JPH0447721B2 - - Google Patents
Info
- Publication number
- JPH0447721B2 JPH0447721B2 JP1836685A JP1836685A JPH0447721B2 JP H0447721 B2 JPH0447721 B2 JP H0447721B2 JP 1836685 A JP1836685 A JP 1836685A JP 1836685 A JP1836685 A JP 1836685A JP H0447721 B2 JPH0447721 B2 JP H0447721B2
- Authority
- JP
- Japan
- Prior art keywords
- steel girder
- auxiliary
- fixing
- members
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000002131 composite material Substances 0.000 claims description 24
- 238000000034 method Methods 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 description 71
- 239000010959 steel Substances 0.000 description 71
- 239000004567 concrete Substances 0.000 description 60
- 238000005452 bending Methods 0.000 description 31
- 238000010276 construction Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 7
- 239000011150 reinforced concrete Substances 0.000 description 7
- 239000011083 cement mortar Substances 0.000 description 3
- 238000005336 cracking Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 239000007767 bonding agent Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】
産業上の利用分野
本発明は、たとえば合成桁橋を架設するとき鉄
筋コンクリート床版と鋼桁とを合成させて合成桁
を形成する工法に関する。DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to a construction method for forming a composite girder by combining a reinforced concrete deck slab and a steel girder, for example, when constructing a composite girder bridge.
背景技術
従来、合成構造部材として多用されているもの
の例としては、橋梁の合成桁橋における鉄筋コン
クリート床版と鋼桁とを合成させた合成桁があ
る。これは鉄筋コンクリート床版と鋼桁とをジベ
ルなどのコネクタを用いて一体化させ、その後の
荷重に対しては両者が共同して抵抗するように構
成したものである。BACKGROUND ART Conventionally, an example of a composite structural member that has been frequently used is a composite girder in which a reinforced concrete deck slab and a steel girder are combined in a composite girder bridge. This is a structure in which a reinforced concrete deck slab and a steel girder are integrated using connectors such as dowels, so that they jointly resist the subsequent load.
発明が解決しようとする問題点
上記先行技術では、合成桁橋の鋼桁には、鋼桁
の自重、床版地覆、高欄、舗装などの死荷重およ
び人や自動車などの活荷重の鉛直荷重によつて正
の曲げモーメントが作用し、鋼桁の上縁側に圧縮
応力が発生し、下縁側には引張応力が発生する。
このような応力に起因して合成桁橋はひび割れな
どの破損が生じることになる。そこで、このよう
な橋の鋼桁および鉄筋コンクリート床版は、前記
荷重に対する所定の許容率を考慮して設計されて
いる。そのため、鋼桁断面が比較的大となり、ま
た鋼桁自体の重量も大となつて大形化する。した
がつて橋梁を構築するにあたつてはコストが高く
つく、という問題がある。Problems to be Solved by the Invention In the above-mentioned prior art, the steel girder of a composite girder bridge is subjected to vertical loads such as the dead weight of the steel girder, the dead load of the deck slab, the handrail, the pavement, etc., and the live load of people and automobiles. As a result, a positive bending moment acts, compressive stress is generated on the upper edge side of the steel girder, and tensile stress is generated on the lower edge side.
Such stress causes damage such as cracks in composite girder bridges. Therefore, the steel girders and reinforced concrete slabs of such bridges are designed taking into consideration a predetermined tolerance rate for the load. Therefore, the cross section of the steel girder becomes relatively large, and the weight of the steel girder itself also becomes large, resulting in an increase in size. Therefore, there is a problem in that the cost of constructing a bridge is high.
また、近年、道路端の鉄筋コンクリート床版の
ひび割れが橋梁の維持管理上の大きな問題として
取上げられている。 Furthermore, in recent years, cracks in reinforced concrete slabs at road edges have been raised as a major problem in bridge maintenance and management.
本発明の目的は、上述の技術的課題を解決し、
鋼桁の軽量化および小形化ならびに鉄筋コンクリ
ート床版のひび割れに対する強度の向上を図るこ
とができるようにした合成構造部材形成工法を提
供することである。 The purpose of the present invention is to solve the above-mentioned technical problems,
An object of the present invention is to provide a method for forming a composite structural member, which makes it possible to reduce the weight and size of a steel girder and to improve the cracking strength of a reinforced concrete slab.
問題点を解決するための手段
請求項1記載の本発明は、基礎部材に補助部材
を設置して一体化する合成構造部材形成工法にお
いて、
前記基礎部材に相互に間隔をあけて一対の固定
部材を固定し、各固定部材間に複数の補助部材を
設置し、少なくとも一方の固定部材と補助部材と
の間にジヤツキを介在し、
このジヤツキを伸張することによつて、基礎部
材にはその部材軸方向に引張力を発生させ、かつ
補助部材には前記部材軸方向に圧縮力を作用さ
せ、この状態で、前記補助部材を基礎部材に固定
し、
次に、ジヤツキを収縮することを特徴とする合
成構造部材形成工法である。Means for Solving the Problems The present invention according to claim 1 provides a composite structural member forming method in which auxiliary members are installed and integrated with a foundation member, comprising: a pair of fixing members spaced apart from each other on the foundation member; is fixed, a plurality of auxiliary members are installed between each fixed member, a jack is interposed between at least one of the fixed members and the auxiliary member, and by stretching this jack, the base member is attached to the base member. A tensile force is generated in the axial direction, and a compressive force is applied to the auxiliary member in the axial direction of the member, and in this state, the auxiliary member is fixed to the base member, and then the jack is contracted. This is a method for forming composite structural members.
請求項2記載の本発明は、基礎部材に補助部材
を設置して一体化する合成構造部材形成工法にお
いて、
前記基礎部材に、相互に間隔をあけて一対の固
定部材を固定し、かつこれらの固定部材間におい
て相互に間隔をあけて複数の中間固定部材を固定
し、
前記一対の固定部材とこれらの固定部材にそれ
ぞれ隣接する各中間固定部材との間および各中間
固定部材間に補助部材をそれぞれ設置し、
前記一対の固定部材と補助部材との間および各
中間固定部材と補助部材との間に、ジヤツキをそ
れぞれ介在し、
これらのジヤツキを伸張することによつて、基
礎部材にはその部材軸方向に引張力を作用させ、
かつ補助部材には前記部材軸方向に圧縮力を作用
させ、この状態で、前記補助部材を基礎部材に固
定し、
次に、ジヤツキを収縮することを特徴とする合
成構造部材形成工法である。 The present invention according to claim 2 provides a method for forming a composite structural member in which an auxiliary member is installed and integrated with a foundation member, comprising: fixing a pair of fixing members to the foundation member at a distance from each other; A plurality of intermediate fixing members are fixed at intervals between the fixing members, and an auxiliary member is provided between the pair of fixing members and each intermediate fixing member adjacent to these fixing members, and between each intermediate fixing member. jacks are interposed between the pair of fixing members and the auxiliary member and between each of the intermediate fixing members and the auxiliary member, and by stretching these jacks, the base member is fixed. Applying tensile force in the axial direction of the member,
The composite structural member forming method is characterized in that a compressive force is applied to the auxiliary member in the axial direction of the member, and in this state, the auxiliary member is fixed to the foundation member, and then the jack is contracted.
作 用
請求項1記載の本発明に従えば、基礎部材に備
えられる固定部材と補助部材との間の少なくとも
一方側にジヤツキが介在され、このジヤツキを伸
張することによつて、基礎部材には引張力が導入
され、補助部材には圧縮力が導入される。その
後、基礎部材と補助部材とを一体化させ、その後
にジヤツキの力を緩めてジヤツキを取り外すこと
によつて、基礎部材には引張応力および曲げモー
メントが残留し、補助部材には圧力応力が残留す
る。このようにして合成構造部材が形成される。Effect According to the present invention as set forth in claim 1, a jack is interposed on at least one side between the fixing member and the auxiliary member provided in the base member, and by stretching this jack, the base member A tensile force is introduced and a compressive force is introduced in the auxiliary member. After that, by integrating the foundation member and the auxiliary member, and then loosening the jacking force and removing the jack, tensile stress and bending moment remain in the foundation member, and pressure stress remains in the auxiliary member. do. A composite structural member is thus formed.
請求項2記載の本発明に従えば、基礎部材に、
一対の固定部材と、これらの固定部材間に相互に
間隔をあけて複数の中間固定部材とを設け、前記
一対の固定部材とこれらに隣接する各中間固定部
材との間および各中間固定部材間に補助部材をそ
れぞれ配置し、次に前記一対の固定部材と補助部
材との間、および各中間固定部材と補助部材との
間に、ジヤツキをそれぞれ介在させ、各ジヤツキ
を伸張することによつて、基礎部材に引張力を導
入し、また補助部材に圧縮力を導入する。 According to the present invention as set forth in claim 2, the base member includes:
A pair of fixing members and a plurality of intermediate fixing members are provided at intervals between these fixing members, and a plurality of intermediate fixing members are provided between the pair of fixing members and each intermediate fixing member adjacent thereto, and between each intermediate fixing member. by placing auxiliary members on the respective sides, interposing jacks between the pair of fixing members and the auxiliary member, and between each intermediate fixing member and the auxiliary member, and stretching each jack. , introduces a tensile force into the base member and a compressive force into the auxiliary member.
このような構成によつて、比較的長い距離にわ
たつて多数の補助部材を敷設する場合であつて
も、大きな出力を有するジヤツキを用いることな
しに、したがつてこのジヤツキによつて押圧され
る補助部材と固定部材に大きな力が作用すること
なしに、前述のような基礎部材に引張力を導入
し、かつ補助部材に圧縮力を導入することができ
る。これによつてジヤツキを大形化することな
く、また補助部材および固定部材の強度を大きく
することなしに、基礎部材と補助部材とを一体化
することができる。 With this configuration, even when a large number of auxiliary members are laid over a relatively long distance, they can be pressed by the jack without using a jack with a large output. A tensile force can be introduced into the base member as described above, and a compressive force can be introduced into the auxiliary member, without large forces acting on the auxiliary member and the fixing member. Thereby, the base member and the auxiliary member can be integrated without increasing the size of the jack and without increasing the strength of the auxiliary member and the fixing member.
実施例
第1図は本発明が実施される橋梁1の構成を示
す側面図であり、第2図はその平面図である。橋
梁1は両端部で橋台2,3によつて支持される。
橋梁1は、その軸線方向に延びるI形断面の複数
の鋼桁4と、これらの鋼桁4によつて支持されて
いる横桁あるいは対傾構と呼ばれる鋼製の部材5
などを含む骨組を有する。鋼桁4の上面には通路
板6が設置されている。この通路板6は、第2図
において図解を容易にするため、右半分が省略さ
れている。この通路板6は、複数のコンクリート
床版7が連接して構成される。Embodiment FIG. 1 is a side view showing the configuration of a bridge 1 in which the present invention is implemented, and FIG. 2 is a plan view thereof. The bridge 1 is supported by abutments 2 and 3 at both ends.
The bridge 1 includes a plurality of steel girders 4 with an I-shaped cross section extending in the axial direction, and steel members 5 called cross beams or anti-tilt structures supported by these steel girders 4.
It has a skeleton that includes etc. A passage plate 6 is installed on the upper surface of the steel girder 4. The right half of the passage plate 6 is omitted in FIG. 2 for ease of illustration. This passage board 6 is constructed by connecting a plurality of concrete slabs 7.
第3図は、コンクリート床版7が鋼桁4に取付
けられた状態の一部を簡略化して示す斜視図であ
り、第4図は第3図の矢符A側から見た側面図で
ある。水平方向に延びる鋼桁4は、鉛直方向に延
びるウエブ9と、ウエブ9の両端部でウエブ9に
直角方向に延びる上フランジ10および下フラン
ジ11とを含む。上フランジ10の上面には、補
助部材であるコンクリート床版7のすべりを防止
するためのすべり防止部材12が備えられる。こ
のすべり防止部材12はたとえばジベルであり、
複数の棒状の突起13から成り、上フランジ10
の上面に溶植されて固定される。このすべり防止
部材12は上フランジ10の上面に間隔をあけて
複数個配置されている。 FIG. 3 is a simplified perspective view of a part of the concrete slab 7 attached to the steel girder 4, and FIG. 4 is a side view seen from the arrow A side in FIG. 3. . The horizontally extending steel girder 4 includes a vertically extending web 9 and an upper flange 10 and a lower flange 11 extending perpendicularly to the web 9 at both ends thereof. A slip prevention member 12 is provided on the upper surface of the upper flange 10 to prevent the concrete floor slab 7, which is an auxiliary member, from slipping. This anti-slip member 12 is, for example, a dowel,
The upper flange 10 consists of a plurality of rod-shaped protrusions 13.
It is melted and fixed on the top surface of the A plurality of these anti-slip members 12 are arranged at intervals on the upper surface of the upper flange 10.
第5図は請求項1に記載された本発明の一実施
例を示す平面図であり、第6図は鋼桁4の両端部
付近を示す断面図である。基礎部材である鋼桁4
の両端部には、鋼桁4と直角方向に延びる固定部
材40,41が備えられている。この固定部材4
0はたとえば軸直角断面がL字状であり、水平方
向(第6図の紙面に垂直方向)に延在する水平部
41aと、水平部41aの端部から垂直方向に延
びる垂直部42aとから成る。この垂直部42a
は補強板43aによつて強固に補強されている。
固定部材40はボルト44aによつて鋼桁4に固
定される。この固定部材40の垂直部42aと、
コンクリート床版7の端面7aとの間には、ジヤ
ツキ45が介在されており、このジヤツキ45は
載置台46上に載置されている。 FIG. 5 is a plan view showing an embodiment of the present invention as set forth in claim 1, and FIG. 6 is a sectional view showing the vicinity of both ends of the steel girder 4. Steel girder 4 which is a foundation member
Fixing members 40 and 41 extending perpendicularly to the steel girder 4 are provided at both ends thereof. This fixing member 4
For example, 0 has an L-shaped cross section perpendicular to the axis, and consists of a horizontal part 41a extending in the horizontal direction (perpendicular to the paper surface of FIG. 6) and a vertical part 42a extending in the vertical direction from the end of the horizontal part 41a. Become. This vertical part 42a
is strongly reinforced by a reinforcing plate 43a.
The fixing member 40 is fixed to the steel girder 4 by bolts 44a. A vertical portion 42a of this fixing member 40,
A jack 45 is interposed between the concrete floor slab 7 and the end surface 7a, and this jack 45 is placed on a mounting table 46.
鋼桁4のもう一方の端部に備えられている固定
部材41もまた固定部材40と同様な構成を有し
ており、対応する部分には同一番号に添字bを付
す。この固定部材41と、コンクリート床版7の
端面7bとの間にもジヤツキ47が介在し、この
ジヤツキ47は載置台48上に載置されている。 The fixing member 41 provided at the other end of the steel girder 4 also has the same configuration as the fixing member 40, and corresponding parts are given the same numbers with the suffix b. A jack 47 is also interposed between this fixing member 41 and the end surface 7b of the concrete floor slab 7, and this jack 47 is placed on a mounting table 48.
コンクリート床版7には、鋼桁4間に敷設され
た時にすべり防止部材12が嵌入することができ
る長孔14が、突起13の位置に対応して複数個
コンクリート床版7の幅方向(第5図の左右方
向)に沿つて形成されている。 The concrete slab 7 has a plurality of elongated holes 14 in the width direction of the concrete slab 7 (first slots) corresponding to the positions of the protrusions 13 into which the anti-slip members 12 can fit when installed between the steel girders 4. 5).
コンクリート床版7を鋼桁4に敷設して通路板
6を形成する工程を以下に説明する。 The process of laying the concrete slab 7 on the steel girder 4 to form the passage board 6 will be described below.
まずコンクリート床版7を鋼桁4間に前記幅方
向に隔間なく仮接合する。その後各コンクリート
床版7の継目部分60(第3図参照)に接着剤を
塗布またはセメントモルタルなどを注入もしくは
打設して、各コンクリート床版7間の一体化を図
る。次にコンクリート床版7の鋼桁4の部材軸方
向に沿うプレストレスを導入し、コンクリート床
版7に圧縮応力を与える。具体的に説明すると、
ジヤツキ45,47が作動するとジヤツキ45,
47のピストン棒49,50が伸張され、これに
よつて鋼桁4に引張力が与えられ、またコンクリ
ート床版7には圧縮力が導入される。次にこのよ
うにしてプレストレスが導入されたコンクリート
床版7を鋼桁4と一体化させる。具体的に説明す
れば、コンクリート床版7の長孔14にコンクリ
ートやセメントモルタルなどを充填して固化させ
る。これによつてコンクリート床版7と鋼桁4と
は相互に固定され一体化される。こうして鋼桁4
とコンクリート床版7とは合成桁となる。このよ
うにしてコンクリート床版7を鋼桁4と合成した
後に、ジヤツキ45,47の各ピストン棒49,
50を縮退させ、固定板40,41とコンクリー
ト床版7間に介在しているジヤツキ45,47を
取外す。 First, the concrete slab 7 is temporarily joined between the steel girders 4 without gaps in the width direction. Thereafter, adhesive is applied or cement mortar or the like is injected or poured into the joint portion 60 (see FIG. 3) of each concrete slab 7 to integrate each concrete slab 7. Next, prestress along the member axis direction of the steel girder 4 of the concrete deck slab 7 is introduced to apply compressive stress to the concrete deck slab 7. To explain specifically,
When jacks 45, 47 operate, jacks 45,
47 piston rods 49, 50 are extended, thereby applying a tensile force to the steel girder 4 and introducing a compressive force to the concrete slab 7. Next, the concrete deck slab 7 into which prestress has been introduced in this manner is integrated with the steel girder 4. Specifically, concrete, cement mortar, or the like is filled into the long holes 14 of the concrete slab 7 and solidified. As a result, the concrete deck slab 7 and the steel girder 4 are fixed to each other and integrated. Thus steel girder 4
and the concrete slab 7 form a composite girder. After combining the concrete slab 7 with the steel girder 4 in this way, each piston rod 49 of the jacks 45, 47,
50 is retracted and the jacks 45, 47 interposed between the fixed plates 40, 41 and the concrete slab 7 are removed.
このような操作により、各ジヤツキ45,47
の力によつて縮められていたコンクリート床版7
は、鋼桁4の部材軸方向に延びようとし、各ジヤ
ツキ45,47によつて伸ばされていた鋼桁4は
部材軸方向に縮もうとする。しかしながら、コン
クリート床版7と鋼桁4とは一体化されており、
鋼桁4の縮もうとする力とコンクリート床版7の
伸びようとする力が等しいので、最初にジヤツキ
45,47によつて導入したコンクリート床版7
の圧縮応力と鋼桁4に作用させた偏心引張力はそ
のまま残されることになる。そのため鋼桁4には
桁を上方に弯曲させる負の曲げモーメントを引張
力が導入される。そして、このような操作を行わ
ない通常の合成桁に比べて本発明に従う合成桁
は、この曲げモーメントの分だけ正の曲げモーメ
ントが小さくなる。その結果、たとえば自動車や
人などの活荷重による正の曲げモーメントが与え
られも、許容曲げ応力までには十分の余裕があ
り、したがつて鋼桁断面を小さくすることも可能
となる。また、コンクリート床版7には圧縮応力
が残されているのでひび割れの防止に大いに役立
つ。 By such operation, each jack 45, 47
Concrete slab 7 which had been compressed by the force of
tends to extend in the axial direction of the steel girder 4, and the steel girder 4, which has been stretched by the jacks 45 and 47, attempts to contract in the axial direction of the member. However, the concrete slab 7 and the steel girder 4 are integrated,
Since the force of the steel girder 4 to contract and the force to extend the concrete slab 7 are equal, the concrete slab 7 introduced by the jacks 45 and 47 first
The compressive stress and the eccentric tensile force acting on the steel girder 4 will remain as they are. Therefore, a tensile force is introduced into the steel girder 4, causing a negative bending moment to bend the girder upwards. The composite girder according to the present invention has a smaller positive bending moment by this bending moment than a normal composite girder that does not undergo such an operation. As a result, even if a positive bending moment is applied due to a live load such as an automobile or a person, there is sufficient margin up to the allowable bending stress, and it is therefore possible to reduce the cross section of the steel girder. Further, since compressive stress remains in the concrete slab 7, it is very useful for preventing cracks.
第7図は請求項1に記載された本発明の他の実
施例のコンクリート床版7を示す平面図であり、
第8図はその一部を拡大した斜視図である。この
コンクリート床版7には、その長手方向に沿う両
端部に凹凸面21が形成されている。この凹凸面
21は、凹所22がその幅方向に沿つて複数個形
成されている。たとえばこのコンクリート床版7
の幅長を1.5mであるとすれば、この凹所22の
奥行d1は2cmであり、ピツチd2は20cmである。
なお、この凹凸面21の形状は、第7図示のよう
な形状に限定されるものではなく、また奥行d1
およびピツチd2の値もこれに限定されるもので
はないことは勿論である。 FIG. 7 is a plan view showing a concrete floor slab 7 according to another embodiment of the present invention as set forth in claim 1,
FIG. 8 is a partially enlarged perspective view. This concrete floor slab 7 has an uneven surface 21 formed at both ends along its longitudinal direction. This uneven surface 21 has a plurality of recesses 22 formed along its width direction. For example, this concrete floor slab 7
If the width of the recess 22 is 1.5 m, the depth d1 of the recess 22 is 2 cm, and the pitch d2 is 20 cm.
Note that the shape of this uneven surface 21 is not limited to the shape shown in FIG.
Of course, the value of pitch d2 is not limited to this.
このような形状を有するコンクリート床版7
を、鋼桁4の上フランジ10上に一定の間隔をあ
けて対向させて配置させる。その後は前述の実施
例と同様にジヤツキ45,47によつてコンクリ
ート床版7に圧縮力を、鋼桁4に引張力を導入す
る。その後、コンクリート床版7を鋼桁4に一体
化させるにあたつて、各コンクリート床版7の相
互に対向する各凹凸面21間の空間23に固着剤
としてのたとえばコンクリートやセメントモルタ
ルなどを充填することによつて、コンクリート床
版7と鋼桁4とを一体化させる。そして、ジヤツ
キの力を緩めてこれを取去る方法は前述の実施例
と同様である。 Concrete floor slab 7 having such a shape
are arranged on the upper flange 10 of the steel girder 4 so as to face each other at a constant interval. Thereafter, compressive force is introduced into the concrete slab 7 and tensile force is introduced into the steel girder 4 by the jacks 45 and 47, as in the previous embodiment. After that, when integrating the concrete slab 7 with the steel girder 4, the spaces 23 between the mutually opposing uneven surfaces 21 of each concrete slab 7 are filled with a bonding agent such as concrete or cement mortar. By doing so, the concrete deck slab 7 and the steel girder 4 are integrated. The method of loosening the force of the jack and removing it is the same as in the previous embodiment.
このように本実施例では、コンクリート床版7
に凹凸面21を形成するようにしたので、コンク
リート床版7が鋼桁4に確実に一体化され、その
ためプレストレスが解放されたときにも、コンク
リート床版7が鋼桁4上を滑つてしまうというよ
うな事態の発生が防がれる。 In this way, in this embodiment, the concrete floor slab 7
Since the uneven surface 21 is formed on the surface, the concrete deck slab 7 is reliably integrated with the steel girder 4, and therefore, even when the prestress is released, the concrete deck slab 7 will not slide on the steel girder 4. This prevents situations such as being put away.
第9図は第5図〜第8図に示される実施例の鋼
桁4にコンクリート床版7が設置され、プレスト
レスが導入された場合の、鋼桁4およびコンクリ
ート床版7の応力度を説明するための図であり、
第10図は第9図に対応した曲げモーメント図で
あり、第11図は第9図の切断面線XI−XIから
見た断面における応力図で、破線は本発明を用い
ない従来工法の場合を示したものである。なお、
第9図では説明の簡略化を図るために鋼桁4は両
端で単純支点26,27で支持されているものと
想定する。鋼桁4が支点26,27で支持されて
いる状態は第9図1で示される。この状態では鋼
桁4には自重による等分布荷重によつて、第10
図1で示されるように放物線で示される正の曲げ
モーメントl1が作用する。このときの応力状態
は第11図1で示されている。 Figure 9 shows the stress levels of the steel girder 4 and concrete slab 7 when the concrete slab 7 is installed on the steel girder 4 of the embodiment shown in Figures 5 to 8 and prestress is introduced. This is a diagram for explaining,
Fig. 10 is a bending moment diagram corresponding to Fig. 9, and Fig. 11 is a stress diagram in the cross section seen from the cutting plane line This is what is shown. In addition,
In FIG. 9, in order to simplify the explanation, it is assumed that the steel girder 4 is supported at both ends by simple supports 26 and 27. The state in which the steel girder 4 is supported by the fulcrums 26 and 27 is shown in FIG. 91. In this state, the steel girder 4 is subjected to a uniformly distributed load due to its own weight,
A positive bending moment l1 acts, which is represented by a parabola as shown in FIG. The stress state at this time is shown in FIG. 11.
次に鋼桁4にコンクリート床版が取付けられた
状態は第9図2で示されており、この状態におけ
る曲げモーメントl2は第10図2で示されてい
る。この曲げモーメントl2は、第9図1で示さ
れる曲げモーメントl1にコンクリート床版7の
自重による曲げモーメントが加算されたものであ
る。またこのときにおける応力図は第11図2で
示されており、鋼桁4の上縁側と下縁側の応力は
第11図1で示される状態よりもさらに増大して
いる。 Next, the state in which the concrete slab is attached to the steel girder 4 is shown in FIG. 9, and the bending moment 12 in this state is shown in FIG. 10, 2. This bending moment 12 is the sum of the bending moment 11 shown in FIG. 91 and the bending moment due to the weight of the concrete slab 7. Further, the stress diagram at this time is shown in FIG. 11, 2, and the stress on the upper edge side and the lower edge side of the steel girder 4 is further increased than in the state shown in FIG. 11.
次にジヤツキ45,47によつて導入力Pの導
入を開始した状態は、第9図3で示されている。
この導入力Pによつて、鋼桁4には引張力が、ま
たコンクリート床版7には圧縮力が導入される。
そのため、コンクリート床版7および鋼桁4には
第11図3で示されるように応力が分布する。な
お、鋼桁4には第10図3で示される負の曲げモ
ーメントl3が発生する。次にこのように導入力
Pが作用した状態でコンクリート床版7と鋼桁4
とを一体化したときの状態は第9図4で示され
る。こうしてコンクリート床版7が鋼桁4と一体
化したときには、第10図3で示される負の曲げ
モーメントl3が第10図2で示される曲げモー
メントl2に加算されて、第10図4の曲げモー
メントl4が発生する。なお、このときの応力状
態は第11図4で示されており、曲げモーメント
l2による応力から曲げモーメントl3による応
力を差し引いたものとなる。 Next, the state in which introduction of the introduction force P is started by the jacks 45 and 47 is shown in FIG. 93.
This introduced force P introduces a tensile force into the steel girder 4 and a compressive force into the concrete slab 7.
Therefore, stress is distributed in the concrete slab 7 and the steel girder 4 as shown in FIG. 11. Note that a negative bending moment l3 shown in FIG. 10 is generated in the steel girder 4. Next, with the introduction force P acting in this way, the concrete slab 7 and the steel girder 4
The state when these are integrated is shown in FIG. 9. When the concrete slab 7 is integrated with the steel girder 4 in this way, the negative bending moment l3 shown in FIG. 10 3 is added to the bending moment l2 shown in FIG. 10 2, and the bending moment shown in FIG. l4 occurs. The stress state at this time is shown in FIG. 11, 4, and is obtained by subtracting the stress due to the bending moment 13 from the stress due to the bending moment 12.
次に、このような鋼桁4とコンクリート床版7
とが一体化した状態で、ジヤツキ45,47によ
つて第9図5で示されるように前記導入力Pを解
放する。これによつて、鋼桁4の両端部付近に
は、前記ジヤツキ45,47の導入力Pの解放に
よつてコンクリート床版7が圧縮された状態から
解放されたことによつて、第10図5で示される
正の曲げモーメントl5が発生する。なお、この
ときの応力状態は第11図5で示されており、第
11図4と同様な応力分布である。 Next, such steel girder 4 and concrete slab 7
In this state, the introduction force P is released by the jacks 45 and 47 as shown in FIG. 9 and 5. As a result, near both ends of the steel girder 4, the concrete slab 7 is released from the compressed state due to the release of the introduction force P of the jacks 45 and 47, as shown in FIG. A positive bending moment l5, designated 5, occurs. The stress state at this time is shown in FIG. 11, 5, and the stress distribution is similar to that in FIG. 11, 4.
このようにしてジヤツキ45,47によつて一
旦導入された導入力Pを解放することによつて、
鋼桁4には偏心引張力が、またコンクリート床版
7には圧縮応力が残留することになり、第11図
6で示される応力分布となる。また第9図6で
は、第10図4で示される曲げモーメントl4
と、第10図5で示される曲げモーメントl5と
が加算されて、第10図6で示される曲げモーメ
ントl6が発生する。第10図6においては、仮
想線l7で示される通常の合成桁における曲げモー
メントに比べて第10図3に示される前記曲げモ
ーメントl3だけ小さくなつている。このように
して通常の合成桁と比較すると、本発明によれば
正の曲げモーメントを小さくすることができるの
で、予め考慮される鉛直荷重による正の曲げモー
メントを打ち消して減少させることが可能とな
る。また鋼桁4の上フランジ10および下フラン
ジ11に発生する応力を小さくすることができ、
しかもコンクリート床版7には圧縮応力を残留さ
せておくことができ、コンクリートのひび割れを
防止することが可能となる。それ故、鋼桁の断面
を小さくすることが可能となるだけでなく、コン
クリート床版のひび割れに対する強度を向上する
ことも可能となり、経済的でかつ耐久性にすぐれ
た合成桁橋を架橋できるのである。 By releasing the introduction force P once introduced by the jacks 45 and 47 in this way,
Eccentric tensile force remains in the steel girder 4, and compressive stress remains in the concrete slab 7, resulting in the stress distribution shown in FIG. 11. In addition, in FIG. 9, the bending moment l4 shown in FIG.
, and the bending moment l5 shown in FIG. 10, are added to generate the bending moment l6 shown in FIG. 10, 6. In FIG. 10, the bending moment 13 shown in FIG. 10 is smaller than the bending moment in a normal composite girder, which is shown by the imaginary line l7. In this way, when compared with a normal composite girder, the present invention can reduce the positive bending moment, so it is possible to cancel out and reduce the positive bending moment due to the vertical load, which is taken into account in advance. . In addition, the stress generated in the upper flange 10 and lower flange 11 of the steel girder 4 can be reduced,
In addition, compressive stress can remain in the concrete slab 7, making it possible to prevent cracks in the concrete. Therefore, it is not only possible to reduce the cross section of the steel girder, but also to improve the strength of the concrete slab against cracking, making it possible to construct an economical and highly durable synthetic girder bridge. be.
通常、合成桁橋の鋼桁部には、鋼桁、床版、地
覆、高欄、および舗装等の死荷重ならびに活荷重
などの鉛直荷重によつて正の曲げモーメントが作
用し、上縁側に圧縮応力、下縁側に引張応力が発
生している。本工法では鋼桁部には引張力と負の
曲げモーメントが作用するので、通常の工法に比
べて上縁側の圧縮応力、下縁側の引張応力ともに
小さくなる。したがつて通常の工法よりも大きな
荷重に抵抗ができることになる。すなわち、同じ
鉛直荷重に対して両者を比較すれば、本工法の方
が鋼桁部の所要断面積は小さくすむことになり、
鋼桁の軽量化、小形化が図られる。また鋼桁断面
を小さくすることによつて、桁高さを低くするこ
とができるので、風圧などの橋梁側面に加わる荷
重を小さくすることが可能となる。また、桁下空
間が制限される箇所にも適用でき、取付け道路の
嵩上げ高さを低くすることによつて経済的にも有
利となる。 Normally, a positive bending moment acts on the steel girder part of a composite girder bridge due to vertical loads such as dead loads and live loads of the steel girders, deck slabs, ground covering, handrails, pavement, etc. Compressive stress and tensile stress occur on the lower edge side. In this construction method, tensile force and negative bending moment act on the steel girder, so the compressive stress on the upper edge side and the tensile stress on the lower edge side are both smaller than in normal construction methods. Therefore, it is able to withstand larger loads than normal construction methods. In other words, if we compare the two for the same vertical load, this method requires a smaller cross-sectional area for the steel girder.
Steel girders can be made lighter and smaller. Furthermore, by reducing the cross section of the steel girder, the height of the girder can be lowered, making it possible to reduce loads such as wind pressure applied to the side surfaces of the bridge. Furthermore, it can be applied to places where the space under the girder is limited, and it is economically advantageous by lowering the height of the access road.
また従来の工法では鉄筋コンクリート床版を施
工するためには型枠を組立てる必要があるが、本
工法においては予め工場等において製作されたプ
レキヤスト床版を用いることもでき、この場合に
は型枠を必要とせず、床版の施工に要する工数、
費用の低減が図られる。 In addition, in conventional construction methods, it is necessary to assemble formwork in order to construct reinforced concrete deck slabs, but with this construction method, precast slabs that have been manufactured in advance at a factory etc. can also be used, and in this case, the formwork must be assembled. The number of man-hours required for the construction of the floor slab,
Costs will be reduced.
第12図は、請求項2に記載された本発明の一
実施例の簡略化した断面図である。この実施例で
は、固定部材40,41間にさらに複数の中間固
定部材70が鋼桁4の予め定めた固定位置に相互
に間隔をあけて固着されている。固定部材40,
41,70の相互間にはコンクリート床版7が介
在されており、さらにこのコンクリート床版7と
固定部材40,41,70間にジヤツキ71が介
在される。このジヤツキ71の働きによつて前述
と同様にコンクリート床版7には圧縮応力が、ま
た鋼桁4には偏心引張力が与えられる。 FIG. 12 is a simplified cross-sectional view of an embodiment of the invention as set forth in claim 2. In this embodiment, a plurality of intermediate fixing members 70 are further fixed between the fixing members 40 and 41 at predetermined fixing positions of the steel girder 4 at intervals. Fixed member 40,
A concrete floor slab 7 is interposed between the concrete floor slabs 7 and the fixing members 40, 41, and 70, and a jack 71 is interposed between the concrete floor slab 7 and the fixing members 40, 41, and 70. Due to the action of this jack 71, compressive stress is applied to the concrete slab 7 and eccentric tensile force is applied to the steel girder 4, as described above.
効 果
請求項1記載の本発明によれば、合成構造部材
を形成する際、設計上考慮される荷重によつて部
材に発生する圧縮力あるいは曲げモーメントとは
逆方向の力が与えられ、そのため、部材の軽量
化、および小形化を図ることができる。Effects According to the present invention as set forth in claim 1, when forming a composite structural member, a force is applied in the opposite direction to the compressive force or bending moment generated in the member due to the load considered in the design, so that , it is possible to reduce the weight and size of the member.
請求項2記載の本発明によれば、基礎部材に複
数の中間固定部材が固定され、これらの中間固定
部材間にそれぞれ補助部材を配置して、前記基礎
部材と一体化するようにしたので、桁長が長い場
合であつても、一度に多くの補助部材を押圧する
ために、大きな力を発揮することができるジヤツ
キを用いる必要がなく、構成が大形化しない。ま
たこのような大きな力を発揮するジヤツキを用い
る必要がないので、各補助部材と固定部材に作用
する力が小さくてすみ、したがつて補助部材およ
び固定部材の強度を大きくする必要はなく、これ
によつて構成を大形化および複雑化することなし
に長い距離にわたつて基礎部材上に補助部材を敷
設することができる。 According to the second aspect of the present invention, a plurality of intermediate fixing members are fixed to the base member, and auxiliary members are arranged between these intermediate fixing members to be integrated with the base member. Even when the beam length is long, there is no need to use a jack that can exert a large force in order to press many auxiliary members at once, and the structure does not become large. In addition, since there is no need to use a jack that exerts such a large force, the force acting on each auxiliary member and fixing member is small, and therefore there is no need to increase the strength of the auxiliary member and fixing member. This allows auxiliary members to be laid on the base member over long distances without increasing the size and complexity of the construction.
第1図は本発明が実施される橋梁1の構成を示
す側面図、第2図はその平面図、第3図はコンク
リート床版7が鋼桁4に取付けられた状態の一部
を簡略化して示す斜視図、第4図は第3図の矢符
A側から見た側面図、第5図は請求項1に記載さ
れた本発明の一実施例を示す平面図、第6図は鋼
桁4の両端部付近を示す断面図、第7図は請求項
1に記載された本発明の他の実施例のコンクリー
ト床版7を示す平面図、第8図は第7図の一部を
拡大した斜視図、第9図は第5図〜第8図に示さ
れる実施例の鋼桁4にコンクリート床版7が設置
されてプレストレスが導入された場合の鋼桁4お
よびコンクリート床版7の応力を説明するための
図、第10図は第9図に対応した曲げモーメント
図、第11図は第9図の切断面線XI−XIから見
た断面における応力図、第12図は請求項2に記
載された本発明の一実施例の断面図である。
1……橋梁、4……鋼桁、7……コンクリート
床版、7a,7b……端面、40,41,70…
…固定部材、45,47,71……ジヤツキ。
FIG. 1 is a side view showing the configuration of a bridge 1 in which the present invention is implemented, FIG. 2 is a plan view thereof, and FIG. FIG. 4 is a side view seen from the arrow A side in FIG. 3, FIG. 7 is a sectional view showing the vicinity of both ends of the girder 4, FIG. 7 is a plan view showing a concrete slab 7 of another embodiment of the present invention as set forth in claim 1, and FIG. 8 is a partial view of FIG. 7. The enlarged perspective view, FIG. 9, shows the steel girder 4 and the concrete deck 7 when the concrete deck slab 7 is installed on the steel girder 4 of the embodiment shown in FIGS. 5 to 8 and prestress is introduced. Fig. 10 is a bending moment diagram corresponding to Fig. 9, Fig. 11 is a stress diagram in a cross section seen from the cutting plane line XI-XI in Fig. 9, and Fig. 12 is a claim diagram. 2 is a cross-sectional view of an embodiment of the present invention described in item 2. FIG. 1... Bridge, 4... Steel girder, 7... Concrete deck slab, 7a, 7b... End face, 40, 41, 70...
...fixing member, 45, 47, 71... jack.
Claims (1)
成構造部材形成工法において、 前記基礎部材に相互に間隔をあけて一対の固定
部材を固定し、各固定部材間に複数の補助部材を
設置し、少なくとも一方の固定部材と補助部材と
の間にジヤツキを介在し、 このジヤツキを伸張することによつて、基礎部
材にはその部材軸方向に引張力を発生させ、かつ
補助部材には前記部材軸方向に圧縮力を作用さ
せ、この状態で、前記補助部材を基礎部材に固定
し、 次に、ジヤツキを収縮することを特徴とする合
成構造部材形成工法。 2 基礎部材に補助部材を設置して一体化する合
成構造部材形成工法において、 前記基礎部材に、相互に間隔をあけて一対の固
定部材を固定し、かつこれらの固定部材間におい
て相互に間隔をあけて複数の中間固定部材を固定
し、 前記一対の固定部材とこれらの固定部材にそれ
ぞれ隣接する各中間固定部材との間および各中間
固定部材間に補助部材をそれぞれ設置し、 前記一対の固定部材と補助部材との間および各
中間固定部材と補助部材との間に、ジヤツキをそ
れぞれ介在し、 これらのジヤツキを伸張することによつて、基
礎部材にはその部材軸方向に引張力を作用させ、
かつ補助部材には前記部材軸方向に圧縮力を作用
させ、この状態で、前記補助部材を基礎部材に固
定し、 次に、ジヤツキを収縮することを特徴とする合
成構造部材形成工法。[Claims] 1. In a composite structural member forming method in which auxiliary members are installed and integrated with a foundation member, a pair of fixing members are fixed to the foundation member at intervals, and a plurality of fixing members are fixed between each fixing member. An auxiliary member is installed, a jack is interposed between at least one fixed member and the auxiliary member, and by stretching this jack, a tensile force is generated in the base member in the axial direction of the member, and A method for forming a composite structural member, characterized in that a compressive force is applied to the auxiliary member in the axial direction of the member, the auxiliary member is fixed to the foundation member in this state, and then the jacks are contracted. 2. In a composite structural member forming method in which auxiliary members are installed and integrated with a foundation member, a pair of fixing members are fixed to the foundation member at a distance from each other, and the space between these fixing members is maintained. fixing a plurality of intermediate fixing members with openings; installing auxiliary members between the pair of fixing members and each intermediate fixing member adjacent to these fixing members, and between each intermediate fixing member; and fixing the pair of fixing members. Jacks are interposed between the member and the auxiliary member and between each intermediate fixing member and the auxiliary member, and by stretching these jacks, a tensile force is applied to the base member in the axial direction of the member. let me,
A method for forming a composite structural member, characterized in that a compressive force is applied to the auxiliary member in the axial direction of the member, the auxiliary member is fixed to the foundation member in this state, and then the jack is contracted.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1836685A JPS61176707A (en) | 1985-01-31 | 1985-01-31 | Formation of synthetic structural member |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1836685A JPS61176707A (en) | 1985-01-31 | 1985-01-31 | Formation of synthetic structural member |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61176707A JPS61176707A (en) | 1986-08-08 |
| JPH0447721B2 true JPH0447721B2 (en) | 1992-08-04 |
Family
ID=11969700
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1836685A Granted JPS61176707A (en) | 1985-01-31 | 1985-01-31 | Formation of synthetic structural member |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61176707A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2005282272A (en) * | 2004-03-30 | 2005-10-13 | Ishikawajima Constr Materials Co Ltd | Construction method for replacing floor slab of composite girder, and device for transferring axial force between floor slabs |
-
1985
- 1985-01-31 JP JP1836685A patent/JPS61176707A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS61176707A (en) | 1986-08-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP0141478B1 (en) | A method for forming a composite structural member | |
| US6293063B2 (en) | Cast-in-place hybrid building system | |
| AU2017304226B2 (en) | Precast concrete formwork, floor system and a method of construction | |
| JP3588325B2 (en) | Construction method of single span and multi span composite girder bridges | |
| CN105952044B (en) | Fully-prefabricated prestressed concrete floor structure and prestressed assembly method | |
| US4363200A (en) | Pre-cast building element and method | |
| US2132220A (en) | Floor construction or the like | |
| JP4844918B2 (en) | Construction method of steel / concrete composite deck using precast concrete board | |
| KR101432087B1 (en) | Composite rahman bridge using preflex beam and horizontal shear connectors and construction method thereof | |
| US2373072A (en) | Rigid frame bridge and method of making the same | |
| US2776471A (en) | Method of erecting prestressed floor sections | |
| JPH0475322B2 (en) | ||
| JPS6282147A (en) | Novel prestressed synthetic beam and its construction | |
| JPH0447721B2 (en) | ||
| JP7266808B1 (en) | Main girder continuous rigid connection method | |
| JPH0426483Y2 (en) | ||
| KR20000054500A (en) | Construction method that introduces compressive stress to bottom plate concrete and bottom moment flange of parent section by using and adjusting the descending and rising process of end point in short span and multi span composite structures | |
| JPH0320524B2 (en) | ||
| KR200230089Y1 (en) | Shifting up and down system of continuous preflex composite girder on temporary support | |
| JP3189081B2 (en) | Manufacturing method of void type full precast two-way slab and void type full precast slab | |
| JP2000291195A (en) | Composite deck and its construction method | |
| JPH03881B2 (en) | ||
| JPS5817773Y2 (en) | Prestressed concrete girder for road bridge | |
| KR200319045Y1 (en) | Concrete deck plate | |
| JPS584006A (en) | Continuous type bridge using prestressed steel beam |