JPH0660631U - Jig for suspending core material - Google Patents

Jig for suspending core material

Info

Publication number
JPH0660631U
JPH0660631U JP3146292U JP3146292U JPH0660631U JP H0660631 U JPH0660631 U JP H0660631U JP 3146292 U JP3146292 U JP 3146292U JP 3146292 U JP3146292 U JP 3146292U JP H0660631 U JPH0660631 U JP H0660631U
Authority
JP
Japan
Prior art keywords
core material
jig
pin
steel core
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3146292U
Other languages
Japanese (ja)
Other versions
JP2529646Y2 (en
Inventor
友行 相模
忠男 村野
安功 花田
良隆 恒見
功 柳沢
信 高清水
菊司 千明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP3146292U priority Critical patent/JP2529646Y2/en
Publication of JPH0660631U publication Critical patent/JPH0660631U/en
Application granted granted Critical
Publication of JP2529646Y2 publication Critical patent/JP2529646Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

(57)【要約】 (修正有) 【目的】 芯材の吊込み用治具に関し、治具用H鋼芯材
と建て込み用芯材との連結の解除をスムーズに行うこと
ができる芯材の吊込み用治具を提供する。 【構成】 ピン挿通孔41が穿設された2枚のプレート
43,45が下端部に取り付く治具用H鋼芯材37と、
治具用H鋼芯材のフランジ37b間に架設された軸に回
動自在に取り付き、地上から延びる操作ワイヤ53が連
結された回動部材47と、回動部材に回動可能に取り付
き、上記ピン挿通孔41に挿入されると共に、その挿入
側先端に抜止め鉄筋挿通部が形成され、操作ワイヤ53
の引張操作による回動部材47の回転でピン挿通孔41
から引き抜かれる固定ピン55と、地上から延長され芯
材37の建て込み時に上記ピン挿通孔41に挿入された
固定ピン55を位置決めして固定ピンの抜止めを図る抜
止め鉄筋57からなる。
(57) [Summary] (Corrected) [Purpose] Regarding the jig for suspending the core material, the core material that can smoothly release the connection between the H steel core material for the jig and the building core material. To provide a hanging jig. [Structure] An H steel core material 37 for a jig having two plates 43 and 45 having pin insertion holes 41 attached to the lower end thereof,
The rotary member 47 is rotatably attached to a shaft that is installed between the flanges 37b of the H steel core material for jigs, and is rotatably attached to the rotating member 47 to which the operation wire 53 extending from the ground is connected, and the rotating member. The operation wire 53 is inserted into the pin insertion hole 41, and a retaining bar insertion portion is formed at the distal end of the insertion side.
The rotation of the rotating member 47 by the pulling operation of the pin insert hole 41
It is composed of a fixing pin 55 that is pulled out from the above, and a retaining bar 57 that extends from the ground and is inserted into the pin insertion hole 41 when the core member 37 is built up to position the fixing pin 55 to prevent the fixing pin from coming off.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、山止め芯材等の建て込みに用いる吊込み用治具の改良に関する。 The present invention relates to an improvement of a hanging jig used for building a mountain stopper core material and the like.

【0002】[0002]

【従来の技術】[Prior art]

土木,建築等の地下構造物を構築するに当たり、従来、掘削部分やその周辺地 盤の崩壊変形を防ぐために山止め工事が行われており、この山止め工事の方法と して、種々の条件に対応する多くの山止め壁の構築工法が知られている。 In constructing underground structures such as civil engineering and buildings, cliff retaining work has been conventionally performed to prevent collapse deformation of the excavated portion and the surrounding ground, and various conditions are used as this cliff retaining method. There are many known construction methods of mountain stop walls.

【0003】 そして、この構築工法の一つとして、例えばアースオーガーで地中を攪拌し、 同時にベントナイトモルタルを圧入してソイル柱を作り、その中にH鋼等の芯材 を建て込み、これを連続して山止め壁を構築するソイルパイル工法があり、この 工法は現場の土砂をそのまま利用してソイル柱を作るため、土砂を地上に搬出す る量が少ない利点を有する。Then, as one of the construction methods, for example, an earth auger is used to stir the ground, and at the same time bentonite mortar is press-fitted to make a soil pillar, and a core material such as H steel is built in the pillar. There is a soil pile method that continuously constructs a cliff wall, and this method has the advantage that the amount of earth and sand carried out is small because soil pillars are made using the earth and sand as it is.

【0004】 ところで、従来、この種の芯材の建て込み作業に於て、建入れ精度を確保する ために吊込み用治具(落し込みアタッチメント)が使用されることがある。 即ち、上述したように上記ソイルパイル工法ではソイル柱に芯材を建て込み、 これを連続して山止め壁を構築するが、芯材をソイル柱に建て込んだ初期の段階 では未だベントナイトモルタルが柔らかいため、芯材を支えて位置決めをしてお く必要がある。そこで、芯材の上部に吊込み用治具を取り付け、そして、この吊 込み用治具を介して芯材を地上からクレーンで支持しておき、ベントナイトモル タルがある程度硬化した段階で、吊込み用治具を地上からの操作で外してこれを 引き上げている。By the way, conventionally, in the work of assembling the core material of this type, a hanging jig (drop attachment) may be used in order to secure the assembling accuracy. That is, as described above, in the soil pile method, the core material is built in the soil pillar and the mountain retaining wall is continuously constructed, but at the early stage when the core material is built in the soil pillar, the bentonite mortar is still soft. Therefore, it is necessary to support the core material for positioning. Therefore, a suspending jig was attached to the upper part of the core material, and the core material was supported by a crane from the ground via this suspending jig, and when the bentonite mortar had hardened to some extent, the suspending jig was suspended. The jig is removed from the ground and pulled up.

【0005】 図6は従来の吊込み用治具の要部斜視図を示し、図中、1は地上からクレーン で吊り下げられた治具用H鋼芯材で、図7に示すようにその下端部には、ピン挿 通孔3が同軸上に穿設されたプレート5,7がウェブ1aの両面に取り付けられ ており、両プレート5,7間に、ソイル柱に建て込むH鋼芯材9のウェブ9aの 上端部が挿入できるようになっている。そして、H鋼芯材9のウェブ9aにも、 ピン挿通孔3と同一径のピン挿通孔11が上部に穿設されており、図7に示すよ うに両プレート5,7間にウェブ9aを挿入したとき、各ピン挿通孔3,11が 同軸上に位置するようになっている。FIG. 6 is a perspective view of a main part of a conventional hoisting jig. In the figure, 1 is an H steel core material for a jig that is suspended from the ground by a crane, and as shown in FIG. At the lower end, plates 5 and 7 with pin insertion holes 3 coaxially drilled are attached to both sides of the web 1a, and between the plates 5 and 7, H steel core material to be built in a soil column. The upper end of the web 9a of 9 can be inserted. A pin insertion hole 11 having the same diameter as the pin insertion hole 3 is also formed in the upper part of the web 9a of the H steel core material 9. As shown in FIG. 7, the web 9a is formed between the plates 5 and 7. When inserted, the pin insertion holes 3 and 11 are positioned coaxially.

【0006】 又、図中、13は上記プレート5に装着されたロック装置13で、当該ロック 装置13は、ピン挿通孔3と同軸上に取り付く筒体15と、当該筒体15内を矢 印A,B方向へ移動可能なピン17と、このピン17を矢印B方向へ付勢するス プリング19、そして、ロック解除ピン21とで構成されている。Further, in the figure, 13 is a lock device 13 mounted on the plate 5, and the lock device 13 has a cylindrical body 15 attached coaxially with the pin insertion hole 3 and an arrow inside the cylindrical body 15. It is composed of a pin 17 movable in the A and B directions, a spring 19 for urging the pin 17 in the arrow B direction, and a lock release pin 21.

【0007】 そして、筒体15の一端には上記ピン挿通孔3と連通するピン挿通孔23が形 成され、又、筒体15の他端側には、ピン17の端部に取り付けられた押し込み ロッド25が挿通するロッド挿通孔27が設けられており、押し込みロッド25 はロッド挿通孔27を介して筒体15の端部から外方へ常時突出した寸法に設定 されている。A pin insertion hole 23 communicating with the pin insertion hole 3 is formed at one end of the cylindrical body 15, and the other end of the cylindrical body 15 is attached to an end of a pin 17. A rod insertion hole 27 through which the push rod 25 is inserted is provided, and the push rod 25 is set to have a size that is always projected outward from the end of the tubular body 15 via the rod insertion hole 27.

【0008】 一方、図7に示すように筒体15内のピン17は、プレート5側に縮径部17 aが形成されており、当該縮径部17aの外周にピン17を矢印B方向へ付勢す るスプリング19が装着されている。そして、当該スプリング19のばね力に抗 して押し込みロッド25を矢印A方向へ押し込むと、上記縮径部17aがピン挿 通孔23を介してピン挿通孔3,11に挿入されるようになっている。On the other hand, as shown in FIG. 7, the pin 17 in the tubular body 15 has a reduced diameter portion 17 a formed on the plate 5 side, and the pin 17 is formed on the outer periphery of the reduced diameter portion 17 a in the direction of arrow B. A biasing spring 19 is attached. When the pushing rod 25 is pushed in the direction of arrow A against the spring force of the spring 19, the reduced diameter portion 17a is inserted into the pin insertion holes 3 and 11 via the pin insertion hole 23. ing.

【0009】 又、筒体15の周壁には、ロック解除ピン21が貫通する解除ピン貫通孔29 が上下方向に穿設されており、スプリング19のばね力に抗して落し込みロッド 25を矢印A方向へ押し込んで、上記縮径部17aをピン挿通孔3,11に挿入 した後、ロック解除ピン21を解除ピン貫通孔29に挿入すると、図8に示すよ うにロック解除ピン21がピン17の端部31に当接してピン17の矢印B方向 への移動が規制されて、H鋼芯材9が治具用H鋼芯材1と連結されるようになっ ている。Further, a release pin through hole 29 through which the lock release pin 21 penetrates is formed in the peripheral wall of the cylindrical body 15 in the up-down direction, and the drop rod 25 is arrowed against the spring force of the spring 19. When the lock release pin 21 is inserted into the release pin through hole 29 after inserting the reduced diameter portion 17a into the pin insertion holes 3 and 11 by pushing in the direction A, as shown in FIG. The H steel core material 9 is connected to the jig H steel core material 1 by restricting the movement of the pin 17 in the arrow B direction by contacting the end portion 31 of the.

【0010】 従って、図8に示すように、H鋼芯材9の上端部に治具用H鋼芯材1を連結し てクレーンでこれらをソイル柱33内に建て込み、ソイル柱33がある程度硬化 するまでH鋼芯材9を支持しておけば、H鋼芯材9の建入れ精度が確保できるこ ととなる。Therefore, as shown in FIG. 8, the jig H steel core material 1 is connected to the upper end portion of the H steel core material 9 and these are built in the soil pillar 33 by a crane. If the H-steel core material 9 is supported until it hardens, the H-steel core material 9 can be installed with high accuracy.

【0011】 そして、ソイル柱33がある程度硬化した段階で、図9に示すようにロック解 除ピン21に結んだワイヤ35を地上から引っ張って解除ピン貫通孔29からロ ック解除ピン21を引き抜けば、スプリング19の復元力によりピン17が矢印 B方向へ移動して治具用H鋼芯材1とH鋼芯材9との連結が解除されるので、治 具用H鋼芯材1を地上にクレーンで引き上げればよい。Then, when the soil pillar 33 is hardened to some extent, the wire 35 connected to the lock release pin 21 is pulled from the ground to pull the lock release pin 21 from the release pin through hole 29 as shown in FIG. If it is pulled out, the restoring force of the spring 19 causes the pin 17 to move in the direction of arrow B to release the connection between the jig H steel core material 1 and the H steel core material 9, so that the jig H steel core material 1 Can be lifted to the ground with a crane.

【0012】[0012]

【考案が解決しようとする課題】[Problems to be solved by the device]

然し乍ら、上述の如き従来の吊込み用治具にあっては、ソイル柱33内に建て 込むことによってベントナイトモルタルがピン挿通孔3,11,23を介して筒 体15内に浸入してしまうため、ベントナイトモルタルがスプリング19の復元 力に支障を来して治具用H鋼芯材1とH鋼芯材9との連結解除がスムーズに行わ れず、又、筒体15内に浸入したベントナイトモルタルの除去作業が面倒である といった欠点があった。 However, in the conventional hanging jig as described above, when it is built in the soil column 33, the bentonite mortar penetrates into the cylindrical body 15 through the pin insertion holes 3, 11 and 23. The bentonite mortar interferes with the restoring force of the spring 19 so that the H steel core material 1 for jigs and the H steel core material 9 are not disconnected smoothly, and the bentonite mortar that has penetrated into the tubular body 15 There was a drawback that the removal work of was troublesome.

【0013】 本考案は斯かる実情に鑑み案出されたもので、構造が簡単で治具用H鋼芯材と 建込み用芯材との連結解除をスムーズに行うことのできる芯材の吊込み用治具を 提供することを目的とする。The present invention has been devised in view of the above circumstances, and has a simple structure and is capable of smoothly releasing the connection between the H steel core material for jigs and the building core material. The purpose is to provide an embedding jig.

【0014】[0014]

【課題を解決するための手段】[Means for Solving the Problems]

斯かる目的を達成するため、本考案に係る芯材の吊込み用治具は、地上からク レーン等で懸吊され、ウェブの下端部の両面に、ピン挿通孔が同軸上に穿設され た2枚のプレートが取り付く治具用H鋼芯材と、治具用H鋼芯材のフランジ間に 架設された支持軸に回動自在に取り付き、地上から延びる操作ワイヤが連結され た回動部材と、当該回動部材に回動可能に取り付き、上記両プレートのピン挿通 孔に挿入されると共に、その挿入側先端に抜止め鉄筋挿通部が形成され、操作ワ イヤの引張操作による回動部材の回転に連動してピン挿通孔から引き抜かれる固 定ピンと、地上から延長され、芯材の建て込み時に上記ピン挿通孔に挿入された 固定ピンを位置決めして固定ピンの抜止めを図る抜止め鉄筋と、からなるもので ある。 In order to achieve such an object, the jig for suspending a core material according to the present invention is suspended from the ground by a crane or the like, and pin insertion holes are coaxially formed on both sides of the lower end portion of the web. The H-core core material for jigs to which two plates are attached, and the support shaft erected between the flanges of the H-steel core material for jigs are rotatably attached, and the operation wire extending from the ground is connected Member and rotatably attached to the rotating member, inserted into the pin insertion holes of both plates, and a retaining bar insertion portion is formed at the tip of the insertion side, and rotation by pulling operation wire is performed. The fixed pin that is pulled out from the pin insertion hole in conjunction with the rotation of the member and the fixed pin that is extended from the ground and inserted into the pin insertion hole when building the core material are positioned to prevent the fixed pin from coming off. It consists of a retaining bar.

【0015】[0015]

【作用】[Action]

建込み用芯材の建入れ精度を確保するために本考案に係る吊込み用治具を用い るには、先ず、両プレート間に芯材を挿入し、そして、プレートに設けたピン挿 通孔に固定ピンを挿入して、抜止め鉄筋で固定ピンを位置決めすれば、治具用H 鋼芯材に芯材が連結されることとなる。 In order to use the hoisting jig according to the present invention to ensure the installation accuracy of the core material for installation, first insert the core material between both plates, and then insert the pins provided on the plates. When the fixing pin is inserted into the hole and the fixing pin is positioned by the retaining bar, the core material is connected to the H steel core material for jigs.

【0016】 そして、これらをクレーン等でソイル柱内に建て込み、ソイル柱がある程度硬 化するまで芯材を支持しておけば、芯材の建入れ精度が確保できることとなる。 そして、ソイル柱がある程度硬化した段階で、抜止め鉄筋を地上から操作して 固定ピンの位置決めを解除した後、操作ワイヤを地上から引っ張ると、回動部材 が支持軸を中心に一方向へ移動してピン挿通孔に挿入された固定ピンが引き抜か れることとなる。Then, if these are built in the soil pillar with a crane or the like and the core material is supported until the soil pillar is hardened to some extent, the accuracy of the core material installation can be secured. When the soil pillar has hardened to some extent, the retaining bar is operated from the ground to release the positioning of the fixing pin, and then the operation wire is pulled from the ground, and the rotating member moves in one direction around the support shaft. Then, the fixed pin inserted in the pin insertion hole is pulled out.

【0017】 このように固定ピンが引き抜かれることによって芯材と治具用H鋼芯材との連 結が解除されるので、最後に治具用H鋼芯材を地上にクレーン等で引き上げれば よい。By pulling out the fixing pin in this way, the connection between the core material and the H steel core material for jigs is released, and finally the H steel core material for jigs is pulled up to the ground by a crane or the like. Good.

【0018】[0018]

【実施例】【Example】

以下、本考案の一実施例を図面に基づき詳細に説明する。尚、図6以下に示す 従来例と同一のものは同一符号を以って表示する。 Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. The same parts as those in the conventional example shown in FIG.

【0019】 図1は本考案に係る吊込み用治具の要部断面図を示し、図中、37は治具用H 鋼芯材で、当該治具用H鋼芯材37は図6に示す治具用H鋼芯材1と同様、地上 からクレーンで懸吊されており、その下端部には、ピン挿通孔39,41が同軸 上に穿設されたプレート43,45がウェブ37aの両面に夫々取り付けられて いる。そして、図2に示すように、両プレート43,45間にH鋼芯材9のウェ ブ9aを挿入したとき、ピン挿通孔39,41とH鋼芯材9のピン挿通孔11が 同軸上に位置するようになっている。FIG. 1 is a sectional view of a main part of a hoisting jig according to the present invention. In FIG. 1, 37 is a jig H steel core material, and FIG. 6 shows the jig H steel core material 37. Similar to the H steel core material 1 for jig shown, it is suspended from the ground by a crane, and at its lower end, plates 43 and 45 having pin insertion holes 39 and 41 coaxially formed are formed on the web 37a. It is attached to each side. Then, as shown in FIG. 2, when the web 9a of the H steel core material 9 is inserted between the plates 43 and 45, the pin insertion holes 39 and 41 and the pin insertion hole 11 of the H steel core material 9 are coaxial. It is located in.

【0020】 又、47は図3に示すように治具用H鋼芯材37のフランジ37b間に架設さ れた支持軸49に回動自在に取り付く回動部材で、当該回動部材47は略く字に 成形された回動操作部47aと、当該回動操作部47aから下方に延びるアーム 部47bとで構成されており、回動操作部47aは、図1及び図4に示すように ウェブ37aに形成されたスリット51を挿通してその挿入側端部が上記支持軸 49に軸着されている。又、回動操作部47aの端部には地上から延びる操作ワ イヤ53が連結されており、図1に示すように当該操作ワイヤ53を上方へ引っ 張ることによって、回動操作部47aが支持軸49を中心に矢印C方向へ回転す るようになっている。Reference numeral 47 is a rotary member that is rotatably attached to a support shaft 49 that is installed between the flanges 37b of the H steel core material 37 for jigs as shown in FIG. The rotary operation part 47a is formed in a substantially V shape, and the arm part 47b extends downward from the rotary operation part 47a. The rotary operation part 47a is, as shown in FIGS. The slit 51 formed in the web 37a is inserted, and the end portion on the insertion side is pivotally attached to the support shaft 49. An operation wire 53 extending from the ground is connected to the end of the rotation operation portion 47a, and the rotation operation portion 47a is supported by pulling the operation wire 53 upward as shown in FIG. It is adapted to rotate in the direction of arrow C about the shaft 49.

【0021】 一方、図1に示すように、アーム部47bの先端にはピン挿通孔39,41に 挿入可能な固定ピン55が矢印方向へ回動自在に取り付けられており、図5の如 く操作ワイヤ53の引張操作によって回動操作部47aが矢印C方向へ回転する と、アーム部47bが矢印D方向に移動し、そして、ピン挿通孔39,41に挿 入された固定ピン55がこれに連動してピン挿通孔39,41から引き抜かれる ようになっている。On the other hand, as shown in FIG. 1, a fixing pin 55 that can be inserted into the pin insertion holes 39 and 41 is attached to the tip of the arm portion 47b so as to be rotatable in the arrow direction, as shown in FIG. When the rotating operation portion 47a is rotated in the arrow C direction by the pulling operation of the operation wire 53, the arm portion 47b is moved in the arrow D direction, and the fixing pin 55 inserted into the pin insertion holes 39 and 41 is released. It is designed to be pulled out from the pin insertion holes 39, 41 in conjunction with.

【0022】 又、図中、57は地上から延長された抜止め鉄筋で、当該抜止め鉄筋57は、 H鋼芯材9の建て込み時にピン挿通孔39,11,41から固定ピン55が抜け ないようにその抜け止めを図るもので、図3に示すように回動操作部47aの一 側面に取り付けたU字状の案内部材59を挿通して下方に延び、そして、図2に 示すようにピン挿通孔39,11,41に挿入された固定ピン55の挿入側端部 に穿設した鉄筋挿通孔61に挿入されている。又、抜止め鉄筋57の先端側には 鉄筋抜止め部材63が取り付けられており、抜止め鉄筋57を引き上げた際に、 当該鉄筋抜止め部材63が案内部材59に当接して抜止め鉄筋57が回動部材4 7から外れないようになっている。尚、図2に示すように鉄筋抜止め部材63は 、抜止め鉄筋57を固定ピン55の鉄筋挿通孔61から引き抜く際に支障を来す ことのない位置に取り付けられている。Further, in the figure, reference numeral 57 denotes a retaining reinforcing bar extended from the ground. The retaining reinforcing bar 57 is such that the fixing pin 55 is pulled out from the pin insertion holes 39, 11, 41 when the H steel core 9 is installed. As shown in FIG. 3, the U-shaped guide member 59 attached to one side surface of the rotation operation portion 47a is inserted to extend downward as shown in FIG. The fixing pin 55 inserted into the pin insertion holes 39, 11, 41 is inserted into the reinforcing bar insertion hole 61 formed at the insertion side end portion. Further, a reinforcing bar retaining member 63 is attached to the tip side of the retaining bar 57, and when the retaining bar 57 is pulled up, the retaining bar 63 comes into contact with the guide member 59 to prevent the retaining bar 57. Does not come off from the rotating member 47. As shown in FIG. 2, the reinforcing bar retaining member 63 is attached to a position that does not cause any trouble when the retaining bar 57 is pulled out from the reinforcing rod insertion hole 61 of the fixing pin 55.

【0023】 本実施例に係る吊込み用治具はこのように構成されているから、H鋼芯材9の 建入れ精度を確保するために上記吊込み用治具を用いるには、先ず、図2に示す ように、両プレート43,45間にH鋼芯材9のウェブ9aを挿入し、そして、 ピン挿通孔39,11,41に固定ピン55を挿入してその挿入側端部の鉄筋挿 通孔61に抜止め鉄筋57を挿通させれば、H鋼芯材9が治具用H鋼芯材37に 連結されることとなる。Since the hanging jig according to the present embodiment is configured as described above, in order to use the hanging jig in order to secure the installation accuracy of the H steel core material 9, first, As shown in FIG. 2, the web 9a of the H-steel core material 9 is inserted between the plates 43 and 45, and the fixing pin 55 is inserted into the pin insertion holes 39, 11, and 41 to insert the end portions of the insertion side. When the retaining bar 57 is inserted through the reinforcing bar insertion hole 61, the H steel core material 9 is connected to the jig H steel core material 37.

【0024】 そして、これらをクレーンで図5に示すようにソイル柱33内に建て込み、ソ イル柱33がある程度硬化するまでH鋼芯材9を支持しておけば、H鋼芯材9の 建入れ精度が確保できることとなる。Then, these are built in the soil column 33 with a crane as shown in FIG. 5, and if the H steel core material 9 is supported until the soil column 33 is hardened to some extent, the H steel core material 9 Construction accuracy can be secured.

【0025】 そして、ソイル柱33がある程度硬化した段階で、図5に示すように抜止め鉄 筋57を地上から引っ張って固定ピン55の鉄筋挿通孔61から引き抜いた後、 操作ワイヤ53を地上から引っ張ると、回動操作部47aが支持軸49を中心と して矢印C方向へ回転すると共にアーム部47bが矢印D方向に移動して、ピン 挿通孔39,11,41に挿入された固定ピン55が引き抜かれることとなる。Then, when the soil pillar 33 has hardened to some extent, as shown in FIG. 5, the retaining bar 57 is pulled from the ground and pulled out from the reinforcing bar insertion hole 61 of the fixing pin 55, and then the operation wire 53 is grounded. When pulled, the rotating operation part 47a rotates about the support shaft 49 in the direction of arrow C, and the arm part 47b moves in the direction of arrow D, so that the fixing pin inserted into the pin insertion hole 39, 11, 41. 55 will be pulled out.

【0026】 このように固定ピン55が引き抜かれることによってH鋼芯材9と治具用H鋼 芯材37との連結が解除されるので、最後に治具用H鋼芯材37を地上にクレー ンで引き上げればよい。By pulling out the fixing pin 55 in this way, the connection between the H steel core material 9 and the jig H steel core material 37 is released, and finally, the jig H steel core material 37 is placed on the ground. Just pull it up with the crane.

【0027】 従って、本実施例によっても、H鋼芯材9の建て込み作業に於てその建入れ精 度を確保することが可能である。 又、上述したように図6に示す従来の吊込み用治具では、ソイル柱33内にH 鋼芯材9を建て込むことによってベントナイトモルタルがピン挿通孔3,11, 23を介して筒体15内に浸入してしまうため、ベントナイトモルタルがスプリ ング19の復元力に支障を来して治具用H鋼芯材1とH鋼芯材9との連結解除が スムーズに行われないといった欠点があったが、本実施例によれば、地上からの 操作ワイヤ53の操作によって固定ピン55がピン挿通孔39,11,41から 確実に引き抜かれるため、治具用H鋼芯材37とH鋼芯材9との連結解除がスム ーズに且つ確実に行うことができることとなった。Therefore, according to the present embodiment as well, it is possible to secure the installation accuracy of the H steel core material 9 during the installation operation. Further, as described above, in the conventional hanging jig shown in FIG. 6, bentonite mortar is inserted into the cylindrical body through the pin insertion holes 3, 11, 23 by building the H 2 steel core material 9 in the soil column 33. Since the bentonite mortar interferes with the restoring force of the spring 19 because it penetrates into the inside 15, the connection between the H steel core material 1 for jigs and the H steel core material 9 cannot be released smoothly. However, according to the present embodiment, since the fixing pin 55 is reliably pulled out from the pin insertion holes 39, 11, 41 by the operation of the operation wire 53 from the ground, the H steel core materials 37 and H for jigs are provided. The connection with the steel core material 9 can be smoothly and reliably released.

【0028】 然も、本実施例に係る吊込み用治具によれば、図6に示す吊込み用治具に比し 付着したベントナイトモルタルの除去作業が容易で、メンテナンス性が良好であ るといった利点も有する。Of course, according to the hanging jig of this embodiment, it is easier to remove the bentonite mortar adhering to the hanging jig shown in FIG. 6 and the maintainability is good. It also has the advantage.

【0029】[0029]

【考案の効果】[Effect of device]

以上述べたように、本考案によれば、治具用H鋼芯材と建込み用芯材との連結 解除が従来に比しスムーズ且つ確実に行うことができると共に、付着したベント ナイトモルタル等の除去作業も容易でメンテナンスが良好である利点を有する。 As described above, according to the present invention, the connection between the H steel core material for jigs and the building core material can be released more smoothly and more reliably than before, and the attached bentonite mortar etc. Has the advantage that it can be easily removed and maintenance is good.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の一実施例に係る吊込み用治具の要部断
面図である。
FIG. 1 is a sectional view of an essential part of a hanging jig according to an embodiment of the present invention.

【図2】図1に示す吊込み用治具でH鋼芯材を連結した
状態を示す断面図である。
FIG. 2 is a cross-sectional view showing a state where H steel core materials are connected by the hanging jig shown in FIG.

【図3】図1のIII − III線断面図である。3 is a sectional view taken along line III-III in FIG.

【図4】図1に示す吊込み用治具の背面図である。FIG. 4 is a rear view of the hanging jig shown in FIG.

【図5】本考案の実施例に係る吊込み用治具を用いてソ
イル柱内にH鋼芯材を建て込んだ状態を示す断面図であ
る。
FIG. 5 is a cross-sectional view showing a state in which an H steel core material is built in a soil column by using the hanging jig according to the embodiment of the present invention.

【図6】従来の吊込み用治具の要部斜視図である。FIG. 6 is a perspective view of a main part of a conventional hanging jig.

【図7】図6に示す吊込み用治具の断面図である。FIG. 7 is a cross-sectional view of the hanging jig shown in FIG.

【図8】図6に示す吊込み用治具を用いてソイル柱内に
H鋼芯材を建て込んだ状態を示す断面図である。
8 is a cross-sectional view showing a state where an H steel core material is built in a soil column by using the hanging jig shown in FIG.

【図9】H鋼芯材と従来の吊込み用治具との連結を解除
した状態を示す断面図である。
FIG. 9 is a cross-sectional view showing a state in which the H steel core material and the conventional hanging jig are disconnected.

【符号の説明】[Explanation of symbols]

9 H鋼芯材 11,39,41 ピン挿通孔 37 治具用H鋼芯材 37a ウェブ 37b フランジ 43,45 プレート 47 回動部材 49 支持軸 53 操作ワイヤ 55 固定ピン 57 抜止め鉄筋 61 鉄筋挿通孔 9 H steel core material 11, 39, 41 pin insertion hole 37 H steel core material for jig 37a Web 37b Flange 43, 45 plate 47 Rotating member 49 Support shaft 53 Operation wire 55 Fixing pin 57 Retaining reinforcing bar 61 Rebar insertion hole

───────────────────────────────────────────────────── フロントページの続き (72)考案者 花田 安功 東京都中央区銀座8丁目21番1号 株式会 社竹中工務店東京本店内 (72)考案者 恒見 良隆 東京都中央区銀座8丁目21番1号 株式会 社竹中工務店東京本店内 (72)考案者 柳沢 功 東京都中央区銀座8丁目21番1号 株式会 社竹中工務店東京本店内 (72)考案者 高清水 信 東京都中央区銀座8丁目21番1号 株式会 社竹中工務店東京本店内 (72)考案者 千明 菊司 東京都杉並区和泉2丁目7番8号 株式会 社アールエスジャパンリーダー内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yasunori Hanada 8-21-1, Ginza, Chuo-ku, Tokyo Stock company Takenaka Corporation Tokyo Main Store (72) Creator Yoshitaka Tsunemi 8-chome, Ginza, Chuo-ku, Tokyo No. 21-1 Takenaka Corporation Tokyo Main Store (72) Inventor Isao Yanagisawa 8-21-1, Ginza Chuo-ku, Tokyo Incorporated Takenaka Corporation Tokyo Main Store (72) Inventor Shin Takashimizu Tokyo 8-21-1, Ginza, Chuo-ku, Stockholder, Takenaka Corporation Tokyo Main Store (72) Inventor Chiaki Kikuji 2-7-8, Izumi, Suginami-ku, Tokyo Within RSS Japan Leader

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 地上からクレーン等で懸吊され、ウェブ
の下端部の両面に、ピン挿通孔が同軸上に穿設された2
枚のプレートが取り付く治具用H鋼芯材と、 治具用H鋼芯材のフランジ間に架設された支持軸に回動
自在に取り付き、地上から延びる操作ワイヤが連結され
た回動部材と、 当該回動部材に回動可能に取り付き、上記両プレートの
ピン挿通孔に挿入されると共に、その挿入側先端に抜止
め鉄筋挿通部が形成され、操作ワイヤの引張操作による
回動部材の回転に連動してピン挿通孔から引き抜かれる
固定ピンと、 地上から延長され、芯材の建て込み時に上記ピン挿通孔
に挿入された固定ピンを位置決めして固定ピンの抜止め
を図る抜止め鉄筋と、 からなることを特徴とする芯材の吊込み用治具。
1. A pin insertion hole is coaxially formed on both surfaces of a lower end portion of a web, which is suspended from the ground by a crane or the like.
A jig H steel core member to which a single plate is attached, and a rotating member rotatably attached to a support shaft installed between the flanges of the jig H steel core member and connected with an operation wire extending from the ground. , Rotatably attached to the rotating member, inserted into the pin insertion holes of both plates, and a retaining bar insertion portion is formed at the tip of the insertion side to rotate the rotating member by pulling the operation wire. A fixed pin that is pulled out from the pin insertion hole in conjunction with, and a retaining bar that extends from the ground and positions the fixed pin inserted into the pin insertion hole when building the core material to prevent the fixed pin from coming off, A jig for suspending a core material, which is made of
JP3146292U 1992-05-13 1992-05-13 Jig for hanging core material Expired - Lifetime JP2529646Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3146292U JP2529646Y2 (en) 1992-05-13 1992-05-13 Jig for hanging core material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3146292U JP2529646Y2 (en) 1992-05-13 1992-05-13 Jig for hanging core material

Publications (2)

Publication Number Publication Date
JPH0660631U true JPH0660631U (en) 1994-08-23
JP2529646Y2 JP2529646Y2 (en) 1997-03-19

Family

ID=12331931

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3146292U Expired - Lifetime JP2529646Y2 (en) 1992-05-13 1992-05-13 Jig for hanging core material

Country Status (1)

Country Link
JP (1) JP2529646Y2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0685439U (en) * 1993-05-20 1994-12-06 株式会社竹中工務店 Auxiliary jig for inserting core material for mountain retaining wall
JP2002138462A (en) * 2000-11-01 2002-05-14 Seiko Kogyo Kk Stress material building equipment and construction method of stress material
JP2007231691A (en) * 2006-03-03 2007-09-13 Toda Constr Co Ltd Insertion jig for core material for continuous wall
JP2019199687A (en) * 2018-05-14 2019-11-21 鹿島建設株式会社 Erection tool
JP2021063352A (en) * 2019-10-11 2021-04-22 ジェコス株式会社 Core member installation jig

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3103330U (en) 2004-02-13 2004-08-05 株式会社サンヅメイト School bag and school bag unit

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0685439U (en) * 1993-05-20 1994-12-06 株式会社竹中工務店 Auxiliary jig for inserting core material for mountain retaining wall
JP2002138462A (en) * 2000-11-01 2002-05-14 Seiko Kogyo Kk Stress material building equipment and construction method of stress material
JP2007231691A (en) * 2006-03-03 2007-09-13 Toda Constr Co Ltd Insertion jig for core material for continuous wall
JP2019199687A (en) * 2018-05-14 2019-11-21 鹿島建設株式会社 Erection tool
JP2021063352A (en) * 2019-10-11 2021-04-22 ジェコス株式会社 Core member installation jig

Also Published As

Publication number Publication date
JP2529646Y2 (en) 1997-03-19

Similar Documents

Publication Publication Date Title
JP4808677B2 (en) Foundation pile excavator
JP2024093116A (en) Pile installation and extraction machine and pile installation method using the pile installation and extraction machine
JPH0660631U (en) Jig for suspending core material
JP3914821B2 (en) Rebar position adjustment jig
JP2000336647A (en) Inner excavation constructing method for precast concrete pile
JP2001026929A (en) Underground obstacle removal method
JP2002138462A (en) Stress material building equipment and construction method of stress material
JPH0730550B2 (en) How to build foundation piles
JP4635725B2 (en) Pile construction system
JPH0345167B2 (en)
JPH06221077A (en) Steering method and device for rotary excavator
JP3129859B2 (en) Expanded bucket
JPH0715873Y2 (en) H-shaped steel pile holding device
JP2005133310A (en) How to build core material in underground continuous wall method
JPH10121466A (en) Stress material chuting device
JPS5820825A (en) Pile formation work and device therefor
JP2540639Y2 (en) Utility pole installation tool
JPS6231502Y2 (en)
JPH10331160A (en) Sheet pile driving device and method for pile driving using the device
JP6978378B2 (en) Built-in jig
JPH10205298A (en) Drilling filling method of grout and pulling device of grouting hose
JPH0685439U (en) Auxiliary jig for inserting core material for mountain retaining wall
JP2001081776A (en) Pile positioning device and pile positioning construction method
JPS6011962Y2 (en) Interlocking pipe extraction device
JPS6129815Y2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term