JPS63201217A - Construction of beam buried in ground - Google Patents
Construction of beam buried in groundInfo
- Publication number
- JPS63201217A JPS63201217A JP3424687A JP3424687A JPS63201217A JP S63201217 A JPS63201217 A JP S63201217A JP 3424687 A JP3424687 A JP 3424687A JP 3424687 A JP3424687 A JP 3424687A JP S63201217 A JPS63201217 A JP S63201217A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- construction
- path
- foundation
- underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 20
- 238000000034 method Methods 0.000 claims abstract description 10
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 7
- 238000004891 communication Methods 0.000 claims description 11
- 238000010586 diagram Methods 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 4
- 210000001520 comb Anatomy 0.000 description 2
- 239000004567 concrete Substances 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000009499 grossing Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
イ 産業上の利用分野
本発明は、柱と梁とで4I属されるラーメン構造物や基
礎梁等を地中に形成する場合、その梁を埋設状態に構築
する方法に関する。DETAILED DESCRIPTION OF THE INVENTION A. Field of Industrial Application The present invention relates to a method of constructing a beam in a buried state when a rigid frame structure or a foundation beam, etc. classified as 4I with columns and beams, is formed underground. .
口 従来技術
従来、地中埋設梁を構築するには、素掘り開削工法や土
留式開削工法等により地下に構築用の空間部を形成して
その空間部に梁を構築し、構築後に開削部の埋め戻しを
していた。Conventional technology Conventionally, in order to construct underground beams, a space for construction is formed underground using the open-cut construction method or the earth retaining method, and the beam is constructed in that space. They were backfilling the area.
ハ 発明が解決しようとする問題点
素掘り開削工法や土留式開削工法を実施するには、地上
に広い工事用地の確保を必要とするばかりか、開削工事
に伴ない発生する騒音や振動が周辺の地盤や構造物に対
して大きな影響を与える。殊に都市再開発の活発化に伴
なう鉄道、道路の高架複線化や狭隘な用地での工事にお
いては、それらの基礎が構築される予定地の地上に、既
設の道路、鉄道、河川、建造物等が存在することは当然
予想され、その場合には一時的な仮工事をして迂回させ
るようにしたり、一旦移転して工事終了後再度元に戻す
といった大規模な補助工事やそのための広大な用地の占
用等が必要となる。殊に鉄道が運営中の路線であると、
その運行を妨げたり、大幅な時刻変更、徐行運転等の運
行規制を行なったり、夜間の突貫作業を余儀無くされる
。C. Problems to be solved by the invention In order to implement the plain excavation method and the earth retaining method, it is not only necessary to secure a large area for construction on the ground, but also the noise and vibrations generated by the excavation work are large in the surrounding area. This has a major impact on the ground and structures of the area. In particular, when constructing elevated double-track railways and roads or constructing narrow sites due to active urban redevelopment, existing roads, railways, rivers, Naturally, it is expected that there will be buildings, etc., and in that case, temporary temporary construction work will be carried out to detour the area, or large-scale auxiliary construction work such as temporarily relocating and returning to the original place after the construction is completed, etc. It will be necessary to occupy a vast amount of land. Especially if it is a route that is currently being operated by a railway.
This may obstruct the operation of the train, make significant time changes, make operation regulations such as driving slowly, or force emergency work to be carried out at night.
二 問題を解決するための手段
本発明は、開削することなく、地上や周辺への影響を大
幅に減らすことにより、安価に短期間で構築を可能とす
る地中埋設梁の構築方法であって、その構成は、掘設さ
れた竪抗同士を地中において接続する水平の連通路を設
け、その連通路の中空部内に鉄筋コンクリートを打設す
ることにある。2. Means for solving the problem The present invention is a method for constructing underground beams that can be constructed inexpensively and in a short period of time by significantly reducing the impact on the ground and surrounding areas without excavation. Its structure consists of providing a horizontal communication path underground that connects the dug vertical shafts, and pouring reinforced concrete into the hollow part of the communication path.
ホ 作用
竪抗同士を接続する水平の連通路は、整梳の入り口が地
上に開口するだけで、地上の状況に全く関係なく形成で
さ、而も中空部はそれ自体が型枠代わりとなるため、そ
の中に打ち込む鉄筋コンクリートは打ち放しをしたまま
後処理は何ら必要としない。E. The horizontal communication passage connecting the working shafts can be formed without regard to the conditions on the ground, simply by opening the entrance of the combing to the ground, and the hollow part itself serves as a formwork. Therefore, the reinforced concrete that is poured into it is left as is and does not require any post-treatment.
へ 実施例
次に本発明に係る梁の構築方法を、地上の営業路線と平
行に構築される高架鉄道の複々線工事において構築され
るラーメン構造物についての実施例を説明する。Embodiment Next, an embodiment of the method for constructing a beam according to the present invention will be described with respect to a rigid frame structure constructed in double-track construction of an elevated railway constructed parallel to an above-ground commercial line.
先ず営業路線1の両脇で、地上に影響の少ない2個所に
所定間隔で各々1対の整梳2.2aを掘設する。この整
梳の深さは、少なくとも埋設梁の位置まで確保し、その
位置は梁が複数段の場合一番深い梁の位置となる。ここ
で整梳間の地盤が充分な強度を有していない場合には、
薬液の注入等により地盤改良処理を行なう0次に竪抗2
.2aの一方を発進整梳、他方を到達整梳に想定し、発
進整梳より到達整梳へ向けて梁の太さに相当する推進管
(ヒユーム管)を打ち込み、その推進管内部を空洞とし
て連通路3を形成する。又同時に他の整梳間2.2又は
2m、2a(路線と直交する方向)にも連通路3a、3
aを形成する0次に前記連通路3に対して上下方向に直
交するスタンドパイプ4.4@・を指定個所及び整梳内
へ垂直に打ち込む、この際地盤の状況により杭打ちが必
要な場合には、スタンドパイプ4の打設と同時に整梳及
びスタンドパイプ4の底へ基礎杭5を打ち込む。First, on both sides of the commercial route 1, a pair of combs 2.2a are dug at predetermined intervals in two locations that have little impact on the ground. The depth of this combing should be ensured at least to the position of the buried beam, and if there are multiple beams, this position will be the position of the deepest beam. If the ground between the combs does not have sufficient strength,
Zero-order vertical shaft 2 where ground improvement treatment is performed by injecting chemical solutions, etc.
.. Assuming that one side of 2a is the starting combing and the other is the final combing, drive a propulsion tube (huyum tube) corresponding to the thickness of the beam from the starting combing toward the final combing, and make the inside of the propulsion tube hollow. A communication path 3 is formed. At the same time, there are communication paths 3a, 3 in other combing gaps 2.2 or 2m, 2a (direction perpendicular to the line).
0 Next, stand pipes 4.4 perpendicular to the communicating path 3 in the vertical direction are driven vertically into the designated areas and into the combing, if piling is required due to ground conditions. At the same time as the stand pipe 4 is being driven, the foundation piles 5 are leveled and driven into the bottom of the stand pipe 4.
これによって打設された基礎杭5上の地中には、スタン
ドパイプ4によって形成された竪穴から成る柱と連通路
2,2aとによる梁とから成る中空ラーメン構造物の骨
組が形成され、この中空部へ鉄筋を配設すると共に、コ
ンクリートを注入して鉄筋コンクリートの打設を行なう
、コンクリートが硬化すれば地中にはラーメン構造物か
ら成る基礎が完成し、その基礎上へ連続して地上構造物
6を構築する。As a result, a framework of a hollow rigid-frame structure is formed in the ground above the foundation piles 5 that have been driven, consisting of columns formed by the vertical holes formed by the stand pipes 4 and beams formed by the communication passages 2 and 2a. Reinforcing steel is placed in the hollow area, and concrete is poured and reinforced concrete is placed. Once the concrete has hardened, a foundation consisting of a rigid frame structure is completed underground, and the above-ground structure is continuously built on top of that foundation. Build object 6.
このようにすれば、スタンドパイプの打ち込みや基礎杭
打ちなどを行う場合以外は、大きな振動はなく、大規模
な開削工事も必要ないから、地上の建造物、道路河川な
どとは関係なく工事ができ、而も周辺の地盤や建造物へ
の影響は極めて少ない、又そのような補助工事がなくな
ることにより、安価で工期も短く、昼間の営業中でも工
事が可能となるのである。In this way, there will be no large vibrations and no large-scale excavation work will be required, except when driving stand pipes or driving foundation piles, so construction work can be carried out regardless of structures on the ground, roads, rivers, etc. However, the impact on the surrounding ground and buildings is extremely small, and since such auxiliary work is no longer required, the construction period is low, the construction period is short, and construction can be carried out even during daytime business hours.
上記実施例においては、連通路を推進管(ヒユーム管)
の打ち込みにより形成したが、H支保工を軸とした矢板
により形成してそれらを取り壊し容易としたトンネル施
工法を採用することもできる。又竪穴はスタンドパイプ
の打ち込みにより形成するばかりでなく、地表から下に
向け、あるいは連通路内から上に向けて掘削したり、推
進工法を下から上に向けて実行してもよい、更に梁の数
、その断面形状、地上構造物等は施工目的により適宜変
更可能であり、杭打ち作業や連通路と直交する竪穴の形
成は、構築物や地曽の状況に応じて増減したり省略する
ことができる。In the above embodiment, the communication path is a propulsion tube (Hyum tube).
Although the tunnel was formed by driving, it is also possible to adopt a tunnel construction method in which the tunnel is formed by sheet piles with H shoring as the axis, which makes it easy to demolish them. In addition to forming a vertical hole by driving a standpipe, it is also possible to excavate it downward from the ground surface or upward from within a communication passage, or by using the propulsion method from the bottom upward. The number of holes, their cross-sectional shape, above-ground structures, etc. can be changed as appropriate depending on the construction purpose, and the number of pile driving operations and the formation of vertical holes perpendicular to the communication path may be increased, decreased, or omitted depending on the structure and ground conditions. Can be done.
ト 効果
本発明の構築方法によれば、地上に既設の道路、鉄道、
河川、建造物等があっても、それらに対して一時的な仮
工事をしたり、移転させるなどの補助工事が必要なくな
り、周辺の建物や地盤への影響も極めて少ないため、現
用建物。G. Effect According to the construction method of the present invention, existing roads, railways,
Even if there are rivers, buildings, etc., there is no need for temporary temporary construction work or auxiliary work such as relocation, and the impact on surrounding buildings and ground is extremely small, so it is an existing building.
営業路線と並行あるいは交叉状に設けられる構築物の地
下における基礎工事は、地上物に何ら影響を与えること
ない、又基礎工事とは関連のない地上における他の工事
と同時進行も可能で、立体的に開発される都市再開発に
おいてもたらされる実益は多大である。Foundation work underground for structures that are installed parallel to or intersecting with commercial routes does not affect anything above ground, and can be carried out simultaneously with other above-ground construction work that is unrelated to the foundation work. The benefits brought about by urban redevelopment in the future are enormous.
図面は本発明に係る構築方法を工程順に示したもので、
第1図は整梳が掘設された状態を示す説明図、第2図は
掘設された竪抗同士が連通路により接続された状態を示
す説明図、第3図はその連通路と竪穴とによりラーメン
構造物の中空状骨組みが形成された状態を示す説明図。
第4図は竪穴の下方へ基礎杭を打設し、中空状骨組みへ
鉄筋コンクリートを打ち込むことにより完成されたラー
メン構造の基礎を示す説明図、第5図は完成された基礎
上に連続して高架建造物が構築された状態を示す説明図
である。
l・・営業路線、2.2a・・整梳、3.3a・・連通
路、4・・スタンドパイプ、5・・基礎杭、6・・地上
構造物The drawings show the construction method according to the present invention in the order of steps,
Figure 1 is an explanatory diagram showing the state in which the leveling comb has been dug, Figure 2 is an explanatory diagram showing the state in which the dug shafts are connected by a communicating passage, and Figure 3 is an explanatory diagram showing the communicating passage and the shaft. FIG. 3 is an explanatory diagram showing a state in which a hollow frame of a rigid frame structure is formed. Figure 4 is an explanatory diagram showing the foundation of a rigid-frame structure completed by driving foundation piles down the shaft and pouring reinforced concrete into the hollow framework. It is an explanatory view showing a state where a building is constructed. l...Business route, 2.2a...Smoothing, 3.3a...Communicating path, 4...Stand pipe, 5...Foundation pile, 6...Ground structure
Claims (1)
連通路を設け、その連通路の中空部内に鉄筋コンクリー
トを打設することを特徴とする地中埋設梁の構築方法。 2 前記連通路が、その連通路と直交する竪穴とによっ
て地中へ中空部から成るラーメン構造物の骨組形状を形
成するものである特許請求の範囲第1項に記載の地中埋
設梁の構築方法。[Claims] 1. Construction of an underground beam characterized by providing a horizontal communication path that connects dug vertical shafts underground, and pouring reinforced concrete into the hollow part of the communication path. Method. 2. Construction of an underground beam according to claim 1, wherein the communicating path forms a frame shape of a rigid frame structure consisting of a hollow part underground by a vertical hole orthogonal to the communicating path. Method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP62034246A JPH0633605B2 (en) | 1987-02-18 | 1987-02-18 | Construction method of underground buried beams |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP62034246A JPH0633605B2 (en) | 1987-02-18 | 1987-02-18 | Construction method of underground buried beams |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63201217A true JPS63201217A (en) | 1988-08-19 |
| JPH0633605B2 JPH0633605B2 (en) | 1994-05-02 |
Family
ID=12408805
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP62034246A Expired - Lifetime JPH0633605B2 (en) | 1987-02-18 | 1987-02-18 | Construction method of underground buried beams |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0633605B2 (en) |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS504810A (en) * | 1973-05-17 | 1975-01-18 |
-
1987
- 1987-02-18 JP JP62034246A patent/JPH0633605B2/en not_active Expired - Lifetime
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS504810A (en) * | 1973-05-17 | 1975-01-18 |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0633605B2 (en) | 1994-05-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108868778B (en) | Non-excavation construction method for large underground structure | |
| CN109914456B (en) | A design and construction method when a bridge and a subway tunnel are built adjacent to each other | |
| CN101418577B (en) | Construction Method of Covering and Excavating Underground Space Pavement in Soft Soil Area | |
| CN102995659A (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
| CN111255462B (en) | Pipe curtain cover excavation top-down construction method for subway station construction | |
| CN108978673A (en) | A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning | |
| JP3586864B2 (en) | Underground structure construction method and elevated traffic path | |
| CN113235613A (en) | Newly-built foundation pit excavation supporting method using adjacent existing fender post | |
| CN113958322B (en) | Tunnel excavation method under existing subway line | |
| CN115450221A (en) | A construction method for a subway crossing a river | |
| JP3930954B2 (en) | Construction method of structure | |
| CN113293798A (en) | Construction method of shallow-buried open-cut tunnel penetrating urban road obliquely | |
| CN110939139B (en) | Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles | |
| KR100455247B1 (en) | Cast-in-site diaphragms wall and the method with benoto method and grouting method of high pressure | |
| CN105804085A (en) | Divisional construction method of multi-unit shaft-type underground stereo garage | |
| JP4303512B2 (en) | Construction method of large section tunnel | |
| CN105986830A (en) | Underground-excavation building method for roadside strip-shaped underground garage | |
| JP2000291398A (en) | Underground structure and its construction method | |
| JPS63201217A (en) | Construction of beam buried in ground | |
| CN108571010A (en) | A method for the integration of prefabricated main structure and support structure in open-cut engineering | |
| JP2656892B2 (en) | Underground structure construction method and continuous underground wall construction method | |
| JP3852686B2 (en) | Three-dimensional intersection construction method and three-dimensional intersection | |
| JPH0721196B2 (en) | Reverse construction method of underground structure | |
| KR102942877B1 (en) | Construction Method of Non-Open Tunnel Using Two Steel Pipes | |
| JP4031284B2 (en) | Construction method for underground structures |