JPH0442496B2 - - Google Patents

Info

Publication number
JPH0442496B2
JPH0442496B2 JP6283588A JP6283588A JPH0442496B2 JP H0442496 B2 JPH0442496 B2 JP H0442496B2 JP 6283588 A JP6283588 A JP 6283588A JP 6283588 A JP6283588 A JP 6283588A JP H0442496 B2 JPH0442496 B2 JP H0442496B2
Authority
JP
Japan
Prior art keywords
water
trench
impermeable wall
sheets
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP6283588A
Other languages
Japanese (ja)
Other versions
JPH01235715A (en
Inventor
Shozo Konno
Nobuyuki Matsui
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6283588A priority Critical patent/JPH01235715A/en
Publication of JPH01235715A publication Critical patent/JPH01235715A/en
Publication of JPH0442496B2 publication Critical patent/JPH0442496B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は地中連続遮水工法に関するものであ
る。
[Detailed Description of the Invention] [Industrial Application Field] This invention relates to an underground continuous water-blocking method.

〔この発明が解決すべき課題〕[Problems to be solved by this invention]

地下構造物を施工中の地下水の湧水を防ぎ、或
いはダム工事における地下水の止水等を目的とし
てダム工事における地下水の止水等を目的として
地中連続壁を構築するか、シートパイルを打設し
てジヨイント部に注入を行う等の工法が採用され
ている。
Construct underground walls or install sheet piles to prevent groundwater from springing up during construction of underground structures, or to stop groundwater during dam construction. Construction methods have been adopted, such as placing the pipe in place and pouring it into the joint.

これら従来の工法を止水のみを目的として構築
する場合、以下のような問題がある。
When these conventional construction methods are used for construction purposes only to stop water, the following problems arise.

○イ 地中連続壁は必要以上の壁厚を施工するのが
通常であり、施工が不必要に大がかりとなると
ともに余分なコンクリートを大量に使用して施
工費が高価である。
○B Underground continuous walls are usually built with a wall thickness greater than necessary, making the construction unnecessarily large-scale and using a large amount of excess concrete, resulting in high construction costs.

○ロ シートパイルを打設してジヨイント部に注入
を行う工法も同じく施工が大がかりであり、材
料費が高価である。
○B The method of driving sheet piles and pouring into the joints also requires extensive construction and is expensive in material cost.

○ハ 地中連続壁において施工費を安価にするため
に壁厚を薄く作ることも考えられるが、狭巾の
溝を掘削し得る機械もなく、例え狭巾の溝が掘
れたとしてもコンクリートの流動性が損なわれ
て均質な地中壁は完成できない。
○C It is possible to make the wall thickness thinner in order to reduce construction costs for underground continuous walls, but there are no machines that can excavate narrow trenches, and even if a narrow trench could be dug, it would be difficult to make the wall thinner. A homogeneous underground wall cannot be completed due to the loss of fluidity.

○ニ また止水の確実性及び信頼性の点で見れば、
コンクリート壁は地震時のクラツクが止水性を
損なわせ、プレキヤストコンクリートパネルや
シートパイルを使用した工法ではジヨイント部
に夾雑物、ベントナイト等を挟み込み充分な止
水性能を得ることができなかつた。
○D Also, from the point of view of water stoppage certainty and reliability,
Cracks during earthquakes impair the water-stopping properties of concrete walls, and construction methods using precast concrete panels or sheet piles were unable to obtain sufficient water-stopping performance due to contaminants, bentonite, etc. being trapped in the joints.

この発明は、施工が容易であつて施工費が安価
となり、且つ止水の確実性、信頼性の高い遮水壁
を構築可能な地中連続遮水壁工法を提供すること
を目的とする。
An object of the present invention is to provide an underground continuous impermeable wall construction method that is easy to construct, has low construction cost, and can construct an impermeable wall that is highly reliable and reliable in stopping water.

〔課題を解決するための手段〕[Means to solve the problem]

この発明にかかる地中連続遮水壁工法は、隣り
合う遮水シートの連結に接着材を使用するもので
ある。
The continuous underground impermeable wall construction method according to the present invention uses an adhesive to connect adjacent impermeable sheets.

遮水シートの一表面の左右端部には上下に連続
する接着材を取付ける。左右に隣り合う遮水シー
トは接着材を向き合わせ部分に対応して上下方向
に連続するパツカーをシートの側方に配設する。
パツカーを膨張して両シートの接着材同士を圧着
し、隣り合うシートを連続させて溝巾方向左右に
仕切る。この溝内に遮水壁を構築する。
Attach vertically continuous adhesive to the left and right ends of one surface of the water-shielding sheet. For the water-shielding sheets that are adjacent to each other on the left and right, a patch car that is continuous in the vertical direction is arranged on the side of the sheet, corresponding to the facing portions of the adhesive material.
The packer is inflated and the adhesive material on both sheets is pressed together, making adjacent sheets continuous and partitioning them to the left and right in the groove width direction. A water-blocking wall will be constructed within this trench.

また溝内へは硬化材を注入して泥水を固化し、
遮水壁を構築することも可能である。ソイルモル
タルを充填してもよい。
In addition, hardening material is injected into the groove to solidify the muddy water.
It is also possible to construct water-tight walls. It may be filled with soil mortar.

またパツカー内には硬化材を充填して膨張さ
せ、パツカーを溝内に存置したままで埋殺して遮
水壁の一部とする。
In addition, a hardening material is filled in the packer and expanded, and the packer is left in the trench and buried to become part of the water-blocking wall.

〔作用〕[Effect]

溝掘削、遮水シート配設、泥水固化、或いはソ
イルモルタル充填という施工であり、施工が大が
かりにならず、簡易となる。
The construction involves digging trenches, installing a water-shielding sheet, solidifying mud, or filling with soil mortar, making the construction simple and unnecessary.

遮水シートを配設したため、クラツク等とは無
関係に止水性が確保される。
Because a water-blocking sheet is installed, water-blocking properties are ensured regardless of cracks, etc.

遮水シートは接着材同士を接着して連結するた
め、連結が容易に行える。
Since the water-blocking sheets are connected by bonding adhesives, connection can be easily performed.

〔実施例〕〔Example〕

以下、図に示す一実施例に基づきこの発明を詳
細に説明する。
Hereinafter, this invention will be explained in detail based on an embodiment shown in the drawings.

〈1〉 溝掘削 地盤に溝1を掘削する。溝1の巾は大きくなく
ともよく、その分施工が大がかりとならない。溝
1掘削にはオーガー等を使用し、溝1内には安定
液として泥水2を充填する。
<1> Trench excavation Excavate trench 1 in the ground. The width of the groove 1 does not need to be large, so the construction does not require a large scale. An auger or the like is used to excavate the groove 1, and the groove 1 is filled with muddy water 2 as a stabilizing liquid.

〈2〉 遮水シート 遮水シート3はポリエチレンシート等が採用で
きる。遮水シート3の一表面の左右両端部には上
下方向に連続して接着材4,4が取付けられてい
る。接着材4としてはアスフアルトゴム等が採用
でき、この接着材4上には離型紙5が貼着されて
いる。離型紙5の下端には剥離ロープ6が結びつ
けられている。
<2> Water-shielding sheet A polyethylene sheet or the like can be used as the water-shielding sheet 3. Adhesives 4, 4 are attached to both left and right ends of one surface of the water-blocking sheet 3 in a continuous manner in the vertical direction. Asphalt rubber or the like can be used as the adhesive 4, and a release paper 5 is stuck on the adhesive 4. A release rope 6 is tied to the lower end of the release paper 5.

〈3〉 遮水シート降下(第2図) 遮水シート3を溝1内に降下する。遮水シート
3は既降下の遮水シート3と端部同士を重ね合わ
せるようにし、接着材4,4を向き合わせるよう
にする。
<3> Lowering the water-shielding sheet (Fig. 2) Lower the water-shielding sheet 3 into the groove 1. The ends of the water-blocking sheet 3 are overlapped with the water-blocking sheet 3 that has already been lowered, and the adhesives 4, 4 are made to face each other.

この遮水シート3とともに袋状の長尺のパツカ
ー7を溝1内に降下する。パツカー7下端にはウ
エイト8がとりつけられており、接続バンド9に
よつて左右のワイヤロープ10,10と一体化さ
れている。
A long bag-shaped packer 7 is lowered into the groove 1 together with the water-blocking sheet 3. A weight 8 is attached to the lower end of the packer 7, and is integrated with left and right wire ropes 10, 10 by a connecting band 9.

パツカー7は例えば第9図のように下部側方に
エア吹込口11を有しており、またパツカー7下
部内には下方に向かつて開口するエアホース12
の上端はパツカー7外部へ突出して排水口13と
なつている。
The pack car 7 has an air blowing port 11 on the side of the lower part as shown in FIG.
The upper end of the drain port 13 protrudes to the outside of the pack car 7.

パツカー7は遮水シート3,3の接着材4,4
に対応して、一方の遮水シート3の接着材4を取
付けた面の裏面側に配設する。
Patsuka 7 is the adhesive material 4, 4 for the waterproof sheets 3, 3.
Correspondingly, the adhesive material 4 of one of the water-shielding sheets 3 is arranged on the back side of the surface on which it is attached.

〈4〉 遮水シート接着(第3図〜第6図) 以上のように遮水シート3,3とパツカー7を
溝1内に配設した後、剥離ロープ6,6を引いて
離型紙5,5を接着材4,4から引き離す。
<4> Adhesion of water-shielding sheets (Figures 3 to 6) After arranging the water-shielding sheets 3, 3 and the packer 7 in the groove 1 as described above, pull the release ropes 6, 6 to attach the release paper 5. , 5 from the adhesive 4, 4.

パツカー7内に泥水を注入してパツカー7を膨
張させ、遮水シート3,3を溝1の内壁に押しつ
けて接着材4,4同士を接着する。以上のように
して遮水シート3,3を連結する。
Mud water is injected into the packer 7 to expand the packer 7, and the waterproof sheets 3, 3 are pressed against the inner wall of the groove 1 to bond the adhesive materials 4, 4 together. The water-blocking sheets 3, 3 are connected in the above manner.

〈5〉 泥水固化(第4図) パツカー7によつて仕切つた溝1の泥水2内に
モルタル、コンクリート等の硬化材14を注入し
て泥水を固化し、遮水壁を構築する。
<5> Solidification of muddy water (Fig. 4) A hardening material 14 such as mortar or concrete is injected into the muddy water 2 in the groove 1 partitioned by the pack car 7 to solidify the muddy water and construct an impermeable wall.

泥水固化後、パツカー7内の圧力水を排出して
パツカー7を回収する。前記第9図のようなパツ
カー7であれば、エア吹込口11から空気を注入
し、エアホース12を通して水をパツカー7の外
へ排出可能となる。
After the muddy water has solidified, the pressure water in the pack car 7 is discharged and the pack car 7 is recovered. With the pack car 7 as shown in FIG. 9, air can be injected from the air inlet 11 and water can be discharged from the pack car 7 through the air hose 12.

岩等の自立性の良い土質の場合は、泥水を必要
とせず無水掘削が可能であり、シート配設後の溝
内の充填剤は泥水固化でなく、ソイルモルタルを
流入させる。
In the case of soil with good self-supporting properties such as rocks, waterless excavation is possible without the need for muddy water, and the filler in the trench after sheet placement is not solidified with muddy water, but filled with soil mortar.

〈6〉 パツカー埋設し 上記の発明以外に、パツカー7にモルタル等の
硬化材を充填して硬化させ、溝1内に埋設して遮
水壁の一部としてもよい。
<6> Burying the packer In addition to the invention described above, the packer 7 may be filled with a hardening material such as mortar and hardened, and then buried in the groove 1 to serve as a part of the water-shielding wall.

〔発明の効果〕〔Effect of the invention〕

この発明は以上のような構成を有し、以下のよ
うな効果を得ることができる。
The present invention has the above configuration and can obtain the following effects.

○イ 溝を掘削し、遮水シートを配設し、泥水をを
固化、或いはソイルモルタルを充填するだけで
あるため、施工は容易となり、大がかりな施工
は不要で施工費は安価となる。
○B. Construction is easy, as it only involves digging a trench, placing a water-shielding sheet, solidifying the muddy water, or filling it with soil mortar, and there is no need for large-scale construction, making the construction cost low.

○ロ 完成した止水壁は内側に遮水シートを挟み込
むため、地震等によるクラツクが発生しても止
水が損なわれることがなく、確実性、信頼性が
高くなる。
○B The completed water-stopping wall will have a water-stopping sheet sandwiched inside, so even if a crack occurs due to an earthquake, the water-stopping will not be impaired, making it more reliable and reliable.

○ハ 泥水を固化し、或いはソイルモルタルを充填
して構築するため、地中壁全体を均一な地中壁
とすることができる。また例え強度の低下する
部分が生じても上記のように遮水シートによつ
て止水性は確保される。
○C Because it is constructed by solidifying muddy water or filling it with soil mortar, the entire underground wall can be made into a uniform underground wall. Furthermore, even if there is a portion where the strength is reduced, water-stopping properties are ensured by the water-blocking sheet as described above.

○ニ 遮水シートは接着材同士を圧着することによ
つて連結するため、連結が容易である。
○D Waterproof sheets are easily connected because they are connected by pressing adhesives together.

○ホ パツカーに硬化材を充填して埋設すれば、回
収の手間もいらず、施工が更に容易となる。
○If the hardening material is filled in a hot pack car and buried, there will be no need to collect it, making construction even easier.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第8図はこの発明の施工順序を示し、
第1図、第2図、第4図、第6図〜第8図のは
斜視図、は平面図、第3図及び第5図は斜視
図、第9図はパツカーの一部切欠き斜視図であ
る。 1……溝、2……泥水、3……遮水シート、4
……接着材、5……離型紙、7……パツカー。
Figures 1 to 8 show the construction order of this invention,
Figures 1, 2, 4, and 6 to 8 are perspective views, are plan views, Figures 3 and 5 are perspective views, and Figure 9 is a partially cutaway perspective view of the pack car. It is a diagram. 1...Gutter, 2...Muddy water, 3...Waterproof sheet, 4
... Adhesive, 5... Release paper, 7... Packer.

Claims (1)

【特許請求の範囲】 1 地盤に形成した溝内に吊り降ろす遮水シート
の一表面の左右端部には上下に連続する接着材を
取付け、左右に隣り合う遮水シートは接着材を向
き合わせて吊り降ろし、両シートの合わせ部分に
対応して上下方向に連続するパツカーをシートの
側方に配設し、パツカーを膨張して両シートの接
着材同士を圧着し、隣り合うシートを連続させて
溝を巾方向左右に仕切り、この溝内に遮水壁を構
築することを特徴とする地中連続壁遮水工法。 2 溝内に硬化材を注入して泥水を固化し、遮水
壁を構築することを特徴とする請求項1記載の地
中連続遮水壁工法。 3 溝内にソイルモルタル充填して遮水壁を構築
したことを特徴とする請求項1記載の地中連続遮
水壁工法。 4 パツカー内には硬化材を充填して膨張させ、
溝内に埋殺して遮水壁の一部とすることを特徴と
する請求項1,2又は3記載の地中連続遮水壁工
法。
[Scope of Claims] 1. Adhesive material is attached vertically and continuously to the left and right ends of one surface of one surface of the water-shielding sheet suspended in a groove formed in the ground, and the adhesive materials are placed facing each other on the left and right adjacent water-shielding sheets. Then, a patch car that is continuous in the vertical direction is placed on the side of the sheet corresponding to the joining part of both sheets, and the patch car is inflated and the adhesive material of both sheets is pressed together to connect the adjacent sheets. This method is characterized by dividing a trench into left and right sides in the width direction, and constructing a water-blocking wall within the trench. 2. The underground continuous impermeable wall construction method according to claim 1, wherein the impermeable wall is constructed by injecting a hardening material into the trench to solidify the muddy water. 3. The underground continuous impermeable wall construction method according to claim 1, wherein the impermeable wall is constructed by filling the trench with soil mortar. 4 Fill the inside of the pack with hardening material and expand it.
4. The underground continuous impermeable wall construction method according to claim 1, 2 or 3, wherein the underground continuous impermeable wall is buried in a trench to form a part of the impermeable wall.
JP6283588A 1988-03-16 1988-03-16 Underground continuous impermeable wall method Granted JPH01235715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6283588A JPH01235715A (en) 1988-03-16 1988-03-16 Underground continuous impermeable wall method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6283588A JPH01235715A (en) 1988-03-16 1988-03-16 Underground continuous impermeable wall method

Publications (2)

Publication Number Publication Date
JPH01235715A JPH01235715A (en) 1989-09-20
JPH0442496B2 true JPH0442496B2 (en) 1992-07-13

Family

ID=13211769

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6283588A Granted JPH01235715A (en) 1988-03-16 1988-03-16 Underground continuous impermeable wall method

Country Status (1)

Country Link
JP (1) JPH01235715A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11350469A (en) * 1998-06-03 1999-12-21 Nishimatsu Constr Co Ltd Waterproof sheet insertion method and watertight sheet insertion device
JP6276595B2 (en) * 2014-01-10 2018-02-07 前田建設工業株式会社 Underwater connection method and apparatus for impermeable sheet, and water stop construction method for underground continuous wall

Also Published As

Publication number Publication date
JPH01235715A (en) 1989-09-20

Similar Documents

Publication Publication Date Title
JPH0443525B2 (en)
CN113323017B (en) Construction method of side wall fertilizer groove foam concrete backfill system
KR102614901B1 (en) Water and root proofing, construction method of composite wall, CIP wall, retaining wall, underground wall, parking lot, underground structure
CN107542115A (en) Underground project waterproof structure and its construction method
CN117513363B (en) Pit-within-pit narrow trough fluidized solidified soil backfill system and construction method
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
CN111441789A (en) Foam concrete transition structure and construction method for bridge-tunnel connection in high and steep terrain
JPH0442496B2 (en)
CN214363691U (en) Repair structure for uneven settlement of underground gallery
CN215857803U (en) Gushing karst fracture water plugging device
CN109306695A (en) Reusable underground diaphragm wall structure and construction method thereof
CN212130501U (en) Foam concrete transition structure for bridge-tunnel connection in high and steep terrain
CN113502851A (en) Construction method of open cut tunnel extension foam concrete backfill structure
JP2595760Y2 (en) Communication line accommodating flexible trough device and communication line accommodating flexible trough
JP2668922B2 (en) Seismic structure of excavated road
JP4081659B2 (en) Impervious plate, connection structure of impermeable plate, and construction method of impermeable wall
JPH0433326B2 (en)
CN220080027U (en) Structure is handled to crossing node of interim stand of foundation ditch and bottom plate
JPH0442495B2 (en)
JPH0617421A (en) Construction method of continuous underground water stop wall
CN114775578B (en) Rotary excavation steel sheet pile under complex stratum and construction process
CN218292040U (en) Row of undercut piping lane tunnel, waterproof composite construction
JPH0786229B2 (en) Impermeable wall using impermeable sheet, construction method thereof, and impermeable sheet used for impermeable wall
CN115853581A (en) Tunnel drainage construction method
JPS60250119A (en) Construction method of underground concrete pipe structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 16

Free format text: PAYMENT UNTIL: 20080713