JPS61270432A - Construction of building - Google Patents
Construction of buildingInfo
- Publication number
- JPS61270432A JPS61270432A JP11279385A JP11279385A JPS61270432A JP S61270432 A JPS61270432 A JP S61270432A JP 11279385 A JP11279385 A JP 11279385A JP 11279385 A JP11279385 A JP 11279385A JP S61270432 A JPS61270432 A JP S61270432A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- building
- construction
- column
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は建造物の構築工法にかかり、詳しくは地表面近
(で各階図を構成する柱や梁、床、外壁等の構造物を最
上層の部分から組み上げ、これを逐次ジヤツキアップす
るようにした建築物、鉄塔、橋脚等の構築工法に関する
。[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a method of constructing a building, and more specifically, the present invention relates to a method of constructing a building. This article relates to construction methods for buildings, steel towers, bridge piers, etc., which are assembled from the upper layer and then jacked up one after another.
(従来技術およびその問題点)
近年、建設業においてはロボット等を用いた施工の自動
化が推進されているが、これらは全工程の極く一部に応
用されているにすぎず、ロボツ1〜化のメリットを十分
に享受するには未だ到っていないのが現状である。これ
は、ロボット化の努力が不足しているために生じた現象
ではなく、建設業における作業環境の特異性、すなわち
作業場が上下左右または前接に逐次、移動するという特
殊な事情に起因するものと考えられる。例えばビル建築
を例にとると、いわゆるSRC構造の場合、骨組みを下
層階から組立てて順次上薩階に移って行くためクレーン
作業との連繋が必要となり、このクレーン作業の時点で
連続的なシステムの流れが途切れてしまうこととなる。(Prior art and its problems) In recent years, automation of construction work using robots and the like has been promoted in the construction industry, but these have only been applied to a small part of the entire process, and robots 1 to 1. At present, we have not yet reached the point where we can fully enjoy the benefits of This phenomenon is not due to a lack of efforts in robotization, but is due to the uniqueness of the working environment in the construction industry, in which the workplace moves up, down, left, right, or forward. it is conceivable that. For example, in the case of building construction, in the case of the so-called SRC structure, the framework is assembled from the lower floors and moved to the upper floors one after another, so it must be linked with crane work, and at the time of this crane work, a continuous system The flow will be interrupted.
また、この他にまず柱を建ててその上端部付近にジヤツ
キを据イ]けると共に、地上で相上げた屋根または床染
をクレーンにより吊上げて建造物を構築する工法が提案
されているが、この方法では多層階の建造物には応用し
に(いという欠点があった。In addition, another method has been proposed in which a building is constructed by first building pillars and placing jacks near the tops of the pillars, and then lifting the roof or floor dyeing that has been raised on the ground using a crane. This method had the disadvantage that it was difficult to apply to multi-story buildings.
史に、従来においては概して大型のクレーンや支保工を
必要とし、しかも高い足場での作業が不可欠であり、設
備の経済性や作業の安全性の点で問題があった。Historically, in the past, large cranes and shoring were generally required, and work on high scaffolding was essential, which caused problems in terms of the economic efficiency of the equipment and the safety of the work.
(発明の目的)
本発明は上記の欠点を解消するべく提案されたもので、
その目的とするとごろは、各階曙を構成する柱や染、床
(尾根)等の構造体を地表面近くの作業空間で最上階の
部分から組上げ、この構造体をジヤツキアップして順次
、下ll1階の構築へと移行していく口とにより、大型
のクレーンや高い足場、あるいは支保工等を必要とぜず
、経済性や安全性に優れ、かつ構築作業のロボツ1〜化
をも可能ならしめた建造物の構築工法を提供することに
ある。(Object of the invention) The present invention has been proposed to solve the above-mentioned drawbacks.
The purpose is to assemble the structures such as the pillars, dyeing, and floors (ridges) that make up each floor from the top floor in a work space near the ground surface, and then jack up this structure and sequentially build it up. By shifting to the construction of floors, there is no need for large cranes, high scaffolding, or support, and it is economical and safe, and it is also possible to use robots for construction work. The purpose of this invention is to provide a construction method for compact buildings.
(発明の構成)
以下、図に沿って本発明を説明する。まず、第1図は本
発明における組立用架台の一実施例を示すもので、図に
おいて1は基礎工の上に形成された庭下唐の床であり、
この床1の上にはTI4製等かつ中空状の架台柱2/′
f−構築される。この架台柱2は、四隅に縦材2aがそ
れぞれ立設され、正面を除く周囲三方には第1図(ロ)
に示す如く水平材2t+および斜材2Cが配設されて縦
材21Iが相nに連結され、また架台柱2の正面におい
ては、縦材2a@に複数の)P板2(1がボルト、ナツ
トによって着脱自在に取付けられる。ここで、架台柱2
の内部空間はジVツキ3.スペーサ4および柱部材5を
収容し得るような大きさに設定され、これらの部材の出
し入れや後述する支持ナツト14の操作は、平板2dを
適宜取外すことにより行なわれるものである。(Structure of the Invention) The present invention will be described below with reference to the drawings. First, FIG. 1 shows an embodiment of the assembly frame according to the present invention, and in the figure, 1 is a garden floor formed on the foundation work,
On top of this floor 1 is a hollow frame column 2/' made of TI4 or the like.
f - constructed. This pedestal column 2 has vertical members 2a erected at each of the four corners, and the surrounding three sides except the front are shown in Fig. 1 (b).
As shown in the figure, a horizontal member 2t+ and a diagonal member 2C are arranged to connect the vertical member 21I to the phase n, and in front of the frame column 2, a plurality of P plates 2 (1 is a bolt, 1 is a bolt, It is removably attached with a nut.Here, the frame column 2
The internal space of 3. The size is set to accommodate the spacer 4 and the column member 5, and the insertion and removal of these members and the operation of the support nut 14, which will be described later, are performed by appropriately removing the flat plate 2d.
また、架台柱2の正面両側に配設された2本の縦材2a
には、必要に応じて補剛材2eが6脱自在に沿設され、
架台柱2の強度の向上が図れるようになっている。更に
、架台柱2の内面には、シャツ1ニアツブ時に柱部材5
に偏心が生じないようにするため、第1図(ハ)に示さ
れる柱部材5に取付けられた支持金物7およびガイド金
物8との遊間を補正するべくガイドレール2tが必要箇
所に付けられると共に、架台柱2の上端部には、第1図
(ホ)に示すようにジヤツキアップ時に仮受反力を支持
するため仮受支持板9が取ト1けられる。In addition, two vertical members 2a arranged on both sides of the front of the pedestal column 2
6 stiffeners 2e are removably provided as needed,
The strength of the pedestal column 2 can be improved. Further, on the inner surface of the frame column 2, a column member 5 is attached when the shirt 1 is put up.
In order to prevent eccentricity from occurring, guide rails 2t are attached at necessary locations to correct the clearance between the supporting hardware 7 and the guide hardware 8 attached to the column member 5 shown in FIG. 1(C). As shown in FIG. 1(E), a temporary support plate 9 is attached to the upper end of the pedestal column 2 in order to support the temporary reaction force during jacking up.
ここで、支持金物7およびガイド金物8は、前述した柱
部材5の偏心用ti11と同時に、施工時に受ける横荷
重に対して組立架台と一体の構造となって抵抗できるよ
うな構造体とし、第1図(ハ1.Fiよび後述の第21
2!1に示す如く、往NI?J5の側面または必要に応
じて底面に取イリボルト10によって着脱自在に取(=
Jけられるものである。そして、支持金物7およびガイ
ド金物E3双方のガイドレール2tとの接触面には、ジ
ヤツキアップ時の各部材1fflに生じる摩擦抵抗を軽
減するため、例えばテフロン等の減摩材11が貼付され
る。Here, the support hardware 7 and the guide hardware 8 are made of a structure that can resist the lateral load received during construction together with the eccentricity ti 11 of the column member 5 described above, as an integral structure with the assembly frame. Figure 1 (C1.Fi and Section 21 below)
As shown in 2!1, former NI? It can be detachably attached to the side of J5 or the bottom of J5 using the removable bolt 10 if necessary (=
It's something that can be kicked. An anti-friction material 11 such as Teflon is attached to the contact surfaces of both the support hardware 7 and the guide hardware E3 with the guide rail 2t in order to reduce the frictional resistance generated in each member 1ffl during jacking up.
なお、第1図において、12はアンノ」−ボルト、13
は仮受スピンドル、14は支持ナツト、15は仮受ナラ
h、1Gは架台東をそれぞれ示している。In addition, in Fig. 1, 12 is Anno'-Bolt, 13 is
14 indicates a temporary support spindle, 14 a support nut, 15 a temporary support nut h, and 1G the mount east.
次に、本発明は各工程を第2図に排すいて詳述する。よ
ず第2図(イ)に示すように建造物のす礎工と最下■の
床1が構築された債、架台柱2と架台果H4とからなる
組立用架台をアンカーボルト12を用いて床1に取付け
る。この際、組立用架台は完成後に当該Fl@−の構造
体として用いると便利であり、また完成に至るまでジヤ
ツキアップ時に建造物の型車を随時仮受けする必要があ
ることを考慮して、完成時の建物の全fi聞を完全に支
持し、かつ地震や風圧等によるtfA荷重に対しても十
分安全であるような構造にする必!芝がある。Next, the present invention will be explained in detail with each step shown in FIG. As shown in Figure 2 (a), the foundation for the building and the bottom part 1 of the floor 1 are constructed using the anchor bolts 12 to assemble the pedestal consisting of the pedestal pillar 2 and the pedestal frame H4. and install it on floor 1. At this time, it is convenient to use the assembly frame as the structure of the Fl@- after completion, and considering that it is necessary to temporarily support the model car of the structure at any time during jacking up until completion, It is necessary to create a structure that fully supports the entire structure of the building and is sufficiently safe against tfA loads caused by earthquakes, wind pressure, etc. There's grass.
次いで、架台柱2の内空部に、油圧によって上下するシ
ャツ4:3を据付け、その頂部に必要に応じてスペーサ
4を取付ける。更に、スベー114の上面に建造物の最
上階の柱となる柱部材5を載せ、この柱部材5に梁部材
18および屋根部材19を連結し、ボルト20.21と
接着剤とによってそれぞれUいに緊結する。Next, a shirt 4:3, which is moved up and down by hydraulic pressure, is installed in the inner space of the frame column 2, and a spacer 4 is attached to the top of the shirt 4, if necessary. Furthermore, a column member 5, which will become a column for the top floor of the building, is placed on the upper surface of the base 114, and a beam member 18 and a roof member 19 are connected to this column member 5, and the bolts 20, 21 and adhesive are used to connect each column member 5 to the column member 5. to be united.
こうして%1帖を終了した後、第2図(01に示すよう
にジヤツキ3を加圧伸長ざセ1組上げた建造物の最上階
の構造体を全体的に押上げる。その債、ジヤツキ3の仲
良終了に伴って仮受ナツト1:)を締め付は支持ナツト
14および仮受スピンドル13により仮受支持根9を介
して組立用架台にて建造物の1@を支持する。しかる1
斐、ジヤツキ3を縮退させてスペーサ4を外し、第2図
(ハ)に示す如くジヤツキ3の上面と押上げが終了した
柱部材5の下面との間に次位の柱部材;)八を挿入する
と1に、ボルト20および接着剤にてlal工部弁部分
結する。After finishing the %1 chapter in this way, as shown in Figure 2 (01), the top floor structure of the building is pushed up as a whole by pressing and expanding one set of jacks 3. Upon completion of the alignment, the temporary support nut 1:) is tightened and the building 1@ is supported on the assembly frame via the temporary support support root 9 by the support nut 14 and temporary support spindle 13. Scold 1
Retract the jack 3, remove the spacer 4, and insert the next column member; Once inserted, the LAL valve part is connected with bolts 20 and adhesive.
次に、第2図(ハ)の状態からジVツV3を1ltlび
伸長させ、建造物の!1iaをジヤツキ3にて支持でき
る状態とした債、取付ポル!・10によって取付けであ
る支持金物7およびガイド金物8を取外し、同時に仮受
ナラ]・15および支持子ツ1〜14を緩めて仮受スピ
ンドル13を上下動可能な状態とする。こうして取外し
た支持金1!57およびガイド金物ε3を新たに継足し
た柱部材5^の側面に取付ポル]・1()によって取+
Jけ、仮受ナラl”1!i、支持ナラ1−14および仮
受スピンドル13等も同時に取付ける。この際、次の工
程の作業に支障がないように、仮受支持板9から上方へ
の仮受スピンドル13の突出長を調節する必要があり、
この作業は仮受ナツト15および支持ナラl〜14を緩
めて仮受スピンドル130位冒を変えることで行なわれ
る。Next, from the state shown in Fig. 2 (c), extend the V3 by 1 ltl to remove the structure! Bonds that can be supported by Jyatsuki 3, installation pole!・Remove the support metal fittings 7 and guide metal fittings 8 attached by 10, and at the same time loosen the temporary support nuts 15 and support pieces 1 to 14 to make the temporary support spindle 13 movable up and down. Attach the support metal 1!57 and guide hardware ε3 that were removed in this way to the side of the newly added column member 5^ using the pole]・1().
At the same time, install the temporary support plate 1"1!i, the support pin 1-14, the temporary support spindle 13, etc. from the temporary support plate 9 upward so as not to interfere with the work in the next process. It is necessary to adjust the protrusion length of the temporary support spindle 13,
This work is carried out by loosening the temporary support nuts 15 and support nuts 1-14 and changing the position of the temporary support spindle 130.
次いで、仮受ナツト15を締め付けながらジヤツキ3を
伸長していき、第2図(ニ)の如くジヤツキ3が上死点
に達した状態で仮受ナツト15により仮受支持板9を介
し組立用架台にて仮受けする。その後ジヤツキ3を縮退
させて第2図(ボ)のようにスペーサ4を挿入し、以後
前述したと同様の工程を第2図(へ)〜(チ)の順で繰
り返す。なお、第2図(ト)、(チ)において5Bは柱
部材を示している。。Next, the jack 3 is extended while tightening the temporary support nut 15, and when the jack 3 reaches the top dead center as shown in FIG. Temporarily receive it on the stand. Thereafter, the jack 3 is retracted and the spacer 4 is inserted as shown in FIG. 2 (B), and the same steps as described above are repeated in the order of FIGS. 2 (F) to (H). In addition, in FIGS. 2(g) and 2(h), 5B indicates a column member. .
このようにして、第2図(す)の如く最上段の次位の階
間の梁部材18Aを架台渠16の上で組立てられるよう
になった時点で、縦部材22、梁部材111Aおよび床
部材2:Sをそれぞれボルト24と接着剤とによって緊
結し、この階随の組立を終了する。以1栗は、ジヤツキ
3を再び伸長して第2図(ヌ)の状態、つまり各階園の
組立工程における第2図(ロ)または第2図(へ)の状
態となり、これらの工程の繰り返しによって建造物の最
上階から順次各階−を仕上げながらジヤツキアップを行
なっていき、最後に架台柱2ヤ栗台県16等からなる組
立用架台を鎖下閣階の柱や楽の鉄骨として利用し、これ
らにコンクリートを打設して建造物を完成させるもので
ある。In this way, as shown in FIG. The members 2:S are fastened together using bolts 24 and adhesive to complete the assembly of this floor. After that, the jack 3 is extended again to become the state shown in Fig. 2 (N), that is, the state shown in Fig. 2 (B) or Fig. 2 (F) in the assembly process of each floor, and these steps are repeated. Then, each floor of the building was finished and jacked up in sequence from the top floor.Finally, the assembly pedestal consisting of 2 trestle pillars and 16 Kuridai prefectures was used as the pillar of the chain lower cabinet floor and the steel frame of the raku. The building will be completed by pouring concrete into these areas.
なお、この実施例においては本発明を建築構造物に応用
した場合を示しているが、本発明はこの他にも鉄塔、煙
突、橋脚等の鋼製またはコンクリート製の建造物の構築
に広く応用することができるものである。Although this embodiment shows the case where the present invention is applied to a building structure, the present invention can also be widely applied to the construction of steel or concrete structures such as steel towers, chimneys, and bridge piers. It is something that can be done.
(発明の効果)
塁上のように本発明によれば、最下層の床の上に立設さ
れた中空状の架台柱の内部に柱部材を配置し、この柱部
材に梁部材、屋1部材または床部材等を緊結して一階層
分の構造体を形成する工程と、この構造体をジヤツキア
ップした後に仮受けする工程とからなり、前記各工程を
繰り返しながら建造物の最上回の部分から下81部分へ
と順次構築してい(ようにしたから、下請の床から2階
の高さまでが作業空間となり、従来の工法のように高所
へ重量物を揚げるための大型クレーンや最上階までの足
場を必要とせず、また支保工も不要として工費の削減が
図れるという効果がある。(Effects of the Invention) According to the present invention, as on the base, a column member is arranged inside a hollow pedestal column erected on the floor of the lowest floor, and a beam member and a roof 1 are attached to this column member. It consists of a step of binding together members or floor materials to form a one-story structure, and a step of jacking up this structure and then temporarily supporting it.While repeating each of the above steps, Since the construction was done sequentially from the bottom 81 sections, the work space was from the subcontractor's floor to the height of the second floor, and as with the conventional construction method, there was a large crane used to lift heavy objects to high places, and the top floor was This has the effect of reducing construction costs as it does not require scaffolding or shoring.
更に、高所での作業を回避できることから、作業の安全
性を高めることができる。Furthermore, since work at heights can be avoided, work safety can be improved.
加えて、各階圓は外壁や床等を仕上げた状態でジヤツキ
アップされるため下層階は天候の影響を受けにくく、こ
の下層階をいわば全天候型の組立作業場として利用する
ことができ、工程管理が確実に行なえると共に、組立用
架台を最下層の構造体あるいはロボツ1−等の自動機器
の作業用足場ないし支台として用いることを可能にして
構築作業のロポツ1〜化、自動化が容易になるという効
果がある。In addition, since each floor is jacked up with the exterior walls and floors finished, the lower floors are less affected by the weather, and this lower floor can be used as an all-weather assembly workshop, ensuring reliable process control. In addition, it is possible to use the assembly stand as a scaffold or support for the lowest structure or automatic equipment such as robots, making it easier to automate construction work. effective.
また、各工程中にクレーン作業が介在するものではない
から、作業の連続性を損なうことなく円滑に施工を行な
うことができ、工期の短縮が図れると共に、多II階の
建造物の構築も容易である等の利点を有する。Additionally, since there is no crane work involved in each process, construction can be carried out smoothly without disrupting the continuity of work, shortening the construction period, and making it easy to construct multi-story buildings. It has the following advantages.
図は本発明の一実施例を示すもので、第1図(イ)は組
立用架台の正面図、同(ロ)は側面図、同(ハ)は同(
イ)のA−へ断面図、同(ニ)は同じくB−B断面図、
同(ホ)は平面図、第2図(イ)〜(ヌ)は本発明にか
かる工法の工程図である。
1・・・・最下閾の床、2・・・・架台柱、3・・・・
ジヤツキ、5,5A、5B・・・・柱部材、18,18
A・・・・梁部材、19・・・・屋根部材、23・・・
・床部材箱1 図 (イ)
(ロ)、2a
=2b
(ハ)
(ニ)
り(The drawings show an embodiment of the present invention, in which FIG. 1 (A) is a front view of the assembly frame, FIG. 1 (B) is a side view, and FIG.
(a) is a sectional view taken along A-, and (d) is also a sectional view taken along B-B.
2(E) is a plan view, and FIGS. 2(A) to 2(N) are process diagrams of the construction method according to the present invention. 1... Bottom threshold floor, 2... Frame pillar, 3...
Jacket, 5, 5A, 5B...Column member, 18, 18
A... Beam member, 19... Roof member, 23...
・Floor material box 1 Figure (a)
(b), 2a = 2b (c) (d) ri(
Claims (1)
部材を配設し、この柱部材に梁部材、屋根部材または床
部材等を緊結して一階層分の構造体を形成する工程と、
この構造体をジャッキアップした後に仮受けする工程と
からなり、前記各工程を繰り返しながら建造物の最上層
の部分から下層部分へと順次構築していくことを特徴と
した建造物の構築工法。A column member is placed inside a hollow pedestal column that is erected on the floor of the lowest floor, and beam members, roof members, floor members, etc. are fastened to this column member to create a one-story structure. a step of forming;
A construction method for a building comprising the steps of jacking up the structure and then temporarily supporting the structure, and building the structure sequentially from the top layer to the lower layer while repeating each of the steps.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11279385A JPS61270432A (en) | 1985-05-24 | 1985-05-24 | Construction of building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11279385A JPS61270432A (en) | 1985-05-24 | 1985-05-24 | Construction of building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61270432A true JPS61270432A (en) | 1986-11-29 |
| JPH0437897B2 JPH0437897B2 (en) | 1992-06-22 |
Family
ID=14595653
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP11279385A Granted JPS61270432A (en) | 1985-05-24 | 1985-05-24 | Construction of building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61270432A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH04357226A (en) * | 1991-02-01 | 1992-12-10 | Kajima Corp | All-weather construction method |
| JP2012184588A (en) * | 2011-03-06 | 2012-09-27 | Kajima Corp | Lifting and lowering method and system of multistoried building |
-
1985
- 1985-05-24 JP JP11279385A patent/JPS61270432A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH04357226A (en) * | 1991-02-01 | 1992-12-10 | Kajima Corp | All-weather construction method |
| JP2012184588A (en) * | 2011-03-06 | 2012-09-27 | Kajima Corp | Lifting and lowering method and system of multistoried building |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0437897B2 (en) | 1992-06-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR19990072014A (en) | Lift-up method for building buildings from above to the ground | |
| CN115306136B (en) | Inclined wall eversion climbing type steel platform construction device and method | |
| CN114508231B (en) | Quick combination construction method for I-steel component | |
| JPS61270432A (en) | Construction of building | |
| JPH1061193A (en) | Method of building steel frame structure and device therefor | |
| CN213597442U (en) | Elevator shaft template operation platform that encorbelments | |
| JP3453181B2 (en) | Working steel stand and method of assembling tower-like structure using the working steel stand | |
| JPH04161566A (en) | Constructing apparatus for large space building | |
| CN114135096A (en) | Ultrahigh structure formwork construction platform and implementation method thereof | |
| JP2696486B2 (en) | Building construction method | |
| CN220522033U (en) | Construction device for connecting superposed beam and superposed member | |
| JPS6237439A (en) | Traveling method | |
| JP2751988B2 (en) | Building construction equipment | |
| JP2946372B2 (en) | Construction method of structure | |
| JP2876991B2 (en) | Steel frame method for high-rise buildings | |
| JPH0533628Y2 (en) | ||
| JP3002054U (en) | Tower crane with multiple main columns as tower mast | |
| JP3224152B2 (en) | Construction method of cross beam in concrete building | |
| JPH0251002B2 (en) | ||
| CN117303242A (en) | Conversion type vertical jacking device and jacking method thereof | |
| CN118517171A (en) | Support structure of outer-expansion overhanging layer formwork and construction method | |
| HK40075842B (en) | Climbing steel platform based apparatus and method for constructing outwardly inclined wall | |
| HK40075842A (en) | Climbing steel platform based apparatus and method for constructing outwardly inclined wall | |
| JP3031511B2 (en) | Construction method of high-rise concrete structure | |
| JPS63167828A (en) | Construction of large-scaled building |