WO2012138058A1 - Procédé de réalisation d'un pilot en béton coulé sur place en utilisant une chemise de coffrage - Google Patents
Procédé de réalisation d'un pilot en béton coulé sur place en utilisant une chemise de coffrage Download PDFInfo
- Publication number
- WO2012138058A1 WO2012138058A1 PCT/KR2012/001477 KR2012001477W WO2012138058A1 WO 2012138058 A1 WO2012138058 A1 WO 2012138058A1 KR 2012001477 W KR2012001477 W KR 2012001477W WO 2012138058 A1 WO2012138058 A1 WO 2012138058A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- mold case
- concrete
- cast
- pile
- case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
Definitions
- the present invention relates to cast-in-place concrete piles, and more specifically, construction of cast-in-place concrete piles using a mold case inserted into a pile drilling hole after concrete is poured. It is about a method.
- piles refer to structures that are used to transfer insufficient support to deep grounds of high strength when mounting structures in soft grounds. These piles can be divided into steel piles, ready-made concrete piles and cast-in-place concrete piles, depending on the material of the body.
- the steel pile is to use a steel pipe or H-shaped steel produced in the factory as a pile, it is constructed by the purchase after driving or pre-excavation.
- ready-made concrete piles are made of RCX Reinforced Concrete piles made in the field or Prestressed Concrete piles or Prestressed Spun High strength Concrete piles produced in the factory. Most of them are high strength PHC piles. In the same way, it is constructed by purchase after driving or digging.
- cast-in-place concrete pile refers to a method of inserting reinforcing steel mesh after excavating the inside, and then pouring concrete to form a pile.
- ready-made product piles and cast-in-place concrete piles such as steel piles and ready-made concrete piles
- the use of ready-made product piles and cast-in-place concrete piles is determined by the size of large sections.
- the cast concrete and cast-in-place concrete piles are to be placed in the ground after drilling the ground.
- quality control and reinforcing steel reinforcement and concrete casting are difficult, for example, small and medium diameters under ⁇ 700 ⁇ are made of ready-made piles, but steel piles and ready-made concrete piles are Since it is expensive or difficult to produce, most of them are constructed with cast-in-place piles.
- the cast-in-place concrete pile is a concrete made by drilling a pile hole to a predetermined depth by using an excavator at a predetermined position of the ground at the site instead of drilling a pre-made concrete pile, and then placing reinforcing bars into the concrete. Say the stakes.
- the technical problem to be solved by the present invention for solving the above-mentioned problems, by inserting the reinforcing bar in the mold case on the ground and cast concrete concrete mold case that can be easily applied on-site casting concrete pile even under medium diameter It is to provide a method of constructing a cast-in-place concrete pile.
- Another technical problem to be achieved by the present invention is to prevent the deformation of the assembled reinforcing bars by inserting a mold case in which the hardened concrete is poured into the pile hole after protecting the reinforcing nets with a mold case.
- the purpose is to provide a method for constructing cast-in-place concrete piles using a case.
- Another technical problem to be achieved by the present invention by placing and inserting the hardened concrete into the mold case and drawing the mold case while giving a vibration, It is to provide a method for constructing concrete piles by using a mold case, which is easy to cast and does not cause material separation and keeps the shape of the concrete pile intact.
- Another technical problem to be achieved by the present invention is to cast concrete mold, and put the mold case after removing the lower base plate to remove the mold case, the cast-in-place concrete pile using the mold case to easily handle the slime of the end of the line It is to provide a construction method.
- the site-casting concrete pile construction method using a mold case according to the present invention the reinforcing bar network and the concrete is inserted into the pre-fabricated mold case on the ground to fill the reinforcing bar and The mold case formed of hard concrete is inserted into the perforated hole of the ground, and the mold casing is drawn to form the cast-in-place concrete pile by the integrated reinforcing bar and concrete.
- the construction method of cast-in-place concrete pile using a mold case according to the present invention a) inserting the assembled reinforcing bar in the mold case; b) connecting a base plate to the mold case tip; c) pouring concrete into the mold case to form a mold case in which concrete is not cast; d) drilling a pile drilling hole in the ground, and inserting the mold case in which the concrete is poured into the pile drilling hole; e) fixing the concrete case in which the concrete is poured into the support ground by a hit using a pile driving; g ) separating the mold case and the base plate; And h) drawing only the mold case while vibrating using the pile driving and forming a concrete pile.
- step e) the mold case may be squeezed and removed by slicing the mold case, and the tip support force may be secured by entering the support ground.
- step b) may be connected to the base plate is integrated with the mold case front end using a tension member.
- the step b) is the base plate is the mole using a shear key It can be connected in one piece with the case end.
- in-site casting concrete pile construction method using the mold case and the tension material a) preparing a mold case formed with the tension member fixing part carried in to the site ; b) assembling a reinforcing bar network and inserting the assembled reinforcing bar network into the mold case; c) connecting a base plate to the mold case tip and inserting a tension member; d) tensioning and fixing the tension member inserted from the base plate to the tension fixing unit; e) pouring concrete not hardened on the mold case to form a mold case in which concrete is poured; f) drilling a pile drilling hole in the ground, and inserting the concrete-casting mold case into the pile drilling hole; g) seating the mold case on which the concrete is poured by the hitting using pile driving to the support ground; h) dismounting the tension member to separate the mold case and the base plate; And i) drawing concrete mold by drawing only the mold case while vibrating using the pile driving
- the method of constructing the cast-in-place concrete pile using the mold case and the tension member according to the present invention may further include the step of cutting the elongated protruding portion of the ground to complete the cast-in-place concrete pile.
- the tension member of step d) is fixed to the tension member fixing unit formed on the upper part of the mold case, the mold case, the base plate and the tension member are integrated to support the load of the concrete until the tension member fixing unit is dismantled. You can do it.
- the step g) may be mounted on the support ground the front end of the mold case in which the concrete is poured while pressing and removing the slime remaining in the pile hole.
- the mold case of step a) is characterized in that the concrete inlet, the reinforcement spacer and the tension fixing unit in the steel pipe case.
- the reinforcing bar network is located in the center by the concrete spacer attached to the inside of the steel pipe case in step b). .
- step c) the base plate is aligned with the lower groove of the mold case, a steel rod or steel wire tension member is inserted, and in step c), the base plate and the mold case are separated seamlessly. It is done.
- step e) is concrete installed at a predetermined interval in the mold case Injecting concrete into the inlet, the concrete inlet is characterized by finishing with an inlet cover.
- the method of building a cast-in-place concrete pile using a mold case and a shear key a) preparing a mold case and bringing it to the site; b) assembling a reinforcing bar network and inserting the assembled reinforcing bar network into the mold case; c) connecting a base plate provided with a shear key to a distal end of the mold case; d) pouring concrete not hardened on the mold case to form a mold case in which concrete is poured; e) drilling a pile drilling hole in the ground, and inserting the mold case in which the concrete is poured into the pile drilling hole; f) seating the concrete casted concrete case on the support ground by smashing using pile driving; g) separating the mold case and the base plate by destroying the shear key by the hit using the pile driving; And h) drawing only the mold case while vibrating using the pile driving to form a cast-in-place concrete pile.
- step c) the shear key is manufactured together with the base plate, and the mold case and the base plate are integrated by making a groove for supporting the shear key at the bottom of the mold case. It is characterized by preventing the pouring of concrete inside the mold case.
- step g the shear key formed on the base plate is destroyed by beating at a load more than the shear key can resist, and the mold case is separated from the base plate.
- the reinforcing bar is inserted into the mold case on the ground and the concrete is poured, the problem of reinforcing the reinforcing bar network due to the mold case is protected even in the small and medium diameter of ⁇ 700 or less, and the concrete hole can be solved. Even under light conditions, cast-in-place concrete piles can be easily applied.
- the deformation of the assembled reinforcing bar does not occur.
- the present invention it is easy to maintain the shape of the intact concrete piles because the material separation of the concrete does not occur because it simply draws the mold case while placing and inserting the concrete into the mold case on the ground and giving vibration. According to the present invention, since the mold case is drawn after the mold case is inserted and the lower base plate is separated, only the mold case is drawn out, and thus it is easy to process the slicing of the tip portion like the embedded pile.
- FIG. 1 is a flowchart illustrating a method of constructing a cast-in-place concrete pile using a mold case and a tension member according to a first embodiment of the present invention.
- FIGS. 2A to 2K are views illustrating a process of constructing a cast-in-place concrete pile using a mold case and a tension member according to the first embodiment of the present invention.
- FIG 3 is a view showing a mold case of a cast-in-place concrete pile using a mold case and a tension member according to the first embodiment of the present invention.
- FIG 4 is a view showing a fixing state after the tension of the cast-in-place concrete pile using the mold case and the tension material according to the first embodiment of the present invention.
- FIG. 5 is a flowchart illustrating a method of constructing a concrete pouring site using a mold case and a shear key according to a second embodiment of the present invention.
- FIG. 6 is a view showing a mold case of the cast-in-place concrete pile using a mold case and a shear key according to a second embodiment of the present invention.
- FIG. 7 is a view showing a fixing state of the cast-in-place concrete pile using a mold case and a shear key according to a second embodiment of the present invention.
- FIG. 8 is a view for explaining the removal of the shear key of the cast-in-place concrete pile using the mold case and the shear key according to the second embodiment of the present invention.
- Base plate 140 Tension material (steel bar or steel wire)
- in-situ concrete pile construction method using a mold case inserting the reinforcing bar network assembled in the mold case, connecting the base plate to the mold case front end, in the mold case
- inserting the reinforcing bar network assembled in the mold case By casting concrete that is not solid, forming a mold case in which concrete is poured, perforating pile drilling holes in the ground, inserting the mold case in which the concrete is poured into pile drilling holes, A mold case in which concrete is poured is seated on the ground, and the mold case and the base plate are separated, and then the mold case is drawn out while vibrating using the pile driving.
- the mold case is to squeeze and remove the slime (slime), to secure the tip support by seating on the support ground.
- the mold case and the base plate fixing and detaching method since the mold case and the base plate must be removed after the mold case is inserted into the ground by placing the mold case, the mold case and the base plate must be removed.
- the method of fixing and separating two methods of using tension material and using shear key are applied. That is, the base plate may be connected to be integrated with the mold case tip by using the tension member. Alternatively, the base plate may be connected to the mold case front end portion by using the shear key.
- FIGS. 1 to 4 a method of constructing a cast-in-place concrete pile using a mold case and a tension member according to a first embodiment of the present invention will be described.
- FIGS. 5 to 8 the present invention It will be described for the construction method of the cast-in-place concrete pile using the mold case and the shear key according to the second embodiment.
- FIGS. 2A to 2K illustrate a mold case and a tension member according to a first embodiment of the present invention. Drawings showing the construction process of cast-in-place concrete piles.
- the mold case 110 may include a steel pipe case 111, a reinforcing spacer 112, a concrete inlet 113, a tension member fixing part 114, an inlet cover 115, a welding part 116, and the like. This will be described later with reference to FIG. 4.
- the reinforcing bar 120 is assembled (S102). Specifically, as shown in Figure 2b, after confirming the drilling depth of the cast-in-place concrete piles, the reinforcing bar 121 and the band reinforcing bars 122 are assembled to prepare a rebar network.
- the assembled reinforcing bar 120 is inserted into the mold case 110 (S103). Specifically, as shown in FIG. 2C, the reinforcing steel mesh 120 is inserted into the prepared mold case 110. In this case, the reinforcing steel mesh is mounted by the concrete spacer 112 attached to the inside of the steel pipe case 111. 120 is centered.
- the base folate 130 is connected and the tension member 140 is inserted.
- S104 the base plate 130 to be installed on the tip portion of the cast-in-place concrete pile is aligned with the lower groove of the mold case 110, and the tension member 140 of the steel rod or steel wire is inserted .
- the base plate 130 and the mold case 110 is in a separated state without a separate seamless.
- the tension member 140 inserted from the base plate 130 to the tension member fixing unit 114 is tensioned (S105). Specifically, as shown in Figure 2e, by tensioning the tension member 140, which is a steel rod, the tip base plate 130 and the mold case 110 of the cast-in-place concrete pile is pressed, the tension member 140 is the mold By fixing the tension member fixing unit 114 formed on the upper part of the case 110, the mold case 110, the base folate 130 and the tension member 140 are integrally formed until the tension member fixing unit 114 is dismantled. By doing so, it supports the load of the subsequently poured internal concrete 150.
- the concrete 150 is poured into the mold case 110, and the mold case 110 in which the concrete is poured is prepared to be inserted into the pile drilling hole (S106). Specifically, as shown in FIG. 2F, the concrete 150 is introduced into the concrete inlet 113 installed at a predetermined interval in the mold case 110, and the concrete inlet 113 is the inlet cover 115. By finishing, the mold case 110 in which the concrete is poured is ready to be inserted into the pile drilling hole.
- the pile drilling hole 410 is drilled to remove slime (S107). Specifically, as shown in Figure 2g, by using the pile driving 300 to drill the pile hole 410 on the ground 400, to remove the slime generated during the drilling.
- the mold case 110 in which the concrete is poured is inserted into the pile drilling hole 410 (S108). Specifically, as shown in FIG. 2H, some slime remains in the pile boring hole 410 formed in the ground 400, and the mold case 110 in which concrete is poured using the pile driving machine 300 is formed. Insert into the pile drilling hole (410).
- the mold case 110 in which the concrete inserted into the ground 400 is poured is put on the supporting ground (S109). Specifically, as shown in FIG. 2i, by hitting the mold case 110 in which concrete is poured using the pile driving machine 300, while pressing and removing the remaining slime, the ground 400 is pressed into the ground 400. The front end of the mold case 110 in which the concrete is not cast is seated on the supporting ground. That is, the mold case 110 may be squeezed and removed by squeezing the mold case, and the tip support may be secured by entering the support ground.
- the rudder is also called a direct rudder by hitting concrete piles, and the rudder is lightly after drilling with the pile rudder. Tell how you are hitting.
- the tension member 140 is dismantled and the mold case 110 is drawn out (S110). Specifically, as shown in Figure 2j, by dismantling the tension member fixing portion 114 of the upper portion of the tension member 140, after separating the mold case 110 and the base plate 130, the pile driving (300) Only the mold case 110 is drawn while giving a vibration.
- the mold case 110 and the base plate 130 which are separated independently are temporarily integrated.
- the concrete case 150 is poured into the mold case 110 and inserted into the pile drilling hole 410, and then the batter is performed by using the pile driving machine 300.
- the mold case 110 and the base plate 130 are separated from each other by dismantling the elongated fixing unit 114 of the upper part of the mold case 110. Then, the mold case By drawing only 110, the concrete pile can be formed.
- FIG. 3 is a view showing a mold case of a concrete pile using a mold case and a tension material according to a first embodiment of the present invention
- Figure 4 is a site casting using a mold case and tension material according to a first embodiment of the present invention
- a diagram showing the settling state after the tension of the concrete pile. 3 the mold case 110 of the cast-in-place concrete pile using the mold case and the tension material according to the first embodiment of the present invention, the steel pipe case 111, reinforcing spacer 112, concrete inlet ( 113, tension fixing unit 114, inlet cover 115, and weld 116.
- Steel pipe case 111 has a plurality of concrete inlet 113 is formed on the outer circumferential surface, the reinforcement spacer 112 is formed on the inside, the tension member fixing portion 114 is formed on the upper end.
- the steel pipe case 111 is formed with a reinforcement spacer 112 to be welded, the concrete is introduced through the concrete penetration 113 After that, the concrete inlet 113 is finished through the inlet cover 115. Afterwards, a mold case in which concrete was poured
- Figure 4 is a view showing a fixing state after the tension of the cast-in-place concrete pile using the mold case and the tension material according to the first embodiment of the present invention.
- the mold case 110 in which the concrete is poured is inserted into the pile drilling hole.
- the concrete spacer 112 is coupled to the inside of the 111 by the welding part 116, and the reinforcing bar 120 is assembled with the main reinforcing bars 121 and the band reinforcing bars 122, and a steel rod, which is a tension member 140, is disposed at the center thereof. Inserted, and concrete 150 is poured into the mold case 110.
- a driving bracket 160 is formed on the side surface, and the driving bracket 160 is shown in FIG. It may be a shape as shown in the cross section which takes the FF line of 4 as an incision line. '
- the base plate 130 as shown in the cross-sectional view of the OC line of Figure 4, the tension member fixing hole 131 is formed, wherein the base plate 130 is a steel plate or PC concrete Can be.
- the tension member 140 is inserted from the base plate 130 to the tension member fixing unit 114 as shown in the cross section taken along the DD line of FIG. 4.
- the tension member 140 and the tension member fixing part 114 may be tightened in a tensioned state as shown in the cross-section of the EE line of FIG. 4, and subsequently the tension member. 140 is disassembled from the tension fixing unit 114, the base plate 130 and the mold case 110 can be separated.
- FIG. 5 is a flowchart illustrating a method of constructing a concrete pile using a mold case and a shear key according to a second embodiment of the present invention
- FIG. 6 illustrates a site using a mold case and a shear key according to a second embodiment of the present invention
- FIG. 7 is a view illustrating a mold case of a cast concrete pile
- FIG. 7 is a view illustrating a fixing state of a cast-in-place concrete pile using a mold case and a shear key according to a second embodiment of the present invention.
- a mold case 210 First, prepare a mold case 210 and bring it to the site (S201). That is, the concrete inlet 213, the reinforcement spacer 212, etc. in the steel pipe or similar case 211 is processed and brought into the construction site.
- the mold case 210 as shown in Figs. 6 and 7, the steel pipe case 211, the reinforcing spacer 212, the concrete inlet 213, the inlet cover 215 and the weld 216 And the like.
- the tension fixing unit 114 shown in FIG. 3 is not formed.
- the reinforcing steel bar 220 consisting of cast steel and strip reinforcement (S202).
- the reinforcing bar 221 and the band reinforcing bars 222 are assembled to prepare the reinforcing bar network.
- the reinforcing wire mesh 220 is inserted into the prepared mold case 210. At this time, the reinforcing steel mesh 220 is positioned at the center by the concrete spacer 212 attached to the inside of the steel pipe case 211. do .
- the base plate 230 provided with the shear key 240 is connected (S204). That is, the base plate 230 to be installed at the distal end of the site-cast concrete Malcook is connected to the mold case 210. At this time, the base plate 230 is provided with a shear key 240.
- the concrete case 250 is poured into the mold case 210, and the mold case 210 in which the concrete is poured is prepared to be inserted into the pile drilling hole (S205). That is, the concrete case 250 is introduced into the concrete inlet 213 installed at predetermined intervals in the mold case 210, and the concrete inlet 213 is closed by the inlet cover 215, where the concrete case is poured into a mold case ( 210 is ready to be inserted into the pile drilling hole.
- the pile drilling hole 410 is drilled and the slime is removed (S206). That is, using the pile driving machine 300 to drill the pile drilling hole 410 on the ground 400, and removes the slime generated during the drilling.
- the mold case 210 in which the hard concrete is poured is inserted into the pile drilling hole 410 (S207). That is, some of the slime remains in the Malkook hole 410 formed in the ground 400, and the mold case 210 in which concrete is poured is inserted into the pile hole 410 using the pile driving machine 300. .
- the concrete placing mold case 210 inserted into the ground 400 is struck and seated on the supporting ground (S208). That is, by hitting the mold case 210 in which the concrete is poured by using the pile driving machine 300, while pressing and removing the remaining slime, the tip portion of the mold case 210 in which the concrete is poured on the supporting ground is pressed. Settle down. At this time, the shear key 240 is broken by the load.
- the mold case 210 is pulled out (S209). Specifically, since the shear key 240 formed at the front end is broken by a smashing, and the mold case 210 and the base plate 230 are separated, the mold case 210 is vibrated using the pile driving device 300. ) Only the concrete casting is completed.
- the base plate 230 includes a shear key 240 using a brittle material such as concrete 7, the lower part of the mold case 210 forms a groove that can support the shear key 240 of the base plate 230, and the two materials are integrated together. Preventing the pouring of concrete 250 inside the mold case 210. Then, by inserting the concrete case in which the mold case 210 is poured into the punching hole, the bottom plate is transmitted to the ground 400 to squeeze or remove the slime so that the base plate is seated on the supporting ground.
- the shear key 240 is broken by the load while the base plate 230 and the mold case 210 are separated. As a result, only the mold case 210 can be pulled out, so that the cast-in-place concrete pile can be completed.
- Figure 8 is a view for explaining the removal of the shear key of the cast-in-place concrete pile using the mold case and the shear key according to the second embodiment of the present invention
- Figure 8a) is a state before the warp to remove the shear key 8
- b) shows a state after the strike for removing the shear key.
- the shear key 240 strikes more than the load that can withstand, the shear key 240 is destroyed. As a result, the mold case 210 and the base plate 230 coupled to the shear key 240 are separated. In addition, such a struck load is transmitted to the base plate 230 by the driving bracket 260 attached to the bottom of the mold case 210, thereby compressing or removing the remaining slime, and thus the base plate 230 Can be seated on the supporting ground.
- the reinforcing bar is inserted into the steel pipe or other similar mold case on the ground and poured concrete. After that, the mold case is inserted into the punched hole as a whole, and after that, similarly to the embedded pile, the mold is inserted into the ground, and then only the mold case is drawn to form a concrete pile.
- the ready-made product pile and the site-cast concrete pile can be provided with many advantages. '
- the reinforcing bar is inserted into the mold case on the ground and the concrete is placed, the reinforcing bar is protected due to the mold case even in the small and medium diameter of ⁇ 700 or less, the problem of placing concrete with a narrow hole diameter Since the solution can be solved, it is easy to apply the cast-in-place concrete pile even under the medium diameter.
- the mold case since the mold case is pulled out while vibrating after inserting and inserting concrete into the mold case, the construction difficulties caused by placing directly in the perforation hole and material separation of concrete do not occur and are intact. It is easy to maintain the shape of the concrete pile.
- the mold case is drawn after the mold case is inserted and the lower base plate is separated, only the mold case is drawn, so that the slime treatment of the tip portion is easy as the embedded pile.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
La présente invention concerne un procédé de réalisation d'un pilot en béton coulé sur place en utilisant une chemise de coffrage. Selon le procédé, après avoir protégé un treillis d'armature avec une chemise de coffrage, la chemise de coffrage dans laquelle est coulé le béton est insérée dans un trou de forage de pilot pour éviter que le treillis d'armature assemblé soit déformé. De même, du fait que la chemise de coffrage est mise en vibration tout en étant tirée vers l'extérieur après le coulage et le façonnage du béton dans la chemise de coffrage, le béton peut être façonné facilement, il ne se produit pas de séparation de matériau et la forme du pilot en béton peut être totalement maintenue. De même, comme de légers impacts sont appliqués après l'insertion de la chemise de coffrage et seule la chemise de coffrage est tirée vers l'extérieur après la séparation d'une semelle inférieure, les boues sur l'extrémité avant peuvent être facilement traitées.
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020110030744A KR101105853B1 (ko) | 2011-04-04 | 2011-04-04 | 몰드 케이스를 이용한 현장타설 콘크리트말뚝의 시공 방법 |
| KR10-2011-0030744 | 2011-04-04 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2012138058A1 true WO2012138058A1 (fr) | 2012-10-11 |
Family
ID=45614294
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/KR2012/001477 Ceased WO2012138058A1 (fr) | 2011-04-04 | 2012-02-28 | Procédé de réalisation d'un pilot en béton coulé sur place en utilisant une chemise de coffrage |
Country Status (2)
| Country | Link |
|---|---|
| KR (1) | KR101105853B1 (fr) |
| WO (1) | WO2012138058A1 (fr) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115030145A (zh) * | 2022-06-24 | 2022-09-09 | 广东众安建筑工程有限公司 | 一种扩翼式钻进跟管桩桩侧注浆施工方法 |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR102220211B1 (ko) | 2019-06-26 | 2021-02-25 | 삼신건설산업 주식회사 | 긴장재 재활용이 가능한 현장 타설 말뚝 및 이를 이용한 시공 방법 |
| KR102299540B1 (ko) * | 2021-06-30 | 2021-09-07 | 한미기초기술 주식회사 | 단면 확장형 주열식 차수벽 시공방법 |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11247183A (ja) * | 1998-02-27 | 1999-09-14 | Nkk Corp | 翼付きねじ込み式鋼管杭及びその施工方法 |
| JP2003027463A (ja) * | 2001-07-19 | 2003-01-29 | Sekisui House Ltd | 鋼管杭用先端部材及び鋼管杭 |
| KR100657176B1 (ko) * | 2004-07-08 | 2006-12-13 | 석운엔지니어링 주식회사 | 선단부 양생후 케이싱 인발식 현장타설 말뚝공법 |
| KR20090130982A (ko) * | 2008-06-17 | 2009-12-28 | 강상욱 | 분리식 말뚝부재 및 그를 이용한 기초말뚝의 시공방법 |
| KR20100114490A (ko) * | 2010-10-05 | 2010-10-25 | 정태원 | 해상 또는 하상 및 초연약층에서 시공되는 현장타설말뚝의 가설용 희생강관의 절감 방법 |
-
2011
- 2011-04-04 KR KR1020110030744A patent/KR101105853B1/ko not_active Expired - Fee Related
-
2012
- 2012-02-28 WO PCT/KR2012/001477 patent/WO2012138058A1/fr not_active Ceased
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11247183A (ja) * | 1998-02-27 | 1999-09-14 | Nkk Corp | 翼付きねじ込み式鋼管杭及びその施工方法 |
| JP2003027463A (ja) * | 2001-07-19 | 2003-01-29 | Sekisui House Ltd | 鋼管杭用先端部材及び鋼管杭 |
| KR100657176B1 (ko) * | 2004-07-08 | 2006-12-13 | 석운엔지니어링 주식회사 | 선단부 양생후 케이싱 인발식 현장타설 말뚝공법 |
| KR20090130982A (ko) * | 2008-06-17 | 2009-12-28 | 강상욱 | 분리식 말뚝부재 및 그를 이용한 기초말뚝의 시공방법 |
| KR20100114490A (ko) * | 2010-10-05 | 2010-10-25 | 정태원 | 해상 또는 하상 및 초연약층에서 시공되는 현장타설말뚝의 가설용 희생강관의 절감 방법 |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115030145A (zh) * | 2022-06-24 | 2022-09-09 | 广东众安建筑工程有限公司 | 一种扩翼式钻进跟管桩桩侧注浆施工方法 |
| CN115030145B (zh) * | 2022-06-24 | 2023-06-30 | 广东众安建筑工程有限公司 | 一种扩翼式钻进跟管桩桩侧注浆施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| KR101105853B1 (ko) | 2012-01-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100982951B1 (ko) | 기시공된 기초 콘크리트체의 보강방법 | |
| JP5202708B2 (ja) | 鋼管杭と、該鋼管杭を用いる杭基礎工法 | |
| KR101056027B1 (ko) | 긴장재를 구비한 변단면 프리스트레스트 콘크리트 복합말뚝과 확대기초의 결합구조 | |
| KR101105853B1 (ko) | 몰드 케이스를 이용한 현장타설 콘크리트말뚝의 시공 방법 | |
| KR20110038443A (ko) | 두부정리가 용이한 구조를 가진 프리스트레스트 콘크리트 말뚝과 확대기초의 결합구조 및 결합시공방법 | |
| KR101341260B1 (ko) | 기존 콘크리트 기초 구조물의 보강 공법 | |
| KR101314080B1 (ko) | 몰드 케이스 및 트레미관을 이용한 현장타설 콘크리트말뚝의 시공 방법 | |
| KR20120039439A (ko) | 엄지말뚝을 이용한 합성벽체 및 이의 시공방법 | |
| KR20160042584A (ko) | 강관을 이용한 cip 흙막이 벽체 | |
| JP4623574B2 (ja) | 杭の構築方法 | |
| KR101414054B1 (ko) | Phc 말뚝 제작용 거푸집 및 이를 이용한 phc 말뚝의 제조방법과 phc 말뚝의 두부보강방법 | |
| KR102023135B1 (ko) | 팔각 케이싱을 이용한 흙막이 공법 | |
| JP2008308945A (ja) | 引張杭併用コンクリート基礎及びその構築方法 | |
| KR101893658B1 (ko) | 모노파일 시공을 위한 현장 타설 말뚝 상단과 교각 하단 사이 연결부 거푸집 장치 및 시공방법 | |
| JP5016521B2 (ja) | アースアンカーおよびその撤去方法 | |
| JP4611113B2 (ja) | 杭と柱の一体化施工方法 | |
| KR20090109282A (ko) | 팩을 이용한 마이크로 파일 기초공법 및 이에 사용되는파일 조립체 | |
| JP2016037706A (ja) | 基礎杭の杭頭部補強工法 | |
| JP6506902B2 (ja) | 杭基礎構造、及び、杭基礎構造の構築方法 | |
| KR20190083898A (ko) | 오버랩 배열구조의 주열식 흙막이 시공 방법 | |
| JP4176104B2 (ja) | 現場造成杭の杭頭処理方法 | |
| KR20190027402A (ko) | 선단부 현장타설 복합 말뚝 공법 | |
| KR20100117826A (ko) | 복합시트파일을 이용한 흙막이 벽체 조성공법 | |
| JP2564465B2 (ja) | 既製杭埋設工法 | |
| KR20130117604A (ko) | 강관말뚝기초 보강장치 및 이를 이용한 기초공법 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12767407 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 12767407 Country of ref document: EP Kind code of ref document: A1 |