JPS60223545A - Iron skeletal assembling construction method of large roof - Google Patents

Iron skeletal assembling construction method of large roof

Info

Publication number
JPS60223545A
JPS60223545A JP8059984A JP8059984A JPS60223545A JP S60223545 A JPS60223545 A JP S60223545A JP 8059984 A JP8059984 A JP 8059984A JP 8059984 A JP8059984 A JP 8059984A JP S60223545 A JPS60223545 A JP S60223545A
Authority
JP
Japan
Prior art keywords
truss
roof
construction
assembling
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8059984A
Other languages
Japanese (ja)
Other versions
JPH0334533B2 (en
Inventor
三浦 正夫
廣澤 宣夫
田原 新六
岡部 信宣
圭治 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP8059984A priority Critical patent/JPS60223545A/en
Publication of JPS60223545A publication Critical patent/JPS60223545A/en
Publication of JPH0334533B2 publication Critical patent/JPH0334533B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は例えば体育館、ホール、屋内野球場等、内部
に大空間を有する建築物の構築における大屋根の鉄骨組
立方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of assembling a steel frame for a large roof in the construction of a building having a large interior space, such as a gymnasium, hall, or indoor baseball field.

〔発明の背景〕[Background of the invention]

体育館、音楽ホール、レジャーセンター尋、大きな内部
空間を必要とする建築物においては、トラス構造の鉄骨
架構を有する大屋根等が利用されている。しかし規模が
大きくなると、その構築においてタワークレーン等の揚
重機械も非常に大型のものが何台も必費となり、また高
所での作業が多いと作業能率も悪く、危険も伴なうため
、安全対策用の設備も重要となり、全体的に工費が高く
つくことになる。
Large roofs with trussed steel frames are used in gymnasiums, music halls, leisure centers, and other buildings that require large internal spaces. However, as the scale increases, construction requires the use of many very large lifting machines such as tower cranes, and work at high places is not efficient and can be dangerous. , equipment for safety measures will also be important, and the overall construction cost will be high.

また、屋根トラスをユニット化して吊り上げ、高所ての
作業を減らすといった方法も採られているが、ジヨイン
トごとに仮設支持台を設けると、仮設設備の組立、解体
のための作充工数が多く、また内部の作業空間が制限さ
れるため、外部からトラスユニットを吊り込むための外
部スペースとそれだけの揚程と吊9上げ能力を有するタ
ワークレーン等が必璧となる。
Another method is to reduce the need for work at heights by hoisting roof trusses into units, but if a temporary support stand is provided for each joint, a large number of man-hours are required to assemble and dismantle the temporary equipment. In addition, since the internal work space is limited, a tower crane or the like is required that has an external space for hoisting the truss unit from the outside, and a tower crane or the like that has the corresponding lifting height and lifting capacity.

〔IA明の目的〕[IA Ming's purpose]

この発明は上述のような従来技術における問題点を解決
するために開発されたもので、大屋根の鉄骨トラスの組
立方法および手順等を工夫して、内部空間および先行架
設部分を有効に利用し、揚重機械等の使用機械の大型化
を抑えるとともに施工能率の向上を図り、工費を低減さ
せることを目的としている。
This invention was developed in order to solve the problems in the prior art as described above, and the method and procedure for assembling the large roof steel truss were devised to make effective use of the internal space and the pre-erected part. The purpose of this project is to reduce the size of machinery used, such as lifting machinery, and improve construction efficiency, thereby reducing construction costs.

〔発明の構成〕[Structure of the invention]

この発明の方法では、まず屋根頂部のコンプレッション
リンクと屋根底部のテンションリングを組立てる。コン
プレッションリングおよびテンションリングは鉄骨梁を
円形あるいは多角形に組んだもので、頂部のコンプレッ
ションリングは軸方向の圧縮力を負担し、屋根底部縁を
構成するテンションリングは屋根荷重等によって作用す
る軸方向の引張力を負担するようになっている。
In the method of this invention, first, the compression link at the top of the roof and the tension ring at the bottom of the roof are assembled. Compression rings and tension rings are made by assembling steel beams into circular or polygonal shapes.The compression ring at the top bears the axial compressive force, and the tension ring that makes up the bottom edge of the roof bears the axial compressive force that is applied by roof loads, etc. It is designed to bear the tensile force of

コンプレッションリングは施工現場内部に設置したトラ
ッククレーン等で鉄骨を中央の仮設支持台上へ吊や上け
て組立てることができる。
The compression ring can be assembled by hoisting the steel frame onto a central temporary support platform using a truck crane or other device installed inside the construction site.

、次に内部のトラッククレーン等を利用して、一対の大
梁と該梁間の先行中トラスで構成され2る先行架設部分
を複数組、順次コンプレッションリングとテンションリ
ング間に架設して行く。
Next, using an internal truck crane or the like, a plurality of sets of two pre-erecting parts each consisting of a pair of girders and a pre-erect truss between the girders are successively erected between the compression ring and the tension ring.

大梁および先行中トラスは分割してユニット化すること
もでき、その場合大梁のジヨイント位置に仮設支持台を
設けておく。このとき、先行架設部分間の空間は上述の
クレーン等の設置スペースおよび屋根トラスを構成する
トラスユニットの地組のためのスペース等として利用す
ることができる。
The girder and the leading truss can be divided into units, in which case a temporary support stand is provided at the joint of the girder. At this time, the space between the preceding construction parts can be used as an installation space for the above-mentioned crane, etc., and a space for assembling the truss units constituting the roof truss.

この状態で、屋根トラスは一応構造的に安定し、次にこ
れら先行架設部分量相互を連結する後行中トラスを架設
して行く。この作業は内部に組立てたタワークレーンや
外部のクレーンを用いて行なうが、先行架設部分を利用
して後行中トラスを架設して行くことが、できるため、
特に仮設支持台等を必要とせず、作業スペースの制約が
少なく、少ないクレーン数で対処させることができる。
In this state, the roof truss is structurally stable for the time being, and then the succeeding middle truss that connects these precedingly erected portions is erected. This work is carried out using an internally assembled tower crane or an external crane, but it is possible to use the preceding construction part to erect the trailing middle truss.
In particular, there is no need for a temporary support stand, there are few restrictions on work space, and it can be handled with a small number of cranes.

また、後行中トラスの一蔀は地組したトラスユニットで
構成し、ウィンチ等により先行架設部分への連結位置ま
で吊り上げて架設することもできる。
Furthermore, one end of the trailing intermediate truss can be constructed by a truss unit assembled on the ground, and the truss unit can be hoisted to a position where it is connected to the preceding construction part using a winch or the like.

このようにして屋根の鉄骨が組立てられた後、屋根表部
を5Iliするパネル等を順次鉄骨に固定して行き、屋
根の仕上げが行なわれる。
After the roof steel frame is assembled in this manner, the panels and the like that cover the roof surface are successively fixed to the steel frame to finish the roof.

〔実施例〕〔Example〕

w41図〜第10図はこの発明の大屋根の鉄骨組立方法
における施工手順の一例を示したものて、次のような手
順で作業が行なわれる。
Figures w41 to 10 show an example of the construction procedure in the method of assembling a large roof steel frame according to the present invention, and the work is carried out in the following procedure.

(1) 大屋根頂部を支持する中央仮設支持台9と外周
部の中間仮設支持台10を組立てる(第1図)。
(1) Assemble the central temporary support stand 9 that supports the top of the large roof and the intermediate temporary support stand 10 on the outer periphery (Fig. 1).

(2) 中央仮設支持台9上にコンプレッションリング
1を組立てる(第2図)。なお、このコンプレッション
リング1には予め大梁のジョ・インド部4を工場にて一
体に取付けておく。
(2) Assemble the compression ring 1 on the central temporary support stand 9 (Fig. 2). Note that the compression ring 1 is integrally attached with the joint section 4 of the girder in advance at the factory.

(3) 屋根底部縁のテンションリング−4を組立てる
(第3図)。このとき、分割した大梁3の第1セクシヨ
ンも同時に組立て(工場でテンション、リング2と一体
にしである)、中間仮設支持台10で支持し、図に示す
ように大梁3の第1セクション間の先行中トラス5を組
んで行く。
(3) Assemble the tension ring-4 on the bottom edge of the roof (Figure 3). At this time, the first section of the divided girder 3 is also assembled at the same time (tensioned at the factory and integrated with the ring 2) and supported by the intermediate temporary support stand 10, as shown in the figure, between the first sections of the girder 3. Assemble truss 5 during the advance.

(4) さらに中間仮設支持台11を設置し、大梁3の
m2セクシヨンを継ぎ足し、中間の先行中トラス5′を
組んで行く(第4図)。なお、この場合並行作業および
揚重機械等との関係で4箇所の先行架設部分の作業順序
を決定する。また各所に均等に荷重がかかるようなるべ
く対称に作業を進めて行くことが望ましい。
(4) Furthermore, install the intermediate temporary support stand 11, add the m2 section of the girder 3, and assemble the intermediate leading intermediate truss 5' (Figure 4). In this case, the work order of the four preceding construction parts will be determined in relation to parallel work and lifting machinery. It is also desirable to carry out the work as symmetrically as possible so that the load is applied equally to all parts.

(5) 大梁3の第3セクシヨンおよび第4セクシヨン
を継ぎ足し、コンプレッションリング1とテンションリ
ング2間を連結する(第5図)。
(5) Add the third and fourth sections of the girder 3 and connect the compression ring 1 and tension ring 2 (Fig. 5).

大梁3の第3セクシヨンと第4セクシヨンとは予め地組
しておき、トラッククレーン尋で吊り上げて架設するこ
とにより、作業の効率を上けることができる。
Work efficiency can be improved by assembling the third and fourth sections of the girder 3 in advance and lifting them up using a truck crane.

(6) 上述(5)の作業を残りの先行架設部分につい
て行なう(W46図)。
(6) Perform the work in (5) above for the remaining pre-erected parts (Figure W46).

(7)先行架設部分の架設を完了する(絹7図)。(7) Complete the construction of the preceding construction part (Figure 7).

なお、後行架設部分については(3)以下の作業と並行
して、後述のトラスユニット7の地組が進行している。
Regarding the trailing construction part, in parallel with the work described below (3), the ground assembly of the truss unit 7, which will be described later, is progressing.

また、屋根頂部8のかざ抄部分等の構築を開始する。Additionally, construction of the roof top portion 8, etc., will begin.

(8) 後行架設部分について、架設位置直下で梁状に
地組したトラスユニット7を、順次大梁3間に架設して
行く(第8図)。この場合、先行架設部分にトラスユニ
ット巻き上げ用の架台を′−設け、ウィンチ等で巻き上
げて架設することができる。
(8) Regarding the trailing construction section, truss units 7 assembled into beams directly below the construction location are successively constructed between the girders 3 (Fig. 8). In this case, a frame for hoisting the truss unit is provided in the preceding construction part, and the truss unit can be hoisted up using a winch or the like.

(9)順次、トラスユニット7を架設し、先行架設部分
の大梁3間を連結して行く(第9図)。
(9) Sequentially erect the truss units 7 and connect the girders 3 of the previously erected portions (Fig. 9).

顛 タワークレーン等を使用して残りの部分のトラス組
みを行ない、後行中トラス6を完成させる(第10図)
2) Assemble the remaining portion of the truss using a tower crane, etc., and complete the trailing middle truss 6 (Figure 10)
.

・ 以上(11〜顛の作業により大屋根の鉄骨部、分の
施工が完了する。
・The construction of the steel frame part of the large roof is completed by completing the work from 11 to 2.

W411図および第12図は先行架設部分の施工の様子
を示したもので、上述の(6)の作業に対応する。トラ
ッククレーンνにより大梁3の第2、セクションが架設
されるとζろで、地上部では架台上でトラスユニット7
の地組が行なわれている。また、既にコンプレッション
リングlとテンションリング2との連結を完了した大梁
3上にはトラスユニット7の巻き上けのためのトラス巻
き上げ架台13が用意されている。
Figure W411 and Figure 12 show the construction of the preceding construction part, and correspond to the work (6) above. When the second section of the girder 3 is erected by the truck crane ν, the truss unit 7 is placed on the trestle at the ground level.
Groundwork is being carried out. Further, a truss hoisting frame 13 for hoisting the truss unit 7 is provided on the girder 3 where the connection between the compression ring l and the tension ring 2 has already been completed.

第13図および第14図は後行中トラス6の施工の様子
を示したもので、上述の(8)〜α・の作業に対応する
FIGS. 13 and 14 show the construction of the trailing intermediate truss 6, and correspond to the operations (8) to α. described above.

トラスユニット7を順次ライ汗等を利用して巻き上げ、
先行架設部分の大梁3間に架設して行く。また、内部に
タワークレーン14を組み立て、架設したトラスユニッ
ト7間に配する鉄骨を吊り上げ、順次後行中トラス6を
組立てて行く。タワークレーン14のマスト部分以外の
組立が完了した後、タワークレーン14は後工程の屋根
用PC板の堆付は等に利用し、作業完了後順次解体され
、外部のクローラ−クレーン等で撤去する。また、中央
仮設支持台9および中間仮設支持台io 、 ilは全
数仮設後ジヤツキダウンし、解体し、撤去する。
The truss unit 7 is sequentially rolled up using dry sweat, etc.
Erection will be carried out between the three girders in the preliminary construction section. Furthermore, a tower crane 14 is assembled inside, the steel frame placed between the erected truss units 7 is lifted up, and the trailing truss 6 is sequentially assembled. After the assembly of the parts other than the mast part of the tower crane 14 is completed, the tower crane 14 is used for later processes such as depositing PC boards for the roof, and after the work is completed, it is sequentially dismantled and removed by an external crawler crane, etc. . In addition, after all of the central temporary support stand 9 and intermediate temporary support stand io, il are temporarily installed, they are jacked down, dismantled, and removed.

第15図および第16図は屋根鉄骨組立完了時の状態を
示したもので、屋根トラス全体で屋根荷重を支持する構
造となり、続いて屋根表面のパネルあるいは天井部分等
の工事が行なわれる。
Figures 15 and 16 show the state when the roof steel frame has been assembled, and the structure is such that the entire roof truss supports the roof load, and then work is carried out on the roof surface panels or ceiling section.

〔発明の効果〕〔Effect of the invention〕

コンプレッションリンクドテンションリングの組立彼先
行架設部分と後行架設部分とに分け、コンプレッション
リングとテンションリング間に架設された先行架設部分
を利用して後行架設部分の架設作業を行なうよう構成し
ているため、内部空間を作業空間として有効に利用する
ことができる。すなわち仮設支持台等を必要としない後
行架設部分にクローラ−クレーン、タワークレーン等の
揚重機械を設置することがで、き、外部に設置する場合
に比べ少ない台数のより小型の揚重機械で大規模な屋根
の、施工に対処することができる。また、仮設支持台の
組立、解体等の手間が少なくなり、さらに、内部のスペ
ースでトラスユニットの地組等を行ない、作業能率を向
上させるとともに、この地組時巻き上はトラス内に照明
器具、キャツトウオーク等の設備を増シ付けることも可
能である。以上のことよル、全体の工費の大幅低減も可
能である。
Assembly of the compression linked tension ring is divided into a leading construction part and a trailing construction part, and the construction is configured such that the leading construction part installed between the compression ring and the tension ring is used to perform the construction work of the trailing construction part. Therefore, the interior space can be effectively used as a work space. In other words, it is possible to install lifting machines such as crawler cranes and tower cranes in the trailing section that does not require temporary supports, etc., and requires fewer and smaller lifting machines than when installing them externally. Can handle the construction of large-scale roofs. In addition, the labor required for assembling and dismantling temporary support stands is reduced, and work efficiency is improved by assembling the truss unit in the internal space. It is also possible to add equipment such as catwalks. Based on the above, it is also possible to significantly reduce the overall construction cost.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第10図はこの発明の実施例における施工手順
の概略を示す平面図、第11図は先行架設部分の施工の
様子を示す平面図、第12図はその縦断面図、第16図
は後行中トラスの施工の様子を示す平面図、第14図は
その縦断面図、第15図は屋根鉄骨組立完了時の平面図
、第16図はその縦断面図である。 l・・・・・・コンプレッションリング、2・・・・・
・テンションリング、3・・・・・・大梁、4・・・・
・・大梁ジヨイント部、5・・・・・・先行中トラス、
6・・・・・・後行中トラス、7・・・・・・トラスユ
ニット、8・・・・・・頂部、9・・・・・・中央仮設
支持台、lO・・・・・・中間仮設支持台、11・・・
・・・中間仮設支持台、12・・・・・・トラッククレ
ーン、13・・・・・・トラス巻き上げ架台、14・・
自・・タワークレーン。 第1図 第2図 第3図 第4図 第5図 第6図 第7図 第8図 v59図 第10図 第11図 第14図 第15図
1 to 10 are plan views showing the outline of the construction procedure in an embodiment of the present invention, FIG. 11 is a plan view showing the state of construction of the preceding construction part, FIG. 14 is a plan view showing the construction of the trailing middle truss, FIG. 14 is a longitudinal sectional view thereof, FIG. 15 is a plan view when roof steel frame assembly is completed, and FIG. 16 is a longitudinal sectional view thereof. l...Compression ring, 2...
・Tension ring, 3...Girder, 4...
・・Girder joint part, 5・・・・Previous truss,
6... Trailing middle truss, 7... Truss unit, 8... Top, 9... Central temporary support stand, lO... Intermediate temporary support stand, 11...
... Intermediate temporary support stand, 12 ... Truck crane, 13 ... Truss hoisting frame, 14 ...
Self...Tower crane. Fig. 1 Fig. 2 Fig. 3 Fig. 4 Fig. 5 Fig. 6 Fig. 7 Fig. 8 Fig. v59 Fig. 10 Fig. 11 Fig. 14 Fig. 15

Claims (1)

【特許請求の範囲】 (11’*ず、屋根頂部のコンプレッションリングおよ
び屋根底部のテンションリングを組立て、次に一対の大
梁と該大梁間の先行中トラスで構成される先行架設部分
、複数組を前記コンプレッションリングとテンションリ
ンク間ニ架設し、その後前記先行架設部分量相互を連結
する後行中トラスを架設して行くことを特徴とする大屋
根の鉄骨組立方法。 (2)後行中トラスの一部は地組したトラスユニットで
構成され、ウィンチにより架設位置まで吊り上けて架設
するan請求の範囲第1項記載の大屋根の鉄骨組立方法
[Claims] (11'* First, assemble the compression ring at the top of the roof and the tension ring at the bottom of the roof, and then assemble a plurality of sets of the preceding construction portion consisting of a pair of girders and a leading middle truss between the girders. A method for assembling a steel frame for a large roof, characterized in that the compression ring and the tension link are erected, and then a trailing middle truss is erected to connect the preceding erected portions. (2) A method of assembling a trailing middle truss A method for assembling a steel frame for a large roof according to claim 1, wherein a part of the truss unit is assembled to the ground and is lifted up to the erection position using a winch.
JP8059984A 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof Granted JPS60223545A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8059984A JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8059984A JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Publications (2)

Publication Number Publication Date
JPS60223545A true JPS60223545A (en) 1985-11-08
JPH0334533B2 JPH0334533B2 (en) 1991-05-23

Family

ID=13722789

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8059984A Granted JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Country Status (1)

Country Link
JP (1) JPS60223545A (en)

Also Published As

Publication number Publication date
JPH0334533B2 (en) 1991-05-23

Similar Documents

Publication Publication Date Title
JPH03241128A (en) Arch dime reinforced by tension member and construction method thereof
CN114837483B (en) High-low span portal steel frame building structure and construction process thereof
CN112267709A (en) Segmented demolition construction method for large-span beam string structure
JP7548869B2 (en) How to build structures
CN114033189A (en) Large-area high-altitude grid structure aluminum grid ceiling construction device and construction method
CN113846792A (en) Workshop steel structure roof, hoisting device and hoisting method thereof
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
CN216665073U (en) Monitoring and lifting structure for complex partition lifting steel structure
JPH0334533B2 (en)
CN117966955A (en) Large-span dome-type truss structure and construction method thereof
JP2858891B2 (en) Construction method of large span dome roof
JPH0718743A (en) Construction method for large span domelike roof
JPH0423709B2 (en)
JPH06240874A (en) Construction of truss beam for long span
JPH0431524A (en) Construction method of dome frame
CN112323988B (en) Connecting and construction process of prefabricated steel-encased concrete column and profiled steel sheet composite slab
JP2690822B2 (en) Steel construction method for low-rise buildings
JP2506464B2 (en) Fence for roofing of industrialized houses
JP2026003966A (en) Steel frame construction method
JPH0339538A (en) Construction work of wooden building
KR0135678B1 (en) Method for installing safety nets on steel structure
WO2025076769A1 (en) Climbing method for self-elevating internal climbing tower crane in variable cross-section structure space
JP2994205B2 (en) Structural assembly method
JPH0527733B2 (en)