JPS6290443A - Chipping work for head of in-situ pile - Google Patents
Chipping work for head of in-situ pileInfo
- Publication number
- JPS6290443A JPS6290443A JP22791585A JP22791585A JPS6290443A JP S6290443 A JPS6290443 A JP S6290443A JP 22791585 A JP22791585 A JP 22791585A JP 22791585 A JP22791585 A JP 22791585A JP S6290443 A JPS6290443 A JP S6290443A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- concrete
- head
- main reinforcing
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は場所打杭の抗頭を能率的に研り取るための工法
に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for efficiently sharpening the head of a cast-in-place pile.
建築物の基礎として場所打杭を施工する場合、掘削孔内
に孔壁の崩壊を防ぐためのヘントナイト溶液を充填した
状態でコンクリートを打設するため、コンクリートの硬
化後における杭頭部分は、ベントナイト溶液の混入によ
り強度の不充分な不適切な状態となっており、一般的に
は杭の築造後にこの杭頭部を研り取る作業を行う。When constructing cast-in-place piles as the foundation of a building, the concrete is filled with hentonite solution in the excavated hole to prevent the wall from collapsing, so after the concrete hardens, the pile cap is filled with bentonite. Due to the solution being mixed in, the strength of the pile is inadequate, and the head of the pile is generally ground down after the pile is constructed.
従来におけるこのような杭頭斫り方法としては、ブレー
カ−によってコンクリートを破砕して行く方法が古くか
ら知られているが、最近ではプライスターなどの膨張材
を使用してコンクリートにクランクを発生さセ、これを
ブレーカ−で小割する方法によって行われることもある
。The conventional method of crushing the pile caps has been to use a breaker to crush the concrete, but recently, the method of crushing the concrete using an expanding material such as plyster has become more popular. This can also be done by dividing it into small pieces using a breaker.
しかしながらこの杭頭の研り作業は、コンクリートが内
部の鉄筋と付着しているために、ブレーカ−などの手段
によりかなりの大きさに及ぶコンクリート塊を少しづつ
破壊していがなければならず、多大な時間と労力とを必
要とする外、騒音も大きいという問題点を有している。However, since the concrete is attached to the internal reinforcing steel, grinding of the pile cap requires breaking down a large chunk of concrete little by little using a breaker or other means. This method requires a lot of time and effort, and also has the problem of being noisy.
c問題点を解決するための手段〕
本発明は、前記のような従来の抗頭部り作業における問
題点を解決し、杭頭を所定の位置において能率よく研り
取れるような新しい工法を提供しようとするものであり
、具体的には、抗頭の断り高さに位置する夫々の主鉄筋
外周に、予じめコンクリートとの付着を防ぐグラスウー
ル等の被膜材を被覆した状態で場所打杭を築造し、コン
クリ−1・の硬化後前記被膜+4の下端部が位置する杭
頭部分の外周から杭内半径方向に向υて削岩機により複
数本の削孔を穿設し、次いでこれらの削孔内に樹形油圧
パッカーを挿入して各削孔を割裂することにより杭頭部
コンクリートを水平に破断し、しかるのら破断抗頭部を
各主鉄筋に沿って吊上げ抜去することを特徴としたもの
である。c Means for Solving the Problems] The present invention solves the problems in the conventional pile head pile work as described above, and provides a new method that can efficiently sharpen the pile head at a predetermined position. Specifically, the outer periphery of each main reinforcing bar located at the cutting height of the shaft is coated with a coating material such as glass wool to prevent adhesion to concrete, and then the piles are cast in place. After concrete 1 has hardened, multiple holes are drilled with a rock drill in the radial direction inside the pile from the outer periphery of the pile cap where the lower end of the coating +4 is located. By inserting a tree-shaped hydraulic packer into the drilled holes and splitting each drilled hole, the concrete pile head is fractured horizontally, and the fracture head is then lifted up and removed along each main reinforcing bar. This is a characteristic feature.
この発明においては、杭頭の研り高さに位置する各主鉄
筋の外周に予しめコンクリートとの付着を防くグラスウ
ール等の被膜材を被覆させて場所打杭を築造するので、
この被膜材で被覆された主鉄筋部分は、コンクリートの
硬化後においても実質的にコンクリ−1・とは11着し
ないこととなり、この被膜材下端部が位置する抗頭コン
クリート部分に水平の破断面を形成すれば、各主鉄筋が
全て曲りのない垂直状態である限り、破断した杭頭部コ
ンクリート部分を主鉄筋に沿って」一方に吊−)−げ抜
去することができる。In this invention, cast-in-place piles are constructed by coating the outer periphery of each main reinforcing bar located at the height of the pile head with a coating material such as glass wool to prevent adhesion to concrete.
The main reinforcing bars covered with this coating material will not substantially adhere to the concrete even after the concrete has hardened, and the fracture surface will be horizontal to the concrete head section where the lower end of this coating material is located. If this is done, as long as all the main reinforcing bars are in a vertical state without bending, the fractured concrete part of the pile head can be lifted and removed in one direction along the main reinforcing bars.
次に本発明に係る抗頭部り工法を図面に示す実施例によ
り説明すれば、まず第1図に示すよ・うtこ、掘削孔l
の掘削終了後、該孔内に挿入する鉄筋篭2の」一端部に
おける抗頭部り高さ位置にある全ての主鉄筋3の外周に
、グラスウール、或いは塩化ビニールなどの合成樹脂製
チューブもしくはテープからなる被膜材4を予じめ挿合
もしくは巻付けて、後に打設されるコンクリートとの?
=I着を防止させておく。Next, the head-height construction method according to the present invention will be explained with reference to an embodiment shown in the drawings. First, as shown in FIG.
After the completion of excavation, attach glass wool, synthetic resin tubes such as vinyl chloride, or tape to the outer periphery of all the main reinforcing bars 3 located at the height of the head at one end of the reinforcing bar cage 2 to be inserted into the hole. The coating material 4 consisting of is inserted or wrapped in advance, and then mixed with the concrete that will be placed later.
= Prevent I-wearing.
その際、各主鉄筋3の十端部は、端面の縁切りを確実に
行うと共に、曲りを修正して全ての主鉄筋3上端部が曲
りのない平行な状態に前処理を施しておく。At this time, the ten end portions of each main reinforcing bar 3 are pretreated to ensure that the end face is edged and to correct any bends so that the upper ends of all the main reinforcing bars 3 are in a parallel state without bending.
前記被膜材4を被膜する長さは、杭築造個所の土質など
の条件に応じて予測される研り高さを判断して、所定の
長さに設定される。The length of the coating material 4 is set to a predetermined length by determining the expected grinding height depending on conditions such as the soil quality of the pile construction site.
第2図のように孔内にコンクリート5が打設されてこれ
が硬化したのち、第3図に示すように前記被膜材4の下
端部が位置する付近の杭5A側面から削岩機6を用いて
杭内半径方向に向けて複数個の削孔7を穿設する。この
削孔7は杭径1500Φのものでは3乃至4個所程度、
2000Φのものでは6個所程度設ければよい。また、
削孔7は被膜材4の設けられている部分であれば、どの
位置でもよいが、被膜材4の下端直下部分であってもよ
い。After concrete 5 is poured into the hole and hardened as shown in FIG. 2, a rock drill 6 is used from the side of the pile 5A near where the lower end of the coating material 4 is located, as shown in FIG. A plurality of holes 7 are drilled in the radial direction inside the pile. This drilling hole 7 is about 3 to 4 holes for a pile with a diameter of 1500Φ.
For a 2000Φ type, it is sufficient to provide about 6 locations. Also,
The hole 7 may be formed at any position as long as the coating material 4 is provided, but it may be located directly below the lower end of the coating material 4.
次に第4図に示すように前記の各削孔7内に樹形油圧バ
ッカー8を挿入し、油圧駆動による楔作用により削孔7
を割裂させる。このパッカー8は第6a図のように一対
の加圧片8bの間に喫8aが挟着された構造のもので、
同す図のように油圧によって喫8aを前進させると両側
の加圧片8bが拡関し、これにより削孔7部分が割裂し
てこの部分から抗頭部ごIンクリート5Bが水平に被断
される。Next, as shown in FIG. 4, a tree-shaped hydraulic backer 8 is inserted into each of the drilled holes 7, and the drilled holes 7 are
split into pieces. This packer 8 has a structure in which a gasket 8a is sandwiched between a pair of pressure pieces 8b as shown in Fig. 6a.
As shown in the same figure, when the shaft 8a is advanced by hydraulic pressure, the pressurizing pieces 8b on both sides expand, thereby splitting the drilled hole 7 part and cutting the counter head concrete 5B horizontally from this part. Ru.
次いで前記二lンクリート5の打設時に予じめ抗頭上端
コンクリート内に埋込まれるように取付けておいた吊環
9を利用して、第5図のように抗頭部コンクリ−)5B
を各主鉄筋3に沿ってに方へ吊上げる。この吊I−げ力
を作用させると、各主鉄筋3とコンクリート5Bとは被
膜材4によって分離され、実質的に付着力が作用してい
ない状態にあるので、被膜材4が主鉄筋3から剥離しな
がらコンクリート5Bが各主鉄筋3に沿って引にげられ
、これにより所り作業が終了する。Next, when pouring the 2-liter concrete 5, the suspension ring 9, which has been installed in advance so as to be embedded in the head concrete, is used to lower the head concrete 5B as shown in Fig. 5.
along each main reinforcing bar 3. When this lifting force is applied, each main reinforcing bar 3 and the concrete 5B are separated by the covering material 4, and since no adhesive force is substantially acting, the covering material 4 is separated from the main reinforcing bar 3. The concrete 5B is pulled along each main reinforcing bar 3 while being peeled off, thereby completing the placement work.
〔効果〕
本発明においては上記のように、コンクリートの打設前
に各主鉄筋3の上端部にグラスウールのような被膜材4
を被覆して、コンクリートが一体に付着しないようにし
ておくことと、各主鉄筋3の曲りを修正しておくという
前処理を必要とするが、このような前処理工程を含めた
としても、主鉄筋とコンクリートとが付着していないの
で、コンクリート部分の破壊としては水平な削孔7を設
けることと油圧バッカーによる破断という簡単な処理で
足りることとなり、従来のようにコンクリートをブレー
カ−によって小割りに破砕していく骨の折れる作業を全
く必要としないので、抗頭研り作業の大幅な能率向1と
労費、二[期の節減を期待することができる。[Effect] As described above, in the present invention, a coating material 4 such as glass wool is applied to the upper end of each main reinforcing bar 3 before concrete is poured.
It is necessary to pre-process the concrete to prevent it from adhering to the main reinforcing bars 3 and to correct the bending of each main reinforcing bar 3, but even if such pre-processing steps are included, Since the main reinforcing bars and concrete are not attached, it is sufficient to simply drill a horizontal hole 7 and break the concrete using a hydraulic backer. Since there is no need for the painstaking work of crushing the grain at all, it is possible to expect a significant efficiency improvement in the head grinding work, as well as a reduction in labor costs and time.
第1図乃至第5図はいずれも本発明に係る杭頭研り作業
の工程順を示す断面図、第6図は本工法において使用す
る投影油圧バッカーの構成を示す拡大断面図である。
1:掘削孔、 2:鉄筋篭、 3:主鉄筋、4:被膜材
、 5:コンクリート、7:削孔、8:投影油圧パッ
カー、8:吊環。1 to 5 are cross-sectional views showing the sequence of steps in the pile head grinding work according to the present invention, and FIG. 6 is an enlarged cross-sectional view showing the configuration of a projected hydraulic backer used in this construction method. 1: Drilling hole, 2: Rebar cage, 3: Main reinforcing bar, 4: Coating material, 5: Concrete, 7: Drilling hole, 8: Projection hydraulic packer, 8: Hanging ring.
Claims (1)
じめコンクリートとの付着を防ぐグラスウール等の被膜
材を被覆した状態で場所打杭を築造し、コンクリートの
硬化後前記被膜材の下端部が位置する杭頭部分の外周か
ら杭内半径方向に向けて削岩機により複数本の削孔を穿
設し、次いでこれらの削孔内に楔形油圧パッカーを挿入
して各削孔を割裂することにより、杭頭部コンクリート
を水平に破断し、しかるのち破断杭頭部を各主鉄筋に沿
って吊上げ抜去することを特徴とした場所打杭の杭頭斫
り工法。(1) Construct cast-in-place piles with the outer periphery of each main reinforcing bar located at the height of the pile cap covered in advance with a coating material such as glass wool to prevent adhesion to concrete, and after the concrete hardens, A rock drill is used to drill multiple holes from the outer periphery of the pile cap where the lower end of the coating material is located in the radial direction inside the pile, and then a wedge-shaped hydraulic packer is inserted into each of these holes. A pile head drilling method for cast-in-place piles, which is characterized in that the concrete pile head is fractured horizontally by splitting the drilled hole, and then the fractured pile head is lifted up and removed along each main reinforcing bar.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22791585A JPS6290443A (en) | 1985-10-15 | 1985-10-15 | Chipping work for head of in-situ pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22791585A JPS6290443A (en) | 1985-10-15 | 1985-10-15 | Chipping work for head of in-situ pile |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPS6290443A true JPS6290443A (en) | 1987-04-24 |
Family
ID=16868288
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP22791585A Pending JPS6290443A (en) | 1985-10-15 | 1985-10-15 | Chipping work for head of in-situ pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6290443A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62254531A (en) * | 1986-04-21 | 1987-11-06 | エイ・ティ・アンド・ティ・コーポレーション | Method and apparatus for generating light pulse flow |
-
1985
- 1985-10-15 JP JP22791585A patent/JPS6290443A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62254531A (en) * | 1986-04-21 | 1987-11-06 | エイ・ティ・アンド・ティ・コーポレーション | Method and apparatus for generating light pulse flow |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108867690B (en) | Reverse construction method for pile plate retaining wall of large foundation pit | |
| JP2000303467A (en) | Self-sustaining earth retaining wall and self-sustaining earth retaining wall construction method | |
| EP0136355A1 (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
| JPH1150418A (en) | Temporary receiving method of bridge girder and mount that can be used for it | |
| JPS6290443A (en) | Chipping work for head of in-situ pile | |
| US20030049079A1 (en) | Method of forming enlarged pile heads | |
| JPS6354093B2 (en) | ||
| JPS6256296B2 (en) | ||
| JP3281554B2 (en) | How to rebuild underground structures | |
| JPS63308113A (en) | Pile head cutting method for cast-in-place piles | |
| CN113389552A (en) | Dead angle area construction method for small-section ultra-deep vertical shaft of hard plastic rock stratum | |
| JP2564465B2 (en) | Ready-made pile burying method | |
| RU2105100C1 (en) | Method for strengthening of strip foundations | |
| JPH0960311A (en) | Lift-up dismantling method | |
| JPH02274992A (en) | Method and device for excavating pile hole | |
| KR200210069Y1 (en) | Removal nailing device in excavation work | |
| JPS6192214A (en) | Method of pulling out pile | |
| TWI748533B (en) | Construction method of high-pressure pouring type spiral pile | |
| JPH02240395A (en) | Construction of shaft | |
| JP3457440B2 (en) | Building construction method using earth anchor | |
| JP2000145354A (en) | Deep foundation excavation method in bedrock | |
| JP2881001B1 (en) | Earth retaining wall construction method for cutting land mountain | |
| JP2838019B2 (en) | Caisson blade framing method | |
| JPH07331666A (en) | Slope cutting method | |
| JP2001011874A (en) | Construction method for structural stud using precast pile |