JPS61221402A - Construction of running road for tramcar - Google Patents

Construction of running road for tramcar

Info

Publication number
JPS61221402A
JPS61221402A JP5854385A JP5854385A JPS61221402A JP S61221402 A JPS61221402 A JP S61221402A JP 5854385 A JP5854385 A JP 5854385A JP 5854385 A JP5854385 A JP 5854385A JP S61221402 A JPS61221402 A JP S61221402A
Authority
JP
Japan
Prior art keywords
rail
concrete
construction
plate
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5854385A
Other languages
Japanese (ja)
Other versions
JPH058281B2 (en
Inventor
星野 彰
弘 中山
大高 陽一
舟戸 登
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP5854385A priority Critical patent/JPS61221402A/en
Publication of JPS61221402A publication Critical patent/JPS61221402A/en
Publication of JPH058281B2 publication Critical patent/JPH058281B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は電車用走行路の施工方法に関するものである。[Detailed description of the invention] <Industrial application field> The present invention relates to a method of constructing a running track for trains.

〈従来の技術〉 コンクリート製道床にレールを敷設する場合に次のよう
な間層がある。
<Conventional technology> When laying rails on a concrete track bed, there are the following interlayers.

くイ〉コンクリート道床上の枕木は正確な高さ、位置に
敷設しなければならない。
B. Sleepers on the concrete track bed must be installed at the correct height and position.

しかしコンクリート道床の形状は正確ではないから、く
さびなどを挿入しつつ枕木の高さや位置を決めるのは手
数を要する作業である。
However, the shape of the concrete track bed is not precise, so determining the height and position of the sleepers while inserting wedges is a time-consuming task.

く口〉所定の高さ、位置に位置決めした枕木の周囲には
間詰めコンクリートを打設して枕木を固定しなければな
らない。
Closing> The sleepers must be fixed by placing filler concrete around the sleepers that have been positioned at the specified height and position.

このように道床コンクリートの表面を多少低(設定し、
その後間詰めコンクリートを打設するという二重の作業
が必要となる。
In this way, the surface of the trackbed concrete is set somewhat low (
After that, the double work of pouring filler concrete is required.

くハ〉コンクリート枕木や間詰めコンクリートの重量の
増加によりスラブに加わる荷重が大きくなる。
Kuha> Due to the increase in the weight of concrete sleepers and filler concrete, the load applied to the slab increases.

そのためスラブ側の寸法が過大となる。Therefore, the dimension on the slab side becomes excessive.

く本発明の目的〉 本発明は上記のような点を改善するた゛めになされたも
ので次のような電車走行路の施工方法を提°供すること
を目的とする。
OBJECTS OF THE INVENTION The present invention has been made to improve the above-mentioned problems, and an object of the present invention is to provide the following method of constructing a train running track.

くイ〉レールの高さ調整が容易な施工方法く口〉スラブ
駆体のコンクリート打設作業を1回行うだけで完成する
ことができ、2回目の間詰めコンクリートの打設を省略
できる施工方法〈本発明の構成〉 次に本発明の施工方法の一例を説明する。
Kui〉Construction method that makes it easy to adjust the height of the rail Kuuchi〉A construction method that can be completed with just one concrete pouring of the slab base and eliminates the need for a second pouring of filler concrete. <Structure of the present invention> Next, an example of the construction method of the present invention will be explained.

くイ〉20桁の設置 橋台その他の基礎1上に20桁2を2列並行に載置する
。(第21図) この20桁の上面には工場での製造時に埋め込みナツト
21を一定の間隔で複数本づつ埋め込んでおく。
〉Installation of 20 girders Place 20 girders 2 in two parallel rows on the bridge abutment or other foundation 1. (FIG. 21) A plurality of embedded nuts 21 are embedded in the upper surface of the 20 digits at regular intervals during manufacturing at a factory.

く口〉ボルトの取り付け(第3図) 埋め込みナツト21にボルト22を垂直にねじ込む。Attachment of bolts (Fig. 3) Screw the bolt 22 vertically into the embedded nut 21.

従ってPCC桁上上面は所定間隔で複数本(実施例では
lii所に4本)のボルト22群が垂直に林立すること
になる。
Therefore, on the upper surface of the PCC girder, a plurality of bolts 22 (four bolts at the lii location in the embodiment) are vertically arranged at predetermined intervals.

同時にスラブコンクリート打設用の底型枠3を20桁2
の間に設置する。
At the same time, 20-digit 2 bottom formwork 3 for slab concrete pouring is installed.
be installed between.

くハ〉仮相の取り付け(第4図) 複数箇所にボルト孔を開孔した鋼製板を受板41として
、ボルト22上に取り付ける。
Kuha〉Attachment of Temporary Phase (Fig. 4) A steel plate with bolt holes drilled in multiple locations is used as the receiving plate 41 and attached on the bolts 22.

受板41の下部に位置させたナツト42を回転すること
によって受板41の高さを正しくセットできる。
By rotating a nut 42 located at the bottom of the receiving plate 41, the height of the receiving plate 41 can be set correctly.

この受板41上に仮相4を、レールの横断方向に位置さ
せて載置する。
The temporary phase 4 is placed on this receiving plate 41 so as to be positioned in the transverse direction of the rail.

仮相4は鋼製の角柱であって、その上面には長手方向に
長孔を開孔する。
The temporary phase 4 is a square column made of steel, and an elongated hole is opened in the longitudinal direction on the upper surface thereof.

長孔には垂直方向のボルトを、長孔に沿って移動可能に
セットしておく。
A vertical bolt is set in the long hole so that it can move along the long hole.

く二〉レールの敷設(第5図) 仮相4上に直交方向にレール5を敷設する。Kuni〉Laying the rails (Fig. 5) A rail 5 is laid on the temporary phase 4 in the orthogonal direction.

この場合にレール5を仮止めする仮固定具51は仮相4
の長孔に沿って移動可能であるから、レール5の横断方
向の位置修正を簡単に行うことができる。
In this case, the temporary fixing tool 51 for temporarily fixing the rail 5 is the temporary fixing tool 51.
Since the rail 5 can be moved along the elongated hole, the transverse position of the rail 5 can be easily corrected.

この段階で上下方向の再調整ができることも勿論である
Of course, readjustment in the vertical direction can be made at this stage.

くホ〉保持板等の設置(第1図) 仮相4は位置と方向調整用の板部材であるため、これと
は別に永久にレールを保持する板である保持板6をレー
ル5下面に吊り下げる。
Kuho〉Installation of holding plates, etc. (Fig. 1) Since the temporary phase 4 is a plate member for adjusting the position and direction, a holding plate 6, which is a plate that permanently holds the rail, is installed on the underside of the rail 5. Be suspended.

保持板6には更に埋め込みナツト61などを吊り下げて
おく。
An embedded nut 61 and the like are further suspended from the holding plate 6.

既にレール5は正しい方向、高さにセットされているか
ら、そのレールに吊り下げる保持板6は高さも位置も測
量する必要なく、ただ取り付けるだけの簡単な作業であ
る。
Since the rail 5 is already set in the correct direction and height, the holding plate 6 to be suspended from the rail does not need to be measured in height or position, and is a simple task of simply attaching it.

この軌道がリニアモーターカー用の軌道であれば、レー
ル5間にリアクションプレート取り付は用の埋め込みナ
ツト7を位置させておけばよい。
If this track is a track for a linear motor car, an embedded nut 7 for attaching the reaction plate may be positioned between the rails 5.

ただし埋め込みナツト7を空中に浮かべるわけにはいか
ないから、レール5間を帯板71で連結し、帯板71の
下面の正確な位置に埋め込みナツト7を固定しておけば
よい。
However, since the embedded nut 7 cannot be floated in the air, it is sufficient to connect the rails 5 with a band plate 71 and fix the embedded nut 7 at an accurate position on the lower surface of the band plate 71.

この帯板71も後には撤去する。This strip plate 71 will also be removed later.

くべ〉スラブコンクリートの打設(第6図)20桁2の
上部空間の正確な位置にレール5等を持ち上げ、かつそ
のレール5からは埋め込みボルト61、埋め込みナツト
7などをぶら下げた状態でコンクリート8を打設する。
Placement of slab concrete (Fig. 6) Raise the rail 5 etc. to the correct position in the upper space of the 20 girder 2, and place the concrete 8 with embedded bolts 61, embedded nuts 7, etc. hanging from the rail 5. to be poured.

この時、後に撤去する仮相等の周囲は溝状に凹設した状
態に残しておく。
At this time, the area around the temporary phase, etc., which will be removed later, is left in a groove-like recessed state.

くト〉仮相等の撤去(第7図) コンクリート8の硬化後、仮相4や帯板71などとレー
ル5との締結を解体して側方へ抜き出して撤去する。
〉Removal of temporary phase, etc. (Figure 7) After the concrete 8 has hardened, the connection between the temporary phase 4, strip plate 71, etc. and the rail 5 is dismantled, pulled out to the side, and removed.

これは信号用電気がレール間に流れるのを防止するため
であるから、絶縁処理をすることにより撤去しない場合
も考えられる。
This is to prevent signal electricity from flowing between the rails, so it may be possible to insulate them and not remove them.

抜き出し後の体積はわずかであるからその跡にモルタル
9などを充填する作業は簡単である。
Since the volume after extraction is small, it is easy to fill the remaining space with mortar 9 or the like.

く本発明の効果〉 本発明は上記したようになるから次の−ような効果を期
待できる。
Effects of the Present Invention> Since the present invention is as described above, the following effects can be expected.

くイ〉コンクリート打設前に、ボルト群及び仮相でレー
ルを支持してお(。
Kui> Before pouring concrete, support the rail with a group of bolts and a temporary structure (.

従って高さの調整、横断方向の位置の調整はきわめて容
易である。
Therefore, height adjustment and transverse position adjustment are extremely easy.

く口〉ボルト群に支えられて正確な位置で空中に浮かん
だ状態のレールに、将来レールを固定すべき支持板など
を吊り下げた後、コンクリートを打設するものである。
After suspending the support plates to which the rail will be fixed in the future, concrete is poured onto the rail, which is suspended in the air at a precise position supported by a group of bolts.

従ってレールは設計通りの位置で正確に、硬化したコン
クリート上に固定されることになる。
Therefore, the rails are fixed onto the hardened concrete exactly in the designed position.

〈ハ〉従って従来のようにスラブ上に枕木をならべて高
さ調整を行うような作業は一切不要であり、足場の悪い
場所で枕木を運搬したり敷設する作業も必要としない。
<C> Therefore, there is no need for the conventional work of arranging sleepers on a slab and adjusting the height, and there is also no need for work to transport or lay sleepers in places with poor footing.

く二〉スラブコンクリートの打設だけで構造物が完了す
るから、従来のような間詰めコンクリートが不要である
2〉The structure can be completed by simply placing slab concrete, so there is no need for conventional filler concrete.

従って無駄な死荷重が減少し、下部構造の寸法も必要最
少限のものとすることができる。
Therefore, unnecessary dead loads are reduced, and the dimensions of the lower structure can be reduced to the minimum necessary.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明の施工方法の一実施例の施工中の状態の
説明図 第2図〜第7図:施工順序の説明図 21:埋め込みナツト 22:ボルト 4:仮相 5:レール 6:保持板 71:帯板 出願人  東 急 建 設 株式会社 一つ じ 第2図 〆
Figure 1: An explanatory diagram of the state during construction of an embodiment of the construction method of the present invention. Figures 2 to 7: An explanatory diagram of the construction order. 21: Embedded nut 22: Bolt 4: Temporary phase 5: Rail 6: Retaining plate 71: Band plate applicant Tokyu Construction Hitotsuji Co., Ltd. Figure 2

Claims (1)

【特許請求の範囲】 スラブコンクリートの打設前に、 スラブ空間内に垂直に立てたボルト上に仮桁を介してレ
ールを載置し、 レールの高さ、方向を設定した後、 レールに吊り下げたレール固定具部材などを埋設する状
態で、 スラブコンクリートを打設して行う、 電車用走行路の施工方法
[Claims] Before placing slab concrete, a rail is placed via a temporary girder on bolts erected vertically in the slab space, and after setting the height and direction of the rail, it is hung on the rail. A method of constructing a train running track by pouring slab concrete while burying the lowered rail fixing components etc.
JP5854385A 1985-03-25 1985-03-25 Construction of running road for tramcar Granted JPS61221402A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5854385A JPS61221402A (en) 1985-03-25 1985-03-25 Construction of running road for tramcar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5854385A JPS61221402A (en) 1985-03-25 1985-03-25 Construction of running road for tramcar

Publications (2)

Publication Number Publication Date
JPS61221402A true JPS61221402A (en) 1986-10-01
JPH058281B2 JPH058281B2 (en) 1993-02-01

Family

ID=13087356

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5854385A Granted JPS61221402A (en) 1985-03-25 1985-03-25 Construction of running road for tramcar

Country Status (1)

Country Link
JP (1) JPS61221402A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp How to build digits
JP2010222800A (en) * 2009-03-23 2010-10-07 Railway Technical Res Inst Bolt-type slip prevention method used for composite structuring of existing steel railway bridge and concrete slab.

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4830207A (en) * 1971-08-25 1973-04-21

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4830207A (en) * 1971-08-25 1973-04-21

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp How to build digits
JP2010222800A (en) * 2009-03-23 2010-10-07 Railway Technical Res Inst Bolt-type slip prevention method used for composite structuring of existing steel railway bridge and concrete slab.

Also Published As

Publication number Publication date
JPH058281B2 (en) 1993-02-01

Similar Documents

Publication Publication Date Title
KR102273901B1 (en) Method for repairing sleeper on concrete bed
CN113931077A (en) Construction method for erecting prefabricated box girder bridge girder erection machine in limited construction space
CN112941975A (en) Combined track slab, prefabricated slab track system and installation and construction method thereof
DK1310594T3 (en) Construction method for a railway on a concrete tile and temporary anchorage for practicing the method
EP1873308A1 (en) Concrete slab railroad track system and method of installing same
CN1699692A (en) Maglev transportation superimposed track beam and manufacturing method thereof
EP1700954A2 (en) Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same
JPS61221402A (en) Construction of running road for tramcar
CN116356614B (en) Longitudinal track panel structure and construction method thereof
CN203403336U (en) Bolt sleeve-pre-buried support of rail transit contact rail insulating support base
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
CN215051635U (en) Light prefabricated ballast bed
CN210127028U (en) Gantry crane end well track beam and gantry crane end well track mounting assembly
JP2589046Y2 (en) Rail frame bearing device
JP7473296B2 (en) Invert and invert construction method
JPS61221403A (en) Construction of running road for tramcar
CN111809460A (en) Rapid high-precision high-speed rail wall type inspection pit track laying construction method
JPH0218085Y2 (en)
JPS6172102A (en) Laying of rail direct connection track
JPH11247101A (en) Anchor fixed track structure and anchor fixed pillow
CN223050722U (en) Assembled track scale
CN221501741U (en) A leveling device for installing a bridge telescopic assembly
CN221501604U (en) Ballastless track laying formwork support tool
CN114717883B (en) Rapid installation method of prefabricated foundation structure for railway detection equipment
JPH09278354A (en) Fastener of crane rail and laying construction method