JPS63147100A - An integrated construction method for shield tunnels that utilizes the primary lining - Google Patents

An integrated construction method for shield tunnels that utilizes the primary lining

Info

Publication number
JPS63147100A
JPS63147100A JP61293274A JP29327486A JPS63147100A JP S63147100 A JPS63147100 A JP S63147100A JP 61293274 A JP61293274 A JP 61293274A JP 29327486 A JP29327486 A JP 29327486A JP S63147100 A JPS63147100 A JP S63147100A
Authority
JP
Japan
Prior art keywords
lining
inner formwork
existing
gable
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61293274A
Other languages
Japanese (ja)
Other versions
JPH0480198B2 (en
Inventor
光政 岡村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP61293274A priority Critical patent/JPS63147100A/en
Publication of JPS63147100A publication Critical patent/JPS63147100A/en
Publication of JPH0480198B2 publication Critical patent/JPH0480198B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 シールドテール内で一次覆工用のセグメントリングを組
み立て後、放射状に摺動可能な部材を両端部に有した内
型枠リングを組み立て、二次覆工材を打設し、−次二次
覆工の同時施工を可能にした一次覆工を活かしたシール
ドトンネルの一体構築工法に関する発明である。
[Detailed Description of the Invention] [Industrial Application Field] After assembling the segment ring for the primary lining within the shield tail, the inner formwork ring having radially slidable members at both ends is assembled, and the second This invention relates to a method for integrally constructing a shield tunnel that takes advantage of the primary lining, which enables simultaneous construction of the secondary lining by placing the secondary lining material.

〔従来の技術〕[Conventional technology]

従来は一次覆工のみによるトンネルが貫通したのち、二
次覆工を施工するため工期が長(なり、−法覆工だけで
地山荷重を支持する期間が比較的長期にわたることと、
その間の荷重変化が明確でないため、−法覆工は永久構
造物として設計せざるを得す、二次覆工が強度上考慮さ
れないため極めて不経済な覆工となっている等の欠点を
有していたものである。
Conventionally, after a tunnel with only a primary lining was penetrated, a secondary lining was constructed, so the construction period was long.
Since the load change during that time is not clear, the -method lining has to be designed as a permanent structure, and the secondary lining is not taken into account in terms of strength, making it an extremely uneconomical lining. That's what I was doing.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

−一次工完了後、二次覆工することによる工期の長期化
という問題点、−法覆工を永久構造物とするための不経
済性という問題点を解決しようとする発明である。
This invention attempts to solve the problems of - prolonging the construction period due to secondary lining after the completion of the primary construction, and - uneconomical problem of making the primary lining a permanent structure.

〔問題点を解決するための手段〕[Means for solving problems]

既設の一次覆エセグメントの前部に一次覆エセグメント
を組み立て固定すると共に一次覆エセグメントの外側に
裏込め材を充填し、既設の内型枠の前部に既設の内型枠
に対し内型枠を千鳥状に組み立て、既設の内型枠の前部
の妻枠と連結した内型枠の後部の妻枠を外方向へスライ
ドした後、ひとつ後の妻枠リングを内方向へ縮め、前記
拡径した妻枠、−法覆エセグメント、既設二次覆工及び
内型枠で囲まれた覆工材注入空間に覆工材を注入し、同
時にシールドマシンを一工程分掘進し、掘進完了後シー
ルドジヤツキを縮めテールにセグメント等を組み立てる
空間を形成して、既設の一次覆エセグメントの前部に一
次覆エセグメントを組み立てる作業を順次くり返し行う
ことにより問題点を解決したものである。
Assemble and fix the primary covering segment to the front of the existing primary covering segment, fill the outside of the primary covering segment with backfill material, and fill the front part of the existing inner formwork with the inner formwork. Assemble the formwork in a staggered manner, slide the rear gable of the inner formwork that is connected to the front gable of the existing inner formwork outward, and then contract the next gable ring inward. The lining material is injected into the lining material injection space surrounded by the expanded gable frame, the overlay segment, the existing secondary lining, and the inner formwork, and at the same time, the shield machine is used to excavate one step, and the excavation is continued. After completion, the problem was solved by retracting the shield jack to create a space in the tail for assembling segments, etc., and then repeating the process of assembling the primary covering segment in front of the existing primary covering segment. .

〔作 用〕[For production]

既設の一次項エセグメントの前部−法覆エセグメントを
組み立て固定し、既設の内型枠の前部に既設の内型枠に
対し内型枠を千鳥状に組み立て、既設の内型枠の前部の
妻枠と連結した内型枠の後部の妻枠を外方向へスライド
した後、ひとつ後の妻枠リングを内方向へ縮め、前記拡
径した妻枠、−法覆エセグメント、既設二次覆工及び内
型枠で囲まれた覆工材注入空間に覆工材を注入し、同時
にシールドマシンを一工程分掘進し、掘進中或いは掘進
後−法覆エセグメントの背面のテールボイドに裏込め材
を充填し掘進完了後シールドジヤツキを縮めテールにセ
グメント等を組み立てる空間を形成して、既設の一次覆
エセグメントの前部に一次覆エセグメントを組み立てる
作業を順次くり返し行うことにより、−法覆工、二次覆
工の同時施工を可能にしたことにより、工期を短縮でき
、初期の地山荷重の作用時点から、雨覆工が合成断面と
し機能することにより極めて経済的な断面を実現するこ
とができる。
Assemble and fix the front part of the existing primary segment and the cover segment, and assemble the inner formwork in a staggered manner to the front part of the existing inner formwork. After sliding the rear gable of the inner form connected to the front gable outward, the next gable ring is contracted inward, and the diameter of the gable has been expanded. Inject the lining material into the lining material injection space surrounded by the secondary lining and inner formwork, and at the same time excavate one step with the shield machine, during or after excavation - into the tail void on the back of the lining segment. After filling with backfilling material and completing excavation, the shield jack is retracted to form a space in which to assemble segments, etc. in the tail, and the work of assembling the primary covering segment in front of the existing primary covering segment is repeated in sequence. - By making it possible to construct the primary lining and secondary lining at the same time, the construction period can be shortened, and the rain lining functions as a composite section from the time when the initial ground load acts, resulting in an extremely economical section. can be realized.

〔実施例〕〔Example〕

既設の一次覆エセグメント(1)の前部に一次覆エセグ
メント(2)を組み立て固定しセグメントリングを形成
する。その後−法覆エセグメント(2)ヒ の内側に主鉄筋及び配力筋を配筋前後に摺動自在の妻枠
(4)を設けた内型枠(5)を、既設の内型枠(6)の
前部に組み立て固定するものであるが、既設の内型枠(
6)に対し連設する内型枠(5)は千鳥状に組み立て(
第8図参照)るものである。
The primary covering segment (2) is assembled and fixed to the front part of the existing primary covering segment (1) to form a segment ring. After that, the main reinforcing bars and distribution bars are installed inside the cover segment (2), and the inner formwork (5) with the gable frame (4) that can be slid freely before and after the reinforcement is installed, is replaced with the existing inner formwork (5). 6), but the existing inner formwork (
The inner formwork (5) that is connected to 6) is assembled in a staggered manner (
(see Figure 8).

内型枠(5)及び(6)は同一構造であってトンネルの
円周方向に4分割され、両側継手板(7)には隣接する
内型枠(5)と連結するボルト孔(8)が穿たれている
The inner forms (5) and (6) have the same structure and are divided into four parts in the circumferential direction of the tunnel, and the joint plates (7) on both sides have bolt holes (8) to connect with the adjacent inner form (5). is worn.

内型枠(5) (61の前後面には外側は内型枠の円弧
と同一の円弧状に形成された妻枠(4)を摺動自在に取
り付け、内型枠の内部で作業の邪魔にならないところに
設けたジヤツキ(9)にて摺動させる。
Inner formwork (5) (The end frame (4), which is formed in the same arc shape as the inner formwork on the outside, is slidably attached to the front and rear surfaces of 61 to prevent work from getting in the way inside the inner formwork. Slide it with the jack (9) provided in a place where it does not become.

内型枠(5)(6)の前後板00)に長孔0υを穿ち、
前後の長孔(1υに作動杆02)を挿通し、作動杆(1
2+の前後端に妻板(4)を固定し、ジヤツキ(9)の
ロッドを作動杆(12)に枢着ジヤツキ(9)の作動に
より妻板(4)を摺動させるものである。ジヤツキ(9
)は内型枠(5) (61の内側に設けた補強部材等に
取り付ければよ(、転用して用いるものである。
Drill a long hole 0υ in the front and rear plates 00) of the inner formwork (5) and (6),
Insert the operating rod 02 into the front and rear long holes (1υ), and
The end plate (4) is fixed to the front and rear ends of the 2+, and the end plate (4) is slid by the operation of the jack (9), which pivots the rod of the jack (9) to the operating rod (12). Jack (9)
) can be attached to the reinforcing member etc. provided inside the inner formwork (5) (61).

覆工材注入空間器の施工を詳細に述べれば既設の内型枠
(6)の前部に内型枠(5)を連接し、ボルト孔aDに
てボルトナツトを用いて固定し、円周方内金ての組み立
てが終了したらば既設の内型枠(6)の前部の妻枠(4
)及び連結した内型枠(5)の後部の妻枠(4)をジヤ
ツキ(9)を作動しロッドを伸し妻枠(4)を外方向へ
スライドし妻枠リングを形成すると同時にひとつ後ろの
妻枠リングを縮め、既設の内型枠(6)及び既設の一次
覆エセグメント(11の前部を気密に閉塞して、既設の
内型枠(6)、既設覆工!23)、既設の一次覆エセグ
メント(1)及び妻枠(4)にて覆工材注入空間(29
を形成する。
To describe the construction of the lining material injection space vessel in detail, the inner formwork (5) is connected to the front part of the existing inner formwork (6), fixed using bolt nuts at the bolt holes aD, and the circumferential direction is After assembling the inner mold, attach the front end frame (4) of the existing inner form (6).
) and the rear gable frame (4) of the connected inner formwork (5) is operated by the jack (9), the rod is extended, and the gable frame (4) is slid outward to form a gable frame ring, and at the same time, the gable frame (4) is moved one position backward. Shrink the gable ring, airtightly close the front part of the existing inner formwork (6) and the existing primary lining segment (11), Lining material injection space (29
form.

その後、覆工材注入管(2ツより覆工材注入空間C5)
に覆工材を注入すると同時にシールドジヤツキ(20)
を作動し、−法覆エセグメント(2)に反力を取す一工
程分ンールドマシン(I8)を掘進させる。
After that, lining material injection pipe (from 2 pipes to lining material injection space C5)
At the same time as injecting lining material, shield jack (20)
- The rolled machine (I8) is excavated by one step to take the reaction force to the cover esegment (2).

掘進中或いは掘進完了後、−法覆エセグメント(2)と
地山の間に形成されるテールボイド(3)に裏込め材を
注入する。
During or after excavation is completed, a backfill material is injected into the tail void (3) formed between the overburden segment (2) and the ground.

その後シールドジヤツキ(20)を作動してロッドを一
工程分縮め一次覆エセグメント(2)を既設−法覆エセ
グメント(1)の前部に連結する。
Thereafter, the shield jack (20) is operated to retract the rod by one step and connect the primary cover segment (2) to the front part of the existing-law cover segment (1).

従って前段で説明中の一次覆エセグメント(2)が既設
の一次覆エセグメント(1)に呼び名が変り、順次この
作業を(り返しシールドトンネルを施工するものである
Therefore, the name of the primary covering segment (2) described in the previous section will be changed to the existing primary covering segment (1), and this work will be carried out one after another (to construct a shield tunnel).

妻枠(4)で−法覆エセグメントと内型枠の前部を密閉
する時は妻枠(4)の溝(t6)に配力筋を嵌合し、す
き間はシール材でシールし覆工材の流れ止めを行う。
When sealing the front part of the inner formwork with the end frame (4), fit the distribution bar into the groove (t6) of the end frame (4), seal the gap with sealing material, and cover. Stop the flow of construction materials.

又−法覆エセグメントを連結組み立てた後、主鉄筋、配
力筋を配筋してもよいが、−法覆エセグメントとを工場
にて生産する際、第2図及び第3図に示すように配筋し
現場にては組み立てるだけにしてもよいものである。
In addition, after connecting and assembling the Ho-over E segments, main reinforcing bars and distribution bars may be arranged, but when producing the Ho-o E segments at a factory, as shown in Figures 2 and 3. It is also possible to simply arrange the reinforcement and assemble it on site.

−法覆エセグメント(1)は内面に鉄筋旨り治具(I3
)を設け、主鉄筋側及び配力筋(19を配筋し、妻枠(
4)には配力筋(15)の挿通用の溝αaを外端部より
刻設しておくものである。
- Houki Esegment (1) has reinforcing steel jig (I3) on the inner surface.
), place reinforcement bars on the main reinforcing bar side and distribution bars (19), and install reinforcement bars (
4) is provided with a groove αa for insertion of the distribution bar (15) from the outer end.

α力は内型枠(5) (61の連結用のボルト孔、08
)はシールドマシンで内部に複数のプレート(I9を同
一円周上に固定し、プレートα9の後部にシールドジヤ
ツキ(20+のシリンダーを固定し、ロッドを一次覆エ
セグメント(1)に当接できるようにする。
α force is the inner formwork (5) (bolt hole for connection of 61, 08
) is a shield machine with multiple plates (I9 fixed on the same circumference, a shield jack (20+ cylinder) fixed on the rear of plate α9, and the rod can be brought into contact with the primary covering segment (1). do it like this.

C9はセレクター゛、器は覆工材注入管、のは既設覆工
材、(24Jは内型枠のスキンプレート、09は覆工材
注入空間を示すものである。
C9 is the selector, the container is the lining material injection pipe, the holder is the existing lining material, (24J is the skin plate of the inner formwork, and 09 is the lining material injection space.

〔発明の効果〕〔Effect of the invention〕

一次、二次覆工の同時施工が可能であるため、工期の短
縮を図ることができる。
Since the primary and secondary lining can be constructed simultaneously, the construction period can be shortened.

また初期の地山荷重の作用時点から、両覆工が合成断面
として機能するので、従来工法に比べて極めて経済的な
断面を実現することができる。
Furthermore, since both linings function as a composite cross section from the time when the initial ground load is applied, it is possible to realize a cross section that is extremely economical compared to conventional construction methods.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はトンネルの縦断面図、第2図は一次覆工用セグ
メントの正面図、第3図は第2図のa−a矢視図、第4
図は第1図のa−a矢視図、第5図は第4図の背面図、
第6図は第5図のb−す矢視図、第7図は同c−c矢視
図、第8図は内枠リングの組み方を示す平面図である。
Fig. 1 is a vertical cross-sectional view of the tunnel, Fig. 2 is a front view of the primary lining segment, Fig. 3 is a view taken along the aa arrow in Fig. 2, and Fig. 4 is a longitudinal sectional view of the tunnel.
The figure is a view taken along arrow a-a in Fig. 1, Fig. 5 is a back view of Fig. 4,
6 is a view taken along the line B in FIG. 5, FIG. 7 is a view taken along the line CC shown in FIG. 5, and FIG. 8 is a plan view showing how to assemble the inner frame ring.

Claims (1)

【特許請求の範囲】[Claims] (1)既設の一次覆工セグメントの前部に一次覆工セグ
メントを組み立て固定し、既設の内型枠の前部に既設の
内型枠に対し内型枠を千鳥状に組み立て、既設の内型枠
の前部の妻枠と連結した内型枠の後部の妻枠を外方向へ
スライドした後、ひとつ後の妻枠リングを内方向へ縮め
、前記拡径した妻枠、一次覆工セグメント、既設二次覆
工及び内型枠で囲まれた覆工材注入空間に覆工材を注入
し、同時にシールドマシンを一工程分掘進し、掘進完了
後シールドジャッキを縮めテールにセグメント等を組み
立てる空間を形成して、既設の一次覆工セグメントの前
部に一次覆工セグメントを組み立てる作業を順次くり返
し行うこと特徴とする一次覆工を活かしたシールドトン
ネルの一体構築工法
(1) Assemble and fix the primary lining segment in front of the existing primary lining segment, assemble the inner formwork in a staggered manner in front of the existing inner formwork, and After sliding the rear gable of the inner formwork connected to the front gable of the formwork outward, the next gable ring is contracted inward, and the expanded gable and primary lining segments are removed. , Inject the lining material into the lining material injection space surrounded by the existing secondary lining and inner formwork, and at the same time excavate one step with the shield machine. After the excavation is completed, retract the shield jack and assemble the segments on the tail. An integrated construction method for shield tunnels that takes advantage of the primary lining, which is characterized by forming a space and repeatedly assembling the primary lining segment in front of the existing primary lining segment.
JP61293274A 1986-12-09 1986-12-09 An integrated construction method for shield tunnels that utilizes the primary lining Granted JPS63147100A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61293274A JPS63147100A (en) 1986-12-09 1986-12-09 An integrated construction method for shield tunnels that utilizes the primary lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61293274A JPS63147100A (en) 1986-12-09 1986-12-09 An integrated construction method for shield tunnels that utilizes the primary lining

Publications (2)

Publication Number Publication Date
JPS63147100A true JPS63147100A (en) 1988-06-20
JPH0480198B2 JPH0480198B2 (en) 1992-12-17

Family

ID=17792704

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61293274A Granted JPS63147100A (en) 1986-12-09 1986-12-09 An integrated construction method for shield tunnels that utilizes the primary lining

Country Status (1)

Country Link
JP (1) JPS63147100A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008109288A (en) * 2006-10-24 2008-05-08 Alpine Electronics Inc Speaker

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008109288A (en) * 2006-10-24 2008-05-08 Alpine Electronics Inc Speaker

Also Published As

Publication number Publication date
JPH0480198B2 (en) 1992-12-17

Similar Documents

Publication Publication Date Title
JP3285261B2 (en) Precast formwork for tunnel lining
CN114704272B (en) Construction method of underground tunnel with first building and then digging
JPS6023599A (en) Tunnel lining method and lining repairing method and shield used in said method
JP3890528B2 (en) Tunnel construction method
JPS63147100A (en) An integrated construction method for shield tunnels that utilizes the primary lining
JP2942874B2 (en) How to join tunnels
JP4750568B2 (en) Tunnel junction construction method and tunnel junction structure
JP4176516B2 (en) Shield machine, tunnel construction method and tunnel
JPH0194199A (en) Method of constructing concrete lining body into ground and segment containing coarse aggregate used for said construction
JP2755772B2 (en) Bonding method and device between shield tunnel and structure or shield tunnel
JPH03140597A (en) Construction work of underground structure
JP3651970B2 (en) Start / arrival method of branch shield machine and lining structure used therefor
JP7617333B1 (en) Center push tube set
JP4392576B2 (en) Tunnel construction method
JP2005188260A (en) How to build a shield tunnel
JPH0462299A (en) Larger section tunnel and construction method thereof
JP3866648B2 (en) Tunnel cross-section change method
JPH0772476B2 (en) How to build a tunnel lining
JP4829593B2 (en) Shield machine and shield method using the same
JPH09328987A (en) Tunnel and construction method
JPS6332239Y2 (en)
JPS63147094A (en) On-site lining construction method for shield tunnel and its lining equipment
JPH05118194A (en) Sealing method of lining in cast-in-place lining shield method
JPH0351499A (en) Cast-in-place lining shield excavator
JP3787807B2 (en) Tunnel construction method using shield excavator