JPS6389727A - Construction work of sheet pile - Google Patents
Construction work of sheet pileInfo
- Publication number
- JPS6389727A JPS6389727A JP23104686A JP23104686A JPS6389727A JP S6389727 A JPS6389727 A JP S6389727A JP 23104686 A JP23104686 A JP 23104686A JP 23104686 A JP23104686 A JP 23104686A JP S6389727 A JPS6389727 A JP S6389727A
- Authority
- JP
- Japan
- Prior art keywords
- excavated
- casing
- mud water
- soil
- view
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 13
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 20
- 239000002689 soil Substances 0.000 claims abstract description 11
- 238000000034 method Methods 0.000 claims abstract description 8
- 238000009412 basement excavation Methods 0.000 claims description 9
- 239000004576 sand Substances 0.000 claims description 7
- 229910000831 Steel Inorganic materials 0.000 abstract description 12
- 239000010959 steel Substances 0.000 abstract description 12
- 101150054854 POU1F1 gene Proteins 0.000 abstract 1
- 239000004575 stone Substances 0.000 abstract 1
- 125000006850 spacer group Chemical group 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000003028 elevating effect Effects 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は地盤中に矢板を連続して施工する施工方法に
関するものである。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a construction method for continuously constructing sheet piles in the ground.
従来から河川護岸工事や水路及び道路の土留擁壁等を構
成するのに鋼管矢板又は鋼矢板を地盤中に連続して施工
する手法が用いられている。BACKGROUND ART Conventionally, a method of continuously constructing steel pipe sheet piles or steel sheet piles into the ground has been used for constructing river bank protection works, retaining walls for waterways and roads, and the like.
こうした従来型の矢板施工法では打込みによる場合が多
く、騒音公害の′問題があり、掘削孔に矢板を建込む方
法では、掘削機を支持する。クローラタイプの大型ベー
スマシーンを必要とすることが屡々ある。このため、作
業スペースの狭い現場では作業性に問題があり、また幅
員の狭い道路では路上作業の為に全面通行止にしなけれ
ばならない場合もあった。These conventional sheet pile construction methods often involve driving, which poses the problem of noise pollution, and in the method of erecting sheet piles into excavated holes, the excavator is supported. A large crawler type base machine is often required. For this reason, work efficiency was problematic at sites with narrow work spaces, and narrow roads sometimes had to be completely closed off to allow for on-road work.
そこで、この発明は前記の様な従来工法の不都合な点を
改善して大型ベースマシンを必要とせず、作業スペース
の狭い所でも作業性がよく、掘削土砂、泥水の処理が容
易であり、路上の作業でも車の交通に与える影響を最小
限に押さえることの出来得る施工方法を提供することを
目的とする。Therefore, this invention improves the disadvantages of the conventional method as described above, does not require a large base machine, has good workability even in a narrow work space, is easy to dispose of excavated soil and mud, and can be used on roads. The purpose is to provide a construction method that can minimize the impact on vehicular traffic even during construction work.
この発明による矢板の施工法は掘削予定位置の両側に沿
って軌条を配設し、この上を走行する掘進機構及びパケ
ットを用いて所定の深度までケーシングを利用して泥水
掘削すると共にパケット内に掘削土砂を収容しつつ複数
本連続掘削して泥水の充満した掘削溝を造成し、この掘
削溝内に矢板を連続配設してパケット内の土砂で掘削溝
を埋め戻し、オーバーフローする泥水を水中ポンプで先
行して掘削したケーシング内に注入する作業を順次繰り
返す点に特徴がある。The method of constructing sheet piles according to this invention is to arrange rails along both sides of the planned excavation location, and use the excavation mechanism and packet that run on the rails to excavate muddy water using the casing to a predetermined depth, and to excavate the mud inside the packet. Multiple excavated soil is continuously excavated to create an excavated trench filled with muddy water, and sheet piles are successively placed in this excavated trench to backfill the excavated trench with the soil in the packet, and the overflowing muddy water is submerged. It is unique in that the process of injecting into the casing, which has been previously excavated using a pump, is repeated sequentially.
以下、図示するこの発明の実施例により説明する。第1
図及び第2図にこの発明による施工法を用いて道路周辺
に鋼矢板を連続して施工する実施例の平面図及び立面図
を示した。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be explained below with reference to illustrated embodiments. 1st
Fig. 2 shows a plan view and an elevation view of an embodiment in which steel sheet piles are continuously constructed around a road using the construction method according to the present invention.
ここで、掘削予定位置の両側に沿ってレール3が配設さ
れ、このレール3上を後述する掘進機12及び土砂投入
用パケット8が走行可能となっている。Here, rails 3 are arranged along both sides of the planned excavation position, and an excavator 12 and an earth and sand charging packet 8, which will be described later, can run on the rails 3.
また、道路面上にはH型鋼4を置きその上にほぼレール
3高さと等しくなるように、メトロデツキ5を敷き、作
業台が構成されている。こうして構成された作業台の左
右にはすべり台7を配置して車の交通を可能としている
。Further, an H-shaped steel 4 is placed on the road surface, and a metro deck 5 is laid thereon so that the height is approximately equal to the height of the rail 3, thereby forming a workbench. Slides 7 are placed on the left and right sides of the workbench constructed in this manner to enable vehicular traffic.
この施工法で用いられる掘進機12は、第6図(a)、
(blの平面図及び側面図で示した様にリーダ−13
掘進機構10及び昇降シリンダー11を備えており、レ
ール3上を移動して所定の掘削位置にケーシング9を埋
設して内部を掘溝し、泥水注入後にケーシング9を引き
抜いて、次の掘削位置に移動するものである。The excavator 12 used in this construction method is shown in Fig. 6(a).
(As shown in the plan view and side view of bl, the reader 13
It is equipped with an excavation mechanism 10 and an elevating cylinder 11, moves on rails 3, buries the casing 9 at a predetermined excavation position, excavates the inside, pulls out the casing 9 after pouring mud, and moves to the next excavation position. It is something that moves.
また、土砂投入用パケット8は第7図(a)。Further, the soil charging packet 8 is shown in FIG. 7(a).
(b)、 (C1,(dlの側面図、正面図、底面図及
び平面図に示した様に、開口上部に100m/m角程度
のフルイを備えており、掘削された土砂の中から所定値
以上の玉石を除去した埋戻し用の土砂を収容してレール
3上を移動可能となっている。(b), (C1, (As shown in the side view, front view, bottom view, and plan view of dl, a sieve of approximately 100 m/m square is installed at the top of the opening, and a predetermined amount of water is extracted from the excavated earth and sand. It is possible to move on the rail 3 by storing earth and sand for backfilling from which boulders exceeding the value have been removed.
ここで、第3図及び第4図に示した一列の掘削部分の平
面図及び断面図において施工手順を説明すると、まず掘
進機12で所定の深度まで掘削後、ケーシング9内に泥
水を注入してケーシング9を引き抜く。この作業を、3
本又は5本分程度繰返し、泥水の充満した掘削孔1を造
成する。(Cの工程)
泥水の充満した掘削孔1内に鋼矢板2の先端部が掘削孔
1内で芯ズレしない様にスペーサー2′が取付られる。Here, the construction procedure will be explained with reference to the plan view and cross-sectional view of a row of excavated parts shown in FIGS. pull out the casing 9. This work, 3
Drill hole 1 filled with muddy water is created by repeating this process for about 1 or 5 times. (Step C) A spacer 2' is installed in the excavated hole 1 filled with muddy water so that the tip of the steel sheet pile 2 will not be misaligned within the excavated hole 1.
このスペーサー2′は第5図(C1に示した形状であり
、クレーンで鋼矢板2を吊上げた時に同図(al、 (
b)に示した様に取付られ、建込用定規6でガイドされ
つつ掘削孔1内に自重でセットされる。(Bの工程)
こうして、鋼矢板2の建込後に掘削した土砂は土砂投入
用パケット8のフルイで玉石を除去して鋼矢板2の周辺
に埋戻される。(Aの工程)この時、ドーパ−フローす
る泥水は水中ポンプ10で先行するケーシング9内に注
入される。This spacer 2' has the shape shown in Figure 5 (C1), and when the steel sheet pile 2 is lifted by a crane,
It is attached as shown in b) and is set in the excavation hole 1 by its own weight while being guided by the construction ruler 6. (Step B) In this way, the earth and sand excavated after the steel sheet pile 2 is erected is backfilled around the steel sheet pile 2 by removing cobblestones with the sieve of the earth and sand charging packet 8. (Step A) At this time, the muddy water flowing through the doper is injected into the preceding casing 9 by the submersible pump 10.
この発明による矢板の施工方法実施例は以上の通りであ
り、次に述べる効果を挙げることができる。The embodiment of the sheet pile construction method according to the present invention is as described above, and the following effects can be achieved.
大型ベースマシンを必要とせず、作業スペースの狭い所
でも作業性がよ(、掘削土砂をパケット内に収容して埋
戻しに効果的に利用し、泥水も先行するケーシングに順
次繰り返し注入利用するため全体の泥水使用量も少なく
処理も容易であり、路上の作業でも車の交通に与える影
響を最小限に押さえることができる。It does not require a large base machine, and it is easy to work even in narrow work spaces (because excavated soil is stored in packets and effectively used for backfilling, and muddy water is also repeatedly injected into the preceding casing) The overall amount of muddy water used is small and it is easy to dispose of, and the impact on vehicle traffic can be kept to a minimum even when working on the road.
また、パケット内に収容した土砂にセメント等の硬化剤
を混入して、掘削溝埋め戻し時の矢板支持力を高めるこ
ともできる。Further, by mixing a hardening agent such as cement into the earth and sand contained in the packet, it is possible to increase the sheet pile supporting force when backfilling an excavated trench.
第1図及び第2図は実施例の全体平面図及び立面図、第
3図及び第4図は実施例の部分平面図及び地中の断面図
、第5図(a)、 (b)はスペーサの取付状態を示す
正面図及び平面図、同図(C1はクリップの拡大図、第
6図(a)、 (b)は掘削機の平面図及び正面図、第
7図fan、 (b)。
(C1,(d)はパケットの側面図、正面図、底面図及
び平面図である。
1−・−・−掘削機、2−・−・・・−鋼矢板、2 ’
−−−−−−・スペーサ、3−・−・−レール、4・
−・−H型鋼、5−一メトロデツキ、6・−−−−−・
建込用定規、7・−・−スベリ台、8−・−・−土砂投
入用パケット、9−・−−・−ケーシング、10−・・
−・・掘進機構、11・−・−昇降シリンダ−112−
・−・・・・掘進機、13・・−・−リーダ。Figures 1 and 2 are an overall plan view and an elevation view of the embodiment, Figures 3 and 4 are a partial plan view and underground sectional view of the embodiment, and Figures 5 (a) and (b). are a front view and a plan view showing the installation state of the spacer, the same figure (C1 is an enlarged view of the clip, Fig. 6 (a), (b) is a plan view and front view of the excavator, Fig. 7 fan, (b) ). (C1, (d) is a side view, a front view, a bottom view, and a plan view of the packet. 1--- Excavator, 2--- Steel sheet pile, 2'
-------・Spacer, 3-・-・-Rail, 4・
-・-H type steel, 5-1 metro deck, 6・------・
Construction ruler, 7--Sliding stand, 8-- Packet for soil injection, 9-- Casing, 10--
--- Excavation mechanism, 11 --- Lifting cylinder - 112-
・−・・Excavator, 13・−・−Leader.
Claims (1)
当該軌条上を走行する掘進機で所定の深度までケーシン
グを利用して泥水掘削すると共に前記軌条上を走行する
パケット内に掘削土砂を収容し、複数本連続掘削して泥
水の充満した掘削溝を造成し、当該掘削溝内に矢板を連
続配設して前記パケット内の土砂で掘削溝を埋め戻し、
オーバーフローする泥水を水中ポンプで先行して掘削し
たケーシング内に注入する作業を順次繰り返すことを特
徴とする矢板の施工方法。[Claims] A construction method in which sheet piles are continuously constructed in the ground, in which rails are arranged along both sides of the planned excavation position,
An excavator running on the rails excavates muddy water to a predetermined depth using a casing, and the excavated soil is stored in a packet running on the rails, and multiple trenches are continuously excavated to create an excavated trench filled with muddy water. and backfilling the excavated trench with earth and sand in the packet by continuously arranging sheet piles in the excavated trench,
A sheet pile construction method characterized by sequentially repeating the process of injecting overflowing muddy water into an excavated casing using a submersible pump.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23104686A JPH076187B2 (en) | 1986-09-29 | 1986-09-29 | Construction method of sheet pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23104686A JPH076187B2 (en) | 1986-09-29 | 1986-09-29 | Construction method of sheet pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6389727A true JPS6389727A (en) | 1988-04-20 |
| JPH076187B2 JPH076187B2 (en) | 1995-01-30 |
Family
ID=16917433
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP23104686A Expired - Lifetime JPH076187B2 (en) | 1986-09-29 | 1986-09-29 | Construction method of sheet pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH076187B2 (en) |
-
1986
- 1986-09-29 JP JP23104686A patent/JPH076187B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH076187B2 (en) | 1995-01-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2022502586A (en) | Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles | |
| EP0810327B1 (en) | Method and device for laying underground continuous walls | |
| CN112064751A (en) | Deep groove construction method for drainage pipeline | |
| JPH1136338A (en) | Construction method for underground structures | |
| JPH07173835A (en) | Excavator for underground continuous wall | |
| RU2209268C1 (en) | Process of development of foundation pit | |
| JP2963972B2 (en) | Construction method for underground structures | |
| JPS6389727A (en) | Construction work of sheet pile | |
| JP2874906B2 (en) | Shaft construction method | |
| JP3681883B2 (en) | Long-cut soil slope reduction method | |
| JPS6117696A (en) | Construction of underground head | |
| JP7566235B1 (en) | Ground improvement methods | |
| JP2963802B2 (en) | How to build an underground parking | |
| JP4279818B2 (en) | Open shield method | |
| JP2745083B2 (en) | Tunnel construction method | |
| JP6403300B1 (en) | How to embed sheet pile | |
| JPH03180614A (en) | Construction of retaining wall for underground structure | |
| KR970007378B1 (en) | Open shield machine | |
| JPH0416622A (en) | Protective structure of underground structure made of concrete and construction method thereof | |
| JP2006266035A (en) | Construction method of ready-made piles | |
| JP2024092472A (en) | Method of entering an open shield machine into a vertical shaft in an open shield construction method and a vertical shaft of an open shield machine | |
| JP2017128943A (en) | Open shield method | |
| JPS6192235A (en) | Fixing of embedded pipe | |
| JPH01121414A (en) | Excavation work of ground | |
| JPS63219727A (en) | Construction of water-stop sheet pile wall |