JPH0363607B2 - - Google Patents

Info

Publication number
JPH0363607B2
JPH0363607B2 JP58145698A JP14569883A JPH0363607B2 JP H0363607 B2 JPH0363607 B2 JP H0363607B2 JP 58145698 A JP58145698 A JP 58145698A JP 14569883 A JP14569883 A JP 14569883A JP H0363607 B2 JPH0363607 B2 JP H0363607B2
Authority
JP
Japan
Prior art keywords
lining
reinforcing bars
ring
construction
concentrically
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58145698A
Other languages
Japanese (ja)
Other versions
JPS6037334A (en
Inventor
Teruaki Fukunaga
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP58145698A priority Critical patent/JPS6037334A/en
Publication of JPS6037334A publication Critical patent/JPS6037334A/en
Publication of JPH0363607B2 publication Critical patent/JPH0363607B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 〔発明の技術分野〕 この発明は、原子炉特に沸騰水型原子炉の圧力
容器を支承する下部ペデスタルの施工方法に関す
る。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method of constructing a lower pedestal for supporting a pressure vessel of a nuclear reactor, particularly a boiling water reactor.

〔発明の技術的背景〕[Technical background of the invention]

沸騰水型原子炉の圧力容器を支承する下部ペデ
スタルの従来の施工方法を第1図について説明す
る。
A conventional construction method for a lower pedestal supporting a pressure vessel of a boiling water reactor will be explained with reference to FIG.

下部ペデスタル1は、その底部に直径の異なる
3個の円環状リングガーダ2,3,4が内外同心
水平に配置され、リングガーダ2,3,4には、
それぞれ内外2列同心円周上直立に多数本の棒状
鉄筋5がその下端において連結され、各列の鉄筋
5には上下方向に間隔を置いて7箇所に水平同心
に各列ごとに直径の異なる円環状鉄筋6ないし1
1が結合されている。最内側、最外側の鉄筋5,
6,5,11の内側、外側には、鋼円筒の内側ラ
イニング12、外側ライニング13が直立に設置
され、内側ライニング12、外側ライニング13
間を埋めコンクリート14を打設することによ
り、鉄筋コンクリート円筒体をなす下部ペデスタ
ル1が形成される。下部ペデスタル1の上端には
中間スラブ15が構築され、中間スラブ15の上
には上部ペデスタル16が構築され、下部ペデス
タル1は、中間スラブ15、上部ペデスタル16
を介して、図示しない圧力容器を支承する。
At the bottom of the lower pedestal 1, three annular ring girders 2, 3, and 4 with different diameters are arranged horizontally and concentrically on the inside and outside, and the ring girders 2, 3, and 4 have the following structure:
A large number of rod-shaped reinforcing bars 5 are connected at their lower ends in two rows, one inside and one outside, standing upright on the circumference, and each row of reinforcing bars 5 has circles with different diameters arranged horizontally and concentrically at seven locations spaced apart in the vertical direction. Circular reinforcing bar 6 or 1
1 are combined. Innermost and outermost reinforcing bars 5,
6, 5, 11, an inner lining 12 and an outer lining 13 made of steel cylinders are installed upright on the inner and outer sides.
By filling the gap and placing concrete 14, the lower pedestal 1, which is a reinforced concrete cylinder, is formed. An intermediate slab 15 is constructed at the upper end of the lower pedestal 1, an upper pedestal 16 is constructed on the intermediate slab 15, and the lower pedestal 1 is constructed from the intermediate slab 15 and the upper pedestal 16.
A pressure vessel (not shown) is supported via.

下部ペデスタル1を施工するには、初めに、リ
ングガーダ2,3,4を、そのそれぞれに固着さ
れている多数本のスタツドジベル17を下向き鉛
直にして、予め打設されているコンクリート基礎
上に内外同心水平に据え付ける。リングガーダ
2,3,4の下方、周囲にコンクリートを打設し
て、リングガーダ2,3,4を固定すると共に水
平床18を構築する。リングガーダ2,3,4の
上半部は、水平床18上に露出する。外側のリン
グガーダ4から外方に若干離れ、水平床18の上
方に距離を置いて水平に仕切床19を設ける。仕
切床19上に鉄筋組立のための工事用足場20を
適所に組み立てる。工事用足場20は、以下の工
事に必要に応じ随時利用される。内側1列目の鉄
筋5をその下端ねじ部を内側のリングガーダ2に
円周上等ピツチに設けられているねじ穴にそれぞ
れねじ込んで連結し直立に組み立てる。次に、リ
ングガーダ2の内側にそれと同心に内側ライニン
グ12を水平床18上に直立に設置する。内側ラ
イニング12には、その下半部外周から放射状に
突出して上下方向複数列に多数本の図示しないス
タツドボルトが固着され、上下方向2箇所の平面
内円周上4等分箇所に、下部ペデスタル1の周壁
の厚さにほぼ等しい長さの円筒形スリーブ21が
外周から放射状に突出して挿通固着されている
が、内側ライニング12を設置するときには、前
記スタツドボルト、スリーブ21が鉄筋5と干渉
しないよう鉄筋5間のすき間を通るように、鉄筋
5と内側ライニング12の関係位置は調整され
る。内側ライニング12の設置前に内側1列目の
鉄筋5を組むのは、この鉄筋5の配置位置が内側
ライニング12の設置位置に近接していて鉄筋5
の配筋が困難なためである。次に、内側1列目の
鉄筋5上下方向7箇所に円環状鉄筋6を下方から
上方へと順次組み付ける。次いで、内側から外
側、下方から上方へと順次鉄筋5、鉄筋7ないし
11を内側1列目の鉄筋5,6と同様にして組み
付ける。次に、外側1列目の鉄筋5,11の外
側、水平床18上にリングガーダ4と同心に直立
に、外側ライニング13を設置する。外側ライニ
ング13は、上下半分、円周方向に4等分された
8分割部分からなり、下半部分内周には、その中
心に向つて多数本図示しないスタツドボルトが固
着され、定置された内側ライニング12に固着の
スリーブ21の外端に対応する位置にはスリーブ
21が挿通可能な直径の穴があけられている。外
側ライニング13は、その下半分を初めに水平床
18上に設置し、その上に上半分を載せ、8分割
部分の合せ面をすべて溶接して一体とする。次い
で、付帯構造物の取付座となる複数個の埋込金物
22を外側ライニング13の外周面に溶接固着
し、スリーブ21それぞれの外端を外側ライニン
グ13に溶接固着する。内側ライニング12、外
側ライニング13間にコンクリート14を打設充
満することにより、鉄筋コンクリート円筒体をな
す下部ペデスタル1が形成される。下部ペデスタ
ル1の施工と並行して水平床18の上面にボトム
ライナ23の敷設工事を行う。下部ペデスタル1
の施工工事とボトムライナ23の敷設工事とは上
下作業となる。
To construct the lower pedestal 1, first, the ring girders 2, 3, and 4, with the multiple stud dowels 17 fixed to each of them facing downward and vertically, are placed inside and outside on the pre-cast concrete foundation. Install concentrically and horizontally. Concrete is placed below and around the ring girders 2, 3, 4 to fix the ring girders 2, 3, 4 and to construct a horizontal floor 18. The upper halves of the ring girders 2, 3, 4 are exposed on the horizontal floor 18. A partition floor 19 is provided horizontally at a distance slightly outward from the outer ring girder 4 and above the horizontal floor 18. Construction scaffolding 20 for assembling reinforcing bars is assembled in place on partition floor 19. The construction scaffolding 20 is used as needed for the following construction work. The reinforcing bars 5 in the inner first row are assembled upright by screwing their lower end threaded parts into screw holes provided in the inner ring girder 2 at equal pitches on the circumference. Next, the inner lining 12 is installed upright on the horizontal floor 18 inside the ring girder 2 and concentrically therewith. A large number of stud bolts (not shown) are fixed to the inner lining 12 in multiple rows in the vertical direction, protruding radially from the outer periphery of the lower half, and lower pedestals are fixed to the inner lining 12 at two equal quarter positions on the circumference in the plane in the vertical direction. A cylindrical sleeve 21 having a length approximately equal to the thickness of the peripheral wall of the inner lining 1 is inserted and fixed to protrude radially from the outer periphery, but when installing the inner lining 12, the stud bolts and the sleeve 21 do not interfere with the reinforcing bar 5. The relative positions of the reinforcing bars 5 and the inner lining 12 are adjusted so that they pass through the gaps between the reinforcing bars 5. The reason why the reinforcing bars 5 in the first inner row are assembled before installing the inner lining 12 is that the reinforcing bars 5 are located close to the location where the inner lining 12 is installed.
This is because reinforcing is difficult. Next, annular reinforcing bars 6 are sequentially assembled from the bottom to the top at seven locations in the vertical direction of the reinforcing bars 5 in the inner first row. Next, the reinforcing bars 5 and 7 to 11 are assembled sequentially from the inside to the outside and from the bottom to the top in the same manner as the reinforcing bars 5 and 6 in the first inner row. Next, the outer lining 13 is installed upright on the horizontal floor 18 outside the first row of reinforcing bars 5 and 11 on the outer side and concentrically with the ring girder 4. The outer lining 13 consists of upper and lower halves, which are divided into 8 equal parts in the circumferential direction, and a large number of stud bolts (not shown) are fixed to the inner periphery of the lower half toward the center. A hole having a diameter through which the sleeve 21 can be inserted is bored at a position corresponding to the outer end of the sleeve 21 fixed to the lining 12. The lower half of the outer lining 13 is first placed on the horizontal floor 18, the upper half is placed on top of it, and all the mating surfaces of the 8 divided parts are welded together to make one piece. Next, a plurality of embedded metal fittings 22 that serve as attachment seats for accessory structures are welded and fixed to the outer circumferential surface of the outer lining 13, and the outer ends of each of the sleeves 21 are welded and fixed to the outer lining 13. By pouring and filling concrete 14 between the inner lining 12 and the outer lining 13, the lower pedestal 1, which is a reinforced concrete cylinder, is formed. In parallel with the construction of the lower pedestal 1, a bottom liner 23 is laid on the upper surface of the horizontal floor 18. Lower pedestal 1
The construction work and the laying work of the bottom liner 23 are vertical work.

〔背景技術の問題点〕[Problems with background technology]

下部ペデスタルの前記従来の施工方法において
は、外側ライニング13は8分割されているもの
を設置現地で組み立て一体に溶接し、且つその外
周に埋込金物22を溶接固着するため、現地で多
くの工数を要し、従つて下部ペデスタル1の工期
が長くなる欠点があり、他方、下部ペデスタル1
の施工工事とボトムライナ23の敷設工事とは上
下作業となるため、工事の安全上から問題があ
り、又、工事が入り組むことにより遅延の虞れを
生ずる欠点があつた。
In the conventional construction method of the lower pedestal, the outer lining 13 is divided into 8 parts, which are assembled and welded together at the installation site, and the embedded metal fittings 22 are welded and fixed to the outer periphery of the outer lining 13, which requires a large number of man-hours at the site. Therefore, there is a disadvantage that the construction period of the lower pedestal 1 is longer.
Since the construction work and the laying work of the bottom liner 23 involve vertical work, there is a problem in terms of construction safety, and there is also a drawback that the complicated construction work may cause delays.

〔発明の目的〕[Purpose of the invention]

この発明は、下部ペデスタルの従来の施工方法
の前記問題点を解決するためになされたもので、
外側ライニングの現地設置の工数を節減しそれに
より下部ペデスタルの施工工期を短縮でき、更に
下部ペデスタルの施工工事に関係なくボトムライ
ナ敷設工事などの外側の工事を安全に行うことが
でき工期の短縮に資する下部ペデスタルの施工方
法を提供することを目的とする。
This invention was made in order to solve the above-mentioned problems of the conventional construction method of the lower pedestal.
This reduces the number of man-hours required for on-site installation of the outer lining, thereby shortening the construction period for the lower pedestal.Furthermore, external work such as laying the bottom liner can be carried out safely regardless of the construction work for the lower pedestal, contributing to shortening the construction period. The purpose of this invention is to provide a method for constructing a lower pedestal.

〔発明の概要〕[Summary of the invention]

この発明による下部ペデスタルの施工方法は、
内周外周をそれぞれ鋼円筒の内側ライニング及び
外側ライニングで被覆され、底部に直径の異なる
複数個の円環状リングガーダを水平内外同心に配
置されて、直立の鉄筋コンクリート円筒体をなし
原子炉圧力容器を支承する下部ペデスタルにおい
て、外側ライニング及び内側ライニングは予め次
記するように形成して置き、次記する順序で工事
を行うことにより前記目的を達するものである。
The method for constructing the lower pedestal according to this invention is as follows:
The inner periphery of the reactor pressure vessel is covered with an inner lining and an outer lining of a steel cylinder, and a plurality of annular ring girders with different diameters are arranged horizontally and concentrically at the bottom of the reactor pressure vessel, forming an upright reinforced concrete cylinder. In the supporting lower pedestal, the outer lining and inner lining are formed in advance as described below, and the construction is carried out in the following order to achieve the above purpose.

外側ライニングは、予め、その下半部内周特定
多数箇所それぞれには、スタツドボルトが中心に
向かい突出して固着され、内周特定複数箇所それ
ぞれには前記円筒体の壁厚にほぼ等しい長さの円
筒形スリーブが中心に向かい挿通突出して固着さ
れ、外周には複数個の埋込金物がその少なくとも
1表面を露出して固着され一体をなしている。
The outer lining is preliminarily fixed with stud bolts protruding toward the center at each of a plurality of specific locations on the inner periphery of the lower half, and a cylinder having a length approximately equal to the wall thickness of the cylindrical body is attached to each of the plurality of specific locations on the inner periphery. A shaped sleeve is inserted through and protrudes toward the center and is fixed thereto, and a plurality of embedded metal parts are fixed to the outer periphery with at least one surface thereof exposed to form an integral structure.

内側ライニングは、上下2分割され、下半部外
周には多数本のスタツドボルトが放射状に突出し
て固着されている。外側ライニングに固着された
スリーブの内端に対応する位置には、スリーブが
挿通できる直径の穴があけられている。
The inner lining is divided into upper and lower halves, and a number of stud bolts are fixedly protruding radially from the outer periphery of the lower half. A hole is bored at a position corresponding to the inner end of the sleeve secured to the outer lining and has a diameter that allows the sleeve to pass therethrough.

下部ペデスタルの施工は次の順序で行う。 Construction of the lower pedestal will be carried out in the following order.

下部ペデスタルの底部となる箇所に複数個のリ
ングガーダを同心円上水平に設置しコンクリート
で固定し、その周囲に水平床を構築する。リング
ガーダの内側に少し離れて工事用足場を組む。こ
の工事用足場を必要に応じ随時利用して以下の工
事を進める。リングガーダと同心その外側水平床
上に外側ライニングを直立に設置する。内側1列
目の鉄筋を残して、外側ライニングの内側に下端
をリングガーダに連結して同心複数列に多数本の
直立棒状鉄筋を組み、この各列の棒状鉄筋に結合
してその上下方向複数箇所に水平に円環状鉄筋
を、外方から内方へ、下方から上方へと組み付け
る。リングガーダの内側、工事用足場の外側に、
外側ライニングと同心直立に内側ライニング下半
部を設置する。内側1列目の棒状鉄筋、円環状鉄
筋を組む。内側ライニング下半部上にその上半部
を心合せ載置し、合せ面を溶接し、スリーブそれ
ぞれの自由端を内側ライニングに溶接する。内側
ライニング外側ライニング間にコンクリートを充
填打設して下部ペデスタルの施工を完了する。
At the bottom of the lower pedestal, multiple ring girders are installed horizontally in a concentric circle and fixed with concrete, and a horizontal floor is constructed around them. Assemble construction scaffolding at a little distance inside the ring girder. This construction scaffolding will be used as needed to proceed with the following construction work. Install the outer lining upright on the outer horizontal floor concentric with the ring girder. Leaving the first row of reinforcing bars on the inside, a large number of vertical reinforcing bars are installed inside the outer lining in multiple concentric rows with the lower end connected to the ring girder, and connected to the bar reinforcing bars in each row to form multiple upright bars in the vertical direction. Assemble circular reinforcing bars horizontally at the location from outside to inside and from bottom to top. Inside the ring girder, outside the construction scaffolding,
Install the lower half of the inner lining upright and concentric with the outer lining. Assemble the bar-shaped reinforcing bars and circular reinforcing bars in the first inner row. The upper half of the inner lining is centered over the lower half, the mating surfaces are welded, and the free ends of each sleeve are welded to the inner lining. Complete the construction of the lower pedestal by filling and pouring concrete between the inner lining and outer lining.

〔発明の実施例〕[Embodiments of the invention]

この発明の一実施例を第2図について説明す
る。第2図に示す部分にして第1図に示す部分と
均等の部分には、第1図におけると同一符号を付
して説明を一部省略し第1図についての前記説明
をもつてそれに代える。
An embodiment of the invention will be described with reference to FIG. Parts shown in FIG. 2 that are equivalent to those shown in FIG. 1 will be given the same reference numerals as in FIG. .

この発明によつて施工される下部ペデスタル3
0の、内周外周をそれぞれ鋼円筒の内側ライニン
グ32外側ライニング33で被覆され、底部に3
個のリングガーダ2,3,4を配置されて、直立
の鉄筋コンクリート円筒体をなすその構成は、従
来の施工法による下部ペデスタル1の前記構成と
類似である。
Lower pedestal 3 constructed according to this invention
0, the inner periphery and outer periphery of the steel cylinder are respectively covered with an inner lining 32 and an outer lining 33, and the bottom part is covered with 3
The structure of the upright reinforced concrete cylinder in which the ring girders 2, 3, and 4 are arranged is similar to the structure of the lower pedestal 1 constructed by the conventional construction method.

内側ライニング32は、初め上下に2分割され
ていて、下半分外周には上下方向7列放射状に突
出して多数本のスタツドボルト34が予め固着さ
れている。外側ライニング33は一体に形成さ
れ、その下半部内周には上下方向7列に中心に向
かい突出して多数本のスタツドボルト35が予め
固着され、内周上半部下半部の円周上4等分箇所
合計8箇所に、予め、下部ペデスタル30の円筒
体壁厚にほぼ等しい長さの円筒形スリーブ21が
中心に向かい突出して挿通固着され、外周には、
付帯構造物の取付座をなす複数個の埋込金物22
が予め少なくともその一表面を露出して固着され
ている。
The inner lining 32 is initially divided into upper and lower halves, and a large number of stud bolts 34 are fixed in advance to the outer periphery of the lower half, projecting radially in seven rows in the vertical direction. The outer lining 33 is integrally formed, and a large number of stud bolts 35 are fixed in advance to the inner periphery of its lower half in seven rows in the vertical direction, protruding toward the center. Cylindrical sleeves 21 having a length approximately equal to the thickness of the cylindrical body wall of the lower pedestal 30 are inserted and fixed in advance to a total of eight separate locations, and protrude toward the center.
A plurality of embedded metal fittings 22 forming attachment seats for ancillary structures
is fixed in advance with at least one surface exposed.

下部ペデスタル30を施工するには、初めに、
それぞれ多数本のスタツドジベル17を固着され
た互いに直径の異なる円環状リングガーダ2,
3,4を、スタツドジベル17を下方にして予め
打設されているコンクリート基礎上に水平同心に
設置し、その下方、周囲にコンクリートを打設し
て、リングガーダ2,3,4を固定すると共に水
平床18を構築する。そのとき、リングガーダ
2,3,4の上半分は水平床18上に露出してい
る。次に内側のリングガーダ2の内側に少し離れ
て水平床18上に工事用足場20を組む。工事用
足場20は、後記する工事に当り必要に応じ随時
利用する。次に、外側のリングガーダ4の外側に
リングガーダ4と同心に水平床18上に、外側ラ
イニング33を直立に設置する。次に、リングガ
ーダ2,3,4それぞれの上端部に円周方向等ピ
ツチ内外2列同心に設けられたねじ穴に下端ねじ
部をねじ込んで、多数本の棒状鉄筋5を内側1列
目を残して外側から内側へと5個の同心円筒空間
内に直立5列に組み立て、配筋された各列の棒状
鉄筋5の上下方向7箇所に、円環状鉄筋11ない
し7を外側から内側へ下方から上方へと順次水平
同心円状に組み付ける。次いで、内側ライニング
32の下半分をリングガーダ2の内側にそれと同
心に水平床18上に直立に設置し、次に残された
内側1列目の鉄筋5,6を配置して後、内側ライ
ニング32の上半部をその下半部上に心合せ載置
する。内側ライニング32の下半部上半部の設置
に当つては、外側ライニング33に固着されたス
リーブ21それぞれの自由端位置に対応して予め
内側ライニング32にあけられているスリーブ2
1が挿通できる直径の穴にスリーブ21のそれぞ
れの自由端がのぞき込むように内側ライニング3
2の設置位置を調整する。次に、内側ライニング
32の下半部上半部の合せ部分、スリーブ21そ
れぞれの自由端と内側ライニング32とを溶接
し、内側ライニング32と外側ライニング33間
にコンクリート14を打設充満し、工事用足場2
0を徹去することにより下部ペデスタル30の施
工が完了する。
To construct the lower pedestal 30, first,
Annular ring girders 2 having different diameters each having a large number of stud dowels 17 fixed thereto,
3 and 4 are installed horizontally and concentrically on a pre-cast concrete foundation with the stud dowel 17 facing downward, concrete is poured below and around it, and the ring girders 2, 3, and 4 are fixed. Build a horizontal floor 18. At that time, the upper halves of the ring girders 2, 3, 4 are exposed on the horizontal floor 18. Next, a construction scaffold 20 is erected on the horizontal floor 18 at a little distance inside the inner ring girder 2. The construction scaffolding 20 is used whenever necessary for the construction work to be described later. Next, the outer lining 33 is installed upright on the horizontal floor 18 outside the outer ring girder 4 and concentrically with the ring girder 4. Next, the lower end threaded portions are screwed into the screw holes provided concentrically in two rows of inner and outer rows at equal pitches in the circumferential direction at the upper end of each of the ring girders 2, 3, and 4. The circular reinforcing bars 11 to 7 are assembled in five upright rows in a concentric cylindrical space from the outside to the inside, and the annular reinforcing bars 11 to 7 are placed at seven locations in the vertical direction of the bar-shaped reinforcing bars 5 in each row from the outside to the inside. Assemble them horizontally and concentrically upwards. Next, the lower half of the inner lining 32 is installed upright on the horizontal floor 18 inside the ring girder 2 and concentrically with it, and then the remaining reinforcing bars 5 and 6 of the inner first row are placed, and then the inner lining The upper half of 32 is aligned and rested on its lower half. When installing the lower half and upper half of the inner lining 32, the sleeves 2 are pre-drilled in the inner lining 32 in correspondence with the free end positions of the sleeves 21 fixed to the outer lining 33.
The inner lining 3 is arranged such that each free end of the sleeve 21 looks into a hole of a diameter that allows the sleeve 21 to pass through the inner lining 3.
Adjust the installation position of 2. Next, the lower half and upper half of the inner lining 32, the free ends of the sleeves 21, and the inner lining 32 are welded together, concrete 14 is cast and filled between the inner lining 32 and the outer lining 33, and construction work is carried out. scaffolding 2
By completely removing 0, construction of the lower pedestal 30 is completed.

〔発明の効果〕〔Effect of the invention〕

この発明による下部ペデスタルの施工方法は、
下部ペデスタルの外周を被覆する外側ライニング
を初めから一体に形成してその外周には予め埋込
金物を固着しているので、従来の施工方法により
外側ライニング8分割部分を設置現場で組み立て
一体に溶接し埋込金物を固着する場合に比し、従
来一体の内側ライニングがこの発明の場合は2分
割されていても、外側ライニング内側ライニング
の溶接を含む設置合計工数は大幅に節減され下部
ペデスタルの施工工期が著しく短縮される効果が
あり、又、施工工事は下部ペデスタルの内側に組
み立てられた工事用足場を利用して内側から行わ
れるため、下部ペデスタルの外側の工事は下部ペ
デスタル施工工事に妨げられることなく並行して
行うことができるのでその分工期の短縮が計れる
効果があり、更に、下部ペデスタル外側の水平床
上のボトムライナの敷設工事と下部ペデスタルの
施工工事とが上下作業になり入り組むことがない
ので、工事の安全度が向上し工期が短縮できる効
果がある。
The method for constructing the lower pedestal according to this invention is as follows:
The outer lining that covers the outer periphery of the lower pedestal is formed integrally from the beginning, and the embedded hardware is fixed to the outer periphery in advance, so the eight parts of the outer lining can be assembled and welded together at the installation site using conventional construction methods. Compared to the case where embedded hardware is fixed, even though the conventionally integrated inner lining is divided into two parts in the case of the present invention, the total installation man-hours including welding of the outer lining and inner lining are greatly reduced, and the construction of the lower pedestal is simplified. This has the effect of significantly shortening the construction period, and since the construction work is carried out from the inside using the construction scaffolding assembled inside the lower pedestal, the work outside the lower pedestal is obstructed by the lower pedestal construction work. This has the effect of shortening the construction period because the work can be done in parallel without having to worry about any problems.Furthermore, the installation work of the bottom liner on the horizontal floor outside the lower pedestal and the construction work of the lower pedestal can be done up and down and become complicated. This has the effect of improving construction safety and shortening the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の施工法による原子炉圧力容器の
下部ペデスタルの縦断面図、第2図はこの発明の
施工方法による下部ペデスタルの縦断面図であ
る。 2,3,4…リングガーダ、5…棒状鉄筋、6
〜11…円環状鉄筋、14…コンクリート、18
…水平床、20…工事用足場、21…スリーブ、
22…埋込金物、30…下部ペデスタル、32…
内側ライニング、33…外側ライニング、34,
35…スタツドボルト。
FIG. 1 is a longitudinal cross-sectional view of a lower pedestal of a reactor pressure vessel constructed using a conventional construction method, and FIG. 2 is a longitudinal cross-sectional view of the lower pedestal constructed using a construction method according to the present invention. 2, 3, 4...Ring girder, 5...Bar-shaped reinforcing bar, 6
~11...Circular reinforcing bar, 14...Concrete, 18
...Horizontal floor, 20...Scaffolding for construction, 21...Sleeve,
22...embedded hardware, 30...lower pedestal, 32...
Inner lining, 33...Outer lining, 34,
35... Stud bolt.

Claims (1)

【特許請求の範囲】 1 内周外周をそれぞれ鋼円筒の内側ライニング
及び外側ライニングで被覆され直立の鉄筋コンク
リート円筒体をなして原子炉圧力容器を支承する
下部ペデスタルの底部となる箇所に直径の異なる
複数個の円環状リングガーダを水平内外同心に配
置し、このリングガーダの下方及び周囲にコンク
リートを打設してリングガーダをその上面を露出
して固定すると共にその周囲に水平床を構築し、
この水平床上最内側の前記リングガーダの内側に
工事用足場を組み、この工事用足場を必要に応じ
随時利用して、前記水平床上最外側の前記リング
ガーダの外側にそれと同心に一体の前記外側ライ
ニングを直立に設置し、次に、前記リングガーダ
に下端部を連結してリングガーダとほぼ同心に複
数円筒空間に沿い直立複数列に多数本の棒状鉄筋
を最内列のものを残して外側から内側へと順次配
置し、この配筋と並行して下方から上方へと前記
内外各列の鉄筋にそれぞれほぼ同心円状に連結し
て上下方向それぞれ複数箇所に円環状鉄筋を順次
水平に配置し、次いで、上下に2分割されている
前記内側ライニングの多数本のスタツドボルトが
外周から放射状に突出して固着されている下半部
を最内側の前記リングガーダと同心にその内側前
記工事用足場の外側に前記水平床上に直立に設置
し、次に、前記の残された最内列の棒状鉄筋及び
円環状鉄筋を配置して後、前記内側ライニングの
上半部を前記下半部上に心合せ載置して上半部下
半部の合せ部分を溶接し、次いで、前記外側ライ
ニングと内側ライニング間にコンクリートを打設
充満した後、前記工事用足場を徹去することによ
る原子炉圧力容器の下部ペデスタルの施工方法。 2 外側ライニングに、予め、その下半部内周特
定多数箇所それぞれに中心に向かい突出してスタ
ツドボルトを固着し、前記内周特定複数箇所それ
ぞれに中心に向かい突出して前記円筒体の壁厚に
ほぼ等しい長さの円筒形スリーブを挿通固着し、
外側ライニングの外周に予め複数個の埋込金物を
その少なくとも1表面を露出して固着することを
特徴とする特許請求の範囲第1項に記載の原子炉
圧力容器の下部ペデスタルの施工方法。
[Scope of Claims] 1. A lower pedestal having an upright reinforced concrete cylinder whose inner periphery is covered with an inner lining and an outer lining of a steel cylinder and which supports a reactor pressure vessel has a plurality of pedestals with different diameters at the bottom part thereof. Annular ring girders are arranged horizontally and concentrically inside and outside, concrete is poured below and around the ring girders to expose the top surface of the ring girders and fix them, and a horizontal floor is constructed around the ring girders,
A construction scaffold is erected inside the ring girder at the innermost position on the horizontal floor, and this construction scaffold is used as needed to install the outer ring girder at the outermost position on the horizontal floor concentrically with the outer ring girder. The lining is installed upright, and then the lower end is connected to the ring girder, and a large number of rod-shaped reinforcing bars are installed in multiple rows upright along multiple cylindrical spaces almost concentrically with the ring girder, leaving the innermost row on the outside. In parallel with this reinforcement, from below to above, circular reinforcing bars are connected to the reinforcing bars in each of the inner and outer rows in a substantially concentric circle, and circular reinforcing bars are sequentially arranged horizontally at multiple locations in the vertical direction. Next, the lower half of the inner lining, which is divided into two upper and lower halves, to which a large number of stud bolts protrude radially from the outer periphery and are fixed, is placed concentrically with the innermost ring girder and inside of the construction scaffold. The upper half of the inner lining is placed vertically on the horizontal floor on the outside, and then, after placing the remaining innermost row of bar reinforcing bars and circular reinforcing bars, the upper half of the inner lining is centered over the lower half. The reactor pressure vessel is constructed by placing them together and welding the joint parts of the upper and lower halves, and then pouring and filling concrete between the outer lining and the inner lining, and then removing the construction scaffolding. Construction method of lower pedestal. 2. Stud bolts are fixed to the outer lining in advance at a plurality of specified locations on the inner periphery of the lower half of the lining, protruding toward the center at each of the plurality of specified locations on the inner periphery, and stud bolts protruding toward the center at each of the plurality of specified locations on the inner periphery and having a wall thickness approximately equal to the wall thickness of the cylindrical body. Insert and secure the length of the cylindrical sleeve,
2. The method of constructing a lower pedestal for a nuclear reactor pressure vessel according to claim 1, wherein a plurality of embedded metal objects are fixed in advance to the outer periphery of the outer lining with at least one surface exposed.
JP58145698A 1983-08-11 1983-08-11 Construction of lower pedestal of pressure container of nuclear reactor Granted JPS6037334A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58145698A JPS6037334A (en) 1983-08-11 1983-08-11 Construction of lower pedestal of pressure container of nuclear reactor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58145698A JPS6037334A (en) 1983-08-11 1983-08-11 Construction of lower pedestal of pressure container of nuclear reactor

Publications (2)

Publication Number Publication Date
JPS6037334A JPS6037334A (en) 1985-02-26
JPH0363607B2 true JPH0363607B2 (en) 1991-10-01

Family

ID=15391036

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58145698A Granted JPS6037334A (en) 1983-08-11 1983-08-11 Construction of lower pedestal of pressure container of nuclear reactor

Country Status (1)

Country Link
JP (1) JPS6037334A (en)

Also Published As

Publication number Publication date
JPS6037334A (en) 1985-02-26

Similar Documents

Publication Publication Date Title
JP2750368B2 (en) Construction method of reactor containment top slab
JPH0363607B2 (en)
US5076732A (en) Method for the construction of concrete shafts for a platform or similar structure and a section for similar use
US5351277A (en) Method of constructing top slab of nuclear reactor container and nuclear reactor container constructed by the method
JP2841953B2 (en) Construction method of steel containment reactor containment vessel
CN223293081U (en) An anchoring structure for steel pipe columns at beam-column joints of cast-in-place concrete garage roofs
JP3146119B2 (en) Reactor containment vessel
JPH11172964A (en) Tower structure construction method
JPH0672940B2 (en) Construction method of reactor containment superstructure
JPH01290849A (en) Skeleton structure of basement side wall
JP7029505B1 (en) Formwork unit and how to build the formwork
JPS63308B2 (en)
JP2669305B2 (en) Structure using covered steel tube concrete columns
JPH04281919A (en) Setting of buried type foot of steel frame post
JPS6338109B2 (en)
JP3308761B2 (en) Reactor containment vessel construction method
JPS62153795A (en) Reactor containment vessel diaphragm floor structure
JP2022063906A (en) Pile head isolation structure and construction method thereof
JPH0247588A (en) Pedestal made of steel
JPH0641979A (en) Foundation of steelwork frame
JPH0784082A (en) Construction method for lining wall of nuclear reactor facilities
JPH0587627B2 (en)
JPH03237391A (en) Storage container constructing method for nuclear power plant
JPS5925994B2 (en) Construction method for conical part of reinforced concrete shielding wall for nuclear reactor
JPS6321772B2 (en)