、これを発電プラント負荷変
化率設定データdloとして目標負荷設定器31に出力
する。目標負荷設定器31はこの発電プラント負荷変化
率設定データdlOを積分することによシ発電プラント
負荷指令データd13を出力し、発電プラント4からフ
ィードバックされる発電プラント現在9荷データd4と
の偏差を比例積分器32でPI演算した発電ユニット制
御指令d15データを、d15側に切替わっている発′
vt!i、ユニット増減負荷制御切替器33を介して3
台の発信ユニット41に加える。同時に、発電ユニット
起動、停止指令d3に基づき発ち、ユニット増減負荷制
御切替指令d12を出力して現在運転中の5台の発電ユ
ニット41のうち、停止すべき2台の発電ユニット増減
負荷切替器33をdll側に切替え、発1uユニット増
減負荷指令dllとして発電ユニット最大負荷変化率デ
ータd6即ち1%/分を出力して所定の2台の発電ユニ
ット41を停止させる。The load change rate control device 2 uses these data d1 to d5 and the power generation unit maximum load change rate data d6, which is stored in advance in the parameter storage unit 23, as 1%/min, the power generation unit maximum, and the load limit value data. 14 as d7
From the % minimum load limit value, first, the maximum load change rate RM is obtained based on the above equation (1), and this is output to the target load setter 31 as the power generation plant load change rate setting data dlo. The target load setter 31 outputs the power plant load command data d13 by integrating the power plant load change rate setting data dlO, and calculates the deviation from the power plant current load data d4 fed back from the power plant 4. The power generation unit control command d15 data calculated by the proportional integrator 32 is transferred to the power generation unit which has been switched to the d15 side.
vt! i, 3 via unit increase/decrease load control switch 33
It is added to the transmission unit 41 of the base. At the same time, the power generation unit increase/decrease load switch 33 is issued based on the power generation unit start/stop command d3 and outputs the unit increase/decrease load control switching command d12 to select two power generation units 41 to be stopped among the five power generation units 41 currently in operation. is switched to the dll side, and outputs the power generation unit maximum load change rate data d6, that is, 1%/min, as the generator 1u unit increase/decrease load command dll, and stops the two predetermined power generation units 41.
この結果、発電プラント4の負荷曲線は第6図のαで示
すように、リニアに100%負荷から50%負荷に向っ
て最大負荷変化率で減少する。即ち、2台の発電ユニッ
ト41はそれぞれ同図の向側γで示すように時刻t1か
ら最大負荷変化率1%/分で下降する。一方、残シ3台
の発〜、ユニット41は、発電プラント4出力d4が前
記(1)式で計算される最大負荷変化率RMで降下する
ように曲線βに沿って降下する。As a result, the load curve of the power generation plant 4 decreases linearly from 100% load to 50% load at the maximum load change rate, as shown by α in FIG. That is, the two power generation units 41 each descend at a maximum load change rate of 1%/min from time t1, as shown by γ on the opposite side of the figure. On the other hand, the remaining three generator units 41 descend along the curve β so that the power generation plant 4 output d4 declines at the maximum load change rate RM calculated by the above equation (1).
次いで、発電プラント4の出力d4が50%負荷に達し
たとき、負荷変化率制御装置2の出力処理部24から出
力される発電プラント目標負荷設定データd9に基づき
負荷制御装置3は発i、プラント現在負荷データd4が
発電プラント4がこの50%負荷を維持するように3台
の発電ユニット41を負荷制御する。Next, when the output d4 of the power generation plant 4 reaches 50% load, the load control device 3 controls the power generation The current load data d4 controls the load of the three power generation units 41 so that the power generation plant 4 maintains this 50% load.
この結果、3台の各発電ユニット41はそれぞれ第6図
の曲線βで示すように時刻t3で14%に達したのちは
、停止すべき2台の各発電ユニット41がそれぞれ曲線
γに沿って4%(時刻t3)から0%(時刻1+)に下
降するのに伴って、16.7%まで上昇する。As a result, after each of the three power generation units 41 reaches 14% at time t3 as shown by the curve β in FIG. As it falls from 4% (time t3) to 0% (time 1+), it increases to 16.7%.
このようにして、発電プラント4の負荷を第1図の場合
と同様、時刻t1からt3までの間に最大負荷変化率で
100%から50%まで減少させることができると共に
、その間リニアに減少させることができるため、複数発
電ユニットから成る発電プラントの系統運用を円滑かつ
安定して行なうことができるようになる。In this way, the load of the power generation plant 4 can be reduced from 100% to 50% at the maximum load change rate between times t1 and t3, as in the case of FIG. 1, and linearly reduced during that time. Therefore, it becomes possible to smoothly and stably operate the system of a power generation plant consisting of a plurality of power generation units.
尚、負荷変化率制御装置2のパラメータ記憶部23に記
憶する発狛、ユニット最大負荷変化率データd6を外部
から変更できるようにすることによシ、発電ユニット4
1のガスタービンおよび蒸気タービンの熱応力管理を容
易にすることができる。Note that by making it possible to change the maximum load change rate data d6 stored in the parameter storage section 23 of the load change rate control device 2 from the outside, the power generation unit 4
Thermal stress management of one gas turbine and a steam turbine can be facilitated.
即チ、一般にガスタービン、蒸気タービジの寿命は、発
電ユニット負荷震動に伴って発生される熱応力の私算仙
によって管理される。発電ユニット負荷変化率が太きけ
れば大きいはど、負荷変化に伴う発生される熱応力が大
きくなる。従って、発電ユニット最大負荷変化率を可変
にすることによシ、ガスタービン、蒸気タービン熱応力
管理が容易にできる効果が得らオ′Lる。In general, the lifespan of gas turbines and steam turbines is controlled by the thermal stress generated by load vibrations of power generating units. The thicker the power generation unit load change rate, the greater the thermal stress generated due to the load change. Therefore, by making the maximum load change rate of the power generation unit variable, it is possible to easily manage the thermal stress of the gas turbine and steam turbine.
以上のように本発明によれば、複数発電ユニットから成
る発電プラントの出力負荷をリニアにしてしかも最大負
荷変化率で制御できるようになる。As described above, according to the present invention, the output load of a power generation plant consisting of a plurality of power generation units can be made linear and controlled at the maximum load change rate.
この結果、中央給電指令所からの負荷変化指令に対する
i!〕従性が良くなシ、市4力系統の安定化に有用な負
荷調整能力の高い発電プラントが得られるようになる。As a result, i! in response to the load change command from the central dispatch center! ] It becomes possible to obtain a power generation plant with good followability and a high load adjustment capacity that is useful for stabilizing the city's four-power grid.
第1図は複数発電ユニットから成る発電プラントの負荷
曲線図、第2図は本発明の一実施例に係る発電プラント
運転制御装置のブロック構成図、第3図は複数発電ユニ
ットから成る発電プラントの部分負荷効率曲線図、第4
図は発電プラント貴石曲線図、第5図は第2図の負荷変
化率制御装置における処理のフローチャート、第6図は
第2図におりる最大負荷変化率制御の一例を説明するだ
めの負荷曲線図である。
1・・・目標負荷発電ユニット目標値設定器、2・・・
負荷変化率制御装置、3・・・負荷制御装置、4・・・
発電プラント、21・・・入力処理部、22・・・最大
負荷変化率計算部、23・・・パラメータ記憶部、24
・・・出力処理部、31・・・目標負荷設定器、32・
・・比例積分器、33・・・発電ユニット増減負荷制御
切替器、34.35111111加算器、41・・・発
電ユニット。
第7図
第2図
第3図
第4図
第5図
第6図FIG. 1 is a load curve diagram of a power generation plant consisting of multiple power generation units, FIG. 2 is a block diagram of a power generation plant operation control device according to an embodiment of the present invention, and FIG. 3 is a load curve diagram of a power generation plant consisting of multiple power generation units. Partial load efficiency curve diagram, 4th
The figure is a power generation plant precious stone curve diagram, Figure 5 is a flowchart of processing in the load change rate control device in Figure 2, and Figure 6 is a load curve explaining an example of maximum load change rate control in Figure 2. It is a diagram. 1...Target load power generation unit target value setter, 2...
Load change rate control device, 3... Load control device, 4...
Power generation plant, 21... Input processing unit, 22... Maximum load change rate calculation unit, 23... Parameter storage unit, 24
... Output processing unit, 31... Target load setting device, 32.
... Proportional integrator, 33... Power generation unit increase/decrease load control switch, 34.35111111 adder, 41... Power generation unit. Figure 7 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6
Claims (1)
転制御装置において、発電ユニット最大、最小負荷制限
値および発電プラント最大負荷変化率を記憶しているパ
ラメータ記憶部、発電プラントの目標負荷、発電ユニッ
ト目標運転台数、発電プラント現在負荷および発電ユニ
ット現在運転台数を入力する入力処理部、前記発電ユニ
ット最大、最小負荷制限値、発電ユニット最大負荷変化
率、発電プラントの目標負荷、発電ユニット目標運転台
数、発電プラントの現在負荷および発電ユニット現在台
数に基づいて発電プラントの最大負荷変化率を算出する
最大負荷変化率計算部、前記発電プラント最大負荷変化
率、発電プラント目標負荷、発電ユニット最大負荷変化
率および発電ユニット増減負荷制御切替指令を出力する
出力処理部の各部か゛ら成る負荷変化率制御装置と、前
記増減負荷制御切替指令に基づき起動、停止すべき発電
ユニットを切替えて前記発電ユニット最大負荷変化率で
起動、停止させると同時に、前記発電プラント最大負荷
変化率および発電プラント目標負荷に応じて残シ運転中
の発電ユニットを制御する負荷制御装置とから成ること
を特徴とする発電グランド運転制御装置。 (2、特許請求の範囲第1項記載において、前記パラメ
ータ記憶部の記憶内容を外部から変更可能としたことを
特徴とする発電グランド運転制御装置。(1) In an operation control device for a power generation plant consisting of multiple power generation units, a parameter storage unit that stores the maximum and minimum load limit values of the power generation unit and the maximum load change rate of the power generation plant, the target load of the power generation plant, and the power generation unit an input processing unit for inputting the target number of operating units, the current load of the power generation plant, and the number of currently operating power generation units, the maximum and minimum load limit values of the power generation units, the maximum load change rate of the power generation units, the target load of the power generation plant, the target number of operating power generation units; a maximum load change rate calculation unit that calculates a maximum load change rate of the power generation plant based on the current load of the power generation plant and the current number of power generation units; a maximum load change rate of the power generation plant; a power generation plant target load; a maximum load change rate of the power generation unit; A load change rate control device consisting of each part of an output processing unit that outputs a power generation unit increase/decrease load control switching command, and a load change rate control device that switches a power generation unit to be started or stopped based on the power generation unit increase/decrease load control change command to maintain the maximum load change rate of the power generation unit. A power generation grand operation control device comprising: a load control device that starts and stops a power generation unit that is currently in operation according to the power generation plant maximum load change rate and the power generation plant target load at the same time. (2. The power generation ground operation control device as set forth in claim 1, wherein the storage contents of the parameter storage section can be changed from the outside.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP57193338A JPS5983204A (en) | 1982-11-05 | 1982-11-05 | Controller for operation of power plant |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP57193338A JPS5983204A (en) | 1982-11-05 | 1982-11-05 | Controller for operation of power plant |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5983204A true JPS5983204A (en) | 1984-05-14 |
| JPH0120763B2 JPH0120763B2 (en) | 1989-04-18 |
Family
ID=16306227
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP57193338A Granted JPS5983204A (en) | 1982-11-05 | 1982-11-05 | Controller for operation of power plant |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5983204A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6275706A (en) * | 1985-09-30 | 1987-04-07 | Toshiba Corp | Generalized load controller |
| JPS63171124A (en) * | 1987-01-05 | 1988-07-14 | 株式会社東芝 | Load regulator |
-
1982
- 1982-11-05 JP JP57193338A patent/JPS5983204A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6275706A (en) * | 1985-09-30 | 1987-04-07 | Toshiba Corp | Generalized load controller |
| JPS63171124A (en) * | 1987-01-05 | 1988-07-14 | 株式会社東芝 | Load regulator |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0120763B2 (en) | 1989-04-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Spichartz et al. | New stability concept for primary controlled variable speed wind turbines considering wind fluctuations and power smoothing | |
| CN114597963B (en) | A method for hydropower station start-up and shutdown units to quickly pass through the vibration zone through AGC | |
| CN111626470B (en) | Electric heating comprehensive coordination optimization scheduling method and system | |
| CN110429668A (en) | Coordinated optimization frequency control method for variable speed and pitch of wind turbines under load reduction | |
| JPS58222730A (en) | Device for operating generating plant | |
| CN105490292A (en) | Energy storage system participated power grid secondary frequency control method and device | |
| CN111594384B (en) | A control method and main control system for a voltage source wind turbine | |
| CN114336670B (en) | Wind-solar-storage combined frequency modulation method and system based on fuzzy logic control | |
| CN108599234A (en) | The virtual inertia and primary frequency modulation control method of Wind turbines | |
| JP5500370B2 (en) | Operation control apparatus and operation control method using multivariable model prediction | |
| JPS5983204A (en) | Controller for operation of power plant | |
| CN116613782A (en) | Light-fire cooperation flexible peak shaving power generation control system and control method | |
| CN112736989B (en) | A frequency modulation method, system, device and readable storage medium involving battery energy storage | |
| Pati et al. | Performance comparison of fuzzy gain scheduling based LFC controller in deregulated AGC of a multi area system incorporating wind energy | |
| CN106877362A (en) | A kind of grid connected wind power power comprehensive regulation method | |
| CN111535885A (en) | Method and device for power distribution of gas-steam combined cycle unit | |
| JPS61157233A (en) | Automatic operating device for generating unit | |
| JPS6243044B2 (en) | ||
| JP2878872B2 (en) | Load control device for multi-shaft combined cycle plant | |
| JPH04128505A (en) | Steam pressure control method of plural boiler and power generator | |
| JPS59201638A (en) | Output controller of composite generating plant | |
| CN117728392A (en) | Load auxiliary decision-making method, system, equipment and storage medium | |
| JPS6341292B2 (en) | ||
| JPH044601B2 (en) | ||
| CN116181497A (en) | A control method and device for a gas turbine combined cycle unit |