JPS62296009A - Piling work - Google Patents
Piling workInfo
- Publication number
- JPS62296009A JPS62296009A JP13877186A JP13877186A JPS62296009A JP S62296009 A JPS62296009 A JP S62296009A JP 13877186 A JP13877186 A JP 13877186A JP 13877186 A JP13877186 A JP 13877186A JP S62296009 A JPS62296009 A JP S62296009A
- Authority
- JP
- Japan
- Prior art keywords
- casing
- pile
- prefabricated
- spiral auger
- auger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 claims abstract description 36
- 239000004568 cement Substances 0.000 claims abstract description 11
- 239000008267 milk Substances 0.000 claims abstract description 6
- 210000004080 milk Anatomy 0.000 claims abstract description 6
- 235000013336 milk Nutrition 0.000 claims abstract description 6
- 239000002689 soil Substances 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 238000009412 basement excavation Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 10
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 235000012489 doughnuts Nutrition 0.000 description 2
- 238000005755 formation reaction Methods 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 210000000056 organ Anatomy 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【発明の詳細な説明】
3、発明の詳細な説明
(発明の目的)
この発明は、地盤耐力を補強する土木作業として採用さ
れる杭打ら工法に関するもので必って、特に低騒音、低
振動によって既成杭を土中に埋入する新規な施工方法を
提供しようとするものである。[Detailed Description of the Invention] 3. Detailed Description of the Invention (Object of the Invention) This invention relates to a pile driving method employed as a civil engineering work to reinforce the bearing capacity of the ground, and is particularly concerned with a pile driving method that is particularly low noise and low. The aim is to provide a new construction method that embeds prefabricated piles into the soil using vibration.
(従来技術)
都市部での土木作業では、その作業過程で発生する騒音
公害あるいは振動公害、それに土砂、廃液等の廃棄処理
等が大ぎな社会問題として取沙汰される。(Prior Art) In civil engineering work in urban areas, noise pollution or vibration pollution generated during the work process, as well as disposal of earth and sand, waste liquid, etc., are discussed as major social problems.
そのため、最近では、それまでのディーゼルハンマーや
振動ハンマーを使用して既成杭を土中に打込んでいく工
法の採用が難しくなり、リバースサーキュレイション工
法やドーナツオーガニ法、あるいは中掘り打撃工法等が
開発、実用化されている。For this reason, it has recently become difficult to adopt the conventional method of driving prefabricated piles into the soil using a diesel hammer or vibrating hammer, and methods such as the reverse circulation method, donut organ method, or hollow impact method are now being used. Developed and put into practical use.
しかし、リバースサーキュレイション工法やドーナツオ
ーガニ法等では、人聞の水や土砂、おるいはベントナイ
ト溶液の混入されたソイルセメント等の廃棄処理の問題
が解決されておらず、また、中掘り打撃工法では、コン
クリートパイルのような肉厚のある既成杭に不向きであ
るといった難点があり、それらの問題の解決が今後の大
きな課題となっている。However, the reverse circulation method and the donut organic method do not solve the problem of disposal of soil cement mixed with human water, earth and sand, or bentonite solution, and the hollow impact method does not solve the problem. However, there are disadvantages in that it is not suitable for thick prefabricated piles such as concrete piles, and solving these problems will be a major challenge in the future.
この発明は、以上のような情勢に鑑み、鋭意開発、研究
を重ねてきた結果、遂に本にきてその成果を得るに至っ
たものであり、その構成の詳細は、以下において説示す
るとおりのものである。In view of the above-mentioned situation, this invention has been developed and researched diligently, and as a result, it has finally been published as a book.The details of its structure are as explained below. It is something.
(発明の構成)
図面に示されている、その施工工程をモデル的に示すこ
の発明を代表する実施例からも明確に理解されるように
、この発明の杭打ら工法は、次のような施工工程からな
るものである。(Structure of the Invention) As can be clearly understood from the representative embodiment of the present invention shown in the drawings, which shows the construction process as a model, the pile driving method of the present invention has the following features. It consists of the construction process.
[第1工程]
スパイラルオーガ1の回転、掘進と共にケイシング2を
土中に圧入し、その鉛直性を確認しながら該ケイシング
2を土中所定深さまで進める。[First Step] The casing 2 is pressed into the soil as the spiral auger 1 rotates and excavates, and the casing 2 is advanced to a predetermined depth in the soil while checking its verticality.
スパイラルオーガ1の回転、掘進時には、その掘繋ヘッ
ドの先端から圧縮空気を噴出さUて掘繋土の排出を円滑
ならしめ、掘繋効率を高めるよう配慮する。なあ、図中
、11は駆動装置、21はケイシング2の圧入装置を夫
々示している。When the spiral auger 1 rotates and excavates, consideration is given to ejecting compressed air from the tip of the connecting head to smooth the discharge of the connecting soil and improve the connecting efficiency. In the figure, 11 indicates a drive device, and 21 indicates a press-fitting device for the casing 2.
[第2工程]
スパイラルオーガ1先端から根固め用セメントミルク3
を注入すると共に、スパイラルオーガ1を回転しながら
ダイシング2内から完全に引上げた後、ケイシング2を
略30cm前後上昇させる。[Second process] Cement milk for root hardening 3 from the tip of spiral auger 1
At the same time, while rotating the spiral auger 1, the dicing 2 is completely pulled up from inside the dicing 2, and then the casing 2 is raised approximately 30 cm.
根固め用セメントミルク3の注入は、第1工程において
説明した圧縮空気の噴出に利用した噴出部によって実施
されるものであり、その注入量は、ケイシング2によっ
て形成される穴の容積と埋入すべき既成杭4の外形によ
って占められる体積との差に略匹敵する数値を目安にし
て決定される。The injection of the cement milk 3 for root hardening is carried out by the jetting part used for jetting the compressed air as explained in the first step, and the injection amount depends on the volume of the hole formed by the casing 2 and the amount of filling. This is determined based on a value that is approximately equal to the difference between the volume occupied by the external shape of the prefabricated pile 4 and the volume occupied by the external shape of the prefabricated pile 4.
この工程においてケイシング2を略30cmはど最後に
上昇させてみることにより、第4工程におけるケイシン
グ2の引上げの作業性を事前に確認することができる。By finally raising the casing 2 by approximately 30 cm in this step, the workability of lifting the casing 2 in the fourth step can be confirmed in advance.
図中、22はケイシング2の巻上げ装置でおる。In the figure, 22 is a hoisting device for the casing 2.
[第3工程]
ダイシング2内にコンクリート抗または!A管杭、H鋼
抗等既成杭4を吊上げ、ダイシング2内に静かに挿入し
て所定深さまで降下させた後、ダイシング2上端に支持
させた仮止め具5で一時的に該既成杭4の降下を停止さ
せ、吊上げ機6から既成杭4の柱頭を解除した上、先の
仮止め具5を操作して一気に該既成杭4をダイシング2
内に沈設させる。[Third step] Concrete or! inside dicing 2! A prefabricated pile 4 such as an A pipe pile or an H steel column is lifted up, gently inserted into the dicing 2 and lowered to a predetermined depth, and then temporarily secured to the prefabricated pile 4 using a temporary fixing device 5 supported on the upper end of the dicing 2. After stopping the descent of the pre-fabricated pile 4 and releasing the column head of the pre-fabricated pile 4 from the lifting machine 6, the pre-fabricated pile 4 is diced 2 at once by operating the temporary fixing device 5 mentioned above.
sink inside.
第2工程からこの第3工程に移行する段階で、スパイラ
ルオーガ1を装着した駆動装置11部分は、杭芯から外
れるよう旋回移動させ、既成杭4の挿入作業に支障を来
たさないよう作業段取りがなされ、その後この第3工程
が実施されるものである。At the stage of transitioning from the second process to this third process, the driving device 11 portion with the spiral auger 1 attached is rotated so as to be removed from the pile core, so as not to interfere with the insertion work of the prefabricated pile 4. Preparations are made, and then this third step is carried out.
既成杭4の吊り上げ機6としては、通常補助クレーンを
備えれば充分であり、適宜クランプやチャック等台付け
61によって既成杭4の柱頭を掴み、吊上げることにな
る。As the lifting machine 6 for the existing pile 4, it is usually sufficient to have an auxiliary crane, and the capital of the existing pile 4 is grasped and lifted using a clamp, chuck, etc., as appropriate.
第1図第3工程図(イ)では、該吊り上げ機6によって
既成杭4を吊り上げた後、ケーシング2内に挿入、降下
する段階の1態様を示し、同図(ロ)では、仮止め具5
を使用して既成杭4を一時的に停止させた状態を示して
いる。1. The third process diagram (A) in FIG. 1 shows one aspect of the stage in which the prefabricated pile 4 is lifted up by the lifting machine 6, and then inserted into the casing 2 and lowered. 5
This shows a state in which the prefabricated pile 4 is temporarily stopped by using the.
この仮止め具5は、例えば第2国事面図、第3図縦断面
図に示されているように、ケイシング2に対して既成杭
4が中心部に位置するよう調整するセンター調整金具5
1.51・・・・・・の中の一つに組込まれて構成され
、挺式に回動自在であり、既成杭4の自重による下向き
の力が作用することにより、その先端噛合い部52が既
成杭4の側面に当接してそのストロークを伸ばすように
回動し、その結果、他のセンター調整金具51.51と
この噛合い部52とで既成杭4の周壁を圧接する形とな
って、既成杭4の降下を一時的に停止させることができ
、逆に、この一時的な停止は、ハンドル部分を下方に押
し下げることにより噛合い部52のストロークが短くな
って圧接状態が解放され、既成杭4はその自重により自
然に降下するようにした構造のもの等によって構成され
る。This temporary fixing tool 5 is a center adjustment fitting 5 that adjusts the prefabricated pile 4 to be located in the center with respect to the casing 2, as shown in the second national affairs map and the vertical cross-sectional view in FIG. 3, for example.
1.51... It is constructed by being incorporated into one of the piles, and is rotatable in a screw-type manner, and when the downward force due to the weight of the existing pile 4 is applied, the end engagement part 52 rotates so as to abut against the side surface of the prefabricated pile 4 and extend its stroke, and as a result, the peripheral wall of the prefabricated pile 4 is brought into pressure contact with the other center adjustment fittings 51 and 51 and this meshing portion 52. As a result, the descent of the pre-formed pile 4 can be temporarily stopped.Conversely, this temporary stop can be achieved by pushing down the handle part to shorten the stroke of the engaging part 52 and releasing the pressed state. The prefabricated pile 4 is constructed so that it naturally descends due to its own weight.
[第4工程]
ダイシング2内に治まった既成杭4の柱頭をスパイラル
オーガ1の先端で押えた上、ケイシング2を静かに引上
げる。[Fourth Step] The capital of the prefabricated pile 4 settled in the dicing 2 is pressed down with the tip of the spiral auger 1, and then the casing 2 is gently pulled up.
スパイラルオーガ1は、先の第3工程において既成杭4
を挿入するために杭芯から外れるよう旋回移動させてお
いたものを、再度杭芯まで戻し、その掘Sヘッドが既成
杭4の柱頭に当たるまで下げ、この工程に入るものであ
る。The spiral auger 1 is attached to the prefabricated pile 4 in the third step.
In order to insert the pile, the pile has been pivoted so as to be removed from the pile core, and is then returned to the pile core and lowered until its digging S head hits the capital of the existing pile 4, and this process begins.
ケイシング2を引上げた後、セメントミルク3が地表よ
り下がりすぎている場合には、改めて既成杭4の周囲に
適宜足のセメントミルク3を補充することがある。After the casing 2 is pulled up, if the cement milk 3 is too low below the ground surface, additional cement milk 3 may be replenished around the existing pile 4 as needed.
以上、第1工程ないし第4工程を円滑に遂行することに
よってこの発明の杭打ら工法が完了するものである。As described above, the pile driving method of the present invention is completed by smoothly performing the first to fourth steps.
(作用効果)
上記のような工程によって実現されるこの発明の杭打ち
工法は、次のような特徴を有するものとなる。(Operation and Effect) The pile driving method of the present invention realized through the steps described above has the following characteristics.
まず第一に、所定深度にIi!lが完了した後において
、従来の如くケイシング2をスパイラルオーガ1と共に
引上げてしまうのではなく、ケイシング2だけをそのま
ま据置いた状態で既成杭4を挿入させる作業工程を採用
していることから、崩壊性の激しい地層でも流水性の大
ぎい地層の現場においても、杭穴周壁の損傷、崩!要の
心配なく円滑な作業が実施できるという特徴点を挙げる
ことができる。First of all, at a given depth Ii! 1 is completed, the casing 2 is not pulled up together with the spiral auger 1 as in the conventional method, but the work process is to insert the prefabricated pile 4 with only the casing 2 left in place, which prevents collapse. Damage and collapse of the surrounding wall of the pile hole can occur even in sites with highly volatile geological formations or large geological formations with flowing water! One of its unique features is that it allows for smooth work to be carried out without worrying about problems.
したがって、従前までの工法がそうであったように、杭
穴周壁の崩壊を防止するために杭穴全体にソイルセメン
トを充填したり、高圧水や空気を送り込む必要が全くな
くなるから、それらを実施するに際して必要となる各種
設備が省略できて極めて経済的、且つ、作業性に冨むも
のになる外、特筆すべきことは、既成杭の挿入時に排斥
される大量のソイルセメントあるいは水の後処理問題が
全くなくなり、公害を引起こすことがなくなるというこ
とである。Therefore, there is no need to fill the entire pile hole with soil cement or to pump high-pressure water or air to prevent the wall around the pile hole from collapsing, as was the case with previous construction methods. In addition to being extremely economical and highly workable as various equipment required for this process can be omitted, what should be noted is the problem of post-treatment of the large amount of soil cement or water that is rejected when inserting prefabricated piles. This means that there will be no pollution at all, and no pollution will be caused.
第二の特徴は、杭穴周壁を保護するケイシング2が繰返
し使用されることから、従前までの現場毎に使い捨てと
なってしまうソイルセメント、水、あるいはシートパイ
ルのような不経済なものがなく、より一層経済的なもの
とすることができるということである。The second feature is that because the casing 2 that protects the surrounding wall of the pile hole is used repeatedly, there is no need for uneconomical materials such as soil cement, water, or sheet pile, which used to be disposable at each site. This means that it can be made even more economical.
第三の特徴は、ケイシング2によって完全に杭穴周壁の
保護が実現され、どのようなタイプの既成杭4でも挿入
可能となることから、設計管理上極めて融通性のめる杭
打ちが可能となること。The third feature is that the casing 2 completely protects the surrounding wall of the pile hole, and any type of prefabricated pile 4 can be inserted, making pile driving extremely flexible in terms of design management. .
第四の特徴は、各工程とも、所謂公害源となる程の騒音
、撮動を発生することがなく、都市部の杭打ち工法に適
っているということ。The fourth feature is that each process does not generate enough noise or photography to become a source of pollution, making it suitable for piling construction in urban areas.
第五の特徴として、仮止め具5を採用した施工工程等既
成杭4の取扱い面において改良が加えられ、他の従前ま
での杭打ら工法に比べて作業性、安全性、経済性とも秀
れた杭打らの実現が可能となるということ。The fifth feature is that improvements have been made in the handling of pre-fabricated piles 4, such as the construction process using temporary fasteners 5, which are superior in terms of workability, safety, and economy compared to other conventional pile driving methods. This means that it will be possible to drive piles in a manner that is easy to achieve.
等々、夫々この発明の特徴として列挙することができる
。etc., can be enumerated as features of this invention.
以上の如く、この発明の杭打も工法は、その特徴ある工
程によつ−Cそれまでのこの取杭打ら工法に比較し、極
めて右利な杭打ち施工を実施することができるものとな
っており、土木施工業者が受ける恩恵は勿論のこと、社
会的に与える影響も大きく、各方面から高い評価を受り
るものと予想される。As mentioned above, the pile driving method of the present invention, due to its characteristic process, can carry out extremely advantageous pile driving construction compared to the previous pile driving method. Not only will this benefit civil engineering contractors, but it will also have a significant impact on society, and is expected to receive high praise from all quarters.
図面は、この発明を代表する実施例に基づくものであり
、第1図は、各工程における中心的な態様によりその施
工工程を示した工程図、第2図は、その施工工程で採用
される仮止め具の使用状態を示した平面図、第3図は、
同縦断面図である。
1・・・スパイラルオーガ、11・・・同駆動装置、2
・・・ケイシング、21・・・同圧入装置、22・・・
同巻上げ装置、3・・・ソイルセメント、4・・・既成
杭、5・・・仮止め具、51・・・同センター調整装置
、52・・・同噛合い部、6・・・吊り上げ殿、61・
・・向合付け、7・・・地盤。
第 1 図
第 第 第 第
−一四The drawings are based on representative examples of this invention, and Figure 1 is a process diagram showing the construction process in terms of the central aspects of each process, and Figure 2 is a process diagram showing the construction process adopted in the construction process. The plan view, Figure 3, showing the state of use of the temporary fastener is as follows:
It is a longitudinal sectional view of the same. 1...Spiral auger, 11...Spiral auger, 2
...Casing, 21...Press-fitting device, 22...
The hoisting device, 3... Soil cement, 4... Ready-made pile, 5... Temporary fastener, 51... The center adjustment device, 52... The meshing part, 6... Lifting hole , 61・
... facing, 7... ground. Figure 1 No. 1-14
Claims (1)
入する杭打ち工法。 第1工程 スパイラルオーガの掘進と共にケイシングを土中に圧入
し、その鉛直性を確認しながら該ケイシングを土中所定
深さまで進める。 第2工程 スパイラルオーガ先端から根固め用セメントミルクを注
入すると共に、スパイラルオーガを回転しながらケイシ
ング内から完全に引上げた後、ケイシングを略30cm
前後上昇させる。 第3工程 ケイシング内にコンクリート杭または鋼管杭、H鋼抗等
既成杭を吊上げ、ケイシング内に静かに挿入して所定深
さまで降下させた後、ケイシング上端に支持させた仮止
め具で一時的に該既成杭の降下を停止させ、吊上げ機か
ら既成杭柱頭を解除した上、先の仮止め具を操作して一
気に該既成杭をケイシング内に沈設させる。 第4工程 ケイシング内に納まった既成杭の柱頭をスパイラルオー
ガ先端で押えた上、ケイシングを静かに引上げる。[Claims] A pile driving method in which prefabricated piles are buried underground in the following first to fourth steps. First step: As the spiral auger excavates, the casing is pressed into the soil, and the casing is advanced to a predetermined depth in the soil while checking its verticality. 2nd step Inject the cement milk for root hardening from the tip of the spiral auger and completely pull it up from inside the casing while rotating the spiral auger, then lift the casing to about 30cm.
Raise it back and forth. 3rd step: Lift a pre-fabricated pile such as a concrete pile, steel pipe pile, or H-steel pile into the casing, insert it gently into the casing, lower it to a predetermined depth, and temporarily secure it with a temporary fixing device supported on the upper end of the casing. After stopping the descent of the prefabricated pile and releasing the prefabricated pile capital from the lifting machine, the prefabricated pile is sunk into the casing at once by operating the previous temporary fixing device. Fourth step: After pressing the column head of the prefabricated pile housed in the casing with the tip of the spiral auger, the casing is gently pulled up.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13877186A JPS62296009A (en) | 1986-06-12 | 1986-06-12 | Piling work |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13877186A JPS62296009A (en) | 1986-06-12 | 1986-06-12 | Piling work |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPS62296009A true JPS62296009A (en) | 1987-12-23 |
Family
ID=15229812
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13877186A Pending JPS62296009A (en) | 1986-06-12 | 1986-06-12 | Piling work |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS62296009A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH03257215A (en) * | 1990-03-07 | 1991-11-15 | Matsuzawa Kiko:Kk | Pile constructing method |
| WO2011105703A3 (en) * | 2010-02-26 | 2011-10-20 | Song Gi-Yong | Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction |
| CN104110033A (en) * | 2014-07-29 | 2014-10-22 | 福建永强岩土股份有限公司 | Hollow long spiral thin-wall cast-in-place pile casing |
-
1986
- 1986-06-12 JP JP13877186A patent/JPS62296009A/en active Pending
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH03257215A (en) * | 1990-03-07 | 1991-11-15 | Matsuzawa Kiko:Kk | Pile constructing method |
| WO2011105703A3 (en) * | 2010-02-26 | 2011-10-20 | Song Gi-Yong | Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction |
| CN104110033A (en) * | 2014-07-29 | 2014-10-22 | 福建永强岩土股份有限公司 | Hollow long spiral thin-wall cast-in-place pile casing |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP3839149A1 (en) | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor | |
| KR100964796B1 (en) | Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction | |
| CN105442605B (en) | Extract PHC and be reused in deep foundation pit supporting construction method | |
| CN110273413A (en) | A kind of efficient construction method of prefabricated pile | |
| JP2003147782A (en) | Foundation structure for constructing a new building on existing basement and construction method | |
| JPS5985028A (en) | Steel pipe pile and laying work thereof | |
| KR100996444B1 (en) | Improved micro pile construction method, uneven section pipe of improved micro pile structure and improved micro pile structure | |
| JPH0220720A (en) | Underground construction method by muddy water excavation | |
| JP4011209B2 (en) | Construction method of shaft | |
| JP2000130066A (en) | Shaft construction method | |
| JP4425073B2 (en) | Cast-in-place concrete construction method | |
| JPH0464618A (en) | Pit excavation work method | |
| JP2874906B2 (en) | Shaft construction method | |
| JPH03257215A (en) | Pile constructing method | |
| JPH0610339A (en) | Reinforced concrete mountain retaining wall and its construction method | |
| JPH0525828A (en) | Floating prevention structure for grounded floor | |
| JPH08209687A (en) | Partial casing pile method | |
| JPS61221413A (en) | Skew pile driving work | |
| JP2838019B2 (en) | Caisson blade framing method | |
| JPS6192235A (en) | Fixing of embedded pipe | |
| JP2001073367A (en) | Burial method of steel pipe pile | |
| JP2001011874A (en) | Construction method of straight pillar using ready-made pile | |
| CN121654115A (en) | Combined supporting method for high-steep side slopes of mountain terrain | |
| JPS58204222A (en) | Pile foundation work | |
| CN114525779A (en) | Auxiliary structure for concrete pouring of onshore pile foundation and use method of auxiliary structure |