JPS6364565B2 - - Google Patents

Info

Publication number
JPS6364565B2
JPS6364565B2 JP3124982A JP3124982A JPS6364565B2 JP S6364565 B2 JPS6364565 B2 JP S6364565B2 JP 3124982 A JP3124982 A JP 3124982A JP 3124982 A JP3124982 A JP 3124982A JP S6364565 B2 JPS6364565 B2 JP S6364565B2
Authority
JP
Japan
Prior art keywords
slab
old
slabs
deck
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3124982A
Other languages
Japanese (ja)
Other versions
JPS58150604A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP3124982A priority Critical patent/JPS58150604A/en
Publication of JPS58150604A publication Critical patent/JPS58150604A/en
Publication of JPS6364565B2 publication Critical patent/JPS6364565B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 本発明は、道路橋等の路面を形成する合成桁床
版の打替工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for replacing composite girder slabs forming the road surface of road bridges and the like.

道路橋等の路面を形成するのに一般に多く採用
されているコンクリート製床版として、合成桁床
版、および非合成桁床版がある。
Concrete deck slabs that are commonly used to form the road surfaces of road bridges and the like include composite girder deck slabs and non-synthetic girder deck slabs.

前者の合成桁床版は、床版とこの床版を支える
鋼製の主桁とが一体で、走行する車輌等の荷重に
抵抗する構造となつたものであり、後者の非合成
桁床版は、主桁自体の強度のみでも前記の荷重に
耐え得る構造のものである。
The former composite girder deck consists of a deck and a steel main girder that supports the deck, and has a structure that resists the loads of moving vehicles, etc., while the latter non-synthetic girder deck The structure is such that the strength of the main girder itself can withstand the above load.

ところで、近年においては、このようなコンク
リート製床版の老巧化に伴ない床版の改修、すな
わち床版の打替工事が次第に多くなりつつある。
この打替工事を行なうにあたり、床版が前述の非
合成桁床版の場合は、その主桁自体が充分な強度
を備えているため片側交通などの方法で交通処理
しながら順次打替工事を行なうことも可能である
が、床版とこれを支える主桁とが一体構造となつ
て荷重に抵抗する合成桁床版の場合には、その合
成桁床版特有の構造から、床版打替時において主
桁の強度不足の問題が生じることが当然予想さ
れ、このため、交通開放下での床版打替工事を行
なうことは非常に困難なものとされている。した
がつて、従来においては、反覆旋工するのに充分
な幅員がある現場以外は、その打替工事区間をま
たぐ、いわゆる応急橋の架設、あるいは迂回路の
確保およびこれに伴なう分枝路の仮設などの手段
で交通処理しながら床版の打替工事を行なつてい
た。
Incidentally, in recent years, with the aging of such concrete floor slabs, the number of floor slab renovations, that is, floor slab replacement work, has been gradually increasing.
When performing this replacement work, if the deck is the non-synthetic girder deck mentioned above, the main girder itself has sufficient strength, so the replacement work will be carried out in stages while handling traffic using methods such as one-sided traffic. However, in the case of composite girder decks where the deck slab and the main girder supporting it are integrated to resist loads, it is not possible to replace the deck due to the unique structure of the composite girder deck. Naturally, it is expected that there will be problems with the strength of the main girder at times, and for this reason, it is extremely difficult to perform floor slab replacement work while the building is open to traffic. Therefore, in the past, unless the site had sufficient width for repeated turning, it was necessary to construct a so-called emergency bridge over the replacement work section, or to secure a detour and branch out accordingly. Work was being carried out to replace the floor slabs while managing traffic through temporary road construction and other methods.

しかしながら、このような従来の方法において
は、前記応急橋の架設にしても、打替工事区間を
またぐ相当大がかりな架設工事となつて多大な手
間と費用がかかり、また、打替工事区間によつて
は迂回路の確保すら困難な場合もしばしば生じる
などの問題点があり、いずれにしても何らかの早
急な解決策が強く望まれていた。
However, in such conventional methods, even when constructing the emergency bridge, it is a fairly large-scale construction work that straddles the replacement work section, which requires a great deal of effort and expense. However, there were problems such as it was often difficult to secure a detour, and in any case, there was a strong desire for some kind of immediate solution.

本発明は、以上のような点を考慮してなされた
もので、迂回路の確保や多大な手間と費用のかか
る応急橋の架設工事などの相当大がかりな交通処
理手段を根本的になくすことができる合成桁床版
の打替工法を提供しようとするものである。
The present invention has been made in consideration of the above points, and makes it possible to fundamentally eliminate fairly large-scale traffic management methods such as securing detours and constructing emergency bridges that require a great deal of effort and expense. The aim is to provide a method for replacing composite girder slabs that can be used.

以下、添付図面を参照し本発明の一実施例につ
いて詳述する。
Hereinafter, one embodiment of the present invention will be described in detail with reference to the accompanying drawings.

本発明による合成桁床版の打替工法は、第1図
〜第4図に示すように、鋼製主桁1,1上の旧床
版2を一定区間だけ、例えば夜間交通止めしてそ
の間に目的とする区間の打替工事を完了すること
ができる程度の区間Lだけ撤去し、その撤去した
後に、予め工場等で製造しておいた公知のコンボ
スラブ等のコンクリートスラブ3,3を敷設する
とともにこのコンクリートスラブ3,3間に必要
量の目地コンクリート4を旋し、さらに主桁1,
1の上部フランジ1a,1a上にもコンクリート
5を打設するなど必要な目地処理を施して旧床版
2とほぼ同様の合成桁床版構造になる新しい床版
6を形成する。そして、この新床版6と旧床板2
とが互いに向き合う端面6a,2a間に、第4図
に示すように、支圧板7,7を介して油圧ジヤツ
キ等からなる軸力伝達装置8を複数セツトし、こ
の軸力伝達装置によつて前記両端面6a,2aが
互いに離間する方向に圧力をかけて新旧両床版
6,2同志に軸方向の応力を与える。そしてさら
に、同図に示すように、新旧両床版6,2上に車
輌走行用の覆工板9を差し渡して打替完了とし、
後は、目地コンクリート4,5等の養生後に交通
開放して覆工板9上を走行させる。このようにし
て、交通量の少ない夜間などにおいて一時的に交
通止めして上述の工法で一定区間の床版を打替
え、これを順次繰り返すことにより打替えてゆ
く。
As shown in Figures 1 to 4, the method for replacing composite girder decks according to the present invention involves closing the old deck slabs 2 on the main steel girders 1 and 1 to traffic for a certain period, for example, at night. Only the section L is removed to the extent that the replacement work of the intended section can be completed, and after that removal, concrete slabs 3, 3, such as a known combo slab, manufactured in advance at a factory etc. are laid. At the same time, the necessary amount of joint concrete 4 is poured between the concrete slabs 3, 3, and the main girders 1,
A new floor slab 6 having a composite girder slab structure almost the same as the old floor slab 2 is formed by performing necessary joint treatment such as pouring concrete 5 on the upper flanges 1a and 1a of 1. And this new floor slab 6 and old floor slab 2
As shown in FIG. 4, between the end surfaces 6a, 2a facing each other, a plurality of axial force transmitting devices 8 consisting of hydraulic jacks etc. are set via bearing plates 7, 7. Pressure is applied to the end surfaces 6a, 2a in a direction to separate them from each other, thereby applying stress in the axial direction to both the old and new floor slabs 6,2. Furthermore, as shown in the figure, a lining plate 9 for vehicle running is passed over both the old and new floor slabs 6, 2 to complete the replacement.
After the joint concrete 4, 5, etc. have cured, the vehicle is opened to traffic and allowed to run on the lining board 9. In this way, traffic is temporarily stopped at night when traffic volume is low, and the floor slabs in a certain section are replaced using the method described above, and this process is repeated one after another.

ところで、本発明による工法を実施する場合に
おいて、最も重要な工程は、新旧両床版6,2間
の隙間Aを形成する区間の処理であるが、この区
間は施工上コンクリート床版が全く存在しないた
め、主桁1,1のみの断面となり、したがつて、
この区間における主桁1,1に応力が集中して主
桁1,1は当然強度不足となる。この処理として
本工法においては、前述のように新旧両床版6,
2間に油圧ジヤツキ等からなる軸力伝達装置8を
複数セツトして両端面6a,2aを互いに離間さ
せる方向に圧力をかけておくようにしているの
で、新旧両床版6,2にそれぞれ作用する応力の
うち特に軸方向(水平方向)の成分が各軸力伝達
装置8を介して互いに伝達し合い、この結果、隙
間Aの区間における主桁1,1に応力が集中しな
くなり、主桁1,1の強度不足は解消される。す
なわち、床版6,2間にセツトされた各軸力伝達
装置8の作用により、床版の存在しない隙間Aの
区間も、強度的にはあたかも合成桁床版のような
断面構造となる。したがつて、図示のようにこの
隙間Aをまたぐ覆工板9を差し渡してその上を走
行させても、その走行する車輌等によつて作用す
るくり返し荷重等に対し充分耐えることができ
る。
By the way, when implementing the construction method according to the present invention, the most important step is the treatment of the section that forms the gap A between the old and new slabs 6 and 2, but this section does not have any concrete slabs at all during construction. Therefore, the cross section is only for the main girders 1 and 1, and therefore,
Stress is concentrated on the main girders 1, 1 in this section, and the main girders 1, 1 naturally lack strength. As for this process, in this construction method, both the old and new floor slabs 6,
A plurality of axial force transmission devices 8 consisting of hydraulic jacks or the like are set between the two to apply pressure in the direction of separating both end surfaces 6a, 2a from each other, so that they act on both the new and old deck slabs 6, 2 respectively. Particularly, the axial direction (horizontal direction) component of the stress caused by The lack of strength in 1,1 will be resolved. That is, due to the action of each axial force transmission device 8 set between the floor slabs 6 and 2, even the section of the gap A where no floor slab exists has a cross-sectional structure similar to that of a composite girder slab in terms of strength. Therefore, even if the lining plate 9 is passed across the gap A and the vehicle is run on it as shown in the figure, it can sufficiently withstand the repeated loads etc. exerted by the running vehicle or the like.

なお、新旧両床版6,2の端面6a,2aから
軸力伝達装置8を介して互いに伝達し合う床版軸
力は、その伝達装置8を等間隔で多数セツトする
ことによつて部分的に集中させずにできるだけ均
一化させるように配慮するのが望ましく、またそ
の場合に作業性等も考慮する必要がある。そこ
で、この軸力伝達装置8としては、それらの点を
充足するものであれば、実施例で示した油圧ジヤ
ツキの他、ねじ機構等によつて支圧板7,7の間
隔を調節できる機械的構造のものなどでも良い。
The floor slab axial force that is transmitted to each other from the end faces 6a, 2a of both the old and new floor slabs 6, 2 via the axial force transmitting device 8 can be partially reduced by setting a large number of the transmitting devices 8 at equal intervals. It is desirable to take care to make it as uniform as possible without concentrating on it, and in this case, it is also necessary to consider workability. Therefore, as long as this axial force transmission device 8 satisfies these points, in addition to the hydraulic jack shown in the embodiment, a mechanical device that can adjust the spacing between the bearing pressure plates 7, 7 using a screw mechanism or the like may be used. It can also be a structural thing.

また、新旧両床版6,2の間隙、つまり隙間A
は、軸力伝達装置8の大きさによつても左右され
るが、主桁1,1に対する応力の集中度合を小さ
くするにはできるだけ狭くする方が望ましく、ま
た、床版打替後においては比較的短時間のうちに
路面として使用されるので、目地コンクリート
4,5は超早強コンクリートが使用される。
Also, the gap between the old and new floor slabs 6 and 2, that is, the gap A
Although it depends on the size of the axial force transmission device 8, it is desirable to make it as narrow as possible in order to reduce the degree of stress concentration on the main girders 1, 1. Since the joint concrete 4 and 5 will be used as a road surface within a relatively short period of time, ultra-early strength concrete is used.

以上詳述したように、本発明にあつては、主桁
上の旧床版を一定区間撤去し、その後にコンクリ
ートスラブを敷設して床版を形成し、この床版と
旧床版との互いに対向する端面間に軸力伝達装置
をセツトするとともにこの軸力伝達装置によつて
両端面が互いに離間する方向に圧力をかけてお
き、さらに前記新旧両床版上に車輌走行用の覆工
板を差し渡すことを特徴とするものであるから、
従来のように迂回路の確保や多大な手間と費用の
かかる応急橋の架設工事などの相当大がかりな交
通処理手段を根本的になくすことができ、非常に
経済的効果が大きいなどの優れた利点がある。
As described in detail above, in the present invention, a certain section of the old deck slab on the main girder is removed, a concrete slab is then laid to form the deck slab, and this floor slab and the old slab are connected. An axial force transmitting device is set between the mutually opposing end surfaces, and pressure is applied by this axial force transmitting device in a direction in which both end surfaces are separated from each other, and a lining for vehicle running is installed on both the old and new deck slabs. Because it is characterized by passing the board,
It has excellent advantages such as being able to fundamentally eliminate the conventional means of traffic management, such as securing detours and constructing emergency bridges, which require a great deal of time and effort, resulting in extremely large economic effects. There is.

【図面の簡単な説明】[Brief explanation of drawings]

図は本発明による工法の一実施例を説明するた
めに示したもので、第1図aおよびbは合成桁床
版の一部断面側面図、および平面図、第2図は第
1図aの−線に沿う断面図、第3図は第1図
bの−線に沿う断面図、第4図は要部の断面
図である。 1……主桁、2……旧床版、2a……端面、3
……コンクリートスラブ、4,5……目地コンク
リート、6……新床版、6a……端面、7……支
圧板、8……軸力伝達装置、9……覆工板、A…
…隙間。
The figures are shown to explain one embodiment of the construction method according to the present invention. Figures 1a and b are partially sectional side views and plan views of the composite girder deck, and Figure 2 is Figure 1a. FIG. 3 is a cross-sectional view taken along the line - of FIG. 1b, and FIG. 4 is a cross-sectional view of the main part. 1...Main girder, 2...Old floor slab, 2a...End face, 3
... Concrete slab, 4, 5 ... Joint concrete, 6 ... New floor slab, 6a ... End surface, 7 ... Bearing plate, 8 ... Axial force transmission device, 9 ... Lining plate, A ...
…gap.

Claims (1)

【特許請求の範囲】[Claims] 1 主桁上の旧床版を一定区間撤去し、その後に
コンクリートスラブを敷設して床版を形成し、こ
の床版と旧床版との互いに対向する端面間に、そ
の両端面が互いに離間する方向に圧力をかけて新
旧両床版同志の軸方向の応力を伝達する軸力伝達
装置をセツトし、さらに前記新旧両床版上に車輌
走行用の覆工板を差し渡すことを特徴とする道路
橋等における合成桁床版の打替工法。
1. A certain section of the old deck slab on the main girder is removed, and then a concrete slab is laid to form a deck slab, and the end faces of this slab and the old slab are spaced apart from each other. The present invention is characterized in that an axial force transmitting device is installed to transmit stress in the axial direction between the old and new floor slabs by applying pressure in the direction of A method for replacing composite girder slabs on road bridges, etc.
JP3124982A 1982-02-26 1982-02-26 Impact replacement of synthetic beam floor plate in road bridge Granted JPS58150604A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3124982A JPS58150604A (en) 1982-02-26 1982-02-26 Impact replacement of synthetic beam floor plate in road bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3124982A JPS58150604A (en) 1982-02-26 1982-02-26 Impact replacement of synthetic beam floor plate in road bridge

Publications (2)

Publication Number Publication Date
JPS58150604A JPS58150604A (en) 1983-09-07
JPS6364565B2 true JPS6364565B2 (en) 1988-12-13

Family

ID=12326089

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3124982A Granted JPS58150604A (en) 1982-02-26 1982-02-26 Impact replacement of synthetic beam floor plate in road bridge

Country Status (1)

Country Link
JP (1) JPS58150604A (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS635365A (en) * 1986-06-25 1988-01-11 Hitachi Ltd Light beam scanning type printer
JPS6356711U (en) * 1986-09-25 1988-04-15
JP2005282272A (en) * 2004-03-30 2005-10-13 Ishikawajima Constr Materials Co Ltd Construction method for replacing floor slab of composite girder, and device for transferring axial force between floor slabs
JP4958061B2 (en) * 2006-03-06 2012-06-20 株式会社Ihiインフラ建設 Replacement method for precast floor slabs for composite girder floor replacement and cast-in-place RC floor slabs for composite girder
JP4954859B2 (en) * 2007-12-10 2012-06-20 ダイチ工営株式会社 Temporary restoration method following removal of bridge expansion and contraction device
JP5266291B2 (en) * 2010-10-12 2013-08-21 横河工事株式会社 Construction method of bridge deck and joint structure of precast deck
JP6837343B2 (en) * 2017-02-03 2021-03-03 首都高速道路株式会社 Floor slab replacement method for synthetic girders
JP2020133214A (en) * 2019-02-19 2020-08-31 株式会社Ihiインフラシステム Floor slab replacement method and vehicle going-over board
JP7570947B2 (en) * 2021-03-04 2024-10-22 株式会社大林組 Temporary lining deck, installation structure for temporary lining deck, and installation method for temporary lining deck

Also Published As

Publication number Publication date
JPS58150604A (en) 1983-09-07

Similar Documents

Publication Publication Date Title
WO2016023462A1 (en) Glued joint connecting method for steel-concrete composite beam of cable-stayed bridge
CN108914778A (en) The method that the concrete slab of a kind of pair of combination beam top flange applies precompression
JPS6364565B2 (en)
CN111719849A (en) A primary and secondary beam forming structure of PC laminated beam and its construction method
CN209836794U (en) Low-height groove-shaped steel-concrete composite beam
JP2003253620A (en) Cable stayed bridge and its construction method
JP2001329510A (en) Precast segment and forming method for bridge girder using it
JP2007169886A (en) Composite structure of main girder and precast floor slab
JPS6282147A (en) Novel prestressed synthetic beam and its construction
CN115652812B (en) Asynchronous construction method of PK section composite beam cable-stayed bridge
JPS6346497Y2 (en)
JPS6059210A (en) Replacing method of bridge reinforced concrete floor panel
JPH08333723A (en) Manufacture of precast concrete floor slab and connecting method thereof
JPS6059209A (en) Replacing method of bridge reinforced concrete floor panel
JPH0380210B2 (en)
JPS6245804A (en) Re-covering of bridge reinforced concrete
JPH0426483Y2 (en)
CN204570450U (en) Compound beam syndeton with perforated panel and the compound beam containing this syndeton
CN204571093U (en) The compound beam syndeton of tape welding nail and the compound beam containing this syndeton
CN111411722A (en) Prefabricated Laminated Beam Slabs for Assembly Systems
JPH01105807A (en) Connection structure of precast concrete floor panel
JPS6245805A (en) Re-covering of bridge concrete floor panel
KR100662207B1 (en) Rigid connection structure using link stud bolt
JP2911304B2 (en) Joining structure and joining method of precast block for bridge
DE974961C (en) Method for manufacturing a girder bridge from steel girders and a pre-stressed deck made of reinforced concrete coupled to these