JPH0820936A - Erection of concrete wall - Google Patents

Erection of concrete wall

Info

Publication number
JPH0820936A
JPH0820936A JP15345094A JP15345094A JPH0820936A JP H0820936 A JPH0820936 A JP H0820936A JP 15345094 A JP15345094 A JP 15345094A JP 15345094 A JP15345094 A JP 15345094A JP H0820936 A JPH0820936 A JP H0820936A
Authority
JP
Japan
Prior art keywords
concrete
precast concrete
formwork
panel formwork
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15345094A
Other languages
Japanese (ja)
Inventor
Yoshio Ueki
良夫 植木
Takao Saito
孝雄 斉藤
Tateo Kobayashi
健郎 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP15345094A priority Critical patent/JPH0820936A/en
Publication of JPH0820936A publication Critical patent/JPH0820936A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To stably install precast concrete panel forms although tie-bars which obstructs placing of concrete are eliminated on installing the precast concrete panel forms and at the same time enable independent directional correction and further, increase the construction speed and secure the safety of the works. CONSTITUTION:Connection members 14 fixed at the rear face of the lower stage precast concrete panel forms (called as form hereunder) 11a, 12a and projected from the upper end of the forms are fixed at the rear face of stacked forms 11b, 12b to connect the upper and lower forms together. When the connection members 14 are fixed at the rear face of the stacked forms, spacers with appropriate thickness are inserted between the rear face of the lower stage form and the connection member or the rear face of the stacked form and the connection member to correct the inclination of the stacked form.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はコンクリートウォール建
設方法に関し、更に詳細には例えば砂防ダム等における
コンクリート壁をプレキャストコンクリートパネル型枠
を用いて建設する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a concrete wall, and more particularly to a method for constructing a concrete wall in a sabo dam using a precast concrete panel formwork.

【0002】[0002]

【従来の技術】従来、砂防ダムのコンクリート壁やコン
クリート重力式ウォール等の建設において、プレキャス
トコンクリートパネルを型枠として用い、最終的にはコ
ンクリート打設と共に埋め殺す工法が知られている。
2. Description of the Related Art Conventionally, there has been known a construction method in which a precast concrete panel is used as a formwork in the construction of a concrete wall of a sabo dam, a concrete gravity type wall, etc., and finally it is buried together with concrete pouring.

【0003】このような従来のプレキャストコンクリー
トパネル型枠(以下、単にプレコンパネル型枠と称す
る)を用いるコンクリート打設方法において、砂防ダム
を建設する場合を例にしてプレコンパネル型枠の組立て
方法を説明する。図8及び図9はプレコンパネル型枠に
よって形成された砂防ダムにおける上流面側の壁面1及
び下流側の壁面2をそれぞれ正面から見た図である。
In a concrete placing method using such a conventional precast concrete panel formwork (hereinafter, simply referred to as a preconpanel formwork), a method of assembling a preconpanel formwork will be described by taking a case of constructing a sabo dam as an example. explain. 8 and 9 are front views of the wall surface 1 on the upstream side and the wall surface 2 on the downstream side in the sabo dam formed by the pre-control panel formwork, respectively.

【0004】このような砂防ダムをプレコンパネル型枠
によって建築する場合には、最初に、プレコンパネル型
枠3が下流面側の位置と上流面側の位置とに所定の間隔
をあけて横方向に連設して設置される。砂防ダムにおけ
るコンクリートウォール建設の場合には図10に示され
るように上流面側のプレコンパネル型枠3は垂直に配置
され、他方下流面側のプレコンパネル型枠3は傾斜して
設置される。
When constructing such an erosion control dam by a pre-control panel formwork, first, the pre-control panel formwork 3 is laterally arranged at a predetermined distance between a position on the downstream side and a position on the upstream side. Will be installed in series. In the case of constructing a concrete wall in a sabo dam, as shown in FIG. 10, the pre-control panel formwork 3 on the upstream side is arranged vertically, while the pre-control panel formwork 3 on the downstream side is installed slanted.

【0005】上流面側及び下流面側共に、プレコンパネ
ル型枠の内側面には、図11に一部が拡大されて示され
るように縦地リブ材となるL型鋼(アングル材)4が上
端部からその約半分が突出するようボルト5等で堅固に
固定される。このアングル材4は、その後このプレコン
パネル型枠3に積み重ねられる他のプレコンパネル型枠
3を連結するために主に利用される。
On both the upstream surface side and the downstream surface side, on the inner surface of the pre-control panel formwork, an L-shaped steel (angle material) 4 serving as a vertical rib material as shown in a partially enlarged view in FIG. It is firmly fixed with a bolt 5 or the like so that about half of it protrudes from the part. This angle member 4 is mainly used for connecting other pre-control panel formwork 3 which is then stacked on the pre-control panel formwork 3.

【0006】上流側に設置されたプレコンパネル型枠3
と下流側に設置されたプレコンパネル型枠3とはターン
バックル付きタイバー6で相互に連結されて設置の安定
化が図られる。このタイバー6の各プレコンパネル型枠
3への取り付けにあたってはタイバー6の各端部を相対
するプレコンパネル型枠3のアングル材4に溶接するこ
とにより結合される。そして、各タイバー6のターンバ
ックル7を回転してその間隔を調整し、これにより特に
下流側のプレコンパネル型枠3の勾配即ち傾斜角度が設
計通りになるように微調整される。
Preconpanel formwork 3 installed on the upstream side
The pre-control panel formwork 3 installed on the downstream side is connected to each other by a tie bar 6 with a turnbuckle to stabilize the installation. When the tie bar 6 is attached to each pre-control panel form 3, the ends of the tie bar 6 are welded to the angle members 4 of the pre-control panel form 3 facing each other. Then, the turnbuckle 7 of each tie bar 6 is rotated to adjust the interval thereof, and thereby the fine adjustment is made so that the gradient, that is, the inclination angle of the pre-control panel formwork 3 on the downstream side becomes as designed.

【0007】このようにして組み立てられた上流側及び
下流側のプレコンパネル型枠3間にその上縁部より下側
のレベルまでコンクリート8が充填される。その後、こ
の充填コンクリート8が養生硬化すると、既設コンクリ
ートから突出している上流側及び下流側のプレコンパネ
ル型枠3上縁部に再び同様な手順で新たなプレコンパネ
ル型枠3が積み重ねられ且つ既設のプレコンパネル型枠
3から突出したアングル材4に固定される。勿論、新た
に積み重ねられたプレコンパネル型枠3にもその内側
に、次のプレコンパネル型枠を連結するためのアングル
材4が上縁部から突出するように取り付けられている。
Between the upstream side and downstream side pre-control panel formwork 3 assembled in this way, concrete 8 is filled to a level below the upper edge thereof. After that, when the filled concrete 8 is cured and hardened, a new pre-control panel form 3 is stacked on the upper edges of the upstream and downstream side pre-control panel forms 3 projecting from the existing concrete by the same procedure and the existing It is fixed to the angle member 4 protruding from the pre-control panel form 3. Of course, an angle member 4 for connecting the next pre-control panel formwork is also attached to the inside of the newly stacked pre-control panel formwork 3 so as to project from the upper edge portion.

【0008】そして、新たに積み重ねられた上流側及び
下流側のプレコンパネル型枠3にはタイバー6が取り付
けられて両側のプレコンパネル型枠3の設置安定化が図
られると共にその間隔が調整され、コンクリートが打設
される。このような工程を繰り返しながら所定高さまで
コンクリート打設が行われ、所望形状の砂防ダムが建設
されていた。
Then, tie bars 6 are attached to the newly stacked upstream side and downstream side pre-control panel formwork 3 to stabilize the installation of the pre-control panel formwork 3 on both sides, and their intervals are adjusted. Concrete is poured. While repeating such a process, concrete was poured to a predetermined height to construct a sabo dam having a desired shape.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、このよ
うな従来のプレコンパネル型枠を使用したコンクリート
ウォールの建設においては、次のような問題点があっ
た。すなわち、従来のこの種のコンクリートウォール建
設方法では、第1に、タイバーがコンクリート打設時に
障害物となると言う問題があった。
However, in the construction of the concrete wall using such a conventional pre-control panel formwork, there are the following problems. That is, in the conventional method for constructing a concrete wall of this type, firstly, there is a problem that the tie bar becomes an obstacle when the concrete is poured.

【0010】第2に、プレコンパネル型枠3は打設され
たコンクリート圧力により変形するためプレコンパネル
型枠3を順次上へ組み立てる時に多少の方向修正を行う
必要があった。このようなプレコンパネル型枠の方向修
正をタイバーのタンーバックルで行おうとすると、両側
のプレコンパネル型枠に等しい引張力が付与されること
から片方ずつの独立修正は難しいと言う問題があった。
Secondly, since the pre-control panel mold 3 is deformed by the concrete pressure applied, it is necessary to make some direction correction when the pre-control panel mold 3 is sequentially assembled upward. When attempting to correct the direction of the pre-control panel formwork with a tie-bar tan buckle, there is a problem that it is difficult to independently correct the pre-control panel formwork on both sides because the same tensile force is applied to the pre-control panel formwork.

【0011】更に、第3として、タイバーの自重による
たるみがプレコンパネル型枠の組立て時に引き寄せ誤差
を生じ、またコンクリート打設後はこのたるみの戻りに
よる誤差を引き起こしプレコン型枠の組立て精度を設計
通りに確保することが非常に難しいと言う問題があっ
た。
Thirdly, the slack due to the weight of the tie bar causes a pulling error during the assembly of the precon panel formwork, and after the concrete is placed, an error due to the return of the slack causes the preconform formwork as designed. There was a problem that it was very difficult to secure.

【0012】そして、第4には、例えば砂防ダムにおけ
るコンクリートウォールのような場合、タイバーが邪魔
してプレコンパネル型枠の組立て等に使用するクレーン
をプレコンパネル型枠間に設置することができないこと
から、型枠外に置いて運転をしなければならない。その
ためクレーンによるプレコンパネル型枠組立て作業に制
約が生じ、結果的に小規模な砂防ダムにしか用いること
ができないと言う問題があった。
Fourth, in the case of a concrete wall in a sabo dam, for example, it is impossible to install a crane used for assembling the pre-control panel formwork between the pre-control panel formwork due to the tie bar obstruction. Therefore, it must be placed outside the formwork for operation. As a result, there is a problem in that the work for assembling the pre-control panel formwork by the crane is restricted, and as a result, it can be used only for a small-scale dam.

【0013】最後に、前述した第2、第3の問題からプ
レコンパネル型枠3を予め数段積み重ねて施工速度を挙
げたり、既設コンクリート面上の作業者に対する安全用
防護壁としたりするようなことができず、従って特に後
者については安全用手摺を別途仮設し、また取り外すと
言う繰り返し作業を行うことが必要となり、これらが建
設コストや工期の短縮化を困難にしていると言う問題が
あった。
Finally, from the above-mentioned second and third problems, the pre-control panel formwork 3 is piled up in several stages in advance to increase the construction speed, and it is used as a safety protection wall for workers on the existing concrete surface. Therefore, especially for the latter, it is necessary to temporarily install a safety handrail and remove it repeatedly, and it is necessary to perform repeated work such as removing the construction cost and shortening the construction period. It was

【0014】本発明の目的は、かかる従来の問題点を解
決するためになされたもので、プレキャストコンクリー
トパネル型枠を設置する際にコンクリート打設に障害と
なるタイバーを廃止しながらもプレキャストコンクリー
トパネル型枠の安定設置を図り、併せて独立した方向修
正を可能とすると共に施工速度の向上や作業の安全確保
を図ることのできるコンクリートウォールの建設方法を
提供することにある。
The object of the present invention is to solve the above-mentioned conventional problems. The precast concrete panel is eliminated while eliminating the tie bar which obstructs the concrete placement when installing the precast concrete panel formwork. It is an object of the present invention to provide a method for constructing a concrete wall, which enables stable installation of a formwork, enables independent direction correction, and improves construction speed and ensures work safety.

【0015】[0015]

【課題を解決するための手段】本発明はコンクリートウ
ォール建設方法であり、前述した技術的課題を解決する
ため以下のように構成されている。
The present invention is a concrete wall construction method, which is configured as follows in order to solve the above-mentioned technical problems.

【0016】〈第1の発明〉本発明は、間隔をあけて設
置されたプレキャストコンクリートパネル型枠間にコン
クリートを打設し、打設コンクリートの硬化に伴ってプ
レキャストコンクリートパネル型枠を積み重ね、その後
再びコンクリートを打設する工程を繰り返すことにより
コンクリートウォールを建設する方法において、下の段
のプレキャストコンクリートパネル型枠の裏面に固定さ
れ、その上端部から突出する連結材を積み重ね段のプレ
キャストコンクリートパネル型枠の裏面に固定して上下
のプレキャストコンクリートパネル型枠相互を連結する
工程を含み、前記積み重ね段のプレキャストコンクリー
トパネル型枠裏面に前記連結材を固定する時、下の段の
プレキャストコンクリートパネル型枠裏面と前記連結材
との間又は前記積み重ね段のプレキャストコンクリート
パネル型枠裏面と前記連結材との間に適宜の厚さのスペ
ーサを入れて前記積み重ね段のプレキャストコンクリー
トパネル型枠の傾きを修正することを特徴とする(請求
項1に対応)。以下、この発明の構成要素について個々
に説明する。
<First Invention> According to the present invention, concrete is placed between precast concrete panel forms which are installed at intervals, and the precast concrete panel forms are piled up as the cast concrete hardens, and thereafter. In the method of constructing a concrete wall by repeating the step of placing concrete again, a precast concrete panel mold for stacking a connecting material that is fixed to the back surface of the precast concrete panel mold for the lower tier and projects from the upper end Including a step of connecting the upper and lower precast concrete panel formwork to each other by fixing to the backside of the frame, and fixing the connecting material to the backside of the stacked precast concrete panel formwork, the precast concrete panel formwork of the lower stage Between the back surface and the connecting material or the product The inclination of the precast concrete panel formwork of the stacking stage is corrected by inserting a spacer having an appropriate thickness between the back surface of the precast concrete panel formwork of the stacking stage and the connecting material (claim 1). Correspondence). The constituent elements of the present invention will be individually described below.

【0017】(上下プレキャストコンクリートパネル型
枠相互連結工程)打設コンクリートの硬化に伴ってプレ
キャストコンクリートパネル型枠を積み重ねる際、下の
段のプレキャストコンクリートパネル型枠の裏面に固定
され、その上端部から突出する連結材を積み重ね段のプ
レキャストコンクリートパネル型枠の裏面に固定する。
この連結材は、所謂アングル材と称される型鋼が使用さ
れる。このアングル材に所定位置にボルト挿通用の穴が
形成されていて、この穴にインサートボルトを通してア
ングル材のプレキャストコンクリートパネル型枠への固
定が図られる。
(Upper and lower precast concrete panel formwork interconnection process) When the precast concrete panel formwork is piled up as the cast concrete hardens, it is fixed to the back surface of the precast concrete panel formwork in the lower stage and from the upper end thereof. The protruding connecting material is fixed to the back side of the precast concrete panel formwork in the stacking stage.
As the connecting material, a section steel called a so-called angle material is used. A hole for inserting a bolt is formed at a predetermined position in this angle member, and an insert bolt is passed through this hole to fix the angle member to the precast concrete panel formwork.

【0018】本発明のコンクリートウォール建設方法で
は、プレキャストコンクリートパネル型枠が積み重ねら
れる下の段のプレキャストコンクリートパネル型枠は、
既設のコンクリートによって固定されるのでアングル材
は主に積み重ねられるプレキャストコンクリートパネル
型枠を支えるために機能する。
In the concrete wall construction method of the present invention, the lower precast concrete panel formwork on which the precast concrete panel forms are stacked is
Being anchored by the existing concrete, the angle members primarily serve to support the precast concrete panel formwork to be stacked.

【0019】従って、アングル材は、下の段のプレキャ
ストコンクリートパネル型枠裏面に当てられる部分の長
さが上端部から突出する部分であって上の段のプレキャ
ストコンクリートパネル型枠の裏面に当てられる部分の
ながさより短く、またアングル材をそれぞれのプレキャ
ストコンクリートパネル型枠裏面に固定するインサート
ボルトの数も下の段に固定するボルトの数が1本で、上
の段に固定するボルトの数は2本とすることができる。
Therefore, the angle member is applied to the back surface of the precast concrete panel formwork in the upper step, which is the part where the length of the part applied to the back surface of the precast concrete panel formwork in the lower step projects from the upper end. It is shorter than the length of the part, and the number of insert bolts that fix the angle member to the back of each precast concrete panel formwork is one bolt that is fixed to the lower step, and the number of bolts that are fixed to the upper step is It can be two.

【0020】(スペーサ装入工程)下の段のプレキャス
トコンクリートパネル型枠上に新たな別のプレキャスト
コンクリートパネル型枠が積み重ねられる時、その方向
即ち傾斜角度を修正する必要が生じる。その場合、下の
段のプレキャストコンクリートパネル型枠から伸長する
アングル材に積み重ね段のプレキャストコンクリートパ
ネル型枠をインサートボルト等を用いて固定する時、下
の段のプレキャストコンクリートパネル型枠裏面とアン
グル材との間又は積み重ね段のプレキャストコンクリー
トパネル型枠裏面とアングル材との間に適宜の厚さのス
ペーサを入れる。
(Spacer charging step) When another new precast concrete panel formwork is stacked on the lower stage precast concrete panel formwork, it is necessary to correct its direction, that is, the inclination angle. In that case, when fixing the stacked precast concrete panel formwork to the angle material that extends from the lower stage precast concrete panel formwork using insert bolts, etc., And a spacer of appropriate thickness between the back surface of the precast concrete panel formwork in the stacking stage and the angle member.

【0021】このようなスペーサとしては、インサート
ボルトに噛ませるようにするC形状の金属製ワッシャー
とすることができる。また、スペーサの厚みの調整は、
このワッシャーの枚数を選択することにより可能とな
る。
As such a spacer, a C-shaped metal washer adapted to be bitten by the insert bolt can be used. Also, adjustment of the spacer thickness is
This is possible by selecting the number of washers.

【0022】〈第2の発明〉本発明は、間隔をあけて設
置されたプレキャストコンクリートパネル型枠間にコン
クリートを打設し、打設コンクリートの硬化に伴ってプ
レキャストコンクリートパネル型枠を積み重ね、その後
再びコンクリートを打設する工程を繰り返すことにより
コンクリートウォールを建設する方法において、積み重
ね段のプレキャストコンクリートパネル型枠の裏面に一
端を取付けたステーの他端を前回打設したコンクリート
に埋設させてプレキャストコンクリートパネル型枠を支
持することを特徴とする(請求項2に対応)。以下この
発明の構成要素について説明する。
<Second Invention> In the present invention, concrete is placed between precast concrete panel forms installed at intervals, the precast concrete panel forms are stacked as the set concrete hardens, and thereafter, In the method of constructing a concrete wall by repeating the step of placing concrete again, in the precast concrete panel formwork of the stacking step, the other end of the stay attached to the back side of the precast concrete is embedded in the previously cast concrete. It is characterized by supporting a panel form (corresponding to claim 2). The components of the present invention will be described below.

【0023】(ステー取付け工程)ステーは、コンクリ
ート圧力によるアングル材への曲げ応力を低減させるた
めに使用される。このステーは、金属製の棒材で形成さ
れ、その一端は上の段のプレキャストコンクリートパネ
ル型枠の裏面に取り付けられる。この取付けについては
プレキャストコンクリートパネル型枠を連結するアング
ル材に溶接などを利用して接続することができる。しか
し、このような取付け方法に限定されるない。例えばス
テーの一端をフック状に曲げ、アングル材に形成された
孔に引っかけるようにして取り付けることもできる。
(Stay Attaching Step) The stay is used to reduce bending stress on the angle member due to concrete pressure. The stay is formed of a metal rod, and one end of the stay is attached to the back surface of the upper precast concrete panel formwork. For this attachment, the precast concrete panel formwork can be connected to the angle member by welding or the like. However, the mounting method is not limited to this. For example, one end of the stay may be bent into a hook shape and hooked in a hole formed in the angle member to be attached.

【0024】このステーの他端は、打設コンクリート中
に埋設してアンカー部とする。従って、ステー他端の形
状や構成は、特に問題とされない。しかし、打設コンク
リートから簡単にはずれないように引き抜きに対する抵
抗を与える意味からL字形又はU字形等に屈曲形成して
おくことが好ましい。
The other end of this stay is embedded in the cast concrete to form an anchor portion. Therefore, the shape or configuration of the other end of the stay does not matter. However, it is preferable to bend and form an L-shape or a U-shape in order to provide resistance against pulling out so as not to easily separate from the poured concrete.

【0025】〈第3の発明〉本発明は、多数のプレキャ
ストコンクリートパネルを型枠としてコンクリートウォ
ールを建設する方法であって、最初に、裏面に連結材を
上端から突出するように固定した第1段目のプレキャス
トコンクリート型枠を間隔をあけて地面に適宜設置する
工程と、同様に連結材が上端から突出するように裏面に
取り付けられた第2段目の別のプレキャストコンクリー
トパネル型枠を前記第1段目のプレキャストコンクリー
トパネル型枠上に積み重ね、この積み重ねられた第2段
目のプレキャストコンクリートパネル型枠裏面に前記第
1段目の前記プレキャストコンクリートパネル型枠から
上方に伸長する前記連結材を固定する工程と、次いで前
記間隔内にコンクリートを打設する工程と、この打設コ
ンクリートが完全に硬化する前に前記第1段目と第2段
目のプレキャストコンクリートパネル型枠を連結してい
る連結材に一端を取り付けられたステーの他端を前記打
設コンクリート内に埋設して前記打設コンクリートの硬
化によって固定する工程と、前記打設コンクリートが硬
化した後再び前記第2段目のプレキャストコンクリート
型枠の上に前述と同様に連結材が上端から突出するよう
に裏面に取り付けられた第3段目の別のプレキャストコ
ンクリートパネル型枠を更に積み重ね、前記第2段目の
プレキャストコンクリート型枠から上方に伸長する前記
連結材に固定する工程と、次いで前記第3段目のプレキ
ャストコンクリートパネル型枠で区画形成される間隔内
にコンクリートを打設する工程とを含み、前記大1段目
のプレキャストコンクリートパネル型枠設置工程を除く
他の前記工程を繰り返して所定の高さまでコンクリート
を打設することを特徴とする(請求項3に対応)。
<Third Invention> The present invention is a method for constructing a concrete wall using a large number of precast concrete panels as a formwork. First, a first connecting member is fixed to the back surface so as to project from the upper end. The step of appropriately installing the precast concrete formwork of the second stage on the ground with a space, and similarly, another precast concrete panel formwork of the second stage is attached to the back surface so that the connecting material projects from the upper end. The connecting material that is stacked on the first-stage precast concrete panel formwork and extends upward from the stacked second-stage precast concrete panel formwork from the first-stage precast concrete panel formwork The step of fixing the concrete, then the step of placing concrete within the interval, and Before hardening, the other end of the stay, one end of which is attached to the connecting material that connects the first-stage and second-stage precast concrete panel formwork, is embedded in the pouring concrete and the pouring is performed. The step of fixing by hardening the concrete, and the step of attaching the connecting material to the back surface of the second-stage precast concrete formwork so as to project from the upper end again on the second-stage precast concrete formwork after the casting concrete has hardened. Stacking another precast concrete panel formwork on the third stage and fixing it to the connecting material extending upward from the precast concrete formwork on the second stage, and then the precast concrete panel form on the third stage A step of placing concrete within a space defined by a frame, and the large first-stage precast concrete panel Repeat other the step of removing the frame installation process, characterized in that concrete is cast to a predetermined height (corresponding to claim 3).

【0026】この第2の発明では、前述した第1の発明
の構成要素に第2の発明の構成要素を加えて成立させて
いる。従って、個々の構成要素は、前述した各発明で説
明していることから、ここでの説明は省略する。
In the second invention, the constituent elements of the second invention are added to the constituent elements of the first invention described above. Therefore, since the individual constituent elements have been described in the above-described inventions, the description thereof is omitted here.

【0027】[0027]

【作用】本発明のコンクリートウォール建設方法は、概
略的には、間隔をあけて設置されたプレキャストコンク
リートパネル型枠間にコンクリートを打設し、打設コン
クリートの硬化に伴ってプレキャストコンクリートパネ
ル型枠を積み重ね、その後再びコンクリートを打設する
工程を繰り返すことによりコンクリートウォールを建設
するものである。
The concrete wall construction method of the present invention is roughly constructed by placing concrete between precast concrete panel forms that are installed at intervals, and the precast concrete panel forms are formed as the cast concrete hardens. The concrete wall is constructed by repeating the steps of stacking and then placing concrete again.

【0028】このようなコンクリートウォール建設方法
において、既設コンクリートのためのプレキャストコン
クリートパネル型枠上に新たに別のプレキャストコンク
リートパネル型枠が積み重ねられる。その際、積み重ね
段のプレキャストコンクリートパネル型枠は、その下の
段のプレキャストコンクリートパネル型枠の裏面に固定
され、その上端部から突出する連結材に固定されて相互
の連結が図られる。
In such a concrete wall construction method, another precast concrete panel formwork is newly stacked on the precast concrete panel formwork for existing concrete. At that time, the precast concrete panel formwork of the stacked stage is fixed to the back surface of the precast concrete panel formwork of the stage below it, and is fixed to the connecting material protruding from the upper end portion thereof to achieve mutual connection.

【0029】積み重ね段のプレキャストコンクリートパ
ネル型枠裏面に連結材を固定する時、積み重ね段のプレ
キャストコンクリートパネル型枠の傾きを修正する必要
があれば、下の段のプレキャストコンクリートパネル型
枠裏面と連結材との間又は積み重ね段のプレキャストコ
ンクリートパネル型枠裏面と連結材との間に適宜の厚さ
のスペーサが入れられ、これにより積み重ね段のプレキ
ャストコンクリートパネル型枠の傾きが設計通りになる
ように調整される。
When fixing the connecting material to the back surface of the precast concrete panel formwork of the stacking stage, if it is necessary to correct the inclination of the precast concrete panel formwork of the stacking stage, connect it to the backside of the precast concrete panel formwork of the lower stage. A spacer with an appropriate thickness is inserted between the timber or between the backside of the stack of precast concrete panel formwork and the connecting material, so that the inclination of the stack of precast concrete panel formwork is as designed. Adjusted.

【0030】このようにして設置されたプレキャストコ
ンクリートパネル型枠間にコンクリートが打設される
と、上下方向に積み重ねられたプレキャストコンクリー
トパネルを連結しているアングル材にコンクリート圧力
による曲げ応力が作用する。アングル材に取り付けられ
るステーはこの曲げ応力低減のための作用をする。
When concrete is placed between the precast concrete panel forms installed in this way, bending stress due to concrete pressure acts on the angle members connecting the vertically stacked precast concrete panels. . The stay attached to the angle member acts to reduce the bending stress.

【0031】[0031]

【実施例】以下、本発明のコンクリートウォール建設方
法を図に示される実施例について更に詳細に説明する。
図1には本発明のコンクリートウォール建設方法を用い
て砂防ダムのコンクリート壁を建設する場合のプレキャ
ストコンクリートパネル型枠(プレコンパネル型枠)組
立て構造10が示されている。この実施例に係る砂防ダ
ムのコンクリート壁建設方法は、最初に、上流側及び下
流側の位置にそれぞれ第1段目のプレコンパネル型枠1
1a、12aが間隔をあけて地面にL鋼材13等を支え
として設置される。
EXAMPLES The concrete wall construction method of the present invention will be described below in more detail with reference to the examples shown in the drawings.
FIG. 1 shows a precast concrete panel formwork (pre-conpanel formwork) assembly structure 10 for constructing a concrete wall for a sabo dam using the concrete wall construction method of the present invention. In the method for constructing a concrete wall of a sabo dam according to this embodiment, first, the first-stage pre-control panel formwork 1 is provided at the upstream side and the downstream side, respectively.
1a and 12a are installed on the ground at intervals with the L steel material 13 and the like as supports.

【0032】その時、当然のことながら上流側及び下流
側のプレコンパネル型枠11a、12aはそれぞれ横方
向にも同様に相互に密着させて所定長さに亘って多数設
置されるが、この発明はプレコンパネル型枠を積み重ね
る時の上下方向の連結関係にあるので、横方向のプレコ
ンパネル型枠の設置に関する説明は省略する。
At this time, it goes without saying that the upstream side and downstream side pre-control panel molds 11a and 12a are also closely attached to each other in the lateral direction, and a large number of them are installed over a predetermined length. Since there is a vertical connection relationship when stacking the pre-control panel formwork, a description of the installation of the pre-control panel formwork in the horizontal direction is omitted.

【0033】砂防ダムの上流側に位置するプレコンパネ
ル型枠11aは垂直に立てられるが、下流側に位置する
プレコンパネル型枠12aは傾斜して設置される。第1
段目のプレコンパネル型枠11a、12aには、図1及
び図2に示されるように裏面に連結用の型鋼であるL形
のアングル材14が上端から突出するようにインサート
ボルト15等で固定されて取り付けられている。
The pre-control panel formwork 11a located upstream of the erosion control dam is erected vertically, while the pre-control panel formwork 12a located downstream is installed at an angle. First
As shown in FIGS. 1 and 2, the pre-contain panel formwork 11a, 12a of the tier is fixed with insert bolts 15 or the like so that an L-shaped angle member 14 which is a shape steel for connection is projected from the upper end on the rear surface. It has been installed.

【0034】このアングル材14は、相互に積み重ねら
れたプレコンパネル型枠を連結するために使用されるも
ので、特に下の段のプレコンパネル型枠上に積み重ねら
れる新たなプレコンパネル型枠を支えることを主目的と
している。従って、図2から明らかなようにアングル材
14は、下の段のプレコンパネル型枠裏面にその下端か
ら全長の約1/3程度の長さ部分が1つのインサートボ
ルト15で固定され、他の2/3の長さ部分は積み重ね
られるプレコンパネル型枠を支えるために下の段のプレ
コンパネル型枠上端から突出している。
This angle member 14 is used to connect the pre-conpanel forms that are stacked on each other, and particularly supports a new pre-conpanel form that is stacked on the lower pre-conpanel forms. The main purpose is that. Therefore, as is apparent from FIG. 2, the angle member 14 is fixed to the back surface of the lower pre-conpanel formwork by a single insert bolt 15 at a length of about 1/3 of the entire length from the lower end thereof. The two-thirds of the length projects from the upper end of the lower preconpanel formwork to support the stacked preconpanel formwork.

【0035】次いで、このように裏面にアングル材14
が取り付けられた第1段目のプレコンパネル型枠11
a、12aの上端には、新たに別なプレコンパネル型枠
11b、12bが第2段目として積み重ねられる。これ
により、第1段目のプレコンパネル型枠11a、12a
の上端から突出したアングル材14は、積み重ね段であ
る第2段目のプレコンパネル型枠11b、12bの裏面
に重なり、それぞれ2つのインサートボルト15により
固定される。
Then, the angle member 14 is formed on the back surface in this manner.
First stage pre-con panel formwork 11 with attached
On the upper ends of a and 12a, new pre-control panel molds 11b and 12b are stacked as the second stage. As a result, the first-stage pre-control panel formwork 11a, 12a
The angle member 14 projecting from the upper end of is overlapped with the back surface of the second-stage pre-control panel formwork 11b, 12b, which is a stacking stage, and is fixed by two insert bolts 15, respectively.

【0036】なお、この第2段目のプレコンパネル型枠
11b、12bにも、次の積み重ね段のプレコンパネル
型枠を支持するためのアングル材14が前述したと同様
に予め裏面に取り付けられていることは言うまでもな
い。
Incidentally, the angle members 14 for supporting the pre-control panel formwork of the next stacking stage are also preliminarily attached to the back surface of the second-stage pre-control panel formwork 11b, 12b in the same manner as described above. Needless to say

【0037】ところで、プレコンパネル型枠の積み重ね
において下の段のプレコンパネル型枠の上端面と上の段
のプレコンパネル型枠の下端面との正確な重ね合わせを
容易に行うため、図3に示されるように上端面中央部に
は全幅に亘って突出部16が形成され、他方下端面中央
部にはこの突出部16がほぼぴったりと嵌合する溝部1
7が形成されている。これにより、プレコンパネル型枠
を積み重ねる時これを下の段のプレコンパネル型枠上端
面に単に乗せるだけで両者の正確な位置決めが可能とな
る。
By the way, in stacking the pre-control panel molds, in order to facilitate accurate superposition of the upper end surface of the lower pre-control panel molds and the lower end surface of the upper pre-control panel molds, FIG. As shown, a protrusion 16 is formed over the entire width in the center of the upper end surface, while a groove 1 is formed in the center of the lower end surface so that the protrusion 16 fits snugly.
7 are formed. As a result, when the pre-control panel molds are stacked, they can be accurately positioned by simply placing them on the upper surface of the lower pre-control panel molds.

【0038】下の段のプレコンパネル型枠上端面に新た
なプレコンパネル型枠を積み重ねる時、その方向の修正
が必要となる場合がある。この傾斜角度の修正方法を、
図4に点線で示されるように例えば下流側に位置する型
枠においてこれを急傾斜にする場合について説明する。
When stacking a new pre-control panel form on the upper surface of the lower-stage pre-control panel form, it may be necessary to correct the direction. How to correct this tilt angle
A case will be described in which, for example, a mold located on the downstream side is steeply inclined as shown by a dotted line in FIG.

【0039】最初に、下の段のプレコンパネル型枠12
a裏面にアングル材14を固定しているインサートボル
ト15を緩め、1枚又は複数枚のC形ワッシャー18を
図5及び図6に示されるようにアングル材14とプレコ
ンパネル型枠裏面との間に横方向から差し込むようにイ
ンサートボルト15に引っ掛けて装着させる。これによ
り、下の段のプレコンパネル型枠12aに対するアング
ル材14の角度が変更することになり、従ってこのアン
グル材14に取付けられた積み重ね段のプレコンパネル
型枠12bの傾斜角度が修正される。
First, the lower pre-control panel formwork 12
a) Loosen the insert bolt 15 that fixes the angle member 14 on the back surface, and insert one or more C-shaped washers 18 between the angle member 14 and the back surface of the pre-conpanel mold as shown in FIGS. 5 and 6. Hook it on the insert bolt 15 so that it can be inserted from the lateral direction. As a result, the angle of the angle member 14 with respect to the lower-stage pre-control panel formwork 12a is changed, and thus the inclination angle of the stacking-stage pre-control panel formwork 12b attached to the angle member 14 is corrected.

【0040】これとは反対に、図7に点線で示されるよ
うに積み重ね段のプレコンパネル型枠12bの傾斜角度
を緩斜面側へ修正する場合には、積み重ね段のプレコン
パネル型枠12b裏面にアングル材14をインサートボ
ルト15で固定する時に図5で示されたと同様な方法で
1枚又は複数枚のC形のワッシャー18を挿入する。但
し、このアングル材14の変更角度の大きさによっては
下の段のプレコンパネル型枠に固定しているインサート
ボルト15を緩めることも必要となる。
On the contrary, as shown by the dotted line in FIG. 7, when the inclination angle of the stacking-stage pre-control panel formwork 12b is corrected to the gentle slope side, the stacking-stage pre-control panel formwork 12b is provided on the rear surface. When fixing the angle member 14 with the insert bolt 15, one or more C-shaped washers 18 are inserted in the same manner as shown in FIG. However, depending on the size of the change angle of the angle member 14, it is necessary to loosen the insert bolt 15 that is fixed to the pre-control panel formwork in the lower stage.

【0041】なお、前述した例では下流側に設置される
プレコンパネル型枠の傾斜修正方法について説明した
が、これは下流側だけではなく上流側に設置されるプレ
コンパネル型枠についても同じである。すなわち、本実
施例では上流側に設置されるプレコンパネル型枠は図1
から明らかなようにほぼ垂直に積み重ねられる。
In the above-mentioned example, the method for correcting the inclination of the pre-control panel formwork installed on the downstream side has been described, but this is the same for the pre-control panel formwork installed not only on the downstream side but also on the upstream side. . That is, in this embodiment, the pre-control panel formwork installed on the upstream side is shown in FIG.
As you can see, they are stacked almost vertically.

【0042】型枠を単に垂直に積み重ねるだけであれ
ば、その方向修正はあまり必要とならないが下段の型枠
がコンクリート圧力により変位することがあり、そのよ
うな場合には修正が必要となることがある。
If the molds are simply stacked vertically, it is not necessary to correct the direction, but the lower mold may be displaced by concrete pressure. In such a case, correction is necessary. There is.

【0043】また、下流側に位置するプレコンパネル型
枠も勾配が均一であれば基本的には修正はあまり必要と
ならない。この場合における修正の必要性も上流側のプ
レコンパネルの場合と同様にコンクリート圧力による変
形に対してである。
Also, the pre-control panel formwork located on the downstream side basically does not require much correction if the gradient is uniform. The need for modification in this case is also for deformation due to concrete pressure, as in the case of the upstream pre-control panel.

【0044】このようにして、第2段目のプレコンパネ
ル型枠11b、12bが積み重ねらると、次いでコンク
リート19が上流側及び下流側の型枠間に打設される。
この時のコンクリートの打設は図1に示されるように第
1段目と第2段目のプレコンパネル型枠11a、11b
及び12a、12bをそれぞれ連結しているアングル材
14の下端部付近まで打設される。
When the second-stage pre-control panel molds 11b and 12b are stacked in this way, concrete 19 is then placed between the upstream and downstream molds.
At this time, the concrete is poured as shown in FIG. 1 in the first-stage and second-stage pre-control panel formwork 11a, 11b.
And 12a, 12b are respectively driven up to near the lower end of the angle member 14.

【0045】そして、この打設コンクリート19が完全
に硬化する前に第1段目と第2段目のプレコンパネル型
枠を連結しているアングル材14の上端側に一端を取り
付けられたステー20の他端が打設コンクリート19内
に埋設させられ、打設コンクリート19が硬化すること
によってステー20の固定が図られる。これにより、積
み重ねられたプレコンパネル型枠11b、12bのより
強固な自立安定化を得ることができると共に、打設コン
クリート圧力によるアングル材への曲げ応力を低減でき
ることからアングル材14の軽量化を図ることもでき
る。
A stay 20 having one end attached to the upper end side of the angle member 14 connecting the first-stage and second-stage pre-control panel formwork before the poured concrete 19 is completely hardened. The other end is embedded in the pouring concrete 19 and the stay 20 is fixed by hardening the pouring concrete 19. As a result, a stronger self-sustaining stabilization of the stacked pre-control panel formwork 11b, 12b can be obtained, and the bending stress to the angle member due to the pressure of the placing concrete can be reduced, so that the angle member 14 can be reduced in weight. You can also

【0046】打設コンクリート19が硬化すると、この
コンクリート19の上に作業者が乗って第2段目のプレ
コンパネル型枠11b、12bに更に新たな第3段目の
プレコンパネル型枠11c、12cを積み重ねる作業を
行う。すなわち、その後は前述した工程の繰り返しであ
り、これにより所定の高さになるまでコンクリートの打
設が繰り返される。
When the cast concrete 19 is hardened, an operator rides on the concrete 19 and the new third-stage pre-control panel formwork 11c, 12c is added to the second-stage pre-control panel formwork 11b, 12b. Do the work of stacking. That is, after that, the above-mentioned steps are repeated, whereby the pouring of concrete is repeated until the predetermined height is reached.

【0047】このような説明から明らかなように、打設
コンクリート19表面上で作業者が次のプレコンパネル
型枠の積み重ね作業並びに他の必要な作業をしている
時、打設コンクリート19表面から約1枚分以上のプレ
コンパネル型枠が常に立設することになることから、こ
れが防護壁となって、作業者の転落等の事故を防ぐこと
ができる。
As is clear from the above description, when the operator is performing the next pre-conpanel formwork stacking work and other necessary work on the surface of the cast concrete 19, the surface of the cast concrete 19 is removed. Since one or more pre-control panel formwork will always be erected, this will serve as a protective wall and prevent accidents such as falling of workers.

【0048】なお、ステー20のアングル材14への取
付けは溶接など考えられるが、それ以外の方法としてス
テー20の一端をフック状に曲げ、アングル材14に形
成した孔(図示せず)に引っかけるようにして取り付け
ることもできる。このステー20の他端は、打設コンク
リート中に埋設してアンカー部とされるので、この他端
形状や構成は特に問題とされない。しかし、打設コンク
リートから簡単にはずれないように引き抜きに対する抵
抗を与える意味からL字形又はU字形等に屈曲形成して
おくことが好ましい。
The stay 20 may be attached to the angle member 14 by welding, but as another method, one end of the stay 20 is bent into a hook shape and hooked in a hole (not shown) formed in the angle member 14. It can also be attached in this way. The other end of the stay 20 is embedded in the cast concrete to serve as an anchor, so that the shape and configuration of the other end are not particularly problematic. However, it is preferable to bend and form an L-shape or a U-shape in order to provide resistance against pulling out so as not to easily separate from the poured concrete.

【0049】このように、この実施例に係る砂防ダムの
コンクリート壁建設方法では、従来のように上流側及び
下流側に間隔をあけて設置されるプレキャストコンクリ
ートパネル型枠の安定的設置のために、型枠間を横断す
る何本ものタイバーを必要としないことから、この型枠
間に比較的広いスペースが確保でき、そのため型枠間に
作業用のクレーンを置くことができ、その結果比較的に
大きな砂防ダムをこのプレキャストコンクリートパネル
型枠を使用して建設することができる。
As described above, in the concrete wall construction method for a sabo dam according to this embodiment, in order to stably install the precast concrete panel formwork, which is installed on the upstream side and the downstream side with a space as in the conventional case. As it does not require many tie bars to traverse between the forms, a relatively large space can be secured between the forms, so that a working crane can be placed between the forms, and as a result Large sabo dams can be constructed using this precast concrete panel formwork.

【0050】前述した実施例では砂防ダムのコンクリー
ト壁を建設する場合について説明したが、本発明ではこ
の実施例に限定されるものではなく、コンクリート重力
式ウォールを含めて種々のコンクリートウォールをプレ
キャストコンクリートパネル型枠で形成する場合に適用
することができる。
In the above-described embodiment, the case of constructing a concrete wall of a sabo dam has been described, but the present invention is not limited to this embodiment, and various concrete walls including concrete gravity type walls are precast concrete. It can be applied when forming with a panel form.

【0051】[0051]

【発明の効果】以上説明したように、本発明のコンクリ
ートウォール建設方法によれば、間隔をあけて配置され
るプレキャストコンクリートパネル型枠を従来のように
型枠間を横断するタイバーを使用することなく強固に自
立させるようにした場合でも、積み重ね段のプレキャス
トコンクリートパネル型枠の方向修正を容易に行うこと
ができる。
As described above, according to the concrete wall construction method of the present invention, the precast concrete panel formwork arranged at intervals is used with the tie bar which traverses the formwork as in the prior art. Even if it is made to be self-supporting strongly without being, it is possible to easily correct the direction of the precast concrete panel formwork in the stacking stage.

【0052】また、タイバーが廃止しても積み重ね段の
プレキャストコンクリートパネル型枠を自立させること
ができることからコンクリート打設の際の障害物がな
く、極めて効率の良いコンクリート打設を行うことがで
きる。しかも、タイバーが存在しないことから、型枠間
のスペースを有効に使用することもでき、更に2段重ね
施工が可能となることことから安全面への有利さ並びに
施工能率の向上をも期待することができる。
Further, even if the tie bar is eliminated, the precast concrete panel formwork in the stacking stage can be made to stand on its own, so that there is no obstacle during concrete pouring, and extremely efficient concrete pouring can be performed. Moreover, since there is no tie bar, the space between the molds can be effectively used, and since two-tiered construction is possible, it is expected to be advantageous in terms of safety and improved construction efficiency. be able to.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のコンクリートウォール建設方法を用い
て砂防ダムのコンクリート壁を建設する場合におけるプ
レキャストコンクリートパネル型枠組立て構造を示す断
面図である。
FIG. 1 is a cross-sectional view showing a precast concrete panel formwork assembly structure in the case of constructing a concrete wall of a sabo dam using the concrete wall construction method of the present invention.

【図2】図1に示されるプレキャストコンクリートパネ
ル型枠組立て構造において積み重ねられたプレキャスト
コンクリートパネル型枠の連結状態を示す部分的な正面
図である。
FIG. 2 is a partial front view showing a connection state of precast concrete panel formwork stacked in the precast concrete panel formwork assembly structure shown in FIG.

【図3】図2の積み重ねられて連結されたプレキャスト
コンクリートパネル型枠を3−3線に沿って切断して示
す断面図である。
FIG. 3 is a cross-sectional view of the precast concrete panel formwork, which is stacked and connected in FIG. 2, taken along line 3-3.

【図4】積み重ねられたプレキャストコンクリートパネ
ル型枠の傾斜角度を修正する方法を示す図3と同様な断
面図である。
FIG. 4 is a cross-sectional view similar to FIG. 3, showing a method of correcting the tilt angle of stacked precast concrete panel forms.

【図5】積み重ねられたプレキャストコンクリートパネ
ル型枠の傾斜角度を修正する方法を示すためアングル材
と下の段のプレキャストコンクリートパネル型枠との固
定部を拡大して示す断面図である。
FIG. 5 is a cross-sectional view showing, in an enlarged manner, a fixing portion between an angle member and a precast concrete panel formwork at a lower stage in order to show a method of correcting an inclination angle of stacked precast concrete panel forms.

【図6】図5に示される下の段のプレキャストコンクリ
ートパネル型枠とアングル材との固定部を拡大して示す
正面図である。
FIG. 6 is an enlarged front view showing a fixed portion between the lower precast concrete panel formwork and the angle member shown in FIG.

【図7】積み重ねられたプレキャストコンクリートパネ
ル型枠の傾斜角度を修正する方法を示す図3と同様な断
面図である。
FIG. 7 is a sectional view similar to FIG. 3, showing a method of correcting the tilt angle of stacked precast concrete panel forms.

【図8】プレキャストコンクリートパネル型枠を用いて
建設された従来の砂防ダムの上流側コンクリート壁を示
す正面図である。
FIG. 8 is a front view showing an upstream concrete wall of a conventional sabo dam constructed using a precast concrete panel formwork.

【図9】プレキャストコンクリートパネル型枠を用いて
建設された従来の砂防ダムの下流側コンクリート壁を示
す正面図である。
FIG. 9 is a front view showing a downstream concrete wall of a conventional sabo dam constructed using a precast concrete panel formwork.

【図10】砂防ダムのコンクリート壁を建設する場合に
おける従来のプレキャストコンクリートパネル型枠組立
て構造を示す断面図である。
FIG. 10 is a cross-sectional view showing a conventional precast concrete panel formwork assembly structure in the case of constructing a concrete wall of a sabo dam.

【図11】図10に示される従来のプレキャストコンク
リートパネル型枠組立て構造の一部を拡大して示す断面
図である。
FIG. 11 is an enlarged sectional view showing a part of the conventional precast concrete panel formwork assembly structure shown in FIG.

【符号の説明】[Explanation of symbols]

10 プレキャストコンクリートパネル型枠組立て構造 11a 第1段目のプレキャストコンクリートパネル型
枠 11b 第2段目のプレキャストコンクリートパネル型
枠 11c 第3段目のプレキャストコンクリートパネル型
枠 12a 第1段目のプレキャストコンクリートパネル型
枠 12b 第2段目のプレキャストコンクリートパネル型
枠 12c 第3段目のプレキャストコンクリートパネル型
枠 13 支え鋼材 14 アングル材 15 インサートボルト 16 突起部 17 溝部 18 C形ワッシャー 19 打設コンクリート 20 ステー
10 Precast concrete panel formwork assembly structure 11a 1st stage precast concrete panel formwork 11b 2nd stage precast concrete panel formwork 11c 3rd stage precast concrete panel formwork 12a 1st stage precast concrete panel Formwork 12b Second-stage precast concrete panel formwork 12c Third-stage precast concrete panel formwork 13 Support steel material 14 Angle material 15 Insert bolt 16 Protrusion 17 Groove 18 C-shaped washer 19 Cast concrete 20 Stay

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 間隔をあけて設置されたプレキャストコ
ンクリートパネル型枠間にコンクリートを打設し、打設
コンクリートの硬化に伴ってプレキャストコンクリート
パネル型枠を積み重ね、その後再びコンクリートを打設
する工程を繰り返すことによりコンクリートウォールを
建設する方法において、 下の段のプレキャストコンクリートパネル型枠の裏面に
固定され、その上端部から突出する連結材を積み重ね段
のプレキャストコンクリートパネル型枠の裏面に固定し
て上下のプレキャストコンクリートパネル型枠相互を連
結する工程を含み、 前記積み重ね段のプレキャストコンクリートパネル型枠
裏面に前記連結材を固定する時、下の段のプレキャスト
コンクリートパネル型枠裏面と前記連結材との間又は前
記積み重ね段のプレキャストコンクリートパネル型枠裏
面と前記連結材との間に適宜の厚さのスペーサを入れて
前記積み重ね段のプレキャストコンクリートパネル型枠
の傾きを修正することを特徴とするコンクリートウォー
ル建設方法。
1. A step of placing concrete between precast concrete panel forms installed at intervals, stacking the precast concrete panel forms with hardening of the placed concrete, and then placing concrete again. In the method of constructing a concrete wall by repeating it, the connecting material protruding from the upper end of the precast concrete panel formwork on the lower step is fixed to the backside of the stacked precast concrete panel formwork, The step of connecting the precast concrete panel formwork to each other, when fixing the connecting material to the back surface of the precast concrete panel formwork of the stacking step, between the back surface of the precast concrete panel formwork of the lower step and the connecting material. Or the precast of the stacking stage Concrete Wall construction method characterized by down cleat panel formwork rear surface and between said connecting members put appropriate thickness spacers to correct the inclination of the precast concrete panel formwork of the stacking stage.
【請求項2】 間隔をあけて設置されたプレキャストコ
ンクリートパネル型枠間にコンクリートを打設し、打設
コンクリートの硬化に伴ってプレキャストコンクリート
パネル型枠を積み重ね、その後再びコンクリートを打設
する工程を繰り返すことによりコンクリートウォールを
建設する方法において、 積み重ね段のプレキャストコンクリートパネル型枠の裏
面に一端を取付けたステーの他端を前回打設したコンク
リートに埋設させてプレキャストコンクリートパネル型
枠を支持することを特徴とするコンクリートウォール建
設方法。
2. A step of placing concrete between precast concrete panel formwork installed at intervals, stacking the precast concrete panel formwork as the cast concrete hardens, and then placing concrete again. In the method of constructing a concrete wall by repeating it, it is necessary to support the precast concrete panel formwork by embedding the other end of the stay with one end attached to the back surface of the precast concrete panel formwork of the stacking stage in the concrete cast last time. Characteristic concrete wall construction method.
【請求項3】 多数のプレキャストコンクリートパネル
を型枠としてコンクリートウォールを建設する方法であ
って、 最初に、裏面に連結材を上端から突出するように固定し
た第1段目のプレキャストコンクリート型枠を間隔をあ
けて地面に適宜設置し、同様に連結材が上端から突出す
るように裏面に取り付けられた第2段目の別のプレキャ
ストコンクリートパネル型枠を前記第1段目のプレキャ
ストコンクリートパネル型枠上に積み重ね、この積み重
ねられた第2段目のプレキャストコンクリートパネル型
枠裏面に前記第1段目の前記プレキャストコンクリート
パネル型枠から上方に伸長する前記連結材を固定し、次
いで前記間隔内にコンクリートを打設する工程と、 この打設コンクリートが完全に硬化する前に前記第1段
目と第2段目のプレキャストコンクリートパネル型枠を
連結している連結材に一端を取り付けられたステーの他
端を前記打設コンクリート内に埋設して前記打設コンク
リートの硬化によって固定する工程と、 前記打設コンクリートが硬化した後再び前記第2段目の
プレキャストコンクリート型枠の上に前述と同様に連結
材が上端から突出するように裏面に取り付けられた第3
段目の別のプレキャストコンクリートパネル型枠を更に
積み重ね、前記第2段目のプレキャストコンクリート型
枠から上方に伸長する前記連結材に固定し、次いで前記
間隔内にコンクリートを打設する工程とを含み、 前記工程を繰り返して所定の高さまでコンクリートを打
設することによりコンクリートウォールを建設する方
法。
3. A method for constructing a concrete wall by using a large number of precast concrete panels as a formwork, wherein first, a first-stage precast concrete formwork having a connecting material fixed to the back surface so as to project from the upper end is provided. The second precast concrete panel formwork of the second stage, which is appropriately installed on the ground at intervals and similarly attached to the back surface so that the connecting material projects from the upper end, is the precast concrete panel formwork of the first stage. Stacked on top, the connecting material extending upward from the precast concrete panel formwork of the first stage is fixed to the back surface of the stacked second stage precast concrete panel formwork, and then concrete is placed in the space. And the step of placing the first and second stages before the concrete is completely cured. A step of embedding the other end of the stay, one end of which is attached to the connecting material connecting the recast concrete panel formwork, and fixing the other end by hardening the poured concrete; and After hardening, the connecting material was attached to the back side of the second-stage precast concrete formwork again so that the connecting material protruded from the upper end in the same manner as described above.
Stacking another precast concrete panel formwork at the second stage, fixing it to the connecting material extending upward from the second stage precast concrete formwork, and then placing concrete in the space. A method for constructing a concrete wall by repeating the above steps and pouring concrete to a predetermined height.
JP15345094A 1994-07-05 1994-07-05 Erection of concrete wall Pending JPH0820936A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15345094A JPH0820936A (en) 1994-07-05 1994-07-05 Erection of concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15345094A JPH0820936A (en) 1994-07-05 1994-07-05 Erection of concrete wall

Publications (1)

Publication Number Publication Date
JPH0820936A true JPH0820936A (en) 1996-01-23

Family

ID=15562825

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15345094A Pending JPH0820936A (en) 1994-07-05 1994-07-05 Erection of concrete wall

Country Status (1)

Country Link
JP (1) JPH0820936A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859162A (en) * 2017-10-31 2018-03-30 广东水电二局股份有限公司 One kind is encorbelmented bracket structure and its construction method
CN116856413A (en) * 2023-07-04 2023-10-10 中交第四航务工程局有限公司 A kind of shore protection and wave wall heightening template
CN118024384A (en) * 2024-03-19 2024-05-14 北京城建设计发展集团股份有限公司 Method for strengthening the foot of prefabricated lightweight wall and formwork system
WO2025194761A1 (en) * 2024-03-19 2025-09-25 北京城建设计发展集团股份有限公司 Ultra-light fabricated wallboard based on multilayer composite strengthening method and preparation method therefor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859162A (en) * 2017-10-31 2018-03-30 广东水电二局股份有限公司 One kind is encorbelmented bracket structure and its construction method
CN116856413A (en) * 2023-07-04 2023-10-10 中交第四航务工程局有限公司 A kind of shore protection and wave wall heightening template
CN118024384A (en) * 2024-03-19 2024-05-14 北京城建设计发展集团股份有限公司 Method for strengthening the foot of prefabricated lightweight wall and formwork system
WO2025194761A1 (en) * 2024-03-19 2025-09-25 北京城建设计发展集团股份有限公司 Ultra-light fabricated wallboard based on multilayer composite strengthening method and preparation method therefor

Similar Documents

Publication Publication Date Title
US20110131908A1 (en) Structure constructed using precast members and method of constructing the same
JP3899366B1 (en) Boxing formwork and boxing method using the same
JPH0941666A (en) Concrete formwork method
JPH0820936A (en) Erection of concrete wall
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
JP4136049B2 (en) Concrete pier construction method
JP3841493B2 (en) Construction method of viaduct using PCa concrete member
JP2993859B2 (en) Sabo dam precast formwork and its use
JP2891931B2 (en) Formwork for building concrete structures
JPH1143952A (en) Construction method of pile foundation
JPH10102423A (en) PCa formwork and pier construction method using this PCa formwork
JP7429906B2 (en) Wall panel mounting structure and reinforced earth wall construction method
JP7811513B2 (en) Reinforced Concrete Frame and Wall Construction Methods
JP2775668B2 (en) Wide-area slope protection method
JP7064898B2 (en) How to build a liquid barrier
CN113027132A (en) Concrete stepped pouring method for subway slope section plate
JP3029908B2 (en) Construction method of concrete structure
JP2001342639A (en) Buried form
JPH05156605A (en) Construction method of arch concrete by arch form support.
JP7503512B2 (en) Construction method for floating structures
JP2004092098A (en) Construction method of concrete overhang
JP2802612B2 (en) Underwater formwork method
JP2952823B2 (en) Construction method of greening method frame
JPH05321229A (en) Construction method of the top of the concrete dam.
JPH08158350A (en) Construction method of wall body

Legal Events

Date Code Title Description
A02 Decision of refusal

Effective date: 20040324

Free format text: JAPANESE INTERMEDIATE CODE: A02