JPH03881B2 - - Google Patents

Info

Publication number
JPH03881B2
JPH03881B2 JP20959983A JP20959983A JPH03881B2 JP H03881 B2 JPH03881 B2 JP H03881B2 JP 20959983 A JP20959983 A JP 20959983A JP 20959983 A JP20959983 A JP 20959983A JP H03881 B2 JPH03881 B2 JP H03881B2
Authority
JP
Japan
Prior art keywords
concrete
steel
girder
composite
steel girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP20959983A
Other languages
Japanese (ja)
Other versions
JPS60102405A (en
Inventor
Hiroo Kishida
Hirofumi Takenaka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HARUMOTO TETSUKOSHO KK
Original Assignee
HARUMOTO TETSUKOSHO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HARUMOTO TETSUKOSHO KK filed Critical HARUMOTO TETSUKOSHO KK
Priority to JP20959983A priority Critical patent/JPS60102405A/en
Priority to EP19890202096 priority patent/EP0350139A3/en
Priority to EP84201618A priority patent/EP0141478B1/en
Priority to DE8484201618T priority patent/DE3483413D1/en
Publication of JPS60102405A publication Critical patent/JPS60102405A/en
Priority to US06/915,900 priority patent/US4710994A/en
Publication of JPH03881B2 publication Critical patent/JPH03881B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】[Detailed description of the invention]

本発明は、プレストレストコンクリート部材を
用いた合成構造部材形成工法に関し、もつと詳し
くはたとえば合成桁橋における鉄筋コンクリート
床版と鋼桁とを合成させた合成桁の形成などに好
適に実施することができる工法に関する。 従来、合成構造部材として多用されているもの
の例としては、橋梁の合成桁橋における鉄筋コン
クリート床版と鋼桁とを合成させた合成桁(梁)
がある。これは、鉄筋コンクリート床版と鋼桁と
をジベルなどのコネクターを用いて一体化させ、
その後の荷重に対しては両者が共同して抵抗する
ようにしたものである。この従来の工法では鉄筋
コンクリート床版の施工は、まず鋼桁を架設し、
次に型枠を施工してからコンクリートを打設して
いる。したがつて型枠、床版の施工に要する工数
が大であり費用が高くつく。そのため鋼桁の軽量
化および小型化が所望されている。 本発明の目的は、上述の技術的課題を解決し、
合成構造部材の小型化および軽量化を実現するこ
とができるプレストレストコンクリート部材を用
いた合成構造部材形成工法を提供することであ
り、さらに詳しくは本発明をたとえば合成桁橋へ
適用することによつて鉄筋コンクリート床版の施
工に要する工数、費用の低減と鋼桁の軽量化、小
型化が実現でき、経済的な合成桁橋を架橋するこ
とが可能となる。プレストレストコンクリート部
材を用いた合成構造部材形成工法を提供すること
である。 第1図は本発明が用いられる橋梁の一実施例の
側面図であり、第2図はその平面図である。橋梁
1は両端部で橋台2,3によつて支持される。橋
梁1は、その軸線方向に延びる工形断面の鋼桁か
らなる複数の主桁4とこれらの主桁によつて支持
されている横桁あるいは対傾構と呼ばれる鋼製の
部材5などを含む骨組を有する。鋼桁4の上面に
は通路板6が設置されている。この通路板6は第
2図において図解を容易にするため右半分が省略
されている。この通路板6は、複数のコンクリー
ト床版7が連接して構成される。このコンクリー
ト床版7は後述するようにその内部に幅方向に延
びるpc鋼(高張力鋼)線8が複数個相互に平行
に埋設されている。なお、コンクリート床版7
は、その内部に埋設されているpc鋼線8が鋼桁
4と平行になるように設置される。なお、pc鋼
線8に代えてpc鋼棒が用いられてもよい。 第3図は本発明に従うプレストレストコンクリ
ート床版7の平面図であり、第4図は第3図の切
断面線−から見た断面図である。コンクリー
ト床版7にはpc鋼線8がターンバツクル9を介
在して幅方向(第3図の左右方向)に延びて埋設
されている。またコンクリート床版7には、この
ターンバツクル9を外囲して長孔10が上方に開
口して形成されている。コンクリート床版7の内
部圧縮応力の解放はこの長孔10によつてターン
バツクル9を外部から操作することによつて行な
われる。ターンバツクル9に代えて本体内部にね
じが軸線方向に沿つて形成されているカツプラー
を用いてもよい。またpc鋼線8にターンバツク
ル9やカツプラーなどの連結手段を介在させなく
ともよく、この場合の内部圧縮応力の解放にあた
つては長孔10においてpc鋼線8を切断しても
よい。なお、長孔15は鋼桁4とコンクリート床
版7とを高強度のモルタルなどを充填することに
よつて一体化するためのものである。 このようなコンクリート床版7は以下の方法に
よつて工場などで予め製作されている。第5図に
示されるように仮想線16で示される型枠を設置
し、必要に応じて長孔9,15のための型枠も設
置しておく。次にこの型枠内に必要な鉄筋ととも
にコンクリートとの付着のないアンボンドpc鋼
線8を配置し、コンクリートを流し込む。所定の
期間養生を行つた後、ジヤツキなどによつてpc
鋼線8に張力を与えて支圧板11,12および定
着部材13,14によつて固定する。このとき、
コンクリートには支圧板11,12を介して圧縮
力が作用し、内部に圧縮応力が発生する。以上の
ようにして予め圧縮応力がその内部に発生してい
るコンクリート床版7が製作される。 第6図はコンクリート床版7が鋼桁4に取付け
られた状態を簡略化して示す斜視図であり、第7
図は第6図の矢符A側から見た正面図である。水
平方向に延びる鋼桁4は、鉛直方向に延びるウエ
ブ20と、ウエブ20の両端部でウエブ20に直
角方向に延びる上フランジ21および下フランジ
22とを含む。上フランジ21の上面にはコンク
リート床版7のすべりを防止するためのすべり防
止部材23が備えられる。このすべり防止部材2
3はたとえばシベルであり、複数の棒状の突起2
4から成り、上フランジ21の上面に溶植されて
固定される。このすべり防止部材23は上フラン
ジ21の上面に間隔をあけて複数個配置されてい
る。 このような鋼桁4にコンクリート床版7の1パ
ネルを、pc鋼線8と鋼桁4とが平行になるよう
にかつ隙間なく敷設する。鋼桁4とコンクリート
床版7とを固定するに当つては、すべり防止部材
23の突起24をコンクリート床版7の下方に突
出したハンチと呼ばれる係止部分7aの所定の位
置に予め設けておいた長孔15に挿入し、その後
高強度のモルタルを前記長孔15に注入して施工
し、コンクリート床版7と鋼桁4とを強固に固定
し一体化する。 次にターンバツクル9または定着部材13また
は14を緩めるなどによつてpc鋼線8の張力を
解放する。これによつて、プレストレス(予め発
生している圧縮応力)によつて縮められていたコ
ンクリート床版7は幅方向に伸びようとする。し
かしながらコンクリート床版7と鋼桁4とは一体
化されているので、その伸びは拘束され、そのた
め鋼桁4には梁を上方に湾曲させるすなわち負の
曲げモーメントと、引張力が作用する。そのた
め、プレストレスが与えられていない通常のコン
クリート床版を鋼桁に設置して合成桁とする場合
に比べて、本発明に従う合成桁は負の曲げモーメ
ントの分だけ正の曲げモーメントが小さくなる。
その結果、自動車や人などの活荷重による正の曲
げモーメントが与えられても、許容曲げ応力まで
には充分の余裕があり、したがつて鋼桁断面を小
さくすることも可能となる。 またこのようなコンクリート床版7は工場にお
いて予め製造されており、橋梁の組立現場ではこ
れを用いて通路板を架設するので、従来のように
現場で型枠を用いてこの型枠にコンクリートを流
し込んで通路板を形成する場合にくらべて型枠が
不用になるので経済的である。また橋梁を設計す
るに際して型枠の荷重を考慮する必要がなくな
り、その分鋼桁の断面を小さくすることができ
る。 第8図はプレストレストコンクリート床版7の
他の実施例の平面図であり、第9図は第8図の切
断面線−から見た断面図である。この実施例
は第3図示の実施例に類似し、対応する部分には
同一の参照符を付す。注目すべきはこの実施例で
はターンバツクル9は使用されていない。そのた
め第3図示の実施例における長孔10も形成され
ていない。このようなプレストレストコンクリー
ト床版7の内部圧縮応力の解放にあたつては、
pc鋼線8の定着部材13,14をジヤツキ操作
などによつて緩めて行なわれる。なお長孔15
は、第3図示の実施例の場合と同様の作用のため
に用いられる。 第10図は鋼桁4に第3図示または第8図示の
コンクリート床版7が設置されたときの、鋼桁4
およびコンクリート床版7の応力度を説明するた
めの図であり、第11図は第10図に対応した曲
げモーメント図を示している。第10図では説明
の簡略化を図るために鋼桁4は両端で単純支点2
6,27で支持されているものと想定する。鋼桁
4が支点26,27で支持されている状態は第1
0図1で示される。この状態では鋼桁4には自重
による等分布荷重によつて第11図1に示される
ように放物線で表わされる正の曲げモーメントl
1が作用する。鋼桁4にコンクリート床版7を設
置して一体化した状態は第10図2で示される。
この状態における曲げモーメントl2は第11図
2で示される。次にコンクリート床版7の内部に
発生しているプレストレスを解放すると、第10
図3図示のようにコンクリートが元の形状に戻ろ
うとする引張力pが鋼桁4に作用し、これによつ
て負の曲げモーメントl3が鋼桁4に作用する。
すなわち第11図3で示されるプレストレスによ
る負の曲げモーメントl3が第11図2の曲げモ
ーメントに加わり、その結果鋼桁4は第11図4
で示されるような曲げモーメントl4が発生する
ことになる。第11図4において仮想線l5で示
される通常の合成桁の曲げモーメントよりも、プ
レストレスによる曲げモーメントl3だけ小さく
なつている。このようにして通常の合成桁と比較
すると、本発明によれば正の曲げモーメントを小
さくできるので、鋼桁4の断面を小さくすること
ができる。 第12図は、プレストレス解放後のコンクリー
ト床版7と鋼桁4とに作用する応力度を具体的に
解析するための基礎となる図である。合成断面に
作用する断面力すなわち軸方向応力Nと曲げモー
メントMは第1式および第2式で表わされる。 N=−pc …(1) M=Ndc=−pc・dc …(2) ただしpcはプレストレスであり、dcはコンク
リート床版7の断面の重心cと合成断面の重心v
との距離を示す。 鋼桁4の縁応力δsu、δslは第3式で表わされ
る。 ここでAvは合成断面の断面積であり、Ivは合
成断面の断面2次モーメントであり、yvsuは合
成断面の重心と上フランジとの距離であり、yvsl
は、合成断面の重心と下フランジとの距離であ
る。 したがつて第1式および第2式を第3式に代入
して縁応力δsu、δslは第4式で示される。 コンクリート床版7の縁応力δcu、δclは当初プ
レストレスpc/コンクリート床版の断面積Acの
圧縮力が生じているので第5式および第6式で示
される。 δcu=pc/Ac+N/nAv−M/n・Ivyvcu =pc/Ac−pc/n・Av+pc・dc/n・Ivyycu …(5) δcl=pc/Ac+N/nAv−M/n・Ivyvcl =pc/Ac−pc/n・Av+pc・dc/n・Ivyycl …(6) ここでnはコンクリートの弾性係数Ecと鋼桁
の弾性係数の比、すなわちn=Es/Ecであり、yvcu は合成断面の重心vとコンクリート床版7の上面
との距離であり、yvclは合成断面の重心vと上フ
ランジとの距離である。 単純活荷重合成桁が用いられる道路橋を型枠を
使用して組立てる場合の合成構造を形成する前に
考慮する荷重は一般には表1で示される。
The present invention relates to a method for forming composite structural members using prestressed concrete members, and more specifically, it can be suitably implemented, for example, for forming composite girders in which reinforced concrete deck slabs and steel girders are combined in composite girder bridges. Regarding construction methods. An example of what has traditionally been widely used as a composite structural member is composite girder (beam), which is a composite of reinforced concrete slabs and steel girders in composite girder bridges.
There is. This is done by integrating the reinforced concrete slab and steel girder using connectors such as dowels.
Both of them jointly resist the subsequent load. In this conventional construction method, the reinforced concrete slab is constructed by first erecting steel girders,
Next, the formwork is constructed and then concrete is poured. Therefore, the number of man-hours required for constructing the formwork and floor slabs is large and the cost is high. Therefore, it is desired to reduce the weight and size of steel girders. The purpose of the present invention is to solve the above-mentioned technical problems,
It is an object of the present invention to provide a construction method for forming a composite structural member using prestressed concrete members that can realize miniaturization and weight reduction of the composite structural member, and more specifically, by applying the present invention to, for example, a composite girder bridge. It is possible to reduce the man-hours and costs required for constructing reinforced concrete slabs, and to make the steel girder lighter and smaller, making it possible to construct an economical composite girder bridge. An object of the present invention is to provide a method for forming a composite structural member using prestressed concrete members. FIG. 1 is a side view of an embodiment of a bridge in which the present invention is used, and FIG. 2 is a plan view thereof. The bridge 1 is supported by abutments 2 and 3 at both ends. The bridge 1 has a framework including a plurality of main girders 4 made of steel girders with a shaped cross section extending in the axial direction, and steel members 5 called transverse girders or anti-tilt structures supported by these main girders. has. A passage plate 6 is installed on the upper surface of the steel girder 4. The right half of the passage plate 6 is omitted in FIG. 2 for ease of illustration. This passage board 6 is constructed by connecting a plurality of concrete floor slabs 7. As will be described later, a plurality of PC steel (high tensile strength steel) wires 8 extending in the width direction are embedded in the concrete slab 7 in parallel with each other. In addition, concrete floor slab 7
is installed so that the PC steel wire 8 buried therein is parallel to the steel girder 4. Note that a PC steel rod may be used instead of the PC steel wire 8. FIG. 3 is a plan view of the prestressed concrete floor slab 7 according to the present invention, and FIG. 4 is a sectional view taken along the section line - in FIG. 3. A PC steel wire 8 is buried in the concrete slab 7 and extends in the width direction (left and right direction in FIG. 3) with a turnbuckle 9 interposed therebetween. Furthermore, a long hole 10 is formed in the concrete slab 7 so as to surround the turnbuckle 9 and open upward. The internal compressive stress of the concrete slab 7 is released by operating the turnbuckle 9 from the outside through the elongated hole 10. Instead of the turnbuckle 9, a coupler may be used in which a screw is formed inside the main body along the axial direction. Moreover, it is not necessary to interpose a connecting means such as a turnbuckle 9 or a coupler in the PC steel wire 8, and in this case, the PC steel wire 8 may be cut at the elongated hole 10 to release the internal compressive stress. The long holes 15 are used to integrate the steel girder 4 and the concrete slab 7 by filling them with high-strength mortar or the like. Such a concrete floor slab 7 is manufactured in advance at a factory or the like by the following method. As shown in FIG. 5, a formwork indicated by an imaginary line 16 is installed, and forms for the long holes 9 and 15 are also installed as necessary. Next, unbonded PC steel wires 8 that do not adhere to concrete are placed in this form together with necessary reinforcing bars, and concrete is poured. After curing for a specified period, the PC is
Tension is applied to the steel wire 8 and it is fixed by bearing plates 11, 12 and fixing members 13, 14. At this time,
A compressive force acts on the concrete via the bearing plates 11 and 12, and compressive stress is generated inside the concrete. As described above, the concrete floor slab 7 in which compressive stress is generated in advance is manufactured. FIG. 6 is a simplified perspective view showing the state in which the concrete slab 7 is attached to the steel girder 4.
The figure is a front view seen from the arrow A side in FIG. 6. The horizontally extending steel girder 4 includes a vertically extending web 20, and an upper flange 21 and a lower flange 22 extending perpendicularly to the web 20 at both ends of the web 20. A slip prevention member 23 is provided on the upper surface of the upper flange 21 to prevent the concrete slab 7 from slipping. This anti-slip member 2
3 is a scibel, for example, and has a plurality of rod-shaped protrusions 2
4, and is fixed by welding on the upper surface of the upper flange 21. A plurality of these anti-slip members 23 are arranged on the upper surface of the upper flange 21 at intervals. One panel of the concrete deck slab 7 is laid on such a steel girder 4 so that the PC steel wire 8 and the steel girder 4 are parallel to each other without any gaps. When fixing the steel girder 4 and the concrete slab 7, the protrusion 24 of the anti-slip member 23 is placed in advance at a predetermined position on a locking part 7a called a haunch that projects below the concrete slab 7. After that, high-strength mortar is injected into the long hole 15 for construction, and the concrete slab 7 and the steel girder 4 are firmly fixed and integrated. Next, the tension in the PC wire 8 is released, such as by loosening the turnbuckle 9 or the fixing member 13 or 14. As a result, the concrete slab 7, which had been contracted due to prestress (compressive stress generated in advance), attempts to expand in the width direction. However, since the concrete slab 7 and the steel girder 4 are integrated, their elongation is restricted, and therefore a negative bending moment and tensile force act on the steel girder 4, which causes the beam to curve upward. Therefore, compared to the case where a normal concrete slab without prestress is installed on a steel girder to form a composite girder, the composite girder according to the present invention has a smaller positive bending moment by the amount of negative bending moment. .
As a result, even if a positive bending moment is applied due to live loads such as automobiles or people, there is sufficient margin up to the allowable bending stress, and it is therefore possible to reduce the cross section of the steel girder. In addition, such concrete deck slabs 7 are manufactured in advance at the factory, and are used to construct the walkway boards at the bridge assembly site, so concrete is poured into the formwork on site using formwork as in the past. Compared to forming passage boards by pouring, it is more economical because no formwork is required. Furthermore, when designing a bridge, there is no need to consider the load of the formwork, and the cross section of the steel girder can be made smaller accordingly. FIG. 8 is a plan view of another embodiment of the prestressed concrete floor slab 7, and FIG. 9 is a sectional view taken from the cutting plane line - in FIG. 8. This embodiment is similar to the embodiment shown in the third figure, and corresponding parts are provided with the same reference numerals. It should be noted that turnbuckle 9 is not used in this embodiment. Therefore, the elongated hole 10 in the embodiment shown in the third figure is also not formed. In releasing the internal compressive stress of such prestressed concrete slab 7,
This is done by loosening the fixing members 13 and 14 of the PC steel wire 8 by jacking or the like. Note that long hole 15
is used for the same function as in the embodiment shown in the third figure. Figure 10 shows the steel girder 4 when the concrete slab 7 shown in Figure 3 or Figure 8 is installed on the steel girder 4.
FIG. 11 shows a bending moment diagram corresponding to FIG. 10. In Fig. 10, in order to simplify the explanation, the steel girder 4 has simple supports 2 at both ends.
Assume that it is supported by 6.27. The state in which the steel girder 4 is supported by the fulcrums 26 and 27 is the first state.
0 is shown in Figure 1. In this state, the steel girder 4 receives a positive bending moment l expressed by a parabola as shown in FIG.
1 comes into play. The state in which the concrete slab 7 is installed and integrated with the steel girder 4 is shown in FIG. 10 2.
The bending moment l2 in this state is shown in FIG. 112. Next, when the prestress generated inside the concrete slab 7 is released, the 10th
As shown in FIG. 3, a tensile force p that causes the concrete to return to its original shape acts on the steel girder 4, thereby causing a negative bending moment l3 to act on the steel girder 4.
That is, the negative bending moment l3 due to the prestress shown in FIG. 113 is added to the bending moment shown in FIG. 112, and as a result, the steel girder 4 is
A bending moment l4 as shown by is generated. The bending moment 13 due to prestress is smaller than the bending moment of a normal composite girder, which is indicated by the imaginary line 15 in FIG. 11 and 4. In this way, when compared with a normal composite girder, according to the present invention, the positive bending moment can be reduced, so the cross section of the steel girder 4 can be made smaller. FIG. 12 is a diagram that serves as a basis for specifically analyzing the degree of stress acting on the concrete deck slab 7 and the steel girder 4 after prestress release. The cross-sectional force, that is, the axial stress N and bending moment M acting on the composite cross section are expressed by the first equation and the second equation. N=-pc...(1) M=Ndc=-pc・dc...(2) However, pc is prestress, and dc is the center of gravity c of the cross section of the concrete slab 7 and the center of gravity v of the composite cross section.
Indicates the distance from The edge stresses δsu and δsl of the steel girder 4 are expressed by the third equation. Here, Av is the cross-sectional area of the composite section, Iv is the second moment of area of the composite section, yvsu is the distance between the center of gravity of the composite section and the upper flange, and yvsl
is the distance between the center of gravity of the composite cross section and the lower flange. Therefore, by substituting the first and second equations into the third equation, the edge stresses δsu and δsl are expressed by the fourth equation. The edge stresses δcu and δcl of the concrete slab 7 are expressed by Equations 5 and 6 since a compressive force of prestress PC/cross-sectional area Ac of the concrete slab is initially generated. δcu=pc/Ac+N/nAv-M/n・Ivyvcu=pc/Ac−pc/n・Av+pc・dc/n・Ivyycu…(5) δcl=pc/Ac+N/nAv−M/n・Ivyvcl=pc/Ac −pc/n・Av+pc・dc/n・Ivyycl…(6) Here, n is the ratio of the elastic modulus of concrete Ec to that of the steel girder, that is, n=Es/Ec, and yvcu is the center of gravity v of the composite cross section. and the upper surface of the concrete slab 7, and yvcl is the distance between the center of gravity v of the composite cross section and the upper flange. When assembling a road bridge using formwork using simple live load composite girders, the loads to be considered before forming the composite structure are generally shown in Table 1.

【表】 したがつて通常の合成桁のときの考慮する荷重
は0.700t/m2〜1.050t/m2であるが、型枠を使用
しない本件では考慮する荷重は0.600t/m2
0.950t/m2となる。したがつて床版施工時の死荷
重を14%〜10%軽くすることができる。 さらに上述の結果、および第4式〜第6式を用
いて、本件発明者が通常の合成桁と本件による合
成桁とを設計計算した一例が第2表に示されてい
る。なお、第2表では許容応力は±2100Kg/cm2
し、コンクリート断面は横が2736cm、縦が230cm
とする。
[Table] Therefore, the load to be considered for ordinary composite girders is 0.700t/m 2 to 1.050t/m 2 , but in this case, where no formwork is used, the load to be considered is 0.600t/m 2 to 1.050t/m 2
It becomes 0.950t/ m2 . Therefore, the dead load during floor slab construction can be reduced by 14% to 10%. Further, Table 2 shows an example in which the present inventor designed and calculated a normal composite girder and a composite girder according to the present invention using the above-mentioned results and Equations 4 to 6. In addition, in Table 2, the allowable stress is ±2100Kg/ cm2 , and the concrete cross section is 2736cm in width and 230cm in length.
shall be.

【表】 第2表によつて鋼桁の重量比は第7式で示され
る。 388.2−341.6/388.3×100=12.0% …(7) すなわち、本発明によれば、鋼桁の重量を従来
よりも12.0%軽くすることができることになる。 通常、合成桁橋の鋼桁部には、鋼桁、床版、地
覆、高欄、舗装等の死荷重および活荷重などの鉛
直荷重によつて正の曲げモーメントが作用し、上
縁側に圧縮応力、下縁側に引張応力が発生してい
る。本工法では内部に圧縮応力の発生しているプ
レキヤストプレストレストコンクリート床版と鋼
桁とを一体化した後、コンクリート床版の応力解
放によつて鋼桁部には引張力と負の曲げモーメン
トが作用するので、通常の工法に比べて上縁側の
圧縮応力、下縁側の引張応力ともに小さくなる。
従つて通常の工法よりも大きな荷重に抵抗ができ
ることになる。すなわち、同じ鉛直荷重に対して
両者を比較すれば、本工法の方が鋼桁部の所要断
面積は小さくてすむことになり、鋼桁の軽量化、
小型化が図れる。また鋼桁断面を小さくすること
によつて、桁高さを低くすることができるので、
風圧などの橋梁側面に加わる荷重を小さくするこ
とが可能となる。また、桁下空間が制限される箇
所にも適用でき、取付け道路の嵩上げ高さを低く
することによつて経済的にも有利となる。 また従来の工法では鉄筋コンクリート床版を施
工するためには型枠を組立てる必要があるが、本
工法においては予め工場等において製作されたプ
レキヤスト床版を用いるので型枠を必要とせず、
床版の施工に要する工数、費用の低減が図れる。 また本発明を圧縮力の作用する合成構造部材に
適用した場合には、部材の設計に際して考慮され
る荷重によつて圧縮力が作用する基礎部材に対し
それと一体化させた内部に圧縮応力の発生してい
るプレキヤストプレストレストコンクリート部材
の応力を解放することによつて、基礎部材には引
張力が作用することになり、荷重によつて発生す
る圧縮力を打消すことになる。すなわち合成桁橋
へ適用した場合と同様に、型枠施工の省略による
工数、費用の低減と部材の軽量化、小型化が図
れ、経済的な合成構造部材を創ることができる。 以上のように、本発明によれば合成構造部材を
形成する際、プレキヤストプレストレストコンク
リート部材を用い、その内部に発生している圧縮
応力を解放することにより、設計上考慮される荷
重によつて部材に発生する圧縮力あるいは曲げモ
ーメントとは逆方向の力が与えられ、そのため部
材の軽量化、小型化が図れる。またプレキヤスト
部材の使用によつて工数、費用の低減および品質
の向上を図ることができる。
[Table] According to Table 2, the weight ratio of the steel girder is shown by equation 7. 388.2−341.6/388.3×100=12.0% (7) That is, according to the present invention, the weight of the steel girder can be reduced by 12.0% compared to the conventional method. Normally, a positive bending moment acts on the steel girder part of a composite girder bridge due to vertical loads such as dead loads and live loads of the steel girders, deck slabs, ground covering, handrails, pavement, etc., causing compression on the upper edge side. Tensile stress is generated on the lower edge side. In this construction method, after the precast prestressed concrete slab, which has internal compressive stress, and the steel girder are integrated, tensile force and negative bending moment are applied to the steel girder by releasing the stress in the concrete slab. As a result, both the compressive stress on the upper edge side and the tensile stress on the lower edge side are smaller than in normal construction methods.
Therefore, it is able to withstand greater loads than conventional construction methods. In other words, if we compare the two methods for the same vertical load, this method requires a smaller cross-sectional area of the steel girder, which reduces the weight of the steel girder.
Can be made smaller. In addition, by reducing the cross section of the steel girder, the height of the girder can be lowered.
It is possible to reduce loads such as wind pressure that are applied to the side of the bridge. Moreover, it can be applied to places where the space under the girder is limited, and it is economically advantageous by lowering the height of the access road. In addition, with conventional construction methods, it is necessary to assemble formwork in order to construct reinforced concrete slabs, but this method uses precast slabs that are pre-fabricated in a factory, etc., so no formwork is required.
The man-hours and costs required for floor slab construction can be reduced. Furthermore, when the present invention is applied to a composite structural member on which compressive force acts, compressive stress is generated inside the foundation member on which compressive force acts due to the load taken into consideration when designing the member. By releasing the stress in the precast prestressed concrete member, a tensile force will act on the foundation member, counteracting the compressive force generated by the load. In other words, as in the case of applying it to a composite girder bridge, the number of man-hours and costs can be reduced by omitting formwork construction, and the components can be made lighter and smaller, making it possible to create an economical composite structural component. As described above, according to the present invention, when forming a composite structural member, a precast prestressed concrete member is used, and by releasing the compressive stress generated inside the member, the load considered in the design can be reduced. A force in the opposite direction to the compressive force or bending moment generated in the member is applied, so that the member can be made lighter and smaller. Furthermore, by using precast members, it is possible to reduce man-hours and costs, and improve quality.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明が使用される橋梁の一実施例の
側面図、第2図はその平面図、第3図は本発明に
従うプレストレスコンクリート床版7の平面図、
第4図は第3図の切断面線−から見た断面
図、第5図はプレストレスコンクリート床版7の
製造方法を説明するための図、第6図はコンクリ
ート床版7が鋼桁4に取付けられた状態を簡略化
して示す斜視図、第7図は第6図の矢符A側から
見た正面図、第8図はプレストレストコンクリー
ト床版7の他の実施例の平面図、第9図は第8図
の切断面線−から見た断面図、第10図は鋼
桁4およびコンクリート床版7の応力度を説明す
るための図、第11は第10図に対応した曲げモ
ーメント図、第12図はコンクリート床版7と鋼
桁4とに作用する応力度を具体的に解析するため
の基礎となる図である。 1……橋梁、4……鋼桁、7……プレストレス
トコンクリート床版、8……pc鋼線、9……タ
ーンバツクル。
FIG. 1 is a side view of an embodiment of a bridge in which the present invention is used, FIG. 2 is a plan view thereof, and FIG. 3 is a plan view of a prestressed concrete slab 7 according to the present invention.
Fig. 4 is a sectional view taken from the cutting plane line - in Fig. 3, Fig. 5 is a diagram for explaining the manufacturing method of the prestressed concrete deck slab 7, and Fig. 6 shows that the concrete slab 7 is a steel girder 4. 7 is a front view seen from the arrow A side of FIG. 6, and FIG. 8 is a plan view of another embodiment of the prestressed concrete floor slab 7. Figure 9 is a sectional view taken from the cutting plane line - in Figure 8, Figure 10 is a diagram for explaining the stress of the steel girder 4 and concrete slab 7, and Figure 11 is a bending moment corresponding to Figure 10. 12 are diagrams that serve as the basis for specifically analyzing the degree of stress acting on the concrete deck slab 7 and the steel girder 4. 1... Bridge, 4... Steel girder, 7... Prestressed concrete slab, 8... PC steel wire, 9... Turnbuckle.

Claims (1)

【特許請求の範囲】[Claims] 1 圧縮応力がその内部に発生しており、かつそ
の圧縮応力を解放する手段を有するプレストレス
トコンクリート部材を予め準備し、前記コンクリ
ート部材を鋼またはコンクリート製の基礎部材
に、前記圧縮応力の作用方向と基礎部材の部材軸
方向とが平行になるよう固定的に設置し、その
後、圧縮応力解放手段によつてコンクリート部材
の圧縮応力を解放することによつて、基礎部材に
前記作用方向に沿う引張力および曲げモーメント
を発生させることを特徴とするプレストレストコ
ンクリート部材を用いた合成構造部材形成工法。
1. Prepare in advance a prestressed concrete member in which compressive stress is generated and which has means for releasing the compressive stress, and place the concrete member on a steel or concrete foundation member in the direction in which the compressive stress acts. By installing the foundation member in a fixed manner so that its axial direction is parallel to the member axis, and then releasing the compressive stress in the concrete member using a compressive stress release means, the tensile force along the acting direction is applied to the foundation member. A method for forming composite structural members using prestressed concrete members, which is characterized by generating bending moments.
JP20959983A 1983-11-07 1983-11-07 Formation of synthetic structural member using prestresed concrete member Granted JPS60102405A (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
JP20959983A JPS60102405A (en) 1983-11-07 1983-11-07 Formation of synthetic structural member using prestresed concrete member
EP19890202096 EP0350139A3 (en) 1983-11-07 1984-11-07 A method for forming a composite structural member
EP84201618A EP0141478B1 (en) 1983-11-07 1984-11-07 A method for forming a composite structural member
DE8484201618T DE3483413D1 (en) 1983-11-07 1984-11-07 METHOD FOR PRODUCING A COMPOSED COMPONENT.
US06/915,900 US4710994A (en) 1983-11-07 1986-10-06 Method of forming a composite structural member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20959983A JPS60102405A (en) 1983-11-07 1983-11-07 Formation of synthetic structural member using prestresed concrete member

Publications (2)

Publication Number Publication Date
JPS60102405A JPS60102405A (en) 1985-06-06
JPH03881B2 true JPH03881B2 (en) 1991-01-09

Family

ID=16575486

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20959983A Granted JPS60102405A (en) 1983-11-07 1983-11-07 Formation of synthetic structural member using prestresed concrete member

Country Status (1)

Country Link
JP (1) JPS60102405A (en)

Also Published As

Publication number Publication date
JPS60102405A (en) 1985-06-06

Similar Documents

Publication Publication Date Title
EP0141478B1 (en) A method for forming a composite structural member
US6244008B1 (en) Lightweight floor panel
JP3588325B2 (en) Construction method of single span and multi span composite girder bridges
CA2440765C (en) Composite structural framing system
US4363200A (en) Pre-cast building element and method
US20210189726A1 (en) Method of introducing prestress to beam-column joint of pc structure in triaxial compression
CN110805144B (en) Full-assembly type high-rise/super high-rise concrete frame support structure system and construction method thereof
KR100949828B1 (en) Steel beam and hybrid beam of steel concrete for slim floor
KR101432087B1 (en) Composite rahman bridge using preflex beam and horizontal shear connectors and construction method thereof
JP2978903B1 (en) Viaduct
CN110392758B (en) Inverted T-section hybrid prestressed concrete beam and panel construction method using the same
KR101752285B1 (en) Hybrid beam with wide PSC lower flange and enlarged section upper flange and structure frame using the same
JPH0475322B2 (en)
CN215802567U (en) Floor slab using concrete laminated slab
JPH0320524B2 (en)
JPH03881B2 (en)
JP3909488B2 (en) Seismic reinforcement structure of existing building and its construction method
JPH05311922A (en) Earthquake resistant wall
JPH11303022A (en) Composite deck for bridge
CN216616208U (en) Connection node of prefabricated component of assembled
WO2004057125A1 (en) A prefabricated multi-floor frame structure
JP4264900B2 (en) Beam-floor joint structure
JPS5920492Y2 (en) PC version strength fixing structure
JPH0447721B2 (en)
JPS6335773B2 (en)