WO2012173092A1 - ボイラ施設建設工法 - Google Patents

ボイラ施設建設工法 Download PDF

Info

Publication number
WO2012173092A1
WO2012173092A1 PCT/JP2012/064923 JP2012064923W WO2012173092A1 WO 2012173092 A1 WO2012173092 A1 WO 2012173092A1 JP 2012064923 W JP2012064923 W JP 2012064923W WO 2012173092 A1 WO2012173092 A1 WO 2012173092A1
Authority
WO
WIPO (PCT)
Prior art keywords
boiler
floor unit
installation
floor
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/JP2012/064923
Other languages
English (en)
French (fr)
Inventor
和仁 仲光
真一郎 竹下
裕司 横井
尚 神垣
幸隆 町田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Mitsubishi Power Ltd
Original Assignee
Babcock Hitachi KK
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Babcock Hitachi KK, Hitachi Plant Technologies Ltd filed Critical Babcock Hitachi KK
Publication of WO2012173092A1 publication Critical patent/WO2012173092A1/ja
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22—STEAM GENERATION
    • F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
    • F22B37/00—Component parts or details of steam boilers
    • F22B37/02—Component parts or details of steam boilers applicable to more than one kind or type of steam boiler
    • F22B37/24—Supporting, suspending or setting arrangements, e.g. heat shielding
    • F22B37/244—Supporting, suspending or setting arrangements, e.g. heat shielding for water-tube steam generators suspended from the top

Definitions

  • the present invention relates to construction of a large boiler and its building, and more particularly to a construction method of a boiler facility suitable for shortening a construction period until a boiler used for a power generation facility installed in a suspended state in a building is installed in the building. .
  • Boilers employed in thermal power plant facilities are large in size, and are expanded by heating, so that they are suspended from a structure called a girder provided at the top end of the facility building. In the construction of a boiler having such a structure, improvement of work safety and shortening of the construction period have been problems.
  • a thermal power plant facility equipped with a boiler is roughly composed of a side-span steel frame that forms the side wall of the building and is equipped with piping facilities, a large beam that spans the upper part of the pair of side-span steel frames, A boiler body suspended from the girder.
  • a thermal power plant facility having such a structure has been constructed by a process as shown in FIG. That is, after assembling one main column provided on the four sides of the side span steel frame, the main column of the assembled node, the floor unit that fits in the side span steel frame, and piping are installed. Repeat these steps as many times as needed to complete the side-span steel frame (steps 1-5). Next, the girder spanned between the side span steel frames is lifted and fixed to the upper part of the side span steel frames (step 6). After that, the boiler is lifted based on the large beam. Here, the boiler is divided into a plurality of units (three in the example shown in FIG. 7), and the lower unit is sequentially engaged while pulling up the upper unit. Installation can be performed in parallel (steps 7-9). Assembling a thermal power plant facility in such a process is disclosed in Patent Document 1, for example.
  • Patent Document 2 discloses a construction method for shortening the construction period of the thermal power plant facility having such a configuration.
  • the construction method disclosed in Patent Document 2 first, four main pillars constituting a side span steel frame are erected. Thereafter, a floor module in which a floor unit, piping and the like are incorporated is arranged between the main pillars.
  • each floor module is carried in after being assembled in advance in a factory, and is lifted up to a predetermined position and installed by a jack arranged on the upper part of the main pillar.
  • the connection material which prevents the fall of a side span steel frame is provided between the main pillars.
  • the boiler module disclosed in Patent Document 2 is a separate type module, and includes a large beam for suspending the boiler, an upper module including a boiler upper unit, and a lower module including a boiler lower unit.
  • the upper module and the lower module are each assembled after being assembled at the factory.
  • an object of the present invention is to provide a boiler facility construction method capable of shortening the construction period until the boiler is installed with respect to the construction of a large boiler and its building.
  • a boiler facility construction method includes a main pillar installation process for installing a main pillar of a boiler building, and a plurality of jack devices provided on the upper part of the main pillar after the main pillar installation process.
  • a floor unit installation process for lifting and fixing the floor units constituting each floor of the main pillar by a plurality of jack devices provided on the upper part of the main pillar. It is characterized by having.
  • the floor unit installation step is jacked up after a step of jacking up by connecting a rod unit of the jack device and a floor unit arranged at the top.
  • the floor unit placed on the lower floor of the floor unit is jacked up to the floor where each floor unit is to be installed by repeating the process of jacking up by connecting the floor unit to the lower side of the jacked floor unit with a temporary suspension. It is better to install it and install it.
  • the floor unit installation process may be completed before the boiler installation process is completed.
  • the main pillar installation process also performs installation of beams and steel frames that prevent the main pillar from falling down. By doing in this way, it is possible to prevent the side span steel frame from falling inward when lifting a relatively heavy heavy beam or the like.
  • the jack apparatus used in the large beam installation process, the boiler installation process, and the floor unit installation process may be partially or entirely used in each process. .
  • the jack device that is mutually used in each process may be moved during execution of another process after the use in each process is completed. By doing in this way, the time required only for the movement of the jack device can be eliminated, and the time required for each process can be shortened.
  • the rods of the jack device used in the large beam installation process, the boiler installation process, and the floor unit installation process can be shared and used in common. desirable.
  • the rods can be easily managed, and the number of unused rods can be reduced by the mutual use of the rods, and the total number of rods used can be reduced.
  • an external crane is used for the main pillar installation process, the external crane is removed after the main pillar installation process is finished, a large beam installation process, a boiler installation process, and The floor unit installation process is preferably performed using a jack device.
  • the front block diagram for demonstrating each process in the construction method of the boiler facility which concerns on embodiment is shown.
  • the plane block diagram for demonstrating each process in the construction method of the boiler facility which concerns on embodiment is shown.
  • FIG. 1 is a diagram showing a front configuration of the boiler facility
  • FIG. 2 is a diagram showing a side configuration of the boiler facility.
  • the boiler facility 10 has a boiler building 12 and a boiler body 30 installed in the building.
  • the boiler building 12 includes a side span steel frame 20 that constitutes a side wall and installs piping and the like (not shown), a steel frame 16 before the can that prevents the side span steel frame 20 from falling, and a steel frame 15 after the can (see FIG. 3-2). ), A large beam 22, a wisteria steel frame 24, and the like.
  • the side span steel frame 20 has four main pillars 14 installed on four sides of the building, and a garter beam 18 that connects two of the four main pillars 14 to form a side wall.
  • the main pillar 14 is composed of four struts 13.
  • the side span steel frame 20 is divided into a plurality of levels, and a floor unit 14a and piping (not shown) are installed for each level.
  • the steel frame 16 in front of the can is a beam provided between the pair of side span steel frames 20 so as to constitute the front wall of the boiler building 12.
  • the steel frame 16 before the can plays a role of preventing the side span steel frames 20 from falling inward (sides facing each other) when lifting heavy objects such as large beams on the side span steel frames 20.
  • the post-can steel frame 15 is a beam provided to constitute the rear wall of the boiler building 12 so as to face the above-mentioned pre-can steel frame 16.
  • the large beam 22 is a beam that is connected to the joint 21 provided at the upper end of the main pillar 14 constituting the side span steel frame 20 and is provided so as to span the upper end of the pair of side span steel frames 20. As shown in FIG. 3A, the connection surface between the joint 21 and the large beam 22 is inclined because the method of Japanese Patent No. 3389839 is used.
  • a plurality of small beams called wisteria steel frames 24 are stretched in the front-rear direction of the boiler building 12 on the lower side of the large beams 22.
  • the boiler body 30, which will be described in detail later, is suspended under the wisteria trellis steel frame 24 based on the large beam 22.
  • the boiler body 30 is suspended from a wisteria trellis steel frame 24 installed with the large beam 22 as a reference.
  • the boiler body 30 according to the embodiment is composed of a plurality of units. In the example shown in FIGS. 1 to 3-1 and 3-2, three units (an upper unit 32, an intermediate unit 34, and a lower unit 36) are shown for ease of explanation.
  • FIG. 3A is a diagram illustrating a front configuration
  • FIG. 3B is a diagram illustrating a top configuration.
  • the first and second sections of the main pillar 14 composed of a plurality of layers are installed.
  • the garter beam 18 and the steel frame 16 before the can are installed between the main pillars 14 of the first node.
  • the installation work of the main pillar 14 and the installation work of the garter beam 18, the steel frame 16 before the can, and the steel frame 15 after the can are performed by an external crane (not shown) arranged around the boiler building construction site (step 1).
  • the third and fourth sections of the main pillar 14 are installed.
  • the garter beam 18 and the front steel frame 16 are installed between the main columns 14 of the second node, and when installing the fourth node, the main column 14 of the third node.
  • the garter beam 18 and the pre-can steel frame 16 are installed between them (step 2).
  • the garter beam 18 and the pre-can steel frame 16 are installed between the main pillars 14 of the fourth knot.
  • a joint 21 serving as a base for fixing the large beam 22 is attached to the upper end of the main column, and a jack device 40 for lifting the large beam 22 and the floor unit 14a is provided at the upper end of the main column 14. It is lifted up.
  • the floor unit 14a is started to be lifted and installed (step 3: floor unit installation process).
  • the floor unit installation process as shown in FIG. 4, the floor unit 14a arranged on the upper floor is lifted with the floor units 14a arranged on the lower floor sequentially connected.
  • the rod 40a of the jack device 40 arranged on the upper part of the main pillar 14 is connected to the uppermost part (the floor unit 14a arranged on the uppermost floor, and this is jacked up.
  • the floor unit 14a disposed on the lower floor is disposed below the floor unit disposed on the uppermost portion, and disposed on the upper floor.
  • the floor unit 14a to be disposed and the floor unit 14a to be disposed on the lower floor are connected by the temporary suspension member 50.
  • the floor unit 14a connected to the upper and lower sides via the temporary suspension member 50 is further increased to a predetermined height.
  • the floor unit 14a, which will be jacked up is then placed on the lower floor and connected by a temporary suspension.
  • Each floor unit 14a is jacked up to the floor to be installed and then installed, and after the installation of each floor unit 14a is completed, the temporary suspension is performed with the connection between the floor units 14a. Remove the material.
  • the temporary suspension material is not limited in its material, form, etc. as long as it has durability sufficient to suspend the floor unit 14a.
  • it may be a wire or a chain.
  • the number of times of jack-up is one (unit of a plurality of target floor units 14a), and the time required to raise and lower the rod 40a can be greatly shortened.
  • the time required for moving the jack device 40 can also be shortened.
  • the post-can steel frame 15 is installed (main pillar installation process). After the installation of the garter beam 18, the steel frame 16 before the can and the steel frame 15 after the can is finished, the external crane (not shown) is removed. And in parallel with the floor unit installation process which lifts and installs the floor unit 14a, the big beam 22 is lifted and installed.
  • the same jack device 40 used in the floor unit installation process formed as a parallel operation and the jack device 40 used for lifting the large beam 22 and the boiler body 30 are employed. Thereby, it becomes possible to aim at the mutual utilization of the jack apparatus 40 between processes, and it can shorten the time required for raising / lowering of an unused jack apparatus or a used jack apparatus.
  • the jack device 40 is moved to the upper end of the garter beam 18 or between the large beams 22 in which the installation has been completed to prepare for the lifting work in the next process.
  • the power reach (crane) not shown with which the upper end of the main pillar 14 is equipped for the movement of the jack apparatus 40 step 4: large beam installation process).
  • the wisteria steel frame 24 (see FIGS. 1 and 2) is installed, and the boiler body 30 is lifted by the jack device 40 provided on the upper part of the girder 22 in parallel with the above-described floor installation process. Do.
  • the boiler body 30 is lifted in such a manner that the divided boiler units are sequentially suspended and engaged. For this reason, a plurality of jack devices 40 are required for the lifting, and the lifting jack devices 40 are added as necessary.
  • six jack devices 40 are added after the large beam installation process, and 32 jack devices 40 are arranged at the upper part of the boiler building 12.
  • the number of jack devices 40 used is not a limiting element for carrying out the invention.
  • the boiler body 30 is lifted from the unit on the upper side.
  • the jack for lifting the secondary module (upper unit 32) and the reheater bank module (for example, the intermediate unit 34) is lifted in Step 5 in the example shown in FIG.
  • the device 40 is prepared.
  • the reheater bank module is lifted.
  • the jack device 40 that lifts the sub-module and the jack device 40 that lifts the floor unit 14a are moved to lift the wind box (step 6).
  • the jack device 40 is moved in parallel with the lifting operation of the reheater, the superheater bank module (for example, the lower unit 36) is lifted, and the boiler body 30 is raised. It is suspended from the girder 22 or the wisteria steel frame 24 (step 7: boiler installation process).
  • the construction period can be greatly shortened as compared with the conventional case.
  • the main pillar and the side span steel frame are configured by sequentially repeating the installation of the main pillar and the floor unit for each section (layer), and then the lifting and installation of the large beam are performed.
  • installation of the main pillar 14 (installation of the side span steel frame 20 not including the floor unit 14a) is performed in advance. Since the installation of the floor unit 14a at each node is performed in parallel with the lifting of the large beam 22 and the lifting of the boiler body 30, the entire construction period can be shortened.
  • the work period required for installation of the floor unit takes about 1 ⁇ 4 days of the entire work period.
  • the construction period itself required for installation of the floor unit is longer than before, but this construction period is performed in parallel with the other construction period, that is, the lifting of the boiler body 30.
  • the entire construction period can be shortened to about 3/4 days compared to the conventional method.
  • the external crane after assembling the steel columns such as the main pillar 14, the garter beam 18, the steel frame 16 before the can, and the steel frame 15 after the can through the external crane (not shown), The external crane is removed and the floor unit 14a is installed via the jack device 40 provided on the main column 14 and the like. For this reason, the period which uses an external crane can be shortened and a construction cost can be suppressed.
  • the assembly of the floor unit 14a constituting the side span steel frame 20 and the assembly of each unit constituting the boiler body 30 can be performed near the ground. For this reason, it is possible to reduce high-altitude work by workers and improve the safety of construction work.
  • the jack device 40 used for lifting the floor unit 14a, the large beam 22 and the like and the jack device 40 for lifting the boiler main body 30 are made common, thereby providing a process.
  • Mutual use of the jack device 40 in between is now possible. For this reason, the time required for raising / lowering the used jack apparatus 40 and the jack apparatus 40 scheduled to be used can be shortened.
  • the jack device 40 used in the boiler facility construction method according to the present embodiment is configured as a jack unit by the operation panel 60, the pump unit 42, and the jack device 40 as shown in FIG.
  • Each pump unit 42 can be operated individually in response to a signal from the operation panel 60, and is configured to supply hydraulic oil to each jack device 40 in accordance with the signal.
  • each jack device By using such a jack unit, the lifting state of each jack device can be individually adjusted, and the suspended object can be stably lifted in a state where the suspended object is kept in a horizontal state or in an arbitrary inclination state. Is possible.
  • the jack devices 40 shown in FIGS. 3A and 3B are individually provided with the pump unit 42.
  • the pump unit 42 is a pair-unit jack device that operates in synchronism. You may make it provide for every.
  • a manifold (distributor), a control valve, and the like may be provided between the pump unit 42 and the jack device 40 so as to branch and control the hydraulic oil. This is because it is possible to individually control each jack device 40 by doing in this way.
  • the jack apparatus 40 was added as needed, if there is room in the empty space of the upper part of the boiler building 12, the number of jack apparatuses required over the whole process. 40 may be lifted in advance. This is because, during the building construction process, work such as dropping an excess jack device to the ground or lifting a required jack device is not necessary.
  • the rod 40a of the jack apparatus 40 used for a large beam installation process, a boiler installation process, and a floor unit installation process shares the dimension (size), such as the length and a diameter, and mutually uses in each process. To do.
  • size such as the length and a diameter
  • the number of unused rods can be reduced.
  • the size of the rod to be used may be different between when lifting a heavy object such as the boiler body 30 and when lifting a relatively light object such as the floor unit 14a. This is because it may be possible to reduce the construction cost by using a small diameter rod rather than increasing the number of long and large diameter rods. In such a case, if a means such as biting a spacer to the jack device is employed, only the size of the rod can be changed while using the common jack device 40.

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

【課題】大型ボイラおよびその建屋の建設に関し、ボイラを据え付けるまでの工期を短縮することのできるボイラ施設建設工法を提供することを目的とする。 【解決手段】ボイラ建屋の四方に位置する主柱14を据え付ける主柱据付工程と、前記主柱据付工程の後に、主柱14の上部に備えられた複数のジャッキ装置40により、主柱14間に大梁22を吊上げて固定する大梁据付工程と、前記大梁据付工程の後に、大梁22に備えた複数のジャッキ装置40を介してボイラ本体30を吊上げて固定するボイラ据付工程と、前記大梁据付工程と前記ボイラ据付工程と並行して、主柱14上部に備えられた複数のジャッキ装置40により、主柱14の各フロアを構成するフロアユニット14aを吊上げて固定するフロアユニット据付工程とを有することを特徴とする。

Description

ボイラ施設建設工法
 本発明は、大型のボイラおよびその建屋の建設に係り、特に建屋に吊下げ状態で据え付けられる発電設備に用いるボイラを建屋に据え付けるまでの建設工期を短縮することに好適なボイラ施設の建設工法に関する。
 火力発電所施設などに採用されるボイラは大型であり、加熱により膨張が生ずることから、施設建屋の天端部分に設けられる大梁と称される構造物に吊下げられる構成が採られている。こうした構造のボイラの建設をするにあたっては、作業の安全性の向上と工期の短縮化が課題とされてきた。
 ボイラを備えた火力発電所施設は、概略的には、建屋の側壁を構成すると共に配管設備などが備えられたサイドスパン鉄骨と、対を成すサイドスパン鉄骨の上部に掛け渡される大梁と、この大梁に吊下されるボイラ本体とを有する。
 このような構成の火力発電所施設は従来、図7に示すような工程で建設されてきた。すなわち、サイドスパン鉄骨の四方に設けられる主柱を1節分組み立てた後、組み立てた節の主柱、サイドスパン鉄骨に収まるフロアユニットおよび配管類の据え付けを行う。こうした作業を必要とされる節の数だけ繰り返し、サイドスパン鉄骨を完成させる(ステップ1~5)。次に、サイドスパン鉄骨間に張り渡す大梁を、サイドスパン鉄骨の上部に吊り上げて固定する(ステップ6)。その後、大梁を基準としてボイラの引き上げを行う。ここで、ボイラは、複数(図7に示す例では3つ)のユニットに分割されており、上部側のユニットを引き上げながら下部側のユニットの係合を順次行うことで、ボイラの吊下げと据え付けを並行して行うことができる(ステップ7~9)。このような工程で火力発電所施設を組み立てることは、例えば特許文献1に開示されている。
 また、このような構成の火力発電所施設の建設工期を短縮するための工法が、特許文献2に開示されている。特許文献2に開示されている工法は、まず、サイドスパン鉄骨を構成する4本の主柱を立設する。その後、フロアユニットや配管等が組み込まれたフロアモジュールを主柱間に配置する。ここで、各フロアモジュールは、予め工場で組み立てられた上で搬入され、主柱の上部に配置されたジャッキによって所定位置まで吊り上げて据え付けられる。なお、主柱間には、サイドスパン鉄骨の倒れ込みを防止する連結材が設けられている。
 次に、主柱の上部に備えられたジャッキを用いてボイラモジュールの吊り上げを行う。特許文献2に開示されているボイラモジュールは、セパレートタイプのモジュールであり、ボイラを吊下するための大梁と、ボイラ上部ユニットとを含む上部モジュールと、ボイラ下部ユニットを含む下部モジュールから成る。ここで、上部モジュール、下部モジュールはそれぞれ工場で組み立てられた上で搬入される。
特許第2927320号公報 特開2002-213707号公報
 火力発電所施設の建設にあたっては、ボイラの据付状態を基準として連結部材や配管類の接続が成される。このため、ボイラ据付までの工期を短縮することができれば、建設工期全体の短縮を図ることができると考えられる。
 そこで本発明では、大型ボイラおよびその建屋の建設に関し、ボイラを据え付けるまでの工期を短縮することのできるボイラ施設建設工法を提供することを目的とする。
 上記目的を達成するための本発明に係るボイラ施設建設工法は、ボイラ建屋の主柱を据え付ける主柱据付工程と、前記主柱据付工程の後に、前記主柱上部に備えられた複数のジャッキ装置により、前記主柱間に大梁を吊上げて固定する大梁据付工程と、前記大梁据付工程の後に、前記大梁に備えた複数のジャッキ装置を介してボイラ本体を吊上げて固定するボイラ据付工程と、前記大梁据付工程と前記ボイラ据付工程と並行して、前記主柱上部に備えられた複数のジャッキ装置により、前記主柱の各フロアを構成するフロアユニットを吊上げて固定するフロアユニット据付工程と、を有することを特徴とする。
 また、上記のような特徴を有するボイラ施設建設工法において前記フロアユニット据付工程は、前記ジャッキ装置のロッドと最上部に配置されるフロアユニットを接続してジャッキアップする工程を経た後、ジャッキアップされたフロアユニットの下階に配置されるフロアユニットをジャッキアップされたフロアユニットの下側に仮吊材により接続してジャッキアップする工程を繰り返すことで各フロアユニットを据付対象とするフロアにまでジャッキアップして据付を行うようにすると良い。このような工法を採ることにより、フロアユニット据付に際してジャッキ装置によるジャッキアップ回数を減らすことができる。また、下階のフロアユニットを吊り上げるためにジャッキ装置自体を移設する等の必要性が無い。
 また、上記のような特徴を有するボイラ施設建設工法において前記フロアユニット据付工程は、前記ボイラ据付工程完了前に完了すると良い。このようなタイミングでフロアユニット据付工程を終えることで、ボイラ据付工程が完了した際には、全ての工程が終了することとなり、並行して行った工程の工期分だけ建設工事全体の工期を短縮することができることとなる。
 また、上記のような特徴を有するボイラ施設建設工法において前記主柱据付工程では、主柱の倒れ込みを防止する梁や鉄骨の据え付けも行うようにすると良い。このようにすることで、比較的重量の重い大梁などの吊上げの際、サイドスパン鉄骨が内側へ倒れ込むことを防止することができる。
 また、上記のような特徴を有するボイラ施設建設工法において前記大梁据付工程と前記ボイラ据付工程、および前記フロアユニット据付工程に用いるジャッキ装置は、その一部または全部を各工程にて相互利用すると良い。このような手段を採ることで、不使用のジャッキ装置や、使用を予定するジャッキ装置を建屋上部と地上との間で逐次昇降させる必要が無くなる。このため、ジャッキ装置の昇降、設置に要する時間を短縮することができる。
 また、各工程にて相互利用する前記ジャッキ装置は、各工程においての使用が終了した後、他の工程実施中に移動が成されるようにすると良い。このようにすることで、ジャッキ装置の移動のためだけに要する時間を無くすことができ、各工程に要する時間の短縮を図ることができる。
 また、上記のような特徴を有するボイラ施設建設工法では、前記大梁据付工程と、前記ボイラ据付工程、および前記フロアユニット据付工程に用いる前記ジャッキ装置のロッドは、サイズを共通として相互利用することが望ましい。このような手段を採ることにより、ロッドの管理が容易になると共に、ロッドの相互利用により不使用ロッドの数が減り、使用ロッドの総数を減らすことができる。
 さらに、上記のような特徴を有するボイラ施設建設工法では、前記主柱据付工程には外部クレーンを用い、前記主柱据付工程終了後に前記外部クレーンを撤去し、大梁据付工程、ボイラ据付工程、およびフロアユニット据付工程は、ジャッキ装置を用いて行うようにすることが望ましい。このようにして工事を進めることで、従来に比べて外部クレーンを使用する期間を短くすることができる。このため、外部クレーンを使用するために必要とされる工費を抑制することができ、工事全体の工費も抑えることができる。
 上記のようなボイラ施設建設工法によれば、大型ボイラおよびその建屋の建設にあたり、ボイラ本体を据え付けるまでの工期を短縮することができる。このため、ボイラ施設建設全体の工期も短縮することが可能となる。
実施形態に係る工法により建設するボイラ施設の一例を示す正面図である。 実施形態に係る工法により建設するボイラ施設の一例を示す側面図である。 実施形態に係るボイラ施設の建設工法における各工程を説明するための正面構成図を示す。 実施形態に係るボイラ施設の建設工法における各工程を説明するための平面構成図を示す。 実施形態におけるフロアユニット据付工程の具体的な実施例を示す斜視図である。 従来の工法による建設工程を示すフローと、実施形態に係る建設工程を示すフローとの比較図である。 実施形態に係るボイラ施設建設工法を実施するにあたり使用するジャッキシステムの概略構成を示す図である。 従来のボイラ施設の建設工法における各工程を説明するための図である。
 以下、本発明のボイラ施設建設工法に係る実施の形態について、図面を参照しつつ詳細に説明する。
 まず、図1、および図2を参照して、本実施形態において建設するボイラ施設の一例の概略構成について説明する。なお、図1はボイラ施設の正面構成を示す図であり、図2は同ボイラ施設の側面構成を示す図である。
 ボイラ施設10は、ボイラ建屋12とこの建屋内に据え付けられるボイラ本体30とを有する。ボイラ建屋12は、側壁を構成すると共に図示しない配管類等の据付を行うサイドスパン鉄骨20と、このサイドスパン鉄骨20の倒れ込みを防止する缶前鉄骨16、缶後鉄骨15(図3-2参照)、大梁22、および藤棚鉄骨24等を有する。サイドスパン鉄骨20は、建屋の四方に据え付けられる4本の主柱14と、この4本の主柱14のうちのそれぞれ2本を連結して側壁を構成するガーター梁18を有する。なお、主柱14は、4本の支柱13により構成される。そして、サイドスパン鉄骨20は複数の階層に区分けされており、各階層毎に、フロアユニット14aや図示しない配管類が据え付けられている。
 缶前鉄骨16は、対を成すサイドスパン鉄骨20間であって、ボイラ建屋12の前面壁を構成するように設けられる梁である。缶前鉄骨16はサイドスパン鉄骨20に、大梁等の重量物を吊上げる際、サイドスパン鉄骨20が内側(互いに向かい合う側)へ倒れ込むことを防止する役割を担う。缶後鉄骨15は、前述した缶前鉄骨16と対向してボイラ建屋12の後面壁を構成するように設けられる梁である。
 大梁22は、サイドスパン鉄骨20を構成する主柱14の上端に設けられた仕口21に接続され、対を成すサイドスパン鉄骨20の上端に架け渡すように設けられる梁である。なお、図3-1に示すように、仕口21と大梁22との接続面は特許第3389839号の工法を使用するため傾斜面としている。大梁22の下部側には、藤棚鉄骨24と呼ばれる複数の小梁がボイラ建屋12の前後方向に張り渡されている。詳細を後述するボイラ本体30は、この大梁22を基準とした藤棚鉄骨24の下に吊下されることとなる。
 ボイラ本体30は、大梁22を基準として据え付けられた藤棚鉄骨24に吊下されている。実施形態に係るボイラ本体30は、複数のユニットから構成されている。なお、図1~図3-1、図3-2に示す例では、説明を簡単化するために、3つのユニット(上部ユニット32、中間部ユニット34、および下部ユニット36)として示している。
 以下、このような基本構成を有するボイラ施設10を建設するための工法について、図3-1、図3-2を参照して説明する。なお、図3-1は正面構成を示す図であり、図3-2は上面構成を示す図である。
 まず、複数の階層(図3-1、図3-2に示す例では4節)から構成される主柱14の第1節目、第2節目の据え付けを行う。第2節目の主柱14の据え付けの際、第1節目の主柱14間にガーター梁18、および缶前鉄骨16を据え付ける。主柱14の据付作業とガーター梁18、缶前鉄骨16、および缶後鉄骨15の据付作業は、ボイラ建屋建設地の周囲に配備する外部クレーン(不図示)によって行う(ステップ1)。
 次に主柱14の第3節目、第4節目の据え付けを行う。ここで、第3節目の据え付けの際には、第2節目の主柱14間にガーター梁18、および缶前鉄骨16を据え付け、第4節目の据え付けの際には第3節目の主柱14間にガーター梁18、および缶前鉄骨16を据え付ける(ステップ2)。なお、主柱14の第4節目の据付完了後には、第4節目の主柱14間にガーター梁18と缶前鉄骨16を据え付ける。
 そして、主柱の上端には、大梁22を固定するための基台となる仕口21が取り付けられると共に、大梁22やフロアユニット14aを吊上げるためのジャッキ装置40が、主柱14の上端部へと吊り上げられる。ジャッキ装置40の吊り上げが終了した後、フロアユニット14aの吊り上げ、据付を開始する(ステップ3:フロアユニット据付工程)。フロアユニット据付工程は図4に示すように、上階に配置されるフロアユニット14aに対して下階に配置されるフロアユニット14aを順次連結させた状態で吊り上げが行われる。具体的には、最上部(最上階に配置されるフロアユニット14aに対して、主柱14の上部に配置されたジャッキ装置40のロッド40aを接続し、これをジャッキアップする。最上階に配置されるフロアユニット14aを所定高さ(例えば階層間高さ)まで吊り上げた後、最上部に配置されるフロアユニットの下部に、下階に配置されるフロアユニット14aを配置し、上階に配置されることとなるフロアユニット14aと下階に配置されることとなるフロアユニット14aとを仮吊材50により接続する。仮吊材50を介して上下に接続されたフロアユニット14aをさらに所定高さまでジャッキアップし、次いで下階に配置されることとなるフロアユニット14aの配置と、仮吊材による接続を成す。このような、階層間の接続とジャッキアップを繰り返し行い、各フロアユニット14aが、据付対象となるフロアにまでジャッキアップし、据付を行う。そして、各フロアユニット14aの据付が終了した後、フロアユニット14a間の接続を行った仮吊材を取り外す。
 なお、仮吊材は、フロアユニット14aを吊下するだけの耐久性を有していれば、その材質、形態等に限定は無い。例えばワイヤであっても良いし、鎖であっても良い。
 各階層に係るフロアユニット14a毎にジャッキアップを行った場合には、各階層に係るフロアユニット14aをジャッキアップする度にジャッキ装置40を移動させる必要が生ずると共に、ジャッキアップの回数も増える。実施形態に係る工法によれば、ジャッキアップ回数は1回(対象とする複数のフロアユニット14a単位)となり、ロッド40aの上げ下げに要する時間を大幅に短縮することができる。また、ジャッキ装置40を移設することなく対象とする複数のフロアユニット14aをジャッキアップすることができるため、ジャッキ装置40の移設に要する時間も短縮することができる。
 フロアユニット据付工程と並行して缶後鉄骨15の据え付けを行う(主柱据付工程)。
ガーター梁18と缶前鉄骨16、および缶後鉄骨15の据付が終了した後、外部クレーン(不図示)を撤去する。そして、フロアユニット14aの吊上げおよび据え付けを行うフロアユニット据付工程と並行して、大梁22の吊上げおよび据付を行う。本実施形態では、並行作業として成されるフロアユニット据付工程で用いるジャッキ装置40と、大梁22の吊り上げやボイラ本体30の吊り上げに用いるジャッキ装置40とは、同じものを採用している。これにより、工程間におけるジャッキ装置40の相互利用を図ることが可能となり、不使用ジャッキ装置や使用ジャッキ装置の昇降に要する時間を短縮することができる。
 このため、主柱14におけるフロアユニット14aの据え付けが終了した後には、ジャッキ装置40をガーター梁18の上端や、据え付けが完了した大梁22の間等に移動させ、次工程での吊り上げ作業に備える。なお、ジャッキ装置40の移動には、主柱14の上端に備えられる図示しないパワーリーチ(クレーン)を用いれば良い(ステップ4:大梁据付工程)。
 大梁22の吊上げ終了後、藤棚鉄骨24(図1、図2参照)の据付を行い、上述したフロア据付工程と並行して、大梁22の上部に設けたジャッキ装置40によるボイラ本体30の吊上げを行う。ボイラ本体30の吊上げは、分割されたボイラユニットを順次吊下げて係合するかたちで行われる。このため、その吊り上げには複数のジャッキ装置40が必要とされ、必要に応じて吊り上げ用のジャッキ装置40の追加を行う。なお、図3-1、図3-2に示す例では、大梁据付工程後に6台のジャッキ装置40を追加して32台のジャッキ装置40をボイラ建屋12の上部に配置する構成としているが、使用するジャッキ装置40の多寡は、発明を実施する上での限定的な要素では無い。
 ボイラ本体30の吊り上げは、上部側のユニットから複合的に行われる。例えば図3-1、図3-2に示す例ではステップ5にて、副側モジュール(上部ユニット32)の吊り上げを行うと共に、再熱器バンクモジュール(例えば中間部ユニット34)を吊り上げるためのジャッキ装置40の準備を行う。
 次に、再熱器バンクモジュールの吊り上げを行う。再熱器の吊り上げ作業と並行して、副側モジュールを吊り上げたジャッキ装置40とフロアユニット14aを吊り上げたジャッキ装置40とを移動させ、ウインドボックスの吊り上げ作業を行う(ステップ6)。
 そして、ウインドボックスの吊り上げを終了させ、再熱器の吊り上げ作業と並行してジャッキ装置40の移動を行い、過熱器バンクモジュール(例えば下部ユニット36)の吊り上げを行い、ボイラ本体30を上昇させて大梁22や藤棚鉄骨24に吊下げる(ステップ7:ボイラ据付工程)。
 このような工法で建設されるボイラ施設10によれば、図5に示すように、従来に比べて工期を大幅に短縮することができる。従来は、主柱の据付とフロアユニットの据付を、各節(階層)毎に順次繰り返し行うことで主柱、並びにサイドスパン鉄骨を構成し、その後に大梁の吊上げ、および据付を行っていた。これに対し本実施形態に係るボイラ施設建設工法では、主柱14の据付(フロアユニット14aを含まないサイドスパン鉄骨20の据付)を先行して行うようにしている。そして、各節におけるフロアユニット14aの据付は、大梁22の吊上げやボイラ本体30の吊上げと並行して行うようにしているため、工期全体の短縮を図ることが可能となった。具体的には、従来工程では、主柱内にフロアユニットを備えたモジュール工法を採用した場合でも、フロアユニットの据付に要する工期は、工期全体の約1/4の日数を要していた。これに対して本実施形態に係る工法によれば、フロアユニットの据付に要する工期自体は従来よりも長くなるが、この工期を他の工期、すなわちボイラ本体30の吊り上げと並行して行うことで、工期全体を従来に比べ、約3/4の日数に短縮させることができるのである。
 また、工期の短縮により、工費の抑制、操業時期の繰上げといった効果を奏することができる。なお、ボイラ本体の吊り上げ手順や、吊り上げに用いるジャッキ装置40の数等は、施工内容により適宜変更することができる。
 また、本実施形態に係るボイラ施設建設工法では、主柱14やガーター梁18、缶前鉄骨16、および缶後鉄骨15等の鉄骨類を外部クレーン(不図示)を介して組付けた後、外部クレーンを撤去して主柱14等に備えられたジャッキ装置40を介してフロアユニット14aの据え付けを行うようにしている。このため、外部クレーンを使用する期間を短縮することができ、工費を抑制することができる。
 また、本実施形態のようなボイラ施設建設工法によれば、サイドスパン鉄骨20を構成するフロアユニット14aの組付けやボイラ本体30を構成する各ユニットの組付けを地上付近で行うことができる。このため、作業者による高所作業を減らすことができ、建設作業の安全性を向上させることが可能となる。
 また、本実施形態に係るボイラ施設建設工法では、フロアユニット14aや大梁22等の吊上げ等に用いるジャッキ装置40と、ボイラ本体30を吊上げるためのジャッキ装置40とを共通化させることで、工程間におけるジャッキ装置40の相互利用を図ることが可能となった。このため、使用済みのジャッキ装置40や、使用を予定されるジャッキ装置40を逐次昇降させるために要する時間を短縮することができる。
 また、本実施形態に係るボイラ施設建設工法で用いるジャッキ装置40は、図6に示すように、操作盤60と、ポンプユニット42、およびジャッキ装置40とによってジャッキユニットを構成している。ポンプユニット42はそれぞれ、操作盤60からの信号を受けて個別に稼動することが可能とされており、信号に従って各ジャッキ装置40に作動油を供給するように構成されている。
 このようなジャッキユニットを用いることで、各ジャッキ装置の吊上げ状態を個別に調整することができ、吊下物の水平を保った状態、あるいは任意の傾きを保った状態で安定して吊上げることが可能となる。
 なお、図3-1、図3-2に示した各ジャッキ装置40は、それぞれ個別にポンプユニット42を備えるように示したが、ポンプユニット42は、同期して稼動される組単位のジャッキ装置毎に設けるようにしても良い。この場合には、ポンプユニット42とジャッキ装置40との間にマニホールド(分配器)と制御弁等を設け、作動油の分岐と制御を行うようにすれば良い。このようにすることで、各ジャッキ装置40の制御を個別に行うことが可能となるからである。
 なお、上記実施形態においては、必要に応じてジャッキ装置40を追加する旨記載したが、ボイラ建屋12の上部の空きスペースに余裕があれば、工程全体に亙って必要とする数のジャッキ装置40を、予め吊り上げておくようにすると良い。これにより、建屋建設工程中に、余剰なジャッキ装置を地上に降ろしたり、必要とされるジャッキ装置を吊り上げたりするといった作業が不要となるからである。
 また、上記実施形態では、大梁据付工程と、ボイラ据付工程、およびフロアユニット据付工程に用いるジャッキ装置40のロッド40aは、その長さや直径といった寸法(サイズ)を共通とし、各工程において相互に利用することとしている。このような手段を採ることで、複数種類のロッド40aをボイラ建屋12の上部に配置しておく必要が無くなり、未使用ロッドの数を減らすことができる。なお、当然に、ボイラ本体30等の重量物の吊り上げを行う場合と、フロアユニット14a等の比較的軽い物の吊り上げを行う場合とにおいて、使用するロッドのサイズを異ならせるようにしても良い。長尺、大径のロッドの数を増やすよりも、小径ロッドを用いた方が、工費を削減することができる場合もあるからである。このような場合には、ジャッキ装置にスペーサを噛ます等の手段を採れば、共通のジャッキ装置40を使用しつつ、ロッドのサイズだけを変更することができる。
10………ボイラ施設、12………ボイラ建屋、13………支柱、14………主柱、14a………フロアユニット、15………缶後鉄骨、16………缶前鉄骨、18………ガーター梁、20………サイドスパン鉄骨、22………大梁、24………藤棚鉄骨、30………ボイラ本体、32………上部ユニット、34………中間部ユニット、36………下部ユニット、40………ジャッキ装置、42………ポンプユニット、50………仮吊材、60(60a,60b)………操作盤。

Claims (8)

  1.  ボイラ建屋の主柱を据え付ける主柱据付工程と、
     前記主柱据付工程の後に、前記主柱上部に備えられた複数のジャッキ装置により、前記主柱間に大梁を吊上げて固定する大梁据付工程と、
     前記大梁据付工程の後に、前記大梁に備えた複数のジャッキ装置を介してボイラ本体を吊上げて固定するボイラ据付工程と、
     前記大梁据付工程と前記ボイラ据付工程と並行して、前記主柱上部に備えられた複数のジャッキ装置により、前記主柱の各フロアを構成するフロアユニットを吊上げて固定するフロアユニット据付工程と、
     を有することを特徴とするボイラ施設建設工法。
  2.  前記フロアユニット据付工程は、前記ジャッキ装置のロッドと最上部に配置されるフロアユニットを接続してジャッキアップする工程を経た後、
     ジャッキアップされたフロアユニットの下階に配置されるフロアユニットをジャッキアップされたフロアユニットの下側に仮吊材により接続してジャッキアップする工程を繰り返すことで各フロアユニットを据付対象とするフロアにまでジャッキアップして据付を行うことを特徴とする請求項1に記載のボイラ施設建設工法。
  3.  前記フロアユニット据付工程は、前記ボイラ据付工程完了前に完了することを特徴とする請求項1または請求項2に記載のボイラ施設建設工法。
  4.  前記主柱据付工程では、主柱の倒れ込みを防止する梁や鉄骨の据え付けも行うことを特徴とする請求項1乃至3のいずれか1項に記載のボイラ施設建設工法。
  5.  前記大梁据付工程と前記ボイラ据付工程、および前記フロアユニット据付工程に用いるジャッキ装置は、その一部または全部を各工程にて相互利用することを特徴とする請求項1乃至4のいずれか1項に記載のボイラ施設建設工法。
  6.  各工程にて相互利用する前記ジャッキ装置は、各工程においての使用が終了した後、他の工程実施中に移動が成されることを特徴とする請求項5に記載のボイラ施設建設工法。
  7.  前記大梁据付工程と、前記ボイラ据付工程、および前記フロアユニット据付工程に用いる前記ジャッキ装置のロッドは、サイズを共通として相互利用することを特徴とする請求項1乃至6のいずれか1項に記載のボイラ施設建設工法。
  8.  前記主柱据付工程には外部クレーンを用い、
     前記主柱据付工程終了後に前記外部クレーンを撤去し、
     大梁据付工程、ボイラ据付工程、およびフロアユニット据付工程は、ジャッキ手段を用いて行うことを特徴とする請求項1乃至7のいずれか1項に記載のボイラ施設建設工法。
PCT/JP2012/064923 2011-06-16 2012-06-11 ボイラ施設建設工法 Ceased WO2012173092A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2011134508A JP5743205B2 (ja) 2011-06-16 2011-06-16 ボイラ施設建設工法
JP2011-134508 2011-06-16

Publications (1)

Publication Number Publication Date
WO2012173092A1 true WO2012173092A1 (ja) 2012-12-20

Family

ID=47357079

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2012/064923 Ceased WO2012173092A1 (ja) 2011-06-16 2012-06-11 ボイラ施設建設工法

Country Status (4)

Country Link
JP (1) JP5743205B2 (ja)
MY (1) MY158699A (ja)
PL (1) PL223560B1 (ja)
WO (1) WO2012173092A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3086034A1 (en) * 2015-04-20 2016-10-26 General Electric Technology GmbH Method for connecting heat exchanging surfaces to a main structure of a boiler, boiler and boiler module
WO2016172018A1 (en) * 2015-04-20 2016-10-27 General Electric Technology Gmbh Method for erecting a boiler

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2933555A1 (en) * 2014-04-15 2015-10-21 Alstom Technology Ltd Method for erecting a boiler, module and boiler comprising the module

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0387503A (ja) * 1989-06-07 1991-04-12 Stein Ind Sa 蒸気化ボイラを備えた蒸気発生装置の組立て方法
JPH04257602A (ja) * 1991-02-08 1992-09-11 Mitsubishi Heavy Ind Ltd 吊下型ボイラの据付工法
JP2010013866A (ja) * 2008-07-04 2010-01-21 Hitachi Plant Technologies Ltd 大梁ブロック吊上げ工法およびこれに利用されるジャッキアップステージ

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3389839B2 (ja) * 1997-09-05 2003-03-24 日立プラント建設株式会社 大梁の据付け工法および大梁の芯出し調整装置
JP2002213707A (ja) * 2001-01-19 2002-07-31 Mitsubishi Heavy Ind Ltd セパレート型ボイラプラント及びその建設工法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0387503A (ja) * 1989-06-07 1991-04-12 Stein Ind Sa 蒸気化ボイラを備えた蒸気発生装置の組立て方法
JPH04257602A (ja) * 1991-02-08 1992-09-11 Mitsubishi Heavy Ind Ltd 吊下型ボイラの据付工法
JP2010013866A (ja) * 2008-07-04 2010-01-21 Hitachi Plant Technologies Ltd 大梁ブロック吊上げ工法およびこれに利用されるジャッキアップステージ

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3086034A1 (en) * 2015-04-20 2016-10-26 General Electric Technology GmbH Method for connecting heat exchanging surfaces to a main structure of a boiler, boiler and boiler module
WO2016172018A1 (en) * 2015-04-20 2016-10-27 General Electric Technology Gmbh Method for erecting a boiler

Also Published As

Publication number Publication date
MY158699A (en) 2016-11-15
PL223560B1 (pl) 2016-10-31
JP2013002739A (ja) 2013-01-07
JP5743205B2 (ja) 2015-07-01
PL406800A1 (pl) 2014-07-21

Similar Documents

Publication Publication Date Title
JP5169549B2 (ja) 大梁ブロック吊上げ工法およびこれに利用されるジャッキアップステージ
WO2021120335A1 (zh) 一种大跨度不等高双向曲面网架的累积提升方法
CN207079729U (zh) 钢结构网架顶升装置
CN102146732A (zh) 超大面积双曲面焊接球网架滑移施工方法
CN105442853B (zh) 一种大跨度异形钢网架与落地钢结构安装施工方法
JP2018115427A (ja) 屋根架構の施工方法
JP5743205B2 (ja) ボイラ施設建設工法
JP7041463B2 (ja) 建物の構築方法
JP6257317B2 (ja) 構造物構築方法および構造物解体方法
JP7548869B2 (ja) 構造物の構築方法
JP2014109392A (ja) ボイラ内足場の構築方法
JP4996370B2 (ja) 架構組立方法および建物の架構
JP5003253B2 (ja) Rc大梁の施工方法
JP7169765B2 (ja) 構造物の構築方法
JP6736226B2 (ja) 塔状建築物上部に建設される構造物の構造体および施工法
JP5039304B2 (ja) ボイラ用架構の構築方法
JP5959701B1 (ja) 走行式重量物昇降装置
JP2019143425A (ja) 足場設置方法及び足場設置構造
CN207727618U (zh) 用于基坑逆作法的地下室梁板结构模板体系
JP7708990B1 (ja) 屋根鉄骨の施工方法
CN105386605A (zh) 一种大空间与阶梯看台处的异形钢网架安装施工方法
CN205134533U (zh) 复杂异形钢网架与钢骨架安装施工结构
JP2006009421A (ja) タワークレーンを用いた建物の施工方法
JP3281974B2 (ja) 壁鉄筋ユニットの組立方法および装置
JP3328790B2 (ja) 高層ビルの組立工法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12799944

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: P.406800

Country of ref document: PL

WWE Wipo information: entry into national phase

Ref document number: IDW00201304873

Country of ref document: ID

NENP Non-entry into the national phase